The document provides a sample question and answer from the PMP exam. The question asks which process should be performed next after the project charter has been approved for a project investigating the feasibility of constructing a hydroelectric dam. The correct answer is to identify stakeholders. Identifying stakeholders is part of the initiating process group, which should be completed before planning processes. The hint also states that all initiating processes need to be completed before moving to planning.