SlideShare a Scribd company logo
1 of 23
Download to read offline
APPIN MINE HIGH VOLTAGE AND VENTILATION
ARRANGEMENTS
COMPLEXITY IN INTEGRATION
• NOVEMBER 2017
SLIDE 2
•INTRODUCTION
•History of the individual mines
•High Voltage supplies
•Ventilation arrangements
•Ventilation and power interlocking
•Organisational structure to support the High Voltage
and Ventilation infrastructure.
•ILLAWARRA COAL
Bulli
Wollongong
Sydney 50kms
SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 4
•SURFACE INFRASTRUCTURE
• Appin Mine – commenced 1962
• West Cliff Mine – commenced 1976 (Originally Kembla Coal and Coke Pty Ltd).
Purchased by Illawarra Coal in late 1997)
Tower Mine – commenced 1980
• Appin Mine:
• Dual drift configuration with Belt Drift and Single Rope drift winder (dolly car)
• 2 x Vertical Shafts for Remote Fan site with Fans capacity of 276m3/sec.
• Remote Gas drainage plant with capability of 5000l/s.
• 2 Main High Voltage Switchyards. 66KV/6.6KV (1x 10MVA + 3 X 5 MVA )
• Gas driven Electrical Generation plant with capacity of 40MW
• SINGLE MINES INFRASTRUCTURE
CONFIGURATION
• West Cliff Mine:
• M&M Drift Winder Single rope winder (Dolly Car)
• Vertical Shaft (500mts) with Bulk Coal winder(760 TPH)
• Vertical shaft with Auxiliary winch
• 2 Main Fans on Site 11KV 800KW also utilised 5 underground Booster Fans. (Total
installed ventilation power of 6.1MW).
• Gas Drainage plant with capacity of 5000 l/s
• Gas Generation Plant 6 MW Capacity.(Utilising Vent Air Methane)
• 2 Main switchyards 66KV/11 KV (2 x 12.5 MVA) (2x 12.5MVA)
SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 6
•SINGLE MINE CONFIGURATION
• Tower Mine
• 2 x Vertical Shafts with M&M Frictional Winder and Bulk Coal Winder
• 2 x 800 KW Ventilation Fans
• Second remote Main fan site (Vent Shaft 3)
• Gas Drainage Plant with capacity of 5000l/s
• 2 Main Switchyard 66KV/11KV ( 2 x 5.4MVA) + ( 1 x 4.5MVA)
• Gas generation Plant with capacity of 40MW
SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 7
•SINGLE MINE CONFIGURATION
•APPIN MINE
WEST PORTAL
NORTH PORTAL
EAST PORTAL
• Appin Mine joined with Tower Mine prior to the commencement of the Douglas project . This allowed
Appin Mine to extend into the Tower lease and continue to maintain longwall production and coal
extraction via Appin Portal. The Douglas project started in the early 2000.
• At this time Tower Main Fans and BCW were decommissioned. M&M Winder and the Gas extraction
plant continued to operate.
• A new High Voltage switchyard ( 66KV/11KV) was built with 2 x vertical bore holes. This was to allow
maintainability of adequate Electrical fault levels for Appin development and longwall operations.
• AREA 9 project was born in mid 2012: $1Billion Project
• The scope of the project was to create a new mining domain and sustain the production forecasts which
were obtained from Appin Mine (Tower) and West Cliff longwalls.
• There was a requirement for 2 coal clearance corridors hence a connection from West Cliff Area 5 into
Area 7 of Appin to maintain coal stream thru the West Cliff BCW and the current Appin Coal stream from
the new Area 9 to Appin Drift belt.
• Due to the mine workings now moving further away from Main Fan Ventilation the project designed and
built a new vertical shaft with 3 high flow mixed (axial / centrifugal) fans (Vent Shaft 6). This site included
Main High Voltage switchyard, Communications equipment, Site drop holes, compressed air supplies
and Tube Bundle Gas Monitoring equipment. Once this was commissioned and operational VS3 Main
Fans at Appin were returned to Down Cast.
SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 9
•FORMATION OF APPIN MINE THROUGH
MAJOR PROJECT DELIVERY
•APPIN MINE CURRENT OPERATIONAL
CONFIGURATION
The mine has:
• 8 Surface Main ventilation fans.
• Appin East 3 (280m3/s @ 5.4kpa)
• Appin North 2 (1 Operating) 253m3/s @ 2.4kpa
• VS6 3 . (2 Operating) 625m3/s @ 8.5kpa
• 1 Underground Booster Fan (146 m3/s @ 2.8kpa)
• 5 Winders –
• Appin East M&M Drift
• Appin West M& M Shaft
• Appin North M&M Drift
• Appin North Bulk Coal Winder
• Appin North Auxiliary Shaft Winder.
• 9 Surface to Seam power cables – 11kV and 6.6kV 4 via bore hole and 5 via vertical
down cast shafts
• 2 Conveyor streams consisting of ~20 conveyors (2 MW VVVF, TPKL and 1 3MW Slip
Ring Induction / Liquid Resistance Starter)
• 2 gas drainage plants. (Appin West 10000l/s + Appin East 10000l/s)
The mine is configured to operate with 2 operating longwalls and 6 development
panels. Currently reduced to operate with 1 longwall and 1 development unit.
•HIGH VOLTAGE SUPPLIES
•APPIN EAST 66/6.6KV SUBSTATION
• 66 / 6.6kV Supply
• 1 x 10 MVA Transformer
