SMALL ANGLE STABILITY: 
Longitudinal Stability
INTRODUCTION 
• In the previous section, we have calculated vertical and 
transverse weight shifts, weight additions, and weight 
removals. In this section we will look at longitudinal weight 
shifts, weight additions, and weight removals. Longitudinal 
problems are done in a different manner because we are 
usually not concerned with the final position of G, but the 
new trim condition of the ship. 
• The consequence of longitudinal shifts, additions, and 
removals of weight is that the ship undergoes a change in 
the forward and after drafts. When the forward and after 
drafts have different magnitudes the ship is said to have 
trim. 
• Trim is defined by the difference between the forward and 
after drafts. 
Trim = Taft - Tfwd
INTRODUCTION Cont. 
• If a ship is "trimmed by the bow," then the forward draft is 
bigger than the after draft. A ship "trimmed by the stern" 
has an after draft bigger than the forward draft. 
•• Recall that the ship rotates about the center of flotation (F) 
which is the centroid of the waterplane area. (It does not 
rotate about midships!) When the centroid of the 
waterplane area is aft of midships the forward draft will 
change by a larger amount than the after draft. This is 
usually the case since a typical ship is wider aft of midships 
than forward of midships.
LONGITUDINAL STABILITY AND TRIM 
• A ship floating at equal draught all along is said to be on an 
even keel, or to have zero trim. If the draughts are not the 
same from bow to stern, the ship is floting with a trim.
LONGITUDINAL STABILITY AND TRIM 
Cont. 
• Two waterlines (or waterplanes) are shown on the ship in 
Figure 1.0; a trimmed waterline (W1L1) and the even keel 
waterline (WL) corresponding to the same displacement. 
They are shown intersecting at the centre of flotation of the 
even keel waterplane. The quantities shown in the figure 
are defined as follows: 
• Centre of Flotation (F): Geometric center of the ship's 
waterline plane. The ship trims about this point. May be 
forward or aft of the midships depending on the ship's hull 
shape at the waterline. 
•• Longitudinal Centre of Flotation (LCF) : Distance from 
the centre of flotation (F) to the midships. Used to 
distribute changes of trim between the fwd and aft 
draughts.
LONGITUDINAL STABILITY AND TRIM 
Cont. 
• Trim (t) : The difference between the forward and after 
draughts 
• Parallel Rise/Sinkage (PR/PS): When weight is 
removed/added from/to a ship at LCF, the forward and aft 
drafts will change by the same amount. Means, no trim 
occur. 
•• Change in Trim (CT): The sum total of the absolute 
values of the change in forward and after drafts. 
• Trimming Arm (d): The distance from the center of 
gravity of the weight to the LCF. If the weight is shifted, (d) 
is the distance shifted.
LONGITUDINAL STABILITY AND TRIM 
Cont. 
• Trimming Moment (TM): Moment about the LCF 
produced by weight additions, removals, or shifts (wd), 
where w is the amount of weight added, removed, or 
shifted. 
• Moment to change Trim One cm (MCTC): The moment 
necessary to produce a change in trim (CT) of one cm. 
Found using the hydrostatic curves. 
• Tons Per cm Immersion (TPC): The number of tons 
added or removed necessary to produce a change in mean 
draft (parallel sinkage) of one cm. Parallel sinkage is when 
the ship changes it’s forward and after drafts by the same 
amount so that no change in trim occurs.
LONGITUDINAL STABILITY AND TRIM 
Cont. 
•TF : Draught forward 
•TA : Draught aft 
•TM : Mean draught at amidships. It is the average of TF and TA. 
••TO : Draught at centre of floation, also called the corresponding 
even keel draught. 
•δTF : Change in draughts forward 
•δTA : Change in draughts after 
• θθ: trim angle 
Figure 2.0 shows more detail on hull geometry and sign conventions adopted in this notes
Figure 2.0
Trim due to Movement of Weights 
ML 
L 
d 
w 
F G1 G W1 L 
B1 B 
1 
W 
L1 
Figure 1.0
Trim due to Movement of Weights 
Cont…… 
• Consider the ship as in Figure 1.0 above, if the weight w is 
moved a distance d meter, G will move to G’’ parallel to the 
direction of movement of w. 
w× × 
d 
Δ 
GG'= w • The shift in weight results in a trimming moment wd and the 
ship will trim until G and B are in line. LCF, the centre of 
floatation is the centre of area of the water plane. For small trim, 
the ship is assumed to be trimming about LCF. The trimming 
moment causes change in trim and hence change in draughts at 
AP and FP.
Trim due to Movement of Weights 
Cont…… 
• Change in trim (CT), 
Change in trim(CT ) = trimming moment 
MCTC 
• Changes in draught forward, δTF and aft, δTA can be obtained 
by dividing trim in proportion to the distance from LCF to the 
y g p p 
positions where the draughts are measured, normally AP and FP.
Trim due to Movement of Weights 
Cont…… 
Amidship 
δTA x 
F 
δTF 
T 
Trim 
T 
TA 
TF 
LBP 
Baseline
Trim due to Movement of Weights 
Cont…… 
• Trim is defined as the difference in the draughts aft and 
forward. 
F A TF TA t = T −T =δ +δ 
• The angle of trim may be expressed as follows 
δ tan = t = TF δ 
= TA 
LBP LBP LBP 
θ 
+ LCF − LCF 
2 2
Trim due to Movement of Weights 
Cont…… 
• Change in draughts forward 
⎟ 
⎟ ⎟ ⎞ 
⎜ ⎜ ⎜ ⎛ 
LBP + 
LCF 
δ = × 
2 
LBP 
t TF 
Ch i d ht ft 
⎟ ⎠ 
⎜ 
⎝ 
⎜ 
• Change in draughts after 
⎟ ⎟ ⎞ 
⎜ ⎜ ⎛ 
LBP − LCF 
2 
⎟ ⎟ ⎠ 
⎜ 
⎝ 
⎜ ⎜ 
= × 
LBP 
t TA 
δ
Small Weight Changes 
• If a small weight w is added or removed from a ship, the 
draught of the ship will change as follows: 
w 
TPC 
Parallel sinkage / rise = Change in trim (CT) trimming moment (TM) w× distance to 
LCF 
MCTC 
= = 
MCTC 
• Once the trim is obtained, the changes δTF and δTA can be 
calculated and the final draughts will include the parallel 
rise/sinkage and δδTF and δδTA.
Exercise 1 
• A ship LBP 100m has MCTC 125 tonne.m while its LCF 
is 2.0 m aft of amidships. Its original draughts are 4.5 m 
at AP and 4.45 m at FP. Find new draughts when a 100 
tonne weight already on board is moved 50 m aft.
Exercise 2 
• A ship LBP 100 m has LCF 3 m aft of amidships and 
floats at 3.2 m and 4.4 m at FP and AP respectively. Its 
TPC is 10 tonne while MCTC 100 tonne.m. 50 tonne 
cargo is removed from 20 m forward of amidships while 
30 tonne is unloaded from cargo hold 15 m aft of 
amidships. Find the final draughts at the perpendiculars.

