SlideShare a Scribd company logo
10 www.bridgeweb.com Bd&e | ISSUE 80 | 2015
N E W S
C
onstruction of the Downtown
Crossing in the USA is
progressing at an accelerated
pace with all three towers completed
and the bridge deck making connection
with land at the Indiana approach.
Steel work is expected to be completed
by late October and the bridge is due
to open to traffic in January with full
completion scheduled for the end of
2016.
The 642m-long, US$860 million
Downtown Crossing, one of the two
currently under construction in this
high growth metropolitan area as
part of the Ohio River Bridges Project,
will connect Louisville, Kentucky to
Covington, Indiana.
Initiated as a second bridge in
the Louisville-Southern Indiana
region, the Downtown Crossing
will increase regional mobility and
reduce congestion by doubling traffic
capacity over the river. It includes
building the new I-65 bridge with
six northbound lanes, reconfiguring
Spaghetti Junction (I-64, I-65 and I-71),
reconfiguring Indiana roadways and
bridge approaches, and rehabilitation
of the Kennedy Bridge (I-65) with six
southbound lanes.
In 2012, the Walsh Construction
design-build team won the contract to
design the structure for the Kentucky
Transportation Cabinet. Buckland &
Taylor, as a sub-consultant to Jacobs
and member of the design-build team,
was responsible for the detailed design
and erection engineering of the cable-
stayed signature span. The final design
of a highly durable yet inherently
flexible three-tower cable-stayed bridge
was delivered by the team with an
accelerated project schedule.
The superstructure consists of
concrete towers with a composite steel
girder and concrete deck; two main
spans each 229m long, supported by 15
cables spaced at 15m centres along the
edge girders; end spans of 92m each;
and carrying six lanes of traffic.
The design minimises the footprint
for the tower foundations by using
just one row of large-diameter shafts
per tower, resulting in a system that
shortens the installation time and
accelerates the overall construction
schedule.
Additionally, the system relies on
cantilever action of the shafts to resist
overturning moments resulting from
longitudinal loads. As a result, the
bridge will be much more flexible in
the longitudinal direction than a typical
cable-stayed bridge founded on a pile
group foundation system with piles
spaced in both directions.
A notable design aspect is the three-
tower arrangement; a requirement
specified by the owner. Unlike
traditional cable-stayed bridges with
a two-tower arrangement where the
top of the towers are restrained by
back-stays attached to the anchor
piers, on the Downtown Crossing the
taller centre tower is the third tower in
the arrangement and is not restrained
to anchor piers at the top. This results
in a greater flexibility, and a dynamic
behaviour that is more like a bridge
with a longer cable-supported span.
To meet the community’s
requirement for enhanced views of
the downtown Louisville skyline the
team designed the upper section of the
tower with no cross strut between the
legs. The design-build team elected to
eliminate any transverse struts below
deck to reduce costs and improve the
construction schedule. As a result, the
system is also flexible in the transverse
direction due to the lack of struts
between the tower legs above the
foundation.
An additional measure used was to
design the pile caps to extend below
the water surface to provide aesthetic
consistency as water levels vary, and
to prevent debris build-up. Pile cap
construction was accomplished by
use of precast concrete elements as a
base for the pile cap formwork, which
together served as a cofferdam for
placing the pile cap concrete. The team
also designed five-sided pentagonal
individual towers to provide further
visual interest.
The most important feature is the
100-year service life, considering the
fact that inspection and maintenance
activities substantially affect bridge
life-cycle costs.
Service life design is in its infancy in
North America and adds an additional
level of complexity to the design.
Buckland & Taylor explicitly performed
and incorporated a probabilistic service
life design into the design process for
the Downtown Crossing.
The concrete service life design on
this bridge was based on the model
code for service life developed by
the FIB in Bulletin 34, 2006, which
addresses service life design for plain
concrete, reinforced concrete and
prestressed concrete structures, and
implemented in ISO 16204:2012 Service
life design of concrete structures.
This approach matches the bridge to
its environment and takes into account
the actual chloride demands that the
structure will experience on location.
The design of the concrete mix, the
concrete cover over the reinforcing
steel and the type of reinforcing steel to
limit the initiation of corrosion during
its design life is a probabilistic approach
analogous to strength design.
A corrosion protection plan to
provide the bridge with a 90%
probability of meeting or exceeding
its prescribed service life has been
developed by Buckland & Taylor.
Performing this service life design
assures KYTC that the new bridge will
require low maintenance and stand the
test of time.
By John Brestin, vice president &
project director, Buckland & Taylor
Downtown Crossing on target for 2016 completion
Rendering of the Downtown Crossing
(Jacobs)Jacobs)Jacobs
Above: Construction of the Downtown
Crossing under way alongside the
existing structure (Buckland & Taylor)Buckland & Taylor)Buckland & Taylor

