SlideShare a Scribd company logo
1 of 6
Download to read offline
PMP EXAM
SAMPLE Q & A
You are managing a project to build five bridges. The project consists of five sequential phases
with each phase delivering one bridge.
After the first phase of the project is complete, which process group of the second phase should
follow?
A. Initiating
B. Planning
C. Executing
D. Closing
HINT: Which process group is performed at the beginning of a new project or a new phase of an
existing project?
Question
The correct answer is A.
The Initiating Process Group is made up of two processes, Develop Project Charter and Identify
Stakeholders. The Initiating Process Group is performed to define a new project or a new phase of
an existing project by obtaining authorization to start the project or phase. The purpose of this
Process Group is to align the stakeholders' expectations and the project purpose, inform
stakeholders of the scope and objectives, and discuss how their participation in the project and
its associated phases can help to ensure their expectations are met.
Answer
In the scenario described, you are about to start a new project phase. Therefore, you should start
with the Develop Project Charter process. It does not necessarily mean you would develop a new
project charter for each consecutive project phase, but it means that you will perform the
processes of the Initiating Process Group starting with the Develop Project Charter process. You
will review the project charter to see if the high-level assumptions and constraints made during
project initiation are still valid, and whether or not the market conditions are still favorable for the
project. Performing this process may result in an update of the charter or an addendum to the
project charter. In an extreme scenario, this process may result in project termination.
Answer
While the A Guide to the Project Management Body of Knowledge (PMBOK® Guide) does not
explicitly mention going back to the Initiating Process Group to look at the project charter, it does
provide several examples implying that the project team may choose to go with each new phase
as a separate, stand-alone project. Undertaking a stand-alone project means performing all its
processes, starting with the Develop Project Charter. The same logic applies to the next process in
the Initiating Process Group, the Identify Stakeholders process. It is possible that new
stakeholders became involved in the project, or some of the previous stakeholders left, or the
level of engagement of the existing stakeholders have changed. Even if nothing has changed, the
Develop Project Charter and the Identify Stakeholders processes should be performed.
Otherwise, how would you be able to conclude that nothing has changed? Therefore, starting the
new phase of the project with the processes of the Initiating Process Group is the best answer to
the question asked.
Answer
All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a Project Management Institute (PMI)® 
Registered Education Provider.

More Related Content

What's hot

PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
 
PMBOK® Vs PRINCE2®
PMBOK®  Vs PRINCE2®PMBOK®  Vs PRINCE2®
PMBOK® Vs PRINCE2®
Rajiv Sharma
 
Projectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit PayalProjectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit Payal
AMIT PAYAL
 

What's hot (20)

Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free CAPM® Exam Sample Question
Free CAPM® Exam Sample QuestionFree CAPM® Exam Sample Question
Free CAPM® Exam Sample Question
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free CAPM® Exam Sample Question
Free CAPM® Exam Sample QuestionFree CAPM® Exam Sample Question
Free CAPM® Exam Sample Question
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4
 
PMBOK® Vs PRINCE2®
PMBOK®  Vs PRINCE2®PMBOK®  Vs PRINCE2®
PMBOK® Vs PRINCE2®
 
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Projectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit PayalProjectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit Payal
 
Project Delivery Lifecycle
Project Delivery LifecycleProject Delivery Lifecycle
Project Delivery Lifecycle
 
Pmp sample questions
Pmp sample questionsPmp sample questions
Pmp sample questions
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 

Similar to Free PMP® Exam Sample Question

Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
PMI_IREP_TP
 
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
eugeniadean34240
 
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-ProjectsDeveloping-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
NIDHI SEN
 
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
gilbertkpeters11344
 

Similar to Free PMP® Exam Sample Question (20)

Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases Introduction
 
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptxharisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
 
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-ProjectsDeveloping-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
A presentation on project life cycle ...
A presentation on project life cycle ...A presentation on project life cycle ...
A presentation on project life cycle ...
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project management
Project managementProject management
Project management
 
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled Projects
 

More from OSP International LLC

More from OSP International LLC (20)

Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam Simulator
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam Simulator
 

Recently uploaded

Recently uploaded (10)

Marketing Management 16 Global Edition by Philip Kotler test bank.docx
Marketing Management 16 Global Edition by Philip Kotler test bank.docxMarketing Management 16 Global Edition by Philip Kotler test bank.docx
Marketing Management 16 Global Edition by Philip Kotler test bank.docx
 
