SlideShare a Scribd company logo
1 of 38
EIA Report for
The Building & Construction Project “Parshwa Luxuria” at S. P. No.
133/1/A, R. S. No. 118/2/1, 118/2/2, 118/3, 118/4 & 119, Bodakdev,
City West, District Ahmedabad, Gujarat. JANUARY 2019
Submitted By
Kundan S. Sanap- 202030016
Akshay P. Jadhav- 202030017
Veermata Jijabai Technological Institute,
Matunga
Table of Content
• Purpose of the study
• Project Description
• Environmental Baseline
• Land use and Land Cover
• Air Environment
• Noise Environment
• Surface Water Environment
• Groundwater Environment
• Soil
• Ecology & Biodiversity environment
• Socio-economic environment
• Potential Environmental Impacts & Mitigation Measures
• Environmental Monitoring Programme
• Project Benefits
• Conclusion
Purpose of the study
• The purpose of the EIA study is
1. To identify existing environmental condition
2. To predict environmental impacts associated with the proposed project
3. To suggest measures to mitigate the adverse impacts and to delineate a comprehensive
environment management plan along with recommendations and suggestions.
4. The different activities that are likely to take place have been identified and mitigation measures
have been proposed
Project Description
• Type of project: - The project falls under Category B of item 8(a) of Schedule of the EIA
Notification 2006 amended till now as Building and Construction projects require prior EC from
the SEIAA, Gujarat.
• Nature: - Building and Construction project (Residential Building)
• Cost of project: - The total Project cost is ~ INR 105 Crore from which the Land cost is ~ INR 35
Crore and the construction cost is ~ INR 70 Crore.
• Connectivity to project site
• By Road: -
• The project site is located on Iscon-Ambli road, Bodakdev, City West, Ahmedabad. Ambli road is ~
0.4 km in S direction & Sindhu bhavan road is ~1.0 km in N direction from the project site. Sardar
Patel Ring Road is ~ 1.2 km in W direction & SG Highway is ~ 1.9 km in E direction from the project
site.
• By Rail: -
• The nearest railway station is Ambli road railway station ~ 2.40 km in NNE direction &
Ahmedabad Central railway station is ~ 11.46 km in ESE direction from the project site
• By Air: -
• Sardar Vallabhbhai Patel International Airport is ~ 14.0 km in ENE direction from the project site
Project Description
• Location-
• The project site is located in Bodakdev, City West, Dist. Ahmedabad, Gujarat.
Project Description
• Location-
• The project site is located at F. P. No.: 133/1/A, R. S. No.: 118/2/1, 118/2/2, 118/3, 118/4 & 119,
Bodakdev, City West, District Ahmedabad.
Project Description
• Study Area- Project site with study area of 10 km
Project Description
• Project Layout Plan: -
Project Description
• Size or Magnitude of Operation: -
• The project have
• total plot area of 6582.76 m2
• Built-up area of 35,734.41 m2.
• The project consists of two building blocks of 48 residential units each.
• Green Belt: -
• Total area for greenbelt development = 660.78 m2 (i.e. >10% of total plot area)
• Area provided for tree plantation = 150 m2 (100 number of trees)
• Area provided for small shrubs & lawns = 510.78 m2
Environmental Baseline
• The baseline environmental quality was assessed through field studies within the impact zone for
various components of the environment with specific reference to environmental aspects, which
may have a bearing on the impacts of the proposed project. The components are listed below:
• Land use and Land Cover
• Air Environment
• Noise Environment
• Surface Water Environment
• Groundwater Environment
• Soil
• Socio-economic environment
• Ecology & Biodiversity environment.
Land use and Land Cover Pattern of Study Area
• Built-up Land or Habitation: -
• Residential/Commercial:
• This is the major class in the study area covering ~ 30 % of total study area. Major city is
Ahmedabad. Santej, Bopal, Shela, Sola, etc. are upcoming fast growing rural to urban areas.
• Industrial Area:
• This class covers ~ 2.5 % of total study. Industrial areas are located at Village Rakanpur,
Santej and along NH-8C near areas Santipura, Chandlodiya, Gota etc.
• Agricultural Land: -
• Crop Land:
• Agricultural land covers ~ 26 % of study area. Agriculture crops such as rice, jowar, wheat,
fodder, castor etc. is cultivated in study area.
• Plantation:
• Eucalyptus plantations were seen near Bhadaj and Telav.
• Vegetation Cover: -
• The study area has ~30 % of vegetation cover. Dominant vegetation is prosopis.
• Wasteland: -
• The study area has ~11 % of total area under wastelands which is mainly land without scrub.
Land use and Land Cover Pattern of Study Area
• Water bodies:
• It is observed that ponds are present mostly in all the villages and places within the study
area.
• River Sabarmati is the major one flowing from ENE to SSE direction in the study area,
• however, Chandrabhaga Nadi forming the minor one in the study area.
• Others:
• Few patches of grassland are present in Sabarmati riverbed.
Ambient Air Quality
• Ambient Air Monitoring was conducted at Six (6) different locations within the study area.
• The frequency of monitoring was 24 hours twice a week at each station spread over one month
with gaseous sample being changed two times (at 8 hour intervals).
• The parameters monitored were Particulate matter (PM10, PM2.5), Sulphur Dioxide (SO2),
Oxides of Nitrogen (NOx), Carbon Monoxide (CO) and Hydrocarbon-HC (as Methane)
• Selected Six Location:
Code Location Coordinates
Distance from
Site (Km)
Direction from
site
Justification
AAQ01 At project Site
23°01'56.08"N
72°29'20.94"E 0 Base
Selected as base
station
AAQ02
Anand Nagar,
off SG Highway
23°00'57.23"N
72°30'33.63"E
2.73 SE
1st predominant
downwind station
AAQ03 Shilaj Village
23°3'17.38"N
72°28'10.08"E 3.23 NW
1st predominant
upwind station
AAQ04 Bopal Village
23°2'1.84"N
72°27'28.18"E 3.23 W
2nd predominant
upwind station
AAQ05
Akar Society,
Vastrapur
23°1'48.16"N
72°31'32.58"E 3.74 E
2nd predominant
downwind station
AAQ06 Santej Village
23°6'3.59"N
72°29'2.71"E 7.65 N Crosswind station
Ambient Air Quality
• Ambient Air Quality Results:
