SlideShare a Scribd company logo
Dr. Walied A. Elsaigh
welsaigh@ksu.edu.sa
Asst. Prof. of Civil Engineering
Jumada’-I 1437H
CE 435
Railway Engineering
RailsFoot
Web
Head
Flat Foot Rail
Text Book
Railway Engineering,
Satish and Agarwal,
2nd edition, 2013
Chapter 6
Page 81-105
Functions of Rails
Types of Rails
Standard Rail Sections
Branding and Stamping
Common section codes
RE: American Railway Engineering Maintenance of Way Association (AREMA).
REHF: AREMA “head free” section.
ARA-A: American Railway Association, “A” section.
ARA-B: American Railway Association, “B” section.
ASCE: American Society of Civil Engineers.
Cont. Standard Rail Sections
HT = Height
BW = Width of Head
HW = Width of Head
W = Web (at center point)
HD = Depth of Head
FD = Fishing
BD =Depth of Base
E =Bolt Hole Elevation
X-Section of Rail
Cont. Standard Rail Sections
Cont. Standard Rail Sections
The rail is designated by its weight per unit length.
52 kg/m rail denotes that it has a
weight of 52 kg per metre length
Factors affecting choice of appropriate rail section:
Heaviest axle load
Maximum permissible speed
Depth of ballast cushion
Type and spacing of sleepers
Selection of Rail Section
Rule of Thumb (Relationship between
maximum axle load and weight of rail section)
Maximum axle load = 560 × sectional weight of rail
Example #1: Determine the maximum axle load for 90 lb/yard rail section
Maximum axle load = 560 × 90 lbs = 50,400 lbs or 22.5 t
Example #2: Determine the suitable rail section weight (kg/ m) to carry a
maximum axle load of 29 ton? (ans: 52kg/m)
Sectional weight of rail in lbs per yard or kg per metre
Lack of facilities for transport of longer rails, particularly on curves.
Difficulties in manufacturing very long rails.
Difficulties in acquiring bigger expansion joints for long rails.
Heavy internal thermal stresses in long rails.
Rail Length
Theoretically, the longer rails are preferred, why?
Reduces number of joints less cost (construction & maintenance)
Provides smooth and comfortable rides.
Length of a rail is limited, Why?
Find out the following: Rail section and length used in KSA
Rail Tests Falling Weight Test
[Tup Test]
A rail piece of 1.5 m (5 ft) is cut. The rail is supported between the bearers
at a prescribed distance. A tup of specified weight (see table) is dropped
from a height of 7.2 m on the centre of the test piece.
One falling weight test is done for
every cast of 100 metric tonnes.
The rail specimen should withstand
the blow without any fracture.
Rail Tests
Tensile Test
A test piece is taken from the head of a rail section and subjected to
the tensile test.
The tensile strength of the rail should not be less than 720 N/mm2,
minimum elongation of 12%
Rail Tests
Hammer Test
No fracture should occur or a lap be disclosed,
otherwise the batch is rejected.
The foot of the test rail piece is rigidly gripped in a vertical position
and the head of the rail is struck with a 4.5 kg hammer. Sufficient number
of blows are given till the web bends and the dimensional value of A given
in the Table below
Rail Defects
Rail Wear
Due to the passage of moving loads and friction between the rail
and the wheel, the rail head gets worn out in the course of service.
The impact of moving loads,
Forces due to acceleration, deceleration, and braking of wheels,
The abrasion due to rail–wheel interaction,
 Effects of weather conditions (i.e. temperature, rains, presence of sand).
Why wear occurs ? (causes of rail-head wear)
Rail Defects
Types of
Rail Wear
Where in the rail wear occurs ?
on top of the rail head (vertical wear)
on the sides of the rail head (lateral wear)
on the ends of the rail (battering of rail ends)
Rail Defects Locations
of Rail Wear
Where in the track wear occurs ?
on sharp curves, due to centrifugal forces
on steep gradients, due to the extra force applied by the engine
on approaches to railway stations, due to acceleration and deceleration
in tunnels and coastal areas, due to humidity and weather effects
Rail Defects
How to Reduce Rail Wear ?
Better maintenance of the track to ensure good packing
as well as proper alignment and use of the correct gauge
Reduction in the number of joints by welding
Lubricating the gauge face of the outer rail in case of curves
Providing check rails in the case of sharp curves
Rail Defects
 By weighing the rail
 By profiling the rail section (Special instruments are available)
incorporates the latest laser and video camera technology to provide accurate and
immediate report on the profile and wear condition of the rail whilst travelling at
track speeds. The video cameras capture full cross-sectional rail profiles from the
base/web fillet area up to the top-of-rail surface to allow comprehensive and
accurate rail measurements.
http://www.mermecgroup.com/diagnostics/tr
ackin%20specti-on/60/1/rail-profile.php
Adapted from:
How to Measure
Rail Wear ?
Rail Defects Rail End Batter
The hammering action of moving loads on rail
joints batters the rail ends in due course of time.
Batter = Beat (hit)
How measured?
If the batter is up to 2 mm, it is classified ‘average’,
If it is between 2 and 3 mm, it is classified as ‘severe’.
Rail Defects Rail End Batter
Adapted from: http://www.bitlanders.com/blogs/corrugation-wear-of-rails-
failure-of-rails-and-rails-welding/441935
Rail Defects Hogging Rail
Rail ends get hogged due to poor maintenance of the
rail joint, yielding formation, loose and faulty fastenings.
Remedial action? (1) Replace joint, (2) Welding joint,
(3) Dehogging, (4) Cropping
Hogged rails: Due to worn out of
rail ends due to load repetition,
the rail gets bent down at its
ends, creating what is termed as
“hogged rails”.
Consequence ? Rough riding, more vibration leading to more defects.
Causes? loose packing under joints and loose fish plate.
Rail Defects Corrugated Rail
Corrugated or Roaring rails: The heads of rails corrugate (fine
depressions on the surface of rails). Causes roaring sounds when
wheels pass over it.
Causes? Found at places where trains brakes or starts its journey, other
reasons such as: composition of steel used to manufacture rails.
Consequences? (1) Unpleasant roaring sound which cause discomfort
to passengers and residents along side the rail track
(2) Vibration causes further deterioration to other track
elements.
Remedial action? (1) Replace rail if corrugation is severe and the defect is
limited to small number of rails
(2) Grind top surface of rail, a grinding train moving at
3 km per hour can be used (as in Germany).