DrupalCamp Atlanta 2022 - Effective Project Management
DrupalCamp Atlanta 2022 - Effective Project ManagementDrupalCamp Atlanta 2022 - Effective Project Management
DrupalCamp Atlanta 2022 - Effective Project Management
 
Team Dynamics: A Journey to Excellence
Team Dynamics: A Journey to ExcellenceTeam Dynamics: A Journey to Excellence
Team Dynamics: A Journey to Excellence
 
TEST BANK for Operations Management, 14th Edition by William J. Stevenson,.pdf
TEST BANK for Operations Management, 14th Edition by William J. Stevenson,.pdfTEST BANK for Operations Management, 14th Edition by William J. Stevenson,.pdf
TEST BANK for Operations Management, 14th Edition by William J. Stevenson,.pdf
 
Mastering Compassion: A Heavenly Perspective on Leadership
Mastering Compassion: A Heavenly Perspective on LeadershipMastering Compassion: A Heavenly Perspective on Leadership
Mastering Compassion: A Heavenly Perspective on Leadership
 
UX in an Agile World - Scrum Gathering
UX in an Agile World -   Scrum GatheringUX in an Agile World -   Scrum Gathering
UX in an Agile World - Scrum Gathering
 
Management 13th Edition by Richard L. Daft test bank.docx
Management 13th Edition by Richard L. Daft test bank.docxManagement 13th Edition by Richard L. Daft test bank.docx
Management 13th Edition by Richard L. Daft test bank.docx
 
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out PackagingW.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
 
🍑👄Vijay Nagar Esℂorts Serviℂe☎️9559995582🍑👄 ℂall Girl serviℂe in Indore☎️Vija...
🍑👄Vijay Nagar Esℂorts Serviℂe☎️9559995582🍑👄 ℂall Girl serviℂe in Indore☎️Vija...🍑👄Vijay Nagar Esℂorts Serviℂe☎️9559995582🍑👄 ℂall Girl serviℂe in Indore☎️Vija...
🍑👄Vijay Nagar Esℂorts Serviℂe☎️9559995582🍑👄 ℂall Girl serviℂe in Indore☎️Vija...
 
Leading People - Harvard Manage Mentor Certificate
Leading People - Harvard Manage Mentor CertificateLeading People - Harvard Manage Mentor Certificate
Leading People - Harvard Manage Mentor Certificate
 

Free PMP® Exam Sample Question

  • 2. You are managing a project to build five bridges. The project consists of five sequential phases with each phase delivering one bridge. After the first phase of the project is complete, which process group of the second phase should follow? A. Initiating B. Planning C. Executing D. Closing HINT: Which process group is performed at the beginning of a new project or a new phase of an existing project? Question
  • 3. The correct answer is A. The Initiating Process Group is made up of two processes, Develop Project Charter and Identify Stakeholders. The Initiating Process Group is performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase. The purpose of this Process Group is to align the stakeholders' expectations and the project purpose, inform stakeholders of the scope and objectives, and discuss how their participation in the project and its associated phases can help to ensure their expectations are met. Answer
  • 4. In the scenario described, you are about to start a new project phase. Therefore, you should start with the Develop Project Charter process. It does not necessarily mean you would develop a new project charter for each consecutive project phase, but it means that you will perform the processes of the Initiating Process Group starting with the Develop Project Charter process. You will review the project charter to see if the high-level assumptions and constraints made during project initiation are still valid, and whether or not the market conditions are still favorable for the project. Performing this process may result in an update of the charter or an addendum to the project charter. In an extreme scenario, this process may result in project termination. Answer
  • 5. While the A Guide to the Project Management Body of Knowledge (PMBOK® Guide) does not explicitly mention going back to the Initiating Process Group to look at the project charter, it does provide several examples implying that the project team may choose to go with each new phase as a separate, stand-alone project. Undertaking a stand-alone project means performing all its processes, starting with the Develop Project Charter. The same logic applies to the next process in the Initiating Process Group, the Identify Stakeholders process. It is possible that new stakeholders became involved in the project, or some of the previous stakeholders left, or the level of engagement of the existing stakeholders have changed. Even if nothing has changed, the Develop Project Charter and the Identify Stakeholders processes should be performed. Otherwise, how would you be able to conclude that nothing has changed? Therefore, starting the new phase of the project with the processes of the Initiating Process Group is the best answer to the question asked. Answer
  • 6. All our questions are updated to the latest  A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a Project Management Institute (PMI)®  Registered Education Provider.