Appin East Pit Top Substation
circa 1960
MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 13
•APPIN EAST 66/6.6 KV FAN SITE SUBSTATION
3 x 5 MVA 66/6.6 KV Tx
• Fed via EDL Power
station
• Ability to “island” the
supply for network
provider outage.
• Ability to “black start”
from GDP supply
Appin East vent Site
Substation circa 1960
•APPIN WEST 66/6.6KV SUBSTATION
• 66/6.6kV Supply
• 2 x 5.4 MVA TX’s
• Fed via EDL Power station
• Ability to “island” the supply for
network provider outage.
• Ability to “black start” from GDP
supply
Appin West Substation
circa 1980
EDL Generation Plant
•APPIN NORTH SUBSTATIONS
• 2 x 2 x 12.5MVA transformers
• 66/11kV Supply
• Internal 66kV supply on mine lease
Appin North Main Substation
circa 1975
Brennans Creek Dam Substation
circa 2008
MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 16
•DOUGLAS PARK NORTH SUBSTATION
• 2 x 12.5MVA transformers
• 66/11kV Supply
• Augmentation through Feeds 66kV
Supply to VS6 via under bore of
Sydney to Canberra Freeway and
southern railway
Douglas Park North Substation
circa 2009
MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 17
•VENT SHAFT 6
Vent Shaft Six Substation circa
2015
• 3 x 6.5MVA transformers
• 66kV/3.3kV/415V Supply
• Supplies 3 x 4.3MW
Surface fans
Appin East Pit Top Substation circa 1960
•Superintendent Automation and Control for Appin Mine
• Electrical Trade
• Electrical Diploma
• Degree in computer Engineering.
• Certified TUF Functional Safety Engineer.
• Primarily Steel Industry and 6 years with Illawarra Coal.
MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 18
•BEN PATON
•VENTILATION ARRANGEMENTS
Fans
• 2 ventilation districts
separated by triple
doors and coffin seal
• VS6: 3 x 3.3kV 4.3MW
VSD Fans (2 duty, 1
standby)
• VS2: 3 x 900KW 6.6kV
DOL Fans
• VS1: 2 x 850KW 11kV
DOL Fans
• North Mains BF: 1 x
1.5MW 11kV DOL Fan
Appin North
Ventilation District
Intertripping
• Failure of VS6 or VS2
trips UG power to
East/West
• Failure of VS1 trips UG
power to North
• Failure of Booster Fan
trips power inbye of the
Booster Fan
Appin East/West
Ventilation District
Booster Fan
VS2
VS1
Doors & Seal
MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 20
•SIL RATED INTERLOCKING SYSTEM
Process:
• Failure Modes and Effects Analysis (FMEA) – multiple iterations
• Layer of Protection Analysis (LOPA) – risk based design methodology
• Defined SIL2 Requirement (Safety Requirements Specification)
• Conceptual (internal) and detailed (external) hardware design
• Software Design (external)
• Installation, testing & commissioning – due to put into service early Dec ’17
System:
• Network of thirteen (13) GuardLogix Safety PLCs connected on dedicated
redundant fibre optic ring
• GuardLogix primarily used for SIL rated communications
• Monitors input signals at fans (triple redundant collar pressure transmitters) and
trips mine feeders and UG circuit breakers
• Required interfacing wiring to fans and feeders while current system in use
MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 21
•SIL RATED INTERLOCKING SYSTEM
• Currently
• 1 statutory Manager for each discipline (Electrical / Mechanical and Mining)
• Each statutory manager has Technical qualified engineers to assist 1 each in the Electrical and
Mechanical area. Mining area is similar but has additional resources to cover for Ventilation and
hence VO officers to assist.
• A new position of Manager Surface infrastructure has been created.
• A surface Superintendent position exists.
• Appin West and VS6 has an Electrical and Mechanical technical engineer for the surface
infrastructure. (Coordinators)
• Appin East and Appin North has an Electrical and Mechanical technical engineer for the surface
infrastructure. (Coordinators)
• Each Portal (Appin North, East and West) has 24/7 rostered coverage for Electrical tradesman
and Day and Afternoon coverage of Mechanical tradesman. Remote Fan sites are covered with
trades from either East and West portals.
MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 22
•ORG STRUCTURE TO SUPPORT HIGH
VOLTAGE
Appin East Pit Top Substation circa 1960
• Special thanks to
• Dave Byrne Manager Electrical Engineering support (2IC)
• Ryan Young Mine Services Electrical coordinator.
• Completing a full review of all Principle Hazard management plans.
• Electrical Control Plan for Appin
• Review of all supporting Standards of Engineering practice.
⎯ Review of content
⎯ Review of legal compliance to legislation.
• Document review to support Departmental TAP inclusive of site interviews and
inspections. (Fire and Explosion)
• Pulling the content together for this presentation.
MARCH 18 SLIDE 23
•THANKYOU

