SlideShare a Scribd company logo
1 of 19
Project Monitoring
Activity
• Name- Kundan Sahadev Sanap
• Roll No. – 202030016
• Subject- Cost Engineering
• Guide- Dr. Vinamra Mishra
Veermata Jijabai Technological Institute,
Matunga
What is Project Monitoring?
• Project monitoring is the process of keeping a
close eye on the entire project management
life cycle and ensuring project activities are
on the right track.
• Monitoring and Controlling are processes
needed to track, review, and regulate the
progress and performance of the project.
Project Monitoring
This Process is concerned with-
• Tracking the project
• Updating the actual work completed
• Updating the actual time taken to complete respective activity
• Comparing Actual project performance with the planned schedule.
• Finally, deciding what should be the changes to improve the project timeline and
get it on time.
Purpose of Project Monitoring
• Rescheduling the project
• Re Budgeting the project
• Re assigning the staff
Benefits of Project Monitoring
• Provides insights into the project progress
• Helps in the better control of the project
• Helps in better co-ordination between team members using different techniques
like team meetings, status reporting
• Helps in managing the data of the project from time to time
Case study of Project Monitoring- Toll Administration Block (G+1)
Case study of Project Monitoring- Toll Administration Block (G+1)
Case study of Project Monitoring- Toll Administration Block (G+1)
Case study of Project Monitoring- Toll Administration Block (G+1)
• Monitoring need to start when you have some progress in hand i.e. some work execution
after planning and scheduling which includes resource allocation and levelling.
Case study of Project Monitoring- Toll Administration Block (G+1)
• For Monitoring we must update the project, steps are as follows:
• Click on the Project tab & in the Status section, choose Update Project.
Case study of Project Monitoring- Toll Administration Block (G+1)
• In the Update Project dialog box, choose Update work as complete through,
and then type or select the date through which you want progress updated.
• Select Set 0% - 100% complete. If you are updating specific tasks, select
Selected Tasks.
Case study of Project Monitoring- Toll Administration Block (G+1)
• So, After updating the project till 10th Jan 2022, the executed work has changed to
52% overall.
Case study of Project Monitoring- Toll Administration Block (G+1)
• But most of the time. the executed work doesn’t coincides with the planning in terms of
duration, so in that case we have to make certain changes about actual dates in order to
monitor the project.
• After updating the project, we have to set the baseline for reference. For that
• Click on the Project toolbar, Schedule section,
• Click on Set Baseline.
• Click Set Baseline & Select the baseline you want to save.
• Click Entire Project.
Case study of Project Monitoring- Toll Administration Block (G+1)
• So, after setting a baseline, to make some changes (if any) in the dates of the activities,
you must open the tracking table. For that,
• Click on the View toolbar, under Data section,
• Click on Tables.
• Click Tracking.
Case study of Project Monitoring- Toll Administration Block (G+1)
• So, after clicking on it, we will be able to see the tracking table in which we can make
changes about the actual start and finish dates.
Case study of Project Monitoring- Toll Administration Block (G+1)
• Here, in this case we can make some changes (in actual start date/ actual finish date) as
per the actual execution of the project and we can see how the project is doing by
comparing it with the baseline.
• So in order to do that, there are some steps to follow:
• Click on the Format toolbar, under Bar Styles section & in Baseline
• Choose the correct baseline that we have set earlier.
Case study of Project Monitoring- Toll Administration Block (G+1)
• So here, as per the execution there are some changes made and are in Red color and after
following the steps mentioned earlier about baseline settings, the Gantt chart turned out like this.
Conclusion
• Project Monitoring helps us to manage things in a better way.
• During execution of project, some resources gets unavailable at point which resulted into
dragging the activity for few more days but, project monitoring helps us to manage the resources
well.
• We can track the work and know where the execution team is lacking and work on those insights
for remaining project for its betterment.
Thank you !!!