• The comparison of the results with the value range indicators NAAQ standards 2009
provided by CPCB(Central Pollution Control Board) for Industrial, residential, rural &
other area indicates:
• At various locations, average concentration of PM10 was observed to be varying from 101 to
166 µg/m3 . Average concentration of PM10 levels are exceeding the permissible limits at all
locations(100 µg/m3). The reason for higher PM10 concentration would be vehicular
emissions and traffic congestion in the urban areas while fuel wood or biomass burning
for cooking in rural areas.
• Average concentration of PM2.5 levels was observed to be in range of 30 to 50 µg/m3 which
is less than the permissible limits(60 µg/m3) for all locations.
• Average concentration of SO2 levels was observed to be in the range of 12.5 to 17.0 µg/m3
which is within the specified limit(80 µg/m3) of CPCB.
• NOx levels were observed to be in the range of 17.1 to 19.2 µg/m3 which is within the
specified limit(80 µg/m3) of CPCB.
• CO levels were observed in the range of 1.223 to 1.523 mg/m3 which is within the specified
limit(4 mg/m3) of CPCB.
Noise Level Monitoring
• Monitoring of noise is done by identifying suitable number of noise quality monitoring locations.
• Sampling Location Details: 5 Locations Selected
Station
Code
Noise Monitoring
Locations
Category of
Area / Zone
Coordinates
Distance between Nearest
Boundaries w.r.t. Project
Site in Km
Direction w.r.t.
Project Site
NL1
Greenbelt area (North)
of Project site
Residential
23⁰01'57.0"N
72⁰29'21.1"E
0.0 Base Station
NL2 Centre of project site Residential
23⁰01'55.0"N
72⁰29'21.3"E
0.0 Base Station
NL3
100 meter (East) from
center of project site Residential
23° 1'57.30"N
72°29'31.51"E 0.1 East
NL4
500 meter from (West)
center of project site
Residential
23⁰01'50.2"N
72⁰28'58.1"E 0.5 West
NL5
1 KM from center of
project site (SW)
Residential
23° 1'20.11"N
72°29'26.82"E
1.0 South West
Noise Level Monitoring
• Results: Readings were taken at five different locations within the study area.
• The baseline average noise levels are presented in table below:
• Noise level during daytime & during night time, in residential area was observed higher than the CPCB
standards i.e., Residential area (55 dBA (d) & 45 dBA (n)) which is due to vehicular movements.
Station
Code
Noise Monitoring
Locations
Category of
Area / Zone
CPCB Limits in
dB (A)
Baseline average Noise
levels in dB (A)
Day Time Night Time Day Time Night Time
NL1
Greenbelt area (North)
of Project site Residential 55.0 45.0 62.0 53.4
NL2
Centre of project site
(garden area) Residential 55.0 45.0 59.4 52.6
NL3
100 meter (East) from
center of project site Residential 55.0 45.0 54.0 44.9
NL4
500 meter from (West)
center of project site
Residential 55.0 45.0 62.4 54.7
NL5
1 KM from center of
project site (SW) Residential 55.0 45.0 64.2 53.9
Surface Water Quality
• Water samples were collected during the baseline study period. The details of surface water
sampling, analysis results and observations of baseline water quality are given further in detail.
• Surface water sampling locations area selected based on review of land use plan, surface drainage
pattern/ground water flow direction & nearby site habitation village/locations in 10 km radius of
the project.
Code Location Source
Distance from
Project Site in
Km
Direction
w.r.t Project
Site
Latitude (N)
Longitude (E)
Juscation of Sample
collection
SW 1 Sabarmati (U/s) River 9.2 ESE
23˚00’33.6” N
72˚31’32.4” E To know the quality of
flowing water body
passing from study area
SW 2 Sabarmati (D/s) River 8.57 SE
22˚59’20.2” N
72˚33’31.3” E
SW 3 Santej Pond 7.9 N
23˚6’11.98” N
72˚28’59.84” E
To know the quality of
stagnant water bodies
coming in the study area
SW 4 Bopal Pond 3.22 WNW
23˚2’18.56” N
72˚27’31.16” E
SW 5 Thaltj Pond 3.14 NE
23˚3’2.68” N
72˚30’42.49” E
SW 6 Vastrapur Lake Dry Lake 4 ENE
23˚02’19.67” N
72˚31’43.31” E
Surface Water Quality
• Observation of Surface Water Quality: The baseline quality of surface water based on the results of
the surface water quality monitoring within the study area, it is observed that,
• In Santej pond TDS, Electrical conductivity, Total Hardness, Mg++ Hardness, Chlorides and
Ammonical Nitrogen value are observed higher than the limits given in standards.
• Bopal Pond BOD value, Total Hardness, Mg++ Hardness and Chlorides value are observed higher
than the acceptable limits.
• In Thaltej Pond Total Hardness, Mg++ Hardness and Ammonical Nitrogen value are observed higher
than the acceptable limits.
• In river water Ammonical nitrogen & chlorides are slightly high.
• Based on visual observation and analytical results it can be conclude that the overall water quality
including river and pond water are polluted due to discharge of city wastewater and other wastes
discharge into the surface water body.
• The above observation shows that
• pond water of SW3, SW4, and SW5 are polluted source where 3-6 parameters > acceptable limits,
• whereas SW1 & SW2 i.e. river water is least polluted source compared to pond water.
• The overall water quality is compared with class E as per classification of Inland Surface Water
Standard and it can be used for irrigation and industrial cooling. If there is no alternate source for
drinking purpose, treatment of surface water is essential before using for any purposes.
Groundwater Quality Monitoring
• The samples were manually collected and analyzed as per APHA(American Public Health
Association) standard Methods (22nd Edition, 2017) for the parameters given in EIA Manual of
MoEF (Sept 2006).
• Groundwater Sampling Locations: 7 Locations
Code Location Source Distance
Direction
W.r.t site
GW 1 Bopal Tube-well 2.80 km West
GW 2 Shilaj Tube-well 3.05 km NW
GW 3 Santej Tube-well 8.49 km NNW
GW 4 Sola Tube-well 5.38 km NE
GW 5 Thaltej Tube-well 2.49 km NE
GW 6 Sarkhej Tube-well 5.57 km SSE
GW-7 Telav Tube-well 8.34 km SW
Groundwater Quality Monitoring
• Observation of Groundwater Quality: The baseline quality of groundwater based on the results of
the Groundwater quality monitoring within the study area, it is observed that,
• TDS is found exceeding the permissible limit more than 2000 mg/lit at Sarkhej (GW-06)