More Related Content

What's hot

83138841 1-1-komponen-jtm
83138841 1-1-komponen-jtm83138841 1-1-komponen-jtm
83138841 1-1-komponen-jtmAgus Supriyanto
 
Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineUlimella Siva Sankar
 
Position Description Mine Geologist 20141124
Position Description Mine Geologist 20141124Position Description Mine Geologist 20141124
Position Description Mine Geologist 20141124Stewart James
 
Resumen nom 020-ener-2011
Resumen nom 020-ener-2011Resumen nom 020-ener-2011
Resumen nom 020-ener-2011Owens Corning
 
Weisbach triangle (1).pptx
Weisbach triangle (1).pptxWeisbach triangle (1).pptx
Weisbach triangle (1).pptxAnkur373212
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous minerSafdar Ali
 
PENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.ppt
PENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.pptPENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.ppt
PENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.pptAdam Superman
 
Study of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous minerStudy of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous minerSafdar Ali
 
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZTYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZANIL KUMAR KUDIRE
 
Caving behaviour in Longwall
Caving behaviour in LongwallCaving behaviour in Longwall
Caving behaviour in LongwallVR M
 
Analysis of subsidence and stability of pillars in a coal mine
Analysis of subsidence and stability of pillars in a coal mineAnalysis of subsidence and stability of pillars in a coal mine
Analysis of subsidence and stability of pillars in a coal minesanjay kumar choudhary
 

What's hot (20)

JARINGAN TEGANGAN RENDAH (JTR)
JARINGAN TEGANGAN RENDAH (JTR)JARINGAN TEGANGAN RENDAH (JTR)
JARINGAN TEGANGAN RENDAH (JTR)
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
POWER SUBSTATION
POWER SUBSTATION  POWER SUBSTATION
POWER SUBSTATION
 
OPERASI SISTEM TENAGA LISTRIK
OPERASI SISTEM TENAGA LISTRIKOPERASI SISTEM TENAGA LISTRIK
OPERASI SISTEM TENAGA LISTRIK
 
83138841 1-1-komponen-jtm
83138841 1-1-komponen-jtm83138841 1-1-komponen-jtm
83138841 1-1-komponen-jtm
 
Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall Mine
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
 