More Related Content

What's hot (20)

Ship handling
Ship handlingShip handling
Ship handling
 
Stability of ships
Stability of shipsStability of ships
Stability of ships
 
Wk 3 effect of free surface of liquids
Wk 3 effect of free surface of liquidsWk 3 effect of free surface of liquids
Wk 3 effect of free surface of liquids
 
Ship stresses
Ship stresses Ship stresses
Ship stresses
 
MANEUVERING & COLLISION AVOIDANCE
MANEUVERING & COLLISION AVOIDANCEMANEUVERING & COLLISION AVOIDANCE
MANEUVERING & COLLISION AVOIDANCE
 
Preliminary ship-design
Preliminary ship-designPreliminary ship-design
Preliminary ship-design
 
Ship Rudder
Ship RudderShip Rudder
Ship Rudder
 
Ship Motion and Stresses
Ship Motion and StressesShip Motion and Stresses
Ship Motion and Stresses
 
Wk 1 intact stability elementary principles
Wk 1 intact stability elementary principlesWk 1 intact stability elementary principles
Wk 1 intact stability elementary principles
 
Nautical Rules of the Road
Nautical Rules of the RoadNautical Rules of the Road
Nautical Rules of the Road
 
Multi hull vessels
Multi hull vesselsMulti hull vessels
Multi hull vessels
 
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu sajiSHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
 