and Telav (GW-07), while the range is between 1198 mg/lit (GW-04: Sola) to 1612 mg/lit
(GW-01: Bopal).
• Chlorides is found near to permissible limit(1000mg/lit) ~ 955 mg/lit at Telav (GW-07).
• Sulphates is exceeding permissible limit more than 400 mg/lit at Sarkhej (GW-06) and
Telav (GW-07).
• Magnesium is also exceeding permissible limit higher than 100 mg/lit at Telav (GW-07).
• Iron content are found higher than desirable limit(0.3 mg/lit) at all locations.
Soil Quality & Characteristics
• A field visit conducted to study site-specific soil quality and condition includes soil texture
mineralogical content, plasticity & possible impact to the environmental setting due to project.
• Soil Sampling: Randomly selected locations
• The soil samples from 0-15 cm depth were collected by using spade and pawada.
• samples were homogenized and about 1 Kg soil sample was collected in the polyethylene bag, labelled
with sample ID & were brought to the laboratory for analysis of physical and chemical properties
Sr. No. Sampling Location Soil texture Lat. & Long.
From the project site
Dir. Dist.
ST01 Bopal village Sandy loam
23° 1'55.31"N
72°27'52.83"E
W 2.4
ST02 Shilaj village Sandy loam
23˚03'18.0"N
72˚28'21.3"E
NW 3.2
ST03 Santej village Loam
23˚06'24.9" N
72˚28'13.7" E
NNW 8.4
ST04 Sola village Sandy loam
23˚04'05.5" N
72˚31'27.1" E
NE 5.3
ST05 Thaltej village Sandy loam
23˚03'26.4" N
72˚30'15.49" E
NNE 3.1
ST06 Bodkdev (At site) Loamy sand
23° 1'55.50"N
72°29'20.84"E
- 0
ST07 Sarkhej village Sandy clay loam
22˚58'54.54" N
72˚30'11.32" E
SE 5.7
ST08 Telav village Sandy loam
22˚59'54.28" N
72˚26'28.56" E
SW 6.1
Soil Quality & Characteristics
• Soil Quality Results:
• The analysis of physicochemical properties of soil samples collected from surrounding area
indicated that,
• Porosity ranged from 35 –56 % and WHC (Water Holding Capacity) varied from 43.17 – 62.4 %, while
permeability ranged from 17.7 – 62.4 mm/hr. The high permeability was on account of sandy to sandy
clay loam texture of soils.
• The EC(Electrical Conductivity) ranged from 0.641 to 1.105 dS/m indicating that soils are normal
(EC<1.0 dS/m) to saline (>EC<1.0 dS/m) and ESP(Exchangeable Sodium) (0.37 to 3.52) was well within
the safe limit of <15.
• The pH ranged from 7.13 – 7.36, indicating that soils are normal (pH = 6.5 to 7.8).
• Among water soluble cations predominance of Na (0.58 to 1.78 g/kg) was seen followed by Ca (0.37 to
1.25 g/kg), Mg (0.01 to 0.45 g/kg) and K (0.16 to 0.42 g/kg).
Ecology and Biodiversity
• This section represents existing biodiversity status of the project site (core zone) and its
surrounding environment of the project study area (buffer zone of 10 km radius).
• Field Data Collection & Observation: -
• After the plot survey it is found that, there is lot of diversity when it comes to the flora and fauna in and
around the study area.
• no rare and endangered flora was observed.
• Among floral species, none of the species can be designated as threatened species. For the recorded
faunal species, none of the species can be designated as an endemic.
Socio-Economics
• This section analyses the existing socio-economic conditions of the habitations as well
as community residing in the project area.
• It also identifies the potential issues and problems in the area. For the design of project,
stakeholder views were taken through the structured questionnaires and focus group
discussions.
Potential Environmental Impacts & Mitigation Measures
• Environmental impacts have been identified based on an assessment of environmental aspects
associated with the project. So, both positive and negative impacts are mentioned below along with
the impacting activities:
• Land use/Land cover:
• Impacts
• Land procurement and site preparation.
• Generation of earth/debris and change in topography of the site due to cutting & filling.
• Betterment of overall land cover characteristics both aesthetically as well as ecologically
• Mitigation measures
• Establish and clearly document land usage permission.
• Clearance of vegetation limited to project footprint.
• Landscape development within site.
• Use of excavated earth for backfilling.
• Storage of top soil separately and its reuse for greenbelt within the site.
Potential Environmental Impacts & Mitigation Measures
• Air quality:
• Impacts
• SPM generation and emission of HC & CO due to Vehicle movement during site preparation
• Dust generation during construction activities and restoration
• Emission of SPM, SO2, NOx, HC & CO due to operation of DG sets.
• Mitigation measures
• PUC (Pollution Under Control) certified all cars /vehicles shall be allowed to enter.
• Vehicular emission can be mitigated by strictly following traffic management plan at site. Also by
maintaining the roads and by controlling speed limit.
• Dust and air emission can be controlled by development of greenbelt / green cover.
• Periodic air quality monitoring will be carried out at project site and other location within study
area.
• Sprinkling of water can be carried out for dust suppression.
• Adequate stack height of 2.0 m will be provided for emission from DG
Potential Environmental Impacts & Mitigation Measures
• Noise:
• Impacts
• Noise due to Vehicle movement during site preparation and occupants
• Noise during operation of construction equipment / machineries.
• Mitigation measures
• Use of well-maintained equipment, machinery and vehicles to avoid generation of high noise.
• Provision of personnel protective equipment (PPEs) like ear plugs/muffs for all the workers at site and
ensuring that the same wore by everybody during construction work.
• Noise to be monitored in ambient air within the premises.
Potential Environmental Impacts & Mitigation Measures
• Surface Water:
• Impacts
• Water resources depletion due to water consumption due to domestic use
• surface water contamination due to generation, handling & disposal of wastewater.
• Mitigation measures
• Separate drainage will be proposed for storm water and for sewage to avoid run off contamination as
well as any contamination of surface water sources.