More Related Content

What's hot

Project control. Management
Project control. ManagementProject control. Management
Project control. ManagementMarius Miron
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & MonitoringJawad Ahmad
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projectsGlen Alleman
 
Vijay Prasad’S Views On Earned Value Management In Project
Vijay Prasad’S Views On Earned Value Management In ProjectVijay Prasad’S Views On Earned Value Management In Project
Vijay Prasad’S Views On Earned Value Management In Projectdestination
 
Software project-management-tools
Software project-management-toolsSoftware project-management-tools
Software project-management-toolsRashna Maharjan
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMMudassir Iqbal
 
Management Control of Projects
Management Control of ProjectsManagement Control of Projects
Management Control of ProjectsE P John
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plantabhishekthakur309
 

What's hot (19)

Project control. Management
Project control. ManagementProject control. Management
Project control. Management
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Cost
CostCost
Cost
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
Vijay Prasad’S Views On Earned Value Management In Project
Vijay Prasad’S Views On Earned Value Management In ProjectVijay Prasad’S Views On Earned Value Management In Project
Vijay Prasad’S Views On Earned Value Management In Project
 
Project management
Project managementProject management
Project management
 
Software project-management-tools
Software project-management-toolsSoftware project-management-tools
Software project-management-tools
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
 
Management Control of Projects
Management Control of ProjectsManagement Control of Projects
Management Control of Projects
 
CEI-BEI Dashboard
CEI-BEI DashboardCEI-BEI Dashboard
CEI-BEI Dashboard
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Measurement & metrics
Measurement & metricsMeasurement & metrics
Measurement & metrics
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plant
 

Similar to Project monitoring activity

CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxMariaNambahu
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Definition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdfDefinition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdfcalf_ville86
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxkiranroy6777
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxRaoAnkitYadav1
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxRaoAnkitYadav1
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfGagandeepKaur617299
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope ManagementTalha Siddiqui
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management ProjectMary Stevenson
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECTSmit Patel
 
06 Tracking Progress on Tasks
06 Tracking Progress on Tasks06 Tracking Progress on Tasks
06 Tracking Progress on TasksSoe Naing Win
 

Similar to Project monitoring activity (20)

MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Definition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdfDefinition of requirements for each project phases.pdf
Definition of requirements for each project phases.pdf
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
 
Project made easy
Project made easyProject made easy
Project made easy
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptx
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope Management
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
06 Tracking Progress on Tasks
06 Tracking Progress on Tasks06 Tracking Progress on Tasks
06 Tracking Progress on Tasks
 

More from Kundan Sanap

Role of artificial intellligence in construction engg & management
Role of artificial intellligence in construction engg & managementRole of artificial intellligence in construction engg & management
Role of artificial intellligence in construction engg & managementKundan Sanap
 
Roles of gps in high rise buildings construction
Roles of gps in high rise buildings constructionRoles of gps in high rise buildings construction
Roles of gps in high rise buildings constructionKundan Sanap
 
Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge Kundan Sanap
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeKundan Sanap
 
Organizational structure of SAIL
Organizational structure of SAILOrganizational structure of SAIL
Organizational structure of SAILKundan Sanap
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its testsKundan Sanap
 
Forecasting method
Forecasting methodForecasting method
Forecasting methodKundan Sanap
 
Project management information system (PMIS)
Project management information system (PMIS)Project management information system (PMIS)
Project management information system (PMIS)Kundan Sanap
 
Environmental impact assessment case study
Environmental impact assessment case studyEnvironmental impact assessment case study
Environmental impact assessment case studyKundan Sanap
 
Case study on flexible pavement failures
Case study on flexible pavement failuresCase study on flexible pavement failures
Case study on flexible pavement failuresKundan Sanap
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge constructionKundan Sanap
 

More from Kundan Sanap (11)

Role of artificial intellligence in construction engg & management
Role of artificial intellligence in construction engg & managementRole of artificial intellligence in construction engg & management
Role of artificial intellligence in construction engg & management
 
Roles of gps in high rise buildings construction
Roles of gps in high rise buildings constructionRoles of gps in high rise buildings construction
Roles of gps in high rise buildings construction
 
Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
Organizational structure of SAIL
Organizational structure of SAILOrganizational structure of SAIL
Organizational structure of SAIL
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its tests
 
Forecasting method
Forecasting methodForecasting method
Forecasting method
 
Project management information system (PMIS)
Project management information system (PMIS)Project management information system (PMIS)
Project management information system (PMIS)
 
