2. You are assigned to manage a project to build five bridges in a metropolitan city. The project is
divided into five sequential phases, with each phase representing the construction of one bridge.
You have just finished the first phase of your project, and you are about to start your second
phase. Which project management process should begin the second phase of the project?
A. Develop Project Charter
B. Develop Project Management Plan
C. Direct and Manage Project Work
D. Monitor and Control Project Work
HINT: Which process group is performed at the beginning of a new project or a new phase of an
existing project?
Question
3. The correct answer is A
The Initiating Process Group is made up of two project management processes, Develop Project Charter and Identify
Stakeholders. The Initiating Process Group is performed to define a new project or a new phase of an existing project by obtaining
authorization to start the project or phase. In the scenario described, you are about to start a new project phase. Therefore, you
should start with the Develop Project Charter process. It does not necessarily mean you would develop a new project charter for
each consecutive project phase, but it means that you will perform the processes of the Initiating Process Group starting with the
Develop Project Charter process. You will review the project charter to see if the high-level assumptions and constraints made
during project initiation are still valid, and whether or not the market conditions are still favorable for the project. Performing this
process may result in an update of the charter or an addendum to the project charter. In an extreme scenario, this process may
result in project termination.
While the A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) does not explicitly mention going back to
the Initiating Process Group to look at the project charter, it does provide several examples implying that the project team may
choose to go with each new phase as a separate, stand-alone project. Undertaking a stand-alone project means performing all its
processes, starting with the Develop Project Charter. The same logic applies to the next process in the Initiating Process Group,
the Identify Stakeholders process. It is possible that new stakeholders became involved in the project, or some of the previous
stakeholders left, or the level of engagement of the existing stakeholders have changed. Even if nothing has changed, the Develop
Project Charter and the Identify Stakeholders' processes should be performed. Otherwise, how would you be able to conclude that
nothing has changed? Therefore, starting the new phase of the project with the Develop Project Charter process is the best
answer to the question asked.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.