• Care shall be taken to reduce water consumption by providing water conservation measures.
• Drip irrigation system will be proposed to reduce fresh water demand for gardening.
Potential Environmental Impacts & Mitigation Measures
• Ground water:
• Impacts
• Ground water contamination due to storage, handling & disposal of wastewater.
• Mitigation Measures
• The ground water occurs under confined conditions under the alternate layers of clay and
sand in study area, the proper zone of formation need to be recharge.
• For which, 02 recharge wells are installed. It is further assumed that, this recharge-well will
improve the present ground water conditions.
• Rainwater harvesting to recharge the ground water has been proposed at site.
• Such activity will reflect in improvement of ground water conditions and sustainability of
recharge structure.
Potential Environmental Impacts & Mitigation Measures
• Soil:
• Impacts
• Soil erosion due to Clearance of vegetation during site preparation,
• Loss in soil fertility due to levelling and Changes in natural topography due to excavation
• Soil Contamination due to storage and handling of solid waste.
• Control over soil erosion due to green belt.
• spillage of solid waste may deteriorate soil quality
• Mitigation Measures
• Spillage of construction materials was avoided to prevent soil contamination and
deterioration on soil quality.
• Spillage of oil, diesel etc. was minimized to avoid soil contamination.
• During excavation, top soil was reused in a stretch of 150 m long & 1.5 m wide along 18 m wide
road on north side of the project site.
Potential Environmental Impacts & Mitigation Measures
• Socio – Economic:
• Impacts
• Positive impact due to creation of jobs and increase in indirect income.
• Mitigation Measures
• The project will provide short term employment opportunities to the local people.
Potential Environmental Impacts & Mitigation Measures
• Ecology and Biodiversity:
• Impacts
• Negative impacts due to clearance of vegetation during site preparation
• barrier to faunal movement due to construction of building structure
• impact on flora & fauna due to vehicle movements
• disturbance to nocturnal fauna & flying patterns of birds due to artificial illumination of project
• positive impact plantation during landscaping & greenbelt development.
• Mitigation Measures
• Maximum trees will be included in the green belt area which will support existing faunal
biodiversity.
• Artificial illumination will be kept in suitable direction and light will be switched off in less time
duration at night.
• For the impact on flora & fauna, No immediate action required because all local species from
project site would be common as reported from nearby environment and well adapted to the
routine urban activities, so they would not face significant impact on their normal movements.
Potential Environmental Impacts & Mitigation Measures
• Occupational health, Community Health and Safety:
• Impacts
• Health & safety risk/hazard to workers due to various construction activities
• Beneficiary effect on occupational health due to landscaping & Greenbelt development.
• Mitigation Measures
• Workers were given all the safety items such as safety helmets, safety belts, jackets, etc. to be safe
from any kind of injuries while doing construction activities.
Environmental Monitoring Programme
• The regular monitoring of environmental parameters is of immense importance to assess the status
of environment during project operation.
• With the knowledge of baseline conditions, the monitoring program will serve as an indicator for
any deterioration in environmental conditions due to operation of the project, to enable taking up
suitable mitigation measures in time to safeguard the environment.
• Environmental Monitoring Plan;
• Air Environment-
• Once in every six months
• At main Gate- Readings to be taken for Ambient air quality monitoring for PM10, PM2.5,
SO2, NOx in ambient and within project premises & comparing them to Permissible values.
• At DG Set- Stack air monitoring for SPM, SO2, NOx, HC & CO in stack of DG set &
comparing them to Permissible values
Environmental Monitoring Programme
• Noise Environment-
• Once in every six months
• At Project site(Various Locations)- Ambient Noise level during day and night time & comparing
them to Permissible values
• Water Environment-
• Once in every six months
• At Project site- One ground water sample of recharge well (Essential parameters as per IS:
10500:1991) & comparing them to Permissible values.
• Solid & Hazardous Waste-
• Once in every week
• At Project site- Solid waste (MSW) Generation, handling, storage and disposal & record
review for random checks for site in-charge.
Project Benefits
• During construction phase direct employment opportunity was created for contractor, laborers
and workers, indirect employments in transportation and construction allied sectors
• During operation phase, long-term job opportunities will be created in terms of security,
housekeeping and gardening personnel which will lead to increase their living standard.
• Exposure of modernized infrastructural & technological facilities due to proposed project
activities will helpful to boost knowledge of employees, workers, locals
• 10% of the plot area is being developed as landscape area /green belt, which will enhance the
beauty and aesthetics of the project area.
• Good solid waste management system consisting of proper collection, designated storage,
provision of composting facility for bio degradable waste disposal.
• Project will set a good example for surrounding area about good solid waste management
system consisting of proper collection, storage & disposal facility.
• Adequate parking space for residents and visitors.
Conclusion
• It can be concluded on a positive note that due to the adequate provision and efficient operation
of proposed environmental management systems and mitigation measures, the project activities
during the operation phase would have manageable & largely have reversible impacts on the
environment and on balance the project would be beneficial to surrounding communities and the
region.
The End