Parts of ship
Parts of shipParts of ship
Parts of ship
 
Ship Construction (Structure Part)
Ship Construction (Structure Part)Ship Construction (Structure Part)
Ship Construction (Structure Part)
 
Speed over groud vs speed over water
Speed over groud vs speed over waterSpeed over groud vs speed over water
Speed over groud vs speed over water
 
Ship Rudders
Ship RuddersShip Rudders
Ship Rudders
 
Ship´s dimension & types of ships
Ship´s dimension & types of shipsShip´s dimension & types of ships
Ship´s dimension & types of ships
 
Structural members of ship
Structural members of shipStructural members of ship
Structural members of ship
 
Hydrostatics 1 n 2
Hydrostatics 1 n 2 Hydrostatics 1 n 2
Hydrostatics 1 n 2
 
double bottom structure
double bottom structuredouble bottom structure
double bottom structure
 

Viewers also liked

Active management of vessel stability
Active management of vessel stabilityActive management of vessel stability
Active management of vessel stabilityPhilip Corsano
 
HUMAN FACTOR CASES ANALYSIS
HUMAN FACTOR CASES ANALYSISHUMAN FACTOR CASES ANALYSIS
HUMAN FACTOR CASES ANALYSISfarahshafinaz
 
Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...
Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...
Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...alaskalng
 
Regs4ships Presentation 2010
Regs4ships Presentation 2010Regs4ships Presentation 2010
Regs4ships Presentation 2010RichardEastham
 
Sms ii implemention
Sms ii implementionSms ii implemention
Sms ii implementionS P Singh
 
Port management and operations
Port management and operations Port management and operations
Port management and operations Maheshkumar Chande
 
Management Comunication
Management ComunicationManagement Comunication
Management ComunicationDeri
 
آشنایی با انواع شناورها
آشنایی با انواع شناورهاآشنایی با انواع شناورها
آشنایی با انواع شناورهاkmsu
 
Strategic Management in Maritime Ports
Strategic Management in Maritime PortsStrategic Management in Maritime Ports
Strategic Management in Maritime PortsParadigma Consulting
 
On Board Security Risk Management
On Board Security Risk ManagementOn Board Security Risk Management
On Board Security Risk ManagementAnten
 
Draft survey calculation_sheet_2010.1
Draft survey calculation_sheet_2010.1Draft survey calculation_sheet_2010.1
Draft survey calculation_sheet_2010.1Paulo Ricardo
 
Marpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency Regulations
Marpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency RegulationsMarpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency Regulations
Marpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency RegulationsMohammud Hanif Dewan M.Phil.
 
Ship dry docking
Ship dry dockingShip dry docking
Ship dry dockingJishnu Saji
 

Viewers also liked (20)

Active management of vessel stability
Active management of vessel stabilityActive management of vessel stability
Active management of vessel stability
 
Small angle stability
Small angle stability Small angle stability
Small angle stability
 
Cg location
Cg locationCg location
Cg location
 
Motion Response Project pdf
Motion Response Project pdfMotion Response Project pdf
Motion Response Project pdf
 
HUMAN FACTOR CASES ANALYSIS
HUMAN FACTOR CASES ANALYSISHUMAN FACTOR CASES ANALYSIS
HUMAN FACTOR CASES ANALYSIS
 
Safety at Sea May 2012
Safety at Sea May 2012Safety at Sea May 2012
Safety at Sea May 2012
 
Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...
Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...
Maritime Navigational Risk Analysis of Shipping North Slope Liquified Natural...
 
Port management System
Port management System Port management System
Port management System
 
Regs4ships Presentation 2010
Regs4ships Presentation 2010Regs4ships Presentation 2010
Regs4ships Presentation 2010
 
Sms ii implemention
Sms ii implementionSms ii implemention
Sms ii implemention
 
Port management and operations
Port management and operations Port management and operations
Port management and operations
 
Management Comunication
Management ComunicationManagement Comunication
Management Comunication
 
آشنایی با انواع شناورها
آشنایی با انواع شناورهاآشنایی با انواع شناورها
آشنایی با انواع شناورها
 
Strategic Management in Maritime Ports
Strategic Management in Maritime PortsStrategic Management in Maritime Ports
Strategic Management in Maritime Ports
 
Risk Mitigation with Compliance Calendars
Risk Mitigation with Compliance CalendarsRisk Mitigation with Compliance Calendars
Risk Mitigation with Compliance Calendars
 