Environmental impact assessment case study
Environmental impact assessment case studyEnvironmental impact assessment case study
Environmental impact assessment case study
 
Case study on flexible pavement failures
Case study on flexible pavement failuresCase study on flexible pavement failures
Case study on flexible pavement failures
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge construction
 

Recently uploaded

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 

Recently uploaded (20)

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 

Project monitoring activity

  • 1. Project Monitoring Activity • Name- Kundan Sahadev Sanap • Roll No. – 202030016 • Subject- Cost Engineering • Guide- Dr. Vinamra Mishra Veermata Jijabai Technological Institute, Matunga
  • 2. What is Project Monitoring? • Project monitoring is the process of keeping a close eye on the entire project management life cycle and ensuring project activities are on the right track. • Monitoring and Controlling are processes needed to track, review, and regulate the progress and performance of the project.
  • 3. Project Monitoring This Process is concerned with- • Tracking the project • Updating the actual work completed • Updating the actual time taken to complete respective activity • Comparing Actual project performance with the planned schedule. • Finally, deciding what should be the changes to improve the project timeline and get it on time.
  • 4. Purpose of Project Monitoring • Rescheduling the project • Re Budgeting the project • Re assigning the staff
  • 5. Benefits of Project Monitoring • Provides insights into the project progress • Helps in the better control of the project • Helps in better co-ordination between team members using different techniques like team meetings, status reporting • Helps in managing the data of the project from time to time
  • 6. Case study of Project Monitoring- Toll Administration Block (G+1)
  • 7. Case study of Project Monitoring- Toll Administration Block (G+1)
  • 8. Case study of Project Monitoring- Toll Administration Block (G+1)
  • 9. Case study of Project Monitoring- Toll Administration Block (G+1) • Monitoring need to start when you have some progress in hand i.e. some work execution after planning and scheduling which includes resource allocation and levelling.
  • 10. Case study of Project Monitoring- Toll Administration Block (G+1) • For Monitoring we must update the project, steps are as follows: • Click on the Project tab & in the Status section, choose Update Project.
  • 11. Case study of Project Monitoring- Toll Administration Block (G+1) • In the Update Project dialog box, choose Update work as complete through, and then type or select the date through which you want progress updated. • Select Set 0% - 100% complete. If you are updating specific tasks, select Selected Tasks.
  • 12. Case study of Project Monitoring- Toll Administration Block (G+1) • So, After updating the project till 10th Jan 2022, the executed work has changed to 52% overall.
  • 13. Case study of Project Monitoring- Toll Administration Block (G+1) • But most of the time. the executed work doesn’t coincides with the planning in terms of duration, so in that case we have to make certain changes about actual dates in order to monitor the project. • After updating the project, we have to set the baseline for reference. For that • Click on the Project toolbar, Schedule section, • Click on Set Baseline. • Click Set Baseline & Select the baseline you want to save. • Click Entire Project.
  • 14. Case study of Project Monitoring- Toll Administration Block (G+1) • So, after setting a baseline, to make some changes (if any) in the dates of the activities, you must open the tracking table. For that, • Click on the View toolbar, under Data section, • Click on Tables. • Click Tracking.
  • 15. Case study of Project Monitoring- Toll Administration Block (G+1) • So, after clicking on it, we will be able to see the tracking table in which we can make changes about the actual start and finish dates.
  • 16. Case study of Project Monitoring- Toll Administration Block (G+1) • Here, in this case we can make some changes (in actual start date/ actual finish date) as per the actual execution of the project and we can see how the project is doing by comparing it with the baseline. • So in order to do that, there are some steps to follow: • Click on the Format toolbar, under Bar Styles section & in Baseline • Choose the correct baseline that we have set earlier.
  • 17. Case study of Project Monitoring- Toll Administration Block (G+1) • So here, as per the execution there are some changes made and are in Red color and after following the steps mentioned earlier about baseline settings, the Gantt chart turned out like this.
  • 18. Conclusion • Project Monitoring helps us to manage things in a better way. • During execution of project, some resources gets unavailable at point which resulted into dragging the activity for few more days but, project monitoring helps us to manage the resources well. • We can track the work and know where the execution team is lacking and work on those insights for remaining project for its betterment.