More Related Content

What's hot

Environmental impact assessment and Initial Environmental Examination
Environmental impact assessment and Initial Environmental ExaminationEnvironmental impact assessment and Initial Environmental Examination
Environmental impact assessment and Initial Environmental ExaminationKinza Irshad
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projectsSandeep Kumar
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentSayyid Ina
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
EIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVEREIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVERvikas rahangdale
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureKANTHARAJAN GANESAN
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTgoswamikusum
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5Bibhabasu Mohanty
 
Eia - environmental impact assessment
Eia - environmental impact assessmentEia - environmental impact assessment
Eia - environmental impact assessmentParth Patel
 
Methods of prediction and assessment techniques of impacts soil
Methods of prediction and assessment techniques of impacts soilMethods of prediction and assessment techniques of impacts soil
Methods of prediction and assessment techniques of impacts soilAbhilasha Tripathi
 
Eia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationEia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationMizanur R. Shohel
 
Impact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaImpact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaMizanur R. Shohel
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentJini Rajendran
 
Environment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal AuditEnvironment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal AuditKANTHARAJAN GANESAN
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrateek Bansal
 
EIA thermal power plant
EIA thermal power plantEIA thermal power plant
EIA thermal power plantvandana bharti
 

What's hot (20)

Environmental impact assessment and Initial Environmental Examination
Environmental impact assessment and Initial Environmental ExaminationEnvironmental impact assessment and Initial Environmental Examination
Environmental impact assessment and Initial Environmental Examination
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projects
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
EIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVEREIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVER
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & Aquaculture
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENT
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5
 
EIA
EIAEIA
EIA
 
EIA Methods
EIA MethodsEIA Methods
EIA Methods
 
Eia - environmental impact assessment
Eia - environmental impact assessmentEia - environmental impact assessment
Eia - environmental impact assessment
 
Methods of prediction and assessment techniques of impacts soil
Methods of prediction and assessment techniques of impacts soilMethods of prediction and assessment techniques of impacts soil
Methods of prediction and assessment techniques of impacts soil
 
Eia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationEia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigration
 
Impact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaImpact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eia
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Environment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal AuditEnvironment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal Audit
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
EIA thermal power plant
EIA thermal power plantEIA thermal power plant
EIA thermal power plant
 
EIA Report
EIA ReportEIA Report
EIA Report
 

Similar to Environmental impact assessment case study

EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...
EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...
EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...IAEME Publication
 
EIA REPORT :Renuka dam project
EIA REPORT :Renuka dam project  EIA REPORT :Renuka dam project
EIA REPORT :Renuka dam project Saurabh Gupta
 
Riverbed mining - Rajasthan
Riverbed mining - RajasthanRiverbed mining - Rajasthan
Riverbed mining - RajasthanUdip Das
 
EIA of Sri Balaji Reservoir, Andhra Pradesh.ppt
EIA of Sri Balaji Reservoir, Andhra Pradesh.pptEIA of Sri Balaji Reservoir, Andhra Pradesh.ppt
EIA of Sri Balaji Reservoir, Andhra Pradesh.pptRaghuGhu1
 
EIA ANALYSIS OF JINDAL THERMAL POWER PLANT
EIA ANALYSIS OF JINDAL THERMAL POWER PLANT EIA ANALYSIS OF JINDAL THERMAL POWER PLANT
EIA ANALYSIS OF JINDAL THERMAL POWER PLANT kapilangopinath
 
ethnol project report sample (banking).pdf
ethnol project report sample (banking).pdfethnol project report sample (banking).pdf
ethnol project report sample (banking).pdfyadurajTambe
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxssuser65cc68
 
A CASE STUDY ON MINING PROJECT EIA PLAN.pptx
A CASE STUDY ON MINING PROJECT EIA PLAN.pptxA CASE STUDY ON MINING PROJECT EIA PLAN.pptx
A CASE STUDY ON MINING PROJECT EIA PLAN.pptxDarpanChaudhary7
 
EIA Presentation Group-2 Final.pptx
EIA Presentation Group-2 Final.pptxEIA Presentation Group-2 Final.pptx
EIA Presentation Group-2 Final.pptxNOORAISLAM
 
Eia report - SGS - Slaughter house
Eia report - SGS - Slaughter houseEia report - SGS - Slaughter house
Eia report - SGS - Slaughter housezubeditufail
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...Mayur Rahangdale
 
ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
 ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptxAzharnawaz22
 
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...Moon Girl
 
Green Development
Green Development Green Development
Green Development ssuser4d7205
 
IRJET-Environmental Impact Assessment for Infrastructure Development project...
IRJET-Environmental Impact Assessment for Infrastructure  Development project...IRJET-Environmental Impact Assessment for Infrastructure  Development project...
IRJET-Environmental Impact Assessment for Infrastructure Development project...IRJET Journal
 
Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...
Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...
Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...CIFOR-ICRAF
 

Similar to Environmental impact assessment case study (20)

EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...
EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...
EVALUATION OF ENVIRONMENTAL IMPACT ASSESSMENT ON INDUSTRIAL PROJECTS: A MODEL...
 