Communication in Organization
Communication in OrganizationCommunication in Organization
Communication in Organization
 
On Board Security Risk Management
On Board Security Risk ManagementOn Board Security Risk Management
On Board Security Risk Management
 
Draft survey calculation_sheet_2010.1
Draft survey calculation_sheet_2010.1Draft survey calculation_sheet_2010.1
Draft survey calculation_sheet_2010.1
 
Marpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency Regulations
Marpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency RegulationsMarpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency Regulations
Marpol Annex VI Chapter IV- GHG Emissions and Energy Efficiency Regulations
 
Ship dry docking
Ship dry dockingShip dry docking
Ship dry docking
 

Similar to Small angle stability longitudinal

Chp4-1to4-8.ppt
Chp4-1to4-8.pptChp4-1to4-8.ppt
Chp4-1to4-8.pptPhamTtTip
 
Ship construction welding
Ship construction  welding Ship construction  welding
Ship construction welding HIMTFaculty
 
Stability of Fishing Vessels – 3 day training of trainers course
Stability of Fishing Vessels – 3 day training of trainers courseStability of Fishing Vessels – 3 day training of trainers course
Stability of Fishing Vessels – 3 day training of trainers courseFAO
 
[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particulars[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particularsSyaifullah Hamim
 
Midterm Ship Handling and Manuevering 31 Mar 22-1.pptx
Midterm Ship Handling and Manuevering 31 Mar 22-1.pptxMidterm Ship Handling and Manuevering 31 Mar 22-1.pptx
Midterm Ship Handling and Manuevering 31 Mar 22-1.pptxNieLReSpiCiO
 
Hull form geometry
Hull form geometryHull form geometry
Hull form geometryUnikl MIMET
 
02.06b Ch6 PPT Slides.pptx
02.06b Ch6 PPT Slides.pptx02.06b Ch6 PPT Slides.pptx
02.06b Ch6 PPT Slides.pptxRenjuRameshwithu
 
Linea de carga - Diseños de barcos ship desing
Linea de carga - Diseños de barcos ship desingLinea de carga - Diseños de barcos ship desing
Linea de carga - Diseños de barcos ship desingwillianeduardo17
 
NAVAL ARCHITECTURE- GEOMETRY OF SHIP
NAVAL ARCHITECTURE- GEOMETRY OF SHIPNAVAL ARCHITECTURE- GEOMETRY OF SHIP
NAVAL ARCHITECTURE- GEOMETRY OF SHIPSomasundaramRenganat
 
Chp5-part2.ppt
Chp5-part2.pptChp5-part2.ppt
Chp5-part2.pptgksaha2007
 
CHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptx
CHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptxCHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptx
CHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptxGlenChrisCasimiro
 
Stabilitas Pelajaran (1) (introduction).ppt
Stabilitas Pelajaran (1) (introduction).pptStabilitas Pelajaran (1) (introduction).ppt
Stabilitas Pelajaran (1) (introduction).pptIskandarZulkarnain24647
 
Offshore Support Vessels Design
Offshore Support Vessels DesignOffshore Support Vessels Design
Offshore Support Vessels DesignAhmed Taha
 
Stability of Fishing Vessels
Stability of Fishing VesselsStability of Fishing Vessels
Stability of Fishing VesselsFAO
 

Similar to Small angle stability longitudinal (20)

Chp4-1to4-8.ppt
Chp4-1to4-8.pptChp4-1to4-8.ppt
Chp4-1to4-8.ppt
 
Displacemnt
DisplacemntDisplacemnt
Displacemnt
 
Final draft survey
Final draft surveyFinal draft survey
Final draft survey
 
Ship construction welding
Ship construction  welding Ship construction  welding
Ship construction welding
 
Stability of Fishing Vessels – 3 day training of trainers course
Stability of Fishing Vessels – 3 day training of trainers courseStability of Fishing Vessels – 3 day training of trainers course
Stability of Fishing Vessels – 3 day training of trainers course
 
[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particulars[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particulars
 
4318455.ppt
4318455.ppt4318455.ppt
4318455.ppt
 
Midterm Ship Handling and Manuevering 31 Mar 22-1.pptx
Midterm Ship Handling and Manuevering 31 Mar 22-1.pptxMidterm Ship Handling and Manuevering 31 Mar 22-1.pptx
Midterm Ship Handling and Manuevering 31 Mar 22-1.pptx
 