More Related Content

What's hot

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Halcrow
 
Bridge pier
Bridge pierBridge pier
Bridge pier
Pritesh Parmar
 
Current Long Span Bridges 16
Current Long Span Bridges 16Current Long Span Bridges 16
Current Long Span Bridges 16
David Collings
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
Faizan Shabbir
 
Bridges
BridgesBridges
Bridges
Deewas Kharka
 
Bridges precast
Bridges precastBridges precast
Bridges precast
Dr Fereidoun Dejahang
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
Eddy Ankit Gangani
 
Types of bridge(concept)
Types of bridge(concept)Types of bridge(concept)
Types of bridge(concept)
Kushal Patel
 
Types of bridge(theory.explanation)
Types of bridge(theory.explanation)Types of bridge(theory.explanation)
Types of bridge(theory.explanation)
Kushal Patel
 
Bridges
BridgesBridges
Bridges
Prevodioci
 
Bridge and culvert
Bridge and culvertBridge and culvert
Bridge and culvert
farazsugh
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
Micotol
 
Bridges by span
Bridges by spanBridges by span
Bridges by span
Dr Fereidoun Dejahang
 
Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structures
Muhammad Qasim Jameel
 
BRIDGE OVERVIEW
BRIDGE OVERVIEWBRIDGE OVERVIEW
BRIDGE OVERVIEW
PRABHAT RAJPUT
 
Bridge collapse
Bridge collapseBridge collapse
Bridge collapse
neeraj verma
 
Bridge,types of bridges
Bridge,types of bridgesBridge,types of bridges
Bridge,types of bridges
jitendra malviya
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
MAHAVIR MEENA
 
Bridges 02
Bridges 02Bridges 02
Design manual-for-small-bridges
Design manual-for-small-bridgesDesign manual-for-small-bridges
Design manual-for-small-bridges
indranaths
 

What's hot (20)

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Bridge pier
Bridge pierBridge pier
Bridge pier
 
Current Long Span Bridges 16
Current Long Span Bridges 16Current Long Span Bridges 16
Current Long Span Bridges 16
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Bridges
BridgesBridges
Bridges
 
Bridges precast
Bridges precastBridges precast
Bridges precast
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Types of bridge(concept)
Types of bridge(concept)Types of bridge(concept)
Types of bridge(concept)
 
Types of bridge(theory.explanation)
Types of bridge(theory.explanation)Types of bridge(theory.explanation)
Types of bridge(theory.explanation)
 
Bridges
BridgesBridges
Bridges
 
Bridge and culvert
Bridge and culvertBridge and culvert
Bridge and culvert
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
 
Bridges by span
Bridges by spanBridges by span
Bridges by span
 
Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structures
 
BRIDGE OVERVIEW
BRIDGE OVERVIEWBRIDGE OVERVIEW
BRIDGE OVERVIEW
 
Bridge collapse
Bridge collapseBridge collapse
Bridge collapse
 
Bridge,types of bridges
Bridge,types of bridgesBridge,types of bridges
Bridge,types of bridges
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Bridges 02
Bridges 02Bridges 02
Bridges 02
 