EIA REPORT :Renuka dam project
EIA REPORT :Renuka dam project  EIA REPORT :Renuka dam project
EIA REPORT :Renuka dam project
 
IMM PRESENTATION
IMM  PRESENTATIONIMM  PRESENTATION
IMM PRESENTATION
 
Riverbed mining - Rajasthan
Riverbed mining - RajasthanRiverbed mining - Rajasthan
Riverbed mining - Rajasthan
 
EIA of Sri Balaji Reservoir, Andhra Pradesh.ppt
EIA of Sri Balaji Reservoir, Andhra Pradesh.pptEIA of Sri Balaji Reservoir, Andhra Pradesh.ppt
EIA of Sri Balaji Reservoir, Andhra Pradesh.ppt
 
EIA ANALYSIS OF JINDAL THERMAL POWER PLANT
EIA ANALYSIS OF JINDAL THERMAL POWER PLANT EIA ANALYSIS OF JINDAL THERMAL POWER PLANT
EIA ANALYSIS OF JINDAL THERMAL POWER PLANT
 
ethnol project report sample (banking).pdf
ethnol project report sample (banking).pdfethnol project report sample (banking).pdf
ethnol project report sample (banking).pdf
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
 
41946 ind-seia
41946 ind-seia41946 ind-seia
41946 ind-seia
 
A CASE STUDY ON MINING PROJECT EIA PLAN.pptx
A CASE STUDY ON MINING PROJECT EIA PLAN.pptxA CASE STUDY ON MINING PROJECT EIA PLAN.pptx
A CASE STUDY ON MINING PROJECT EIA PLAN.pptx
 
EIA Presentation Group-2 Final.pptx
EIA Presentation Group-2 Final.pptxEIA Presentation Group-2 Final.pptx
EIA Presentation Group-2 Final.pptx
 
Eia report - SGS - Slaughter house
Eia report - SGS - Slaughter houseEia report - SGS - Slaughter house
Eia report - SGS - Slaughter house
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
 
ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
 ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
 
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
 
Iee
IeeIee
Iee
 
Green Development
Green Development Green Development
Green Development
 
Al04602259263
Al04602259263Al04602259263
Al04602259263
 
IRJET-Environmental Impact Assessment for Infrastructure Development project...
IRJET-Environmental Impact Assessment for Infrastructure  Development project...IRJET-Environmental Impact Assessment for Infrastructure  Development project...
IRJET-Environmental Impact Assessment for Infrastructure Development project...
 
Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...
Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...
Contributions of CH4 and N2O to peat GHG emissions from forest and oil palm p...
 

More from Kundan Sanap

Cash flow report using ms project
Cash flow report  using ms projectCash flow report  using ms project
Cash flow report using ms projectKundan Sanap
 
Project monitoring activity
Project monitoring activityProject monitoring activity
Project monitoring activityKundan Sanap
 
Role of artificial intellligence in construction engg &amp; management
Role of artificial intellligence in construction engg &amp; managementRole of artificial intellligence in construction engg &amp; management
Role of artificial intellligence in construction engg &amp; managementKundan Sanap
 
Roles of gps in high rise buildings construction
Roles of gps in high rise buildings constructionRoles of gps in high rise buildings construction
Roles of gps in high rise buildings constructionKundan Sanap
 
Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge Kundan Sanap
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeKundan Sanap
 
Organizational structure of SAIL
Organizational structure of SAILOrganizational structure of SAIL
Organizational structure of SAILKundan Sanap
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its testsKundan Sanap
 
Forecasting method
Forecasting methodForecasting method
Forecasting methodKundan Sanap
 
Project management information system (PMIS)
Project management information system (PMIS)Project management information system (PMIS)
Project management information system (PMIS)Kundan Sanap
 
Case study on flexible pavement failures
Case study on flexible pavement failuresCase study on flexible pavement failures
Case study on flexible pavement failuresKundan Sanap
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge constructionKundan Sanap
 

More from Kundan Sanap (12)

Cash flow report using ms project
Cash flow report  using ms projectCash flow report  using ms project
Cash flow report using ms project
 
Project monitoring activity
Project monitoring activityProject monitoring activity
Project monitoring activity
 
Role of artificial intellligence in construction engg &amp; management
Role of artificial intellligence in construction engg &amp; managementRole of artificial intellligence in construction engg &amp; management
Role of artificial intellligence in construction engg &amp; management
 
Roles of gps in high rise buildings construction
Roles of gps in high rise buildings constructionRoles of gps in high rise buildings construction
Roles of gps in high rise buildings construction
 
Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
Organizational structure of SAIL
Organizational structure of SAILOrganizational structure of SAIL
Organizational structure of SAIL
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its tests
 
Forecasting method
Forecasting methodForecasting method
Forecasting method
 
Project management information system (PMIS)
Project management information system (PMIS)Project management information system (PMIS)
Project management information system (PMIS)
 
Case study on flexible pavement failures
Case study on flexible pavement failuresCase study on flexible pavement failures
Case study on flexible pavement failures
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge construction
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