Hull form geometry
Hull form geometryHull form geometry
Hull form geometry
 
02.06b Ch6 PPT Slides.pptx
02.06b Ch6 PPT Slides.pptx02.06b Ch6 PPT Slides.pptx
02.06b Ch6 PPT Slides.pptx
 
Linea de carga - Diseños de barcos ship desing
Linea de carga - Diseños de barcos ship desingLinea de carga - Diseños de barcos ship desing
Linea de carga - Diseños de barcos ship desing
 
NAVAL ARCHITECTURE- GEOMETRY OF SHIP
NAVAL ARCHITECTURE- GEOMETRY OF SHIPNAVAL ARCHITECTURE- GEOMETRY OF SHIP
NAVAL ARCHITECTURE- GEOMETRY OF SHIP
 
Chp5-part2.ppt
Chp5-part2.pptChp5-part2.ppt
Chp5-part2.ppt
 
CHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptx
CHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptxCHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptx
CHAPTER 3_NAS (CASIMIRO & CRISTOBAL).pptx
 
4 ship dimensions
4 ship dimensions4 ship dimensions
4 ship dimensions
 
Stabilitas Pelajaran (1) (introduction).ppt
Stabilitas Pelajaran (1) (introduction).pptStabilitas Pelajaran (1) (introduction).ppt
Stabilitas Pelajaran (1) (introduction).ppt
 
4_1.ppt
4_1.ppt4_1.ppt
4_1.ppt
 
Stabilitas Pelajaran (1).ppt
Stabilitas Pelajaran (1).pptStabilitas Pelajaran (1).ppt
Stabilitas Pelajaran (1).ppt
 
Offshore Support Vessels Design
Offshore Support Vessels DesignOffshore Support Vessels Design
Offshore Support Vessels Design
 
Stability of Fishing Vessels
Stability of Fishing VesselsStability of Fishing Vessels
Stability of Fishing Vessels
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 