Position Description Mine Geologist 20141124
Position Description Mine Geologist 20141124Position Description Mine Geologist 20141124
Position Description Mine Geologist 20141124
 
Plumbing mensuras-2
Plumbing mensuras-2Plumbing mensuras-2
Plumbing mensuras-2
 
Resumen nom 020-ener-2011
Resumen nom 020-ener-2011Resumen nom 020-ener-2011
Resumen nom 020-ener-2011
 
Weisbach triangle (1).pptx
Weisbach triangle (1).pptxWeisbach triangle (1).pptx
Weisbach triangle (1).pptx
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
 
Canalizaciones
CanalizacionesCanalizaciones
Canalizaciones
 
PENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.ppt
PENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.pptPENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.ppt
PENGOPERASIAN & PEMELIHARAAN JARING DISTRIBUSI TENAGA LISTRIK.ppt
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
Study of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous minerStudy of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous miner
 
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZTYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
 
Caving behaviour in Longwall
Caving behaviour in LongwallCaving behaviour in Longwall
Caving behaviour in Longwall
 
Mecanica de suelos 2
Mecanica de suelos 2Mecanica de suelos 2
Mecanica de suelos 2
 
Analysis of subsidence and stability of pillars in a coal mine
Analysis of subsidence and stability of pillars in a coal mineAnalysis of subsidence and stability of pillars in a coal mine
Analysis of subsidence and stability of pillars in a coal mine
 

Similar to Complexity in integration high voltage and ventilation systems Warwick Young

Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptaryan5808
 
Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...
Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...
Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...Société Française d'Energie Nucléaire
 
Hydropower engineering practical
Hydropower engineering practicalHydropower engineering practical
Hydropower engineering practicalumesh gawande
 
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotMike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotjames hamilton
 
B3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka Iceland
B3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka IcelandB3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka Iceland
B3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka IcelandIceland Geothermal
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futurejames hamilton
 
Avdhehs kumar presention kstps kota
Avdhehs kumar presention kstps kotaAvdhehs kumar presention kstps kota
Avdhehs kumar presention kstps kotaAvdhesh kumar NIET
 
Wind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, coWind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, condkelley
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING Om Prakash
 
Kiet pv presentation
Kiet pv presentationKiet pv presentation
Kiet pv presentationcapricorn_ktl
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptxTalhaAbdulRehman2
 
Presentation transformer and control room thermal power plant jhalawar
Presentation transformer and control room thermal power plant jhalawarPresentation transformer and control room thermal power plant jhalawar
Presentation transformer and control room thermal power plant jhalawarVishalSen33
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngSafdar Ali
 

Similar to Complexity in integration high voltage and ventilation systems Warwick Young (20)

Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training ppt
 
Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...
Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...
Philippe Anglaret the VP Business Development for Alstom Nuclear (Atoms for t...
 
Hydropower engineering practical
Hydropower engineering practicalHydropower engineering practical
Hydropower engineering practical
 
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotMike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
 
B3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka Iceland
B3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka IcelandB3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka Iceland
B3 - KS ORKA: Joint Venture Kaishan China & Hugar Orka Iceland
 
Brian Cowell EDF Energy Chief Nuclear Officer (Atoms for the Future 2013)
Brian Cowell EDF Energy Chief Nuclear Officer (Atoms for the Future 2013)Brian Cowell EDF Energy Chief Nuclear Officer (Atoms for the Future 2013)
Brian Cowell EDF Energy Chief Nuclear Officer (Atoms for the Future 2013)
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-future
 
Avdhehs kumar presention kstps kota
Avdhehs kumar presention kstps kotaAvdhehs kumar presention kstps kota
Avdhehs kumar presention kstps kota
 
Hesham Saafan C.V.1
Hesham Saafan C.V.1Hesham Saafan C.V.1
Hesham Saafan C.V.1
 
Sanitary Pump Station Rehabilitation
Sanitary Pump Station RehabilitationSanitary Pump Station Rehabilitation
Sanitary Pump Station Rehabilitation
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
Wind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, coWind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, co
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
 
Kiet pv presentation
Kiet pv presentationKiet pv presentation
Kiet pv presentation
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
 