More Related Content

What's hot

Points and crossing
Points and crossingPoints and crossing
Points and crossing
Akash Patel
 
Geometric design of track
Geometric design of trackGeometric design of track
Geometric design of track
JOYCHENKENGLANG
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
Chockalingam T
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
RAMPRASAD KUMAWAT
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
MayuriPatel90
 
Railway track
Railway trackRailway track
Railway track
Dewang Agrawal
 
Points and crossings ( special assigments )
Points and crossings ( special assigments )Points and crossings ( special assigments )
Points and crossings ( special assigments )
hiranrathva
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
Deven Diran
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
KHUSHBU SHAH
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
Bathla Tuition Centre
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
Mani Vel
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Shanmugaraj M
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
Gowtham G
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
KHUSHBU SHAH
 
RAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERINGRAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERING
bhavin_pindoriya
 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018
ishwar dhakad
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
Vijai Krishnan V
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
Mohd Bakhsh
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
Hossam Shafiq I
 

What's hot (20)

Points and crossing
Points and crossingPoints and crossing
Points and crossing
 
Geometric design of track
Geometric design of trackGeometric design of track
Geometric design of track
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
Railway track
Railway trackRailway track
Railway track
 
Points and crossings ( special assigments )
Points and crossings ( special assigments )Points and crossings ( special assigments )
Points and crossings ( special assigments )
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway Gauge
Railway GaugeRailway Gauge
Railway Gauge
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
RAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERINGRAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERING
 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
 

Similar to 05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. Elsaigh)

Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
srinivas2036
 
Defects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptxDefects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptx
SuhasR37
 
lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdf
ssuser75acc8
 
chapter-3 Track Stracture.pptx
chapter-3  Track Stracture.pptxchapter-3  Track Stracture.pptx
chapter-3 Track Stracture.pptx
MamushLeta
 
P.way
P.wayP.way
P.way
vaignan
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineering
Dnyaneshwar More
 
Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1
Arun G
 
UNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.pptUNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.ppt
SwapnilGorade1
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
Irfan Nasir
 
089 CC2011 Crete (2011) Rail Straightness Control in Service
089 CC2011 Crete (2011) Rail Straightness Control in Service089 CC2011 Crete (2011) Rail Straightness Control in Service
089 CC2011 Crete (2011) Rail Straightness Control in ServiceAndrea Bracciali
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGEAELC
 
Rail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysisRail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysis
MIDAS Information Technology
 
Fatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element methodFatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element method
eSAT Publishing House
 
Fatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element methodFatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element method
eSAT Journals
 
5. wire rope and sample problem
5. wire rope and sample problem5. wire rope and sample problem
5. wire rope and sample problem
kamaraj college of engineeing and technology
 