Environmental impact assessment case study

  • 1. EIA Report for The Building & Construction Project “Parshwa Luxuria” at S. P. No. 133/1/A, R. S. No. 118/2/1, 118/2/2, 118/3, 118/4 & 119, Bodakdev, City West, District Ahmedabad, Gujarat. JANUARY 2019 Submitted By Kundan S. Sanap- 202030016 Akshay P. Jadhav- 202030017 Veermata Jijabai Technological Institute, Matunga
  • 2. Table of Content • Purpose of the study • Project Description • Environmental Baseline • Land use and Land Cover • Air Environment • Noise Environment • Surface Water Environment • Groundwater Environment • Soil • Ecology & Biodiversity environment • Socio-economic environment • Potential Environmental Impacts & Mitigation Measures • Environmental Monitoring Programme • Project Benefits • Conclusion
  • 3. Purpose of the study • The purpose of the EIA study is 1. To identify existing environmental condition 2. To predict environmental impacts associated with the proposed project 3. To suggest measures to mitigate the adverse impacts and to delineate a comprehensive environment management plan along with recommendations and suggestions. 4. The different activities that are likely to take place have been identified and mitigation measures have been proposed
  • 4. Project Description • Type of project: - The project falls under Category B of item 8(a) of Schedule of the EIA Notification 2006 amended till now as Building and Construction projects require prior EC from the SEIAA, Gujarat. • Nature: - Building and Construction project (Residential Building) • Cost of project: - The total Project cost is ~ INR 105 Crore from which the Land cost is ~ INR 35 Crore and the construction cost is ~ INR 70 Crore. • Connectivity to project site • By Road: - • The project site is located on Iscon-Ambli road, Bodakdev, City West, Ahmedabad. Ambli road is ~ 0.4 km in S direction & Sindhu bhavan road is ~1.0 km in N direction from the project site. Sardar Patel Ring Road is ~ 1.2 km in W direction & SG Highway is ~ 1.9 km in E direction from the project site. • By Rail: - • The nearest railway station is Ambli road railway station ~ 2.40 km in NNE direction & Ahmedabad Central railway station is ~ 11.46 km in ESE direction from the project site • By Air: - • Sardar Vallabhbhai Patel International Airport is ~ 14.0 km in ENE direction from the project site
  • 5. Project Description • Location- • The project site is located in Bodakdev, City West, Dist. Ahmedabad, Gujarat.
  • 6. Project Description • Location- • The project site is located at F. P. No.: 133/1/A, R. S. No.: 118/2/1, 118/2/2, 118/3, 118/4 & 119, Bodakdev, City West, District Ahmedabad.
  • 7. Project Description • Study Area- Project site with study area of 10 km
  • 9. Project Description • Size or Magnitude of Operation: - • The project have • total plot area of 6582.76 m2 • Built-up area of 35,734.41 m2. • The project consists of two building blocks of 48 residential units each. • Green Belt: - • Total area for greenbelt development = 660.78 m2 (i.e. >10% of total plot area) • Area provided for tree plantation = 150 m2 (100 number of trees) • Area provided for small shrubs & lawns = 510.78 m2
  • 10. Environmental Baseline • The baseline environmental quality was assessed through field studies within the impact zone for various components of the environment with specific reference to environmental aspects, which may have a bearing on the impacts of the proposed project. The components are listed below: • Land use and Land Cover • Air Environment • Noise Environment • Surface Water Environment • Groundwater Environment • Soil • Socio-economic environment • Ecology & Biodiversity environment.
  • 11. Land use and Land Cover Pattern of Study Area • Built-up Land or Habitation: - • Residential/Commercial: • This is the major class in the study area covering ~ 30 % of total study area. Major city is Ahmedabad. Santej, Bopal, Shela, Sola, etc. are upcoming fast growing rural to urban areas. • Industrial Area: • This class covers ~ 2.5 % of total study. Industrial areas are located at Village Rakanpur, Santej and along NH-8C near areas Santipura, Chandlodiya, Gota etc. • Agricultural Land: - • Crop Land: • Agricultural land covers ~ 26 % of study area. Agriculture crops such as rice, jowar, wheat, fodder, castor etc. is cultivated in study area. • Plantation: • Eucalyptus plantations were seen near Bhadaj and Telav. • Vegetation Cover: - • The study area has ~30 % of vegetation cover. Dominant vegetation is prosopis. • Wasteland: - • The study area has ~11 % of total area under wastelands which is mainly land without scrub.
  • 12. Land use and Land Cover Pattern of Study Area • Water bodies: • It is observed that ponds are present mostly in all the villages and places within the study area. • River Sabarmati is the major one flowing from ENE to SSE direction in the study area, • however, Chandrabhaga Nadi forming the minor one in the study area. • Others: • Few patches of grassland are present in Sabarmati riverbed.
  • 13. Ambient Air Quality • Ambient Air Monitoring was conducted at Six (6) different locations within the study area. • The frequency of monitoring was 24 hours twice a week at each station spread over one month with gaseous sample being changed two times (at 8 hour intervals). • The parameters monitored were Particulate matter (PM10, PM2.5), Sulphur Dioxide (SO2), Oxides of Nitrogen (NOx), Carbon Monoxide (CO) and Hydrocarbon-HC (as Methane) • Selected Six Location: Code Location Coordinates Distance from Site (Km) Direction from site Justification AAQ01 At project Site 23°01'56.08"N 72°29'20.94"E 0 Base Selected as base station AAQ02 Anand Nagar, off SG Highway 23°00'57.23"N 72°30'33.63"E 2.73 SE 1st predominant downwind station AAQ03 Shilaj Village 23°3'17.38"N 72°28'10.08"E 3.23 NW 1st predominant upwind station AAQ04 Bopal Village 23°2'1.84"N 72°27'28.18"E 3.23 W 2nd predominant upwind station AAQ05 Akar Society, Vastrapur 23°1'48.16"N 72°31'32.58"E 3.74 E 2nd predominant downwind station AAQ06 Santej Village 23°6'3.59"N 72°29'2.71"E 7.65 N Crosswind station