Presentation transformer and control room thermal power plant jhalawar
Presentation transformer and control room thermal power plant jhalawarPresentation transformer and control room thermal power plant jhalawar
Presentation transformer and control room thermal power plant jhalawar
 
Ntpc training ppt
Ntpc training pptNtpc training ppt
Ntpc training ppt
 
adi ntpc.pptx
adi ntpc.pptxadi ntpc.pptx
adi ntpc.pptx
 
Vivek ppt
Vivek pptVivek ppt
Vivek ppt
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 

More from NSW Environment and Planning

06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industryNSW Environment and Planning
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)NSW Environment and Planning
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)NSW Environment and Planning
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)NSW Environment and Planning
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...NSW Environment and Planning
 

More from NSW Environment and Planning (20)

12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
 
11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust
 
09 learning from disasters
09 learning from disasters09 learning from disasters
09 learning from disasters
 
13 explosives awareness
13 explosives awareness13 explosives awareness
13 explosives awareness
 
10 incident reporting to the regulator 2020
10 incident reporting to the regulator 202010 incident reporting to the regulator 2020
10 incident reporting to the regulator 2020
 
08 dust safety and health surveillance
08 dust safety and health surveillance08 dust safety and health surveillance
08 dust safety and health surveillance
 
07 feedback and consultation
07 feedback and consultation07 feedback and consultation
07 feedback and consultation
 
06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industry
 
05 reviewing your SMS
05 reviewing your SMS05 reviewing your SMS
05 reviewing your SMS
 
04. slinging and lifting equipment
04. slinging and lifting equipment04. slinging and lifting equipment
04. slinging and lifting equipment
 
Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)
 
Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)
 
Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)
 
Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)
 
Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)
 
Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...
 

Recently uploaded

31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...Christina Parmionova
 
Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!SERUDS INDIA
 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31JSchaus & Associates
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...kajalverma014
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetkumargunjan9515
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Global Network
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfSERUDS INDIA
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...Namrata Singh
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processNAP Global Network
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxScottMeyers35
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCNAP Global Network
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehousesubs7
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCNAP Global Network
 
unang digmaang pandaigdig tagalog version
unang digmaang pandaigdig tagalog versionunang digmaang pandaigdig tagalog version
unang digmaang pandaigdig tagalog versionGLADYSNUEVO1
 

Recently uploaded (20)

31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
 
Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!
 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
unang digmaang pandaigdig tagalog version
unang digmaang pandaigdig tagalog versionunang digmaang pandaigdig tagalog version
unang digmaang pandaigdig tagalog version
 