5. wire rope and sample problem
5. wire rope and sample problem5. wire rope and sample problem
5. wire rope and sample problem
KAMARAJ COLLEGE OF ENGINEERING AND TECHNOLOGY
 
Sleeper
Sleeper Sleeper
Sleeper
Jayshiv Thakkar
 
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed BridgeIRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET Journal
 

Similar to 05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. Elsaigh) (20)

Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
 
3rd unit
3rd unit3rd unit
3rd unit
 
Defects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptxDefects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptx
 
lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdf
 
chapter-3 Track Stracture.pptx
chapter-3  Track Stracture.pptxchapter-3  Track Stracture.pptx
chapter-3 Track Stracture.pptx
 
Project Report
Project ReportProject Report
Project Report
 
P.way
P.wayP.way
P.way
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineering
 
Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1
 
UNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.pptUNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.ppt
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
 
089 CC2011 Crete (2011) Rail Straightness Control in Service
089 CC2011 Crete (2011) Rail Straightness Control in Service089 CC2011 Crete (2011) Rail Straightness Control in Service
089 CC2011 Crete (2011) Rail Straightness Control in Service
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
 
Rail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysisRail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysis
 
Fatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element methodFatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element method
 
Fatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element methodFatigue analysis of rail joint using finite element method
Fatigue analysis of rail joint using finite element method
 
5. wire rope and sample problem
5. wire rope and sample problem5. wire rope and sample problem
5. wire rope and sample problem
 
5. wire rope and sample problem
5. wire rope and sample problem5. wire rope and sample problem
5. wire rope and sample problem
 
Sleeper
Sleeper Sleeper
Sleeper
 
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed BridgeIRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
 

More from Hossam Shafiq I

14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
Hossam Shafiq I
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
Hossam Shafiq I
 
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
Hossam Shafiq I
 
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
Hossam Shafiq I
 
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
Hossam Shafiq I
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
Hossam Shafiq I
 
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
Hossam Shafiq I
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
Hossam Shafiq I
 
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
Hossam Shafiq I
 
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
Hossam Shafiq I
 
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
Hossam Shafiq I
 
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
Hossam Shafiq I
 
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
Hossam Shafiq I
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
Hossam Shafiq I
 
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
Hossam Shafiq I
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
Hossam Shafiq I
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
Hossam Shafiq I
 
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
Hossam Shafiq I
 
14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...
14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...
14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...
Hossam Shafiq I
 
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
Hossam Shafiq I
 

More from Hossam Shafiq I (20)

14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
 
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
 
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
 
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
 
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
 
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
 
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
 
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
 
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
 
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
 
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
 
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
 
14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...
14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...
14 Analysis of Signalized Intersections (Traffic Engineering هندسة المرور & P...
 
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
 

Recently uploaded

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 

Recently uploaded (20)

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 

05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. Elsaigh)