Design manual-for-small-bridges
Design manual-for-small-bridgesDesign manual-for-small-bridges
Design manual-for-small-bridges
 

Viewers also liked

9 „მოგზაურობა მზის სისტემაში“
9 „მოგზაურობა მზის სისტემაში“9 „მოგზაურობა მზის სისტემაში“
9 „მოგზაურობა მზის სისტემაში“
mtbiblia
 
Diapositivas
DiapositivasDiapositivas
Diapositivas
madeleynecatano
 
La Corrupcion mata
La Corrupcion mataLa Corrupcion mata
La Corrupcion mata
Nahum Azaña
 
Luxe et Nouveaux Médias - partie 2
Luxe et Nouveaux Médias - partie 2Luxe et Nouveaux Médias - partie 2
Luxe et Nouveaux Médias - partie 2
Neil Tamzali
 
How to convert your leads into sales - Clif Shaw
How to convert your leads into sales - Clif ShawHow to convert your leads into sales - Clif Shaw
How to convert your leads into sales - Clif Shaw
Rebecca Caroe
 
Rintihan rabaah - in making
Rintihan rabaah - in makingRintihan rabaah - in making
Rintihan rabaah - in making
Zubir Zolkipli
 
Placer
PlacerPlacer
Placer
Durero
 
notificasion
notificasionnotificasion
notificasion
Cristian Cedeño
 
Mapa 2 actividad 3 luis puerto
Mapa 2 actividad 3 luis puertoMapa 2 actividad 3 luis puerto
Mapa 2 actividad 3 luis puerto
Luis Puerto
 
02 08 evaluacion_de_competencias_v1.7
02 08 evaluacion_de_competencias_v1.702 08 evaluacion_de_competencias_v1.7
02 08 evaluacion_de_competencias_v1.7
Gaizka Bilbao Navarro
 
Republic of the philippines
Republic of the philippinesRepublic of the philippines
Republic of the philippines
manuel hidalgo
 
Picture 01 820 (1)
Picture 01 820 (1)Picture 01 820 (1)
Picture 01 820 (1)akky85
 
Justin bieber
Justin bieberJustin bieber
Justin bieber
natynitsuj
 
Mohammad syaltut abduh case study
Mohammad syaltut abduh case studyMohammad syaltut abduh case study
Mohammad syaltut abduh case study
Mohammad Syaltut Abduh
 

Viewers also liked (15)

9 „მოგზაურობა მზის სისტემაში“
9 „მოგზაურობა მზის სისტემაში“9 „მოგზაურობა მზის სისტემაში“
9 „მოგზაურობა მზის სისტემაში“
 
Diapositivas
DiapositivasDiapositivas
Diapositivas
 
La Corrupcion mata
La Corrupcion mataLa Corrupcion mata
La Corrupcion mata
 
Luxe et Nouveaux Médias - partie 2
Luxe et Nouveaux Médias - partie 2Luxe et Nouveaux Médias - partie 2
Luxe et Nouveaux Médias - partie 2
 
How to convert your leads into sales - Clif Shaw
How to convert your leads into sales - Clif ShawHow to convert your leads into sales - Clif Shaw
How to convert your leads into sales - Clif Shaw
 
Rintihan rabaah - in making
Rintihan rabaah - in makingRintihan rabaah - in making
Rintihan rabaah - in making
 
Placer
PlacerPlacer
Placer
 
notificasion
notificasionnotificasion
notificasion
 
Mapa 2 actividad 3 luis puerto
Mapa 2 actividad 3 luis puertoMapa 2 actividad 3 luis puerto
Mapa 2 actividad 3 luis puerto
 