Complexity in integration high voltage and ventilation systems Warwick Young

  • 1. APPIN MINE HIGH VOLTAGE AND VENTILATION ARRANGEMENTS COMPLEXITY IN INTEGRATION • NOVEMBER 2017
  • 2. SLIDE 2 •INTRODUCTION •History of the individual mines •High Voltage supplies •Ventilation arrangements •Ventilation and power interlocking •Organisational structure to support the High Voltage and Ventilation infrastructure.
  • 4. SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 4 •SURFACE INFRASTRUCTURE
  • 5. • Appin Mine – commenced 1962 • West Cliff Mine – commenced 1976 (Originally Kembla Coal and Coke Pty Ltd). Purchased by Illawarra Coal in late 1997) Tower Mine – commenced 1980 • Appin Mine: • Dual drift configuration with Belt Drift and Single Rope drift winder (dolly car) • 2 x Vertical Shafts for Remote Fan site with Fans capacity of 276m3/sec. • Remote Gas drainage plant with capability of 5000l/s. • 2 Main High Voltage Switchyards. 66KV/6.6KV (1x 10MVA + 3 X 5 MVA ) • Gas driven Electrical Generation plant with capacity of 40MW • SINGLE MINES INFRASTRUCTURE CONFIGURATION
  • 6. • West Cliff Mine: • M&M Drift Winder Single rope winder (Dolly Car) • Vertical Shaft (500mts) with Bulk Coal winder(760 TPH) • Vertical shaft with Auxiliary winch • 2 Main Fans on Site 11KV 800KW also utilised 5 underground Booster Fans. (Total installed ventilation power of 6.1MW). • Gas Drainage plant with capacity of 5000 l/s • Gas Generation Plant 6 MW Capacity.(Utilising Vent Air Methane) • 2 Main switchyards 66KV/11 KV (2 x 12.5 MVA) (2x 12.5MVA) SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 6 •SINGLE MINE CONFIGURATION
  • 7. • Tower Mine • 2 x Vertical Shafts with M&M Frictional Winder and Bulk Coal Winder • 2 x 800 KW Ventilation Fans • Second remote Main fan site (Vent Shaft 3) • Gas Drainage Plant with capacity of 5000l/s • 2 Main Switchyard 66KV/11KV ( 2 x 5.4MVA) + ( 1 x 4.5MVA) • Gas generation Plant with capacity of 40MW SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 7 •SINGLE MINE CONFIGURATION
  • 8. •APPIN MINE WEST PORTAL NORTH PORTAL EAST PORTAL
  • 9. • Appin Mine joined with Tower Mine prior to the commencement of the Douglas project . This allowed Appin Mine to extend into the Tower lease and continue to maintain longwall production and coal extraction via Appin Portal. The Douglas project started in the early 2000. • At this time Tower Main Fans and BCW were decommissioned. M&M Winder and the Gas extraction plant continued to operate. • A new High Voltage switchyard ( 66KV/11KV) was built with 2 x vertical bore holes. This was to allow maintainability of adequate Electrical fault levels for Appin development and longwall operations. • AREA 9 project was born in mid 2012: $1Billion Project • The scope of the project was to create a new mining domain and sustain the production forecasts which were obtained from Appin Mine (Tower) and West Cliff longwalls. • There was a requirement for 2 coal clearance corridors hence a connection from West Cliff Area 5 into Area 7 of Appin to maintain coal stream thru the West Cliff BCW and the current Appin Coal stream from the new Area 9 to Appin Drift belt. • Due to the mine workings now moving further away from Main Fan Ventilation the project designed and built a new vertical shaft with 3 high flow mixed (axial / centrifugal) fans (Vent Shaft 6). This site included Main High Voltage switchyard, Communications equipment, Site drop holes, compressed air supplies and Tube Bundle Gas Monitoring equipment. Once this was commissioned and operational VS3 Main Fans at Appin were returned to Down Cast. SEPTEMBER 2017 APPIN RESTART PROJECT SLIDE 9 •FORMATION OF APPIN MINE THROUGH MAJOR PROJECT DELIVERY
  • 10. •APPIN MINE CURRENT OPERATIONAL CONFIGURATION The mine has: • 8 Surface Main ventilation fans. • Appin East 3 (280m3/s @ 5.4kpa) • Appin North 2 (1 Operating) 253m3/s @ 2.4kpa • VS6 3 . (2 Operating) 625m3/s @ 8.5kpa • 1 Underground Booster Fan (146 m3/s @ 2.8kpa) • 5 Winders – • Appin East M&M Drift • Appin West M& M Shaft • Appin North M&M Drift • Appin North Bulk Coal Winder • Appin North Auxiliary Shaft Winder. • 9 Surface to Seam power cables – 11kV and 6.6kV 4 via bore hole and 5 via vertical down cast shafts • 2 Conveyor streams consisting of ~20 conveyors (2 MW VVVF, TPKL and 1 3MW Slip Ring Induction / Liquid Resistance Starter) • 2 gas drainage plants. (Appin West 10000l/s + Appin East 10000l/s) The mine is configured to operate with 2 operating longwalls and 6 development panels. Currently reduced to operate with 1 longwall and 1 development unit.
  • 12. •APPIN EAST 66/6.6KV SUBSTATION • 66 / 6.6kV Supply • 1 x 10 MVA Transformer Appin East Pit Top Substation circa 1960