  • 14. Ambient Air Quality • Ambient Air Quality Results: • The comparison of the results with the value range indicators NAAQ standards 2009 provided by CPCB(Central Pollution Control Board) for Industrial, residential, rural & other area indicates: • At various locations, average concentration of PM10 was observed to be varying from 101 to 166 µg/m3 . Average concentration of PM10 levels are exceeding the permissible limits at all locations(100 µg/m3). The reason for higher PM10 concentration would be vehicular emissions and traffic congestion in the urban areas while fuel wood or biomass burning for cooking in rural areas. • Average concentration of PM2.5 levels was observed to be in range of 30 to 50 µg/m3 which is less than the permissible limits(60 µg/m3) for all locations. • Average concentration of SO2 levels was observed to be in the range of 12.5 to 17.0 µg/m3 which is within the specified limit(80 µg/m3) of CPCB. • NOx levels were observed to be in the range of 17.1 to 19.2 µg/m3 which is within the specified limit(80 µg/m3) of CPCB. • CO levels were observed in the range of 1.223 to 1.523 mg/m3 which is within the specified limit(4 mg/m3) of CPCB.
  • 15. Noise Level Monitoring • Monitoring of noise is done by identifying suitable number of noise quality monitoring locations. • Sampling Location Details: 5 Locations Selected Station Code Noise Monitoring Locations Category of Area / Zone Coordinates Distance between Nearest Boundaries w.r.t. Project Site in Km Direction w.r.t. Project Site NL1 Greenbelt area (North) of Project site Residential 23⁰01'57.0"N 72⁰29'21.1"E 0.0 Base Station NL2 Centre of project site Residential 23⁰01'55.0"N 72⁰29'21.3"E 0.0 Base Station NL3 100 meter (East) from center of project site Residential 23° 1'57.30"N 72°29'31.51"E 0.1 East NL4 500 meter from (West) center of project site Residential 23⁰01'50.2"N 72⁰28'58.1"E 0.5 West NL5 1 KM from center of project site (SW) Residential 23° 1'20.11"N 72°29'26.82"E 1.0 South West
  • 16. Noise Level Monitoring • Results: Readings were taken at five different locations within the study area. • The baseline average noise levels are presented in table below: • Noise level during daytime & during night time, in residential area was observed higher than the CPCB standards i.e., Residential area (55 dBA (d) & 45 dBA (n)) which is due to vehicular movements. Station Code Noise Monitoring Locations Category of Area / Zone CPCB Limits in dB (A) Baseline average Noise levels in dB (A) Day Time Night Time Day Time Night Time NL1 Greenbelt area (North) of Project site Residential 55.0 45.0 62.0 53.4 NL2 Centre of project site (garden area) Residential 55.0 45.0 59.4 52.6 NL3 100 meter (East) from center of project site Residential 55.0 45.0 54.0 44.9 NL4 500 meter from (West) center of project site Residential 55.0 45.0 62.4 54.7 NL5 1 KM from center of project site (SW) Residential 55.0 45.0 64.2 53.9
  • 17. Surface Water Quality • Water samples were collected during the baseline study period. The details of surface water sampling, analysis results and observations of baseline water quality are given further in detail. • Surface water sampling locations area selected based on review of land use plan, surface drainage pattern/ground water flow direction & nearby site habitation village/locations in 10 km radius of the project. Code Location Source Distance from Project Site in Km Direction w.r.t Project Site Latitude (N) Longitude (E) Juscation of Sample collection SW 1 Sabarmati (U/s) River 9.2 ESE 23˚00’33.6” N 72˚31’32.4” E To know the quality of flowing water body passing from study area SW 2 Sabarmati (D/s) River 8.57 SE 22˚59’20.2” N 72˚33’31.3” E SW 3 Santej Pond 7.9 N 23˚6’11.98” N 72˚28’59.84” E To know the quality of stagnant water bodies coming in the study area SW 4 Bopal Pond 3.22 WNW 23˚2’18.56” N 72˚27’31.16” E SW 5 Thaltj Pond 3.14 NE 23˚3’2.68” N 72˚30’42.49” E SW 6 Vastrapur Lake Dry Lake 4 ENE 23˚02’19.67” N 72˚31’43.31” E
  • 18. Surface Water Quality • Observation of Surface Water Quality: The baseline quality of surface water based on the results of the surface water quality monitoring within the study area, it is observed that, • In Santej pond TDS, Electrical conductivity, Total Hardness, Mg++ Hardness, Chlorides and Ammonical Nitrogen value are observed higher than the limits given in standards. • Bopal Pond BOD value, Total Hardness, Mg++ Hardness and Chlorides value are observed higher than the acceptable limits. • In Thaltej Pond Total Hardness, Mg++ Hardness and Ammonical Nitrogen value are observed higher than the acceptable limits. • In river water Ammonical nitrogen & chlorides are slightly high. • Based on visual observation and analytical results it can be conclude that the overall water quality including river and pond water are polluted due to discharge of city wastewater and other wastes discharge into the surface water body. • The above observation shows that • pond water of SW3, SW4, and SW5 are polluted source where 3-6 parameters > acceptable limits, • whereas SW1 & SW2 i.e. river water is least polluted source compared to pond water. • The overall water quality is compared with class E as per classification of Inland Surface Water Standard and it can be used for irrigation and industrial cooling. If there is no alternate source for drinking purpose, treatment of surface water is essential before using for any purposes.
  • 19. Groundwater Quality Monitoring • The samples were manually collected and analyzed as per APHA(American Public Health Association) standard Methods (22nd Edition, 2017) for the parameters given in