02 08 evaluacion_de_competencias_v1.7
02 08 evaluacion_de_competencias_v1.702 08 evaluacion_de_competencias_v1.7
02 08 evaluacion_de_competencias_v1.7
 
Mattino
MattinoMattino
Mattino
 
Republic of the philippines
Republic of the philippinesRepublic of the philippines
Republic of the philippines
 
Picture 01 820 (1)
Picture 01 820 (1)Picture 01 820 (1)
Picture 01 820 (1)
 
Justin bieber
Justin bieberJustin bieber
Justin bieber
 
Mohammad syaltut abduh case study
Mohammad syaltut abduh case studyMohammad syaltut abduh case study
Mohammad syaltut abduh case study
 

Similar to BDE80_p10

Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
Matthias Schueller
 
CB_SeptOct_2015_bridges
CB_SeptOct_2015_bridgesCB_SeptOct_2015_bridges
CB_SeptOct_2015_bridges
Rebecca Abel
 
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
Lucas de Brito Nascimento
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
SauravShahane
 
Lane ave bridge report
Lane ave bridge reportLane ave bridge report
Lane ave bridge report
John Mangini
 
Southland colonial pedestrianoverpass_tre0003-g_technicalproposal
Southland colonial pedestrianoverpass_tre0003-g_technicalproposalSouthland colonial pedestrianoverpass_tre0003-g_technicalproposal
Southland colonial pedestrianoverpass_tre0003-g_technicalproposal
Brendan O'Connor
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
Lisa Cain
 
Harthill footbridge
Harthill footbridgeHarthill footbridge
Harthill footbridge
Glenn Corewyn
 
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaComposite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Suhas Khedkar
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Dr.Subramanian Narayanan
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
IRJET Journal
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
T.Y. Lin International
 
report
reportreport
report
Ravi Panchal
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)
Mohamed Yassin
 
Reinforcement of Driscoll Bridge
Reinforcement of Driscoll BridgeReinforcement of Driscoll Bridge
Reinforcement of Driscoll Bridge
PostTensioningInstitute
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
jupallipavan2911
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptx
Spidra1
 
Presentation PPT.pdf
Presentation PPT.pdfPresentation PPT.pdf
Presentation PPT.pdf
MRVOLDEMORT1
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
Javad Akhtar
 

Similar to BDE80_p10 (20)

Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
CB_SeptOct_2015_bridges
CB_SeptOct_2015_bridgesCB_SeptOct_2015_bridges
CB_SeptOct_2015_bridges
 
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Lane ave bridge report
Lane ave bridge reportLane ave bridge report
Lane ave bridge report
 
Southland colonial pedestrianoverpass_tre0003-g_technicalproposal
Southland colonial pedestrianoverpass_tre0003-g_technicalproposalSouthland colonial pedestrianoverpass_tre0003-g_technicalproposal
Southland colonial pedestrianoverpass_tre0003-g_technicalproposal
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
 
Harthill footbridge
Harthill footbridgeHarthill footbridge
Harthill footbridge
 
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaComposite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
 
report
reportreport
report
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)
 
Reinforcement of Driscoll Bridge
Reinforcement of Driscoll BridgeReinforcement of Driscoll Bridge
Reinforcement of Driscoll Bridge
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptx
 
Presentation PPT.pdf
Presentation PPT.pdfPresentation PPT.pdf
Presentation PPT.pdf
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
 