  • 13. MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 13 •APPIN EAST 66/6.6 KV FAN SITE SUBSTATION 3 x 5 MVA 66/6.6 KV Tx • Fed via EDL Power station • Ability to “island” the supply for network provider outage. • Ability to “black start” from GDP supply Appin East vent Site Substation circa 1960
  • 14. •APPIN WEST 66/6.6KV SUBSTATION • 66/6.6kV Supply • 2 x 5.4 MVA TX’s • Fed via EDL Power station • Ability to “island” the supply for network provider outage. • Ability to “black start” from GDP supply Appin West Substation circa 1980 EDL Generation Plant
  • 15. •APPIN NORTH SUBSTATIONS • 2 x 2 x 12.5MVA transformers • 66/11kV Supply • Internal 66kV supply on mine lease Appin North Main Substation circa 1975 Brennans Creek Dam Substation circa 2008
  • 16. MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 16 •DOUGLAS PARK NORTH SUBSTATION • 2 x 12.5MVA transformers • 66/11kV Supply • Augmentation through Feeds 66kV Supply to VS6 via under bore of Sydney to Canberra Freeway and southern railway Douglas Park North Substation circa 2009
  • 17. MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 17 •VENT SHAFT 6 Vent Shaft Six Substation circa 2015 • 3 x 6.5MVA transformers • 66kV/3.3kV/415V Supply • Supplies 3 x 4.3MW Surface fans Appin East Pit Top Substation circa 1960
  • 18. •Superintendent Automation and Control for Appin Mine • Electrical Trade • Electrical Diploma • Degree in computer Engineering. • Certified TUF Functional Safety Engineer. • Primarily Steel Industry and 6 years with Illawarra Coal. MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 18 •BEN PATON
  • 19. •VENTILATION ARRANGEMENTS Fans • 2 ventilation districts separated by triple doors and coffin seal • VS6: 3 x 3.3kV 4.3MW VSD Fans (2 duty, 1 standby) • VS2: 3 x 900KW 6.6kV DOL Fans • VS1: 2 x 850KW 11kV DOL Fans • North Mains BF: 1 x 1.5MW 11kV DOL Fan Appin North Ventilation District Intertripping • Failure of VS6 or VS2 trips UG power to East/West • Failure of VS1 trips UG power to North • Failure of Booster Fan trips power inbye of the Booster Fan Appin East/West Ventilation District Booster Fan VS2 VS1 Doors & Seal
  • 20. MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 20 •SIL RATED INTERLOCKING SYSTEM Process: • Failure Modes and Effects Analysis (FMEA) – multiple iterations • Layer of Protection Analysis (LOPA) – risk based design methodology • Defined SIL2 Requirement (Safety Requirements Specification) • Conceptual (internal) and detailed (external) hardware design • Software Design (external) • Installation, testing & commissioning – due to put into service early Dec ’17 System: • Network of thirteen (13) GuardLogix Safety PLCs connected on dedicated redundant fibre optic ring • GuardLogix primarily used for SIL rated communications • Monitors input signals at fans (triple redundant collar pressure transmitters) and trips mine feeders and UG circuit breakers • Required interfacing wiring to fans and feeders while current system in use
  • 21. MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 21 •SIL RATED INTERLOCKING SYSTEM
  • 22. • Currently • 1 statutory Manager for each discipline (Electrical / Mechanical and Mining) • Each statutory manager has Technical qualified engineers to assist 1 each in the Electrical and Mechanical area. Mining area is similar but has additional resources to cover for Ventilation and hence VO officers to assist. • A new position of Manager Surface infrastructure has been created. • A surface Superintendent position exists. • Appin West and VS6 has an Electrical and Mechanical technical engineer for the surface infrastructure. (Coordinators) • Appin East and Appin North has an Electrical and Mechanical technical engineer for the surface infrastructure. (Coordinators) • Each Portal (Appin North, East and West) has 24/7 rostered coverage for Electrical tradesman and Day and Afternoon coverage of Mechanical tradesman. Remote Fan sites are covered with trades from either East and West portals. MARCH 18 GAS DRAINAGE SYSTEM UPGRADE - PHASE 1 SLIDE 22 •ORG STRUCTURE TO SUPPORT HIGH VOLTAGE Appin East Pit Top Substation circa 1960
  • 23. • Special thanks to • Dave Byrne Manager Electrical Engineering support (2IC) • Ryan Young Mine Services Electrical coordinator. • Completing a full review of all Principle Hazard management plans. • Electrical Control Plan for Appin • Review of all supporting Standards of Engineering practice. ⎯ Review of content ⎯ Review of legal compliance to legislation. • Document review to support Departmental TAP inclusive of site interviews and inspections. (Fire and Explosion) • Pulling the content together for this presentation. MARCH 18 SLIDE 23 •THANKYOU