Small angle stability longitudinal

  • 1. SMALL ANGLE STABILITY: Longitudinal Stability
  • 2. INTRODUCTION • In the previous section, we have calculated vertical and transverse weight shifts, weight additions, and weight removals. In this section we will look at longitudinal weight shifts, weight additions, and weight removals. Longitudinal problems are done in a different manner because we are usually not concerned with the final position of G, but the new trim condition of the ship. • The consequence of longitudinal shifts, additions, and removals of weight is that the ship undergoes a change in the forward and after drafts. When the forward and after drafts have different magnitudes the ship is said to have trim. • Trim is defined by the difference between the forward and after drafts. Trim = Taft - Tfwd
  • 3. INTRODUCTION Cont. • If a ship is "trimmed by the bow," then the forward draft is bigger than the after draft. A ship "trimmed by the stern" has an after draft bigger than the forward draft. •• Recall that the ship rotates about the center of flotation (F) which is the centroid of the waterplane area. (It does not rotate about midships!) When the centroid of the waterplane area is aft of midships the forward draft will change by a larger amount than the after draft. This is usually the case since a typical ship is wider aft of midships than forward of midships.
  • 4. LONGITUDINAL STABILITY AND TRIM • A ship floating at equal draught all along is said to be on an even keel, or to have zero trim. If the draughts are not the same from bow to stern, the ship is floting with a trim.
  • 5. LONGITUDINAL STABILITY AND TRIM Cont. • Two waterlines (or waterplanes) are shown on the ship in Figure 1.0; a trimmed waterline (W1L1) and the even keel waterline (WL) corresponding to the same displacement. They are shown intersecting at the centre of flotation of the even keel waterplane. The quantities shown in the figure are defined as follows: • Centre of Flotation (F): Geometric center of the ship's waterline plane. The ship trims about this point. May be forward or aft of the midships depending on the ship's hull shape at the waterline. •• Longitudinal Centre of Flotation (LCF) : Distance from the centre of flotation (F) to the midships. Used to distribute changes of trim between the fwd and aft draughts.
  • 6. LONGITUDINAL STABILITY AND TRIM Cont. • Trim (t) : The difference between the forward and after draughts • Parallel Rise/Sinkage (PR/PS): When weight is removed/added from/to a ship at LCF, the forward and aft drafts will change by the same amount. Means, no trim occur. •• Change in Trim (CT): The sum total of the absolute values of the change in forward and after drafts. • Trimming Arm (d): The distance from the center of gravity of the weight to the LCF. If the weight is shifted, (d) is the distance shifted.
  • 7. LONGITUDINAL STABILITY AND TRIM Cont. • Trimming Moment (TM): Moment about the LCF produced by weight additions, removals, or shifts (wd), where w is the amount of weight added, removed, or shifted. • Moment to change Trim One cm (MCTC): The moment necessary to produce a change in trim (CT) of one cm. Found using the hydrostatic curves. • Tons Per cm Immersion (TPC): The number of tons added or removed necessary to produce a change in mean draft (parallel sinkage) of one cm. Parallel sinkage is when the ship changes it’s forward and after drafts by the same amount so that no change in trim occurs.
  • 8. LONGITUDINAL STABILITY AND TRIM Cont. •TF : Draught forward •TA : Draught aft •TM : Mean draught at amidships. It is the average of TF and TA. ••TO : Draught at centre of floation, also called the corresponding even keel draught. •δTF : Change in draughts forward •δTA : Change in draughts after • θθ: trim angle Figure 2.0 shows more detail on hull geometry and sign conventions adopted in this notes
  • 10. Trim due to Movement of Weights ML L d w F G1 G W1 L B1 B 1 W L1 Figure 1.0
  • 11. Trim due to Movement of Weights Cont…… • Consider the ship as in Figure 1.0 above, if the weight w is moved a distance d meter, G will move to G’’ parallel to the direction of movement of w. w× × d Δ GG'= w • The shift in weight results in a trimming moment wd and the ship will trim until G and B are in line. LCF, the centre of floatation is the centre of area of the water plane. For small trim, the ship is assumed to be trimming about LCF. The trimming moment causes change in trim and hence change in draughts at AP and FP.
  • 12. Trim due to Movement of Weights Cont…… • Change in trim (CT), Change in trim(CT ) = trimming moment MCTC • Changes in draught forward, δTF and aft, δTA can be obtained by dividing trim in proportion to the distance from LCF to the y g p p positions where the draughts are measured, normally AP and FP.
  • 13. Trim due to Movement of Weights Cont…… Amidship δTA x F δTF T Trim T TA TF LBP Baseline
  • 14. Trim due to Movement of Weights Cont…… • Trim is defined as the difference in the draughts aft and forward. F A TF TA t = T −T =δ +δ • The angle of trim may be expressed as follows δ tan = t = TF δ = TA LBP LBP LBP θ + LCF − LCF 2 2
  • 15. Trim due to Movement of Weights Cont…… • Change in draughts forward ⎟ ⎟ ⎟ ⎞ ⎜ ⎜ ⎜ ⎛ LBP + LCF δ = × 2 LBP t TF Ch i d ht ft ⎟ ⎠ ⎜ ⎝ ⎜ • Change in draughts after ⎟ ⎟ ⎞ ⎜ ⎜ ⎛ LBP − LCF 2 ⎟ ⎟ ⎠ ⎜ ⎝ ⎜ ⎜ = × LBP t TA δ
  • 16. Small Weight Changes • If a small weight w is added or removed from a ship, the draught of the ship will change as follows: w TPC Parallel sinkage / rise = Change in trim (CT) trimming moment (TM) w× distance to LCF MCTC = = MCTC • Once the trim is obtained, the changes δTF and δTA can be calculated and the final draughts will include the parallel rise/sinkage and δδTF and δδTA.
  • 17. Exercise 1 • A ship LBP 100m has MCTC 125 tonne.m while its LCF is 2.0 m aft of amidships. Its original draughts are 4.5 m at AP and 4.45 m at FP. Find new draughts when a 100 tonne weight already on board is moved 50 m aft.
  • 18. Exercise 2 • A ship LBP 100 m has LCF 3 m aft of amidships and floats at 3.2 m and 4.4 m at FP and AP respectively. Its TPC is 10 tonne while MCTC 100 tonne.m. 50 tonne cargo is removed from 20 m forward of amidships while 30 tonne is unloaded from cargo hold 15 m aft of amidships. Find the final draughts at the perpendiculars.