BDE80_p10

  • 1. 10 www.bridgeweb.com Bd&e | ISSUE 80 | 2015 N E W S C onstruction of the Downtown Crossing in the USA is progressing at an accelerated pace with all three towers completed and the bridge deck making connection with land at the Indiana approach. Steel work is expected to be completed by late October and the bridge is due to open to traffic in January with full completion scheduled for the end of 2016. The 642m-long, US$860 million Downtown Crossing, one of the two currently under construction in this high growth metropolitan area as part of the Ohio River Bridges Project, will connect Louisville, Kentucky to Covington, Indiana. Initiated as a second bridge in the Louisville-Southern Indiana region, the Downtown Crossing will increase regional mobility and reduce congestion by doubling traffic capacity over the river. It includes building the new I-65 bridge with six northbound lanes, reconfiguring Spaghetti Junction (I-64, I-65 and I-71), reconfiguring Indiana roadways and bridge approaches, and rehabilitation of the Kennedy Bridge (I-65) with six southbound lanes. In 2012, the Walsh Construction design-build team won the contract to design the structure for the Kentucky Transportation Cabinet. Buckland & Taylor, as a sub-consultant to Jacobs and member of the design-build team, was responsible for the detailed design and erection engineering of the cable- stayed signature span. The final design of a highly durable yet inherently flexible three-tower cable-stayed bridge was delivered by the team with an accelerated project schedule. The superstructure consists of concrete towers with a composite steel girder and concrete deck; two main spans each 229m long, supported by 15 cables spaced at 15m centres along the edge girders; end spans of 92m each; and carrying six lanes of traffic. The design minimises the footprint for the tower foundations by using just one row of large-diameter shafts per tower, resulting in a system that shortens the installation time and accelerates the overall construction schedule. Additionally, the system relies on cantilever action of the shafts to resist overturning moments resulting from longitudinal loads. As a result, the bridge will be much more flexible in the longitudinal direction than a typical cable-stayed bridge founded on a pile group foundation system with piles spaced in both directions. A notable design aspect is the three- tower arrangement; a requirement specified by the owner. Unlike traditional cable-stayed bridges with a two-tower arrangement where the top of the towers are restrained by back-stays attached to the anchor piers, on the Downtown Crossing the taller centre tower is the third tower in the arrangement and is not restrained to anchor piers at the top. This results in a greater flexibility, and a dynamic behaviour that is more like a bridge with a longer cable-supported span. To meet the community’s requirement for enhanced views of the downtown Louisville skyline the team designed the upper section of the tower with no cross strut between the legs. The design-build team elected to eliminate any transverse struts below deck to reduce costs and improve the construction schedule. As a result, the system is also flexible in the transverse direction due to the lack of struts between the tower legs above the foundation. An additional measure used was to design the pile caps to extend below the water surface to provide aesthetic consistency as water levels vary, and to prevent debris build-up. Pile cap construction was accomplished by use of precast concrete elements as a base for the pile cap formwork, which together served as a cofferdam for placing the pile cap concrete. The team also designed five-sided pentagonal individual towers to provide further visual interest. The most important feature is the 100-year service life, considering the fact that inspection and maintenance activities substantially affect bridge life-cycle costs. Service life design is in its infancy in North America and adds an additional level of complexity to the design. Buckland & Taylor explicitly performed and incorporated a probabilistic service life design into the design process for the Downtown Crossing. The concrete service life design on this bridge was based on the model code for service life developed by the FIB in Bulletin 34, 2006, which addresses service life design for plain concrete, reinforced concrete and prestressed concrete structures, and implemented in ISO 16204:2012 Service life design of concrete structures. This approach matches the bridge to its environment and takes into account the actual chloride demands that the structure will experience on location. The design of the concrete mix, the concrete cover over the reinforcing steel and the type of reinforcing steel to limit the initiation of corrosion during its design life is a probabilistic approach analogous to strength design. A corrosion protection plan to provide the bridge with a 90% probability of meeting or exceeding its prescribed service life has been developed by Buckland & Taylor. Performing this service life design assures KYTC that the new bridge will require low maintenance and stand the test of time. By John Brestin, vice president & project director, Buckland & Taylor Downtown Crossing on target for 2016 completion Rendering of the Downtown Crossing (Jacobs)Jacobs)Jacobs Above: Construction of the Downtown Crossing under way alongside the existing structure (Buckland & Taylor)Buckland & Taylor)Buckland & Taylor