  • 1. Dr. Walied A. Elsaigh welsaigh@ksu.edu.sa Asst. Prof. of Civil Engineering Jumada’-I 1437H CE 435 Railway Engineering RailsFoot Web Head Flat Foot Rail
  • 2. Text Book Railway Engineering, Satish and Agarwal, 2nd edition, 2013 Chapter 6 Page 81-105
  • 5. Standard Rail Sections Branding and Stamping Common section codes RE: American Railway Engineering Maintenance of Way Association (AREMA). REHF: AREMA “head free” section. ARA-A: American Railway Association, “A” section. ARA-B: American Railway Association, “B” section. ASCE: American Society of Civil Engineers.
  • 7. HT = Height BW = Width of Head HW = Width of Head W = Web (at center point) HD = Depth of Head FD = Fishing BD =Depth of Base E =Bolt Hole Elevation X-Section of Rail Cont. Standard Rail Sections
  • 8. Cont. Standard Rail Sections The rail is designated by its weight per unit length. 52 kg/m rail denotes that it has a weight of 52 kg per metre length
  • 9. Factors affecting choice of appropriate rail section: Heaviest axle load Maximum permissible speed Depth of ballast cushion Type and spacing of sleepers Selection of Rail Section Rule of Thumb (Relationship between maximum axle load and weight of rail section) Maximum axle load = 560 × sectional weight of rail Example #1: Determine the maximum axle load for 90 lb/yard rail section Maximum axle load = 560 × 90 lbs = 50,400 lbs or 22.5 t Example #2: Determine the suitable rail section weight (kg/ m) to carry a maximum axle load of 29 ton? (ans: 52kg/m) Sectional weight of rail in lbs per yard or kg per metre
  • 10. Lack of facilities for transport of longer rails, particularly on curves. Difficulties in manufacturing very long rails. Difficulties in acquiring bigger expansion joints for long rails. Heavy internal thermal stresses in long rails. Rail Length Theoretically, the longer rails are preferred, why? Reduces number of joints less cost (construction & maintenance) Provides smooth and comfortable rides. Length of a rail is limited, Why? Find out the following: Rail section and length used in KSA
  • 11. Rail Tests Falling Weight Test [Tup Test] A rail piece of 1.5 m (5 ft) is cut. The rail is supported between the bearers at a prescribed distance. A tup of specified weight (see table) is dropped from a height of 7.2 m on the centre of the test piece. One falling weight test is done for every cast of 100 metric tonnes. The rail specimen should withstand the blow without any fracture.
  • 12. Rail Tests Tensile Test A test piece is taken from the head of a rail section and subjected to the tensile test. The tensile strength of the rail should not be less than 720 N/mm2, minimum elongation of 12%
  • 13. Rail Tests Hammer Test No fracture should occur or a lap be disclosed, otherwise the batch is rejected. The foot of the test rail piece is rigidly gripped in a vertical position and the head of the rail is struck with a 4.5 kg hammer. Sufficient number of blows are given till the web bends and the dimensional value of A given in the Table below
  • 14. Rail Defects Rail Wear Due to the passage of moving loads and friction between the rail and the wheel, the rail head gets worn out in the course of service. The impact of moving loads, Forces due to acceleration, deceleration, and braking of wheels, The abrasion due to rail–wheel interaction,  Effects of weather conditions (i.e. temperature, rains, presence of sand). Why wear occurs ? (causes of rail-head wear)
  • 15. Rail Defects Types of Rail Wear Where in the rail wear occurs ? on top of the rail head (vertical wear) on the sides of the rail head (lateral wear) on the ends of the rail (battering of rail ends)
  • 16. Rail Defects Locations of Rail Wear Where in the track wear occurs ? on sharp curves, due to centrifugal forces on steep gradients, due to the extra force applied by the engine on approaches to railway stations, due to acceleration and deceleration in tunnels and coastal areas, due to humidity and weather effects
  • 17. Rail Defects How to Reduce Rail Wear ? Better maintenance of the track to ensure good packing as well as proper alignment and use of the correct gauge Reduction in the number of joints by welding Lubricating the gauge face of the outer rail in case of curves Providing check rails in the case of sharp curves
  • 18. Rail Defects  By weighing the rail  By profiling the rail section (Special instruments are available) incorporates the latest laser and video camera technology to provide accurate and immediate report on the profile and wear condition of the rail whilst travelling at track speeds. The video cameras capture full cross-sectional rail profiles from the base/web fillet area up to the top-of-rail surface to allow comprehensive and accurate rail measurements. http://www.mermecgroup.com/diagnostics/tr ackin%20specti-on/60/1/rail-profile.php Adapted from: How to Measure Rail Wear ?
  • 19. Rail Defects Rail End Batter The hammering action of moving loads on rail joints batters the rail ends in due course of time. Batter = Beat (hit) How measured? If the batter is up to 2 mm, it is classified ‘average’, If it is between 2 and 3 mm, it is classified as ‘severe’.
  • 20. Rail Defects Rail End Batter Adapted from: http://www.bitlanders.com/blogs/corrugation-wear-of-rails- failure-of-rails-and-rails-welding/441935
  • 21. Rail Defects Hogging Rail Rail ends get hogged due to poor maintenance of the rail joint, yielding formation, loose and faulty fastenings. Remedial action? (1) Replace joint, (2) Welding joint, (3) Dehogging, (4) Cropping Hogged rails: Due to worn out of rail ends due to load repetition, the rail gets bent down at its ends, creating what is termed as “hogged rails”. Consequence ? Rough riding, more vibration leading to more defects. Causes? loose packing under joints and loose fish plate.
  • 22. Rail Defects Corrugated Rail Corrugated or Roaring rails: The heads of rails corrugate (fine depressions on the surface of rails). Causes roaring sounds when wheels pass over it. Causes? Found at places where trains brakes or starts its journey, other reasons such as: composition of steel used to manufacture rails. Consequences? (1) Unpleasant roaring sound which cause discomfort to passengers and residents along side the rail track (2) Vibration causes further deterioration to other track elements. Remedial action? (1) Replace rail if corrugation is severe and the defect is limited to small number of rails (2) Grind top surface of rail, a grinding train moving at 3 km per hour can be used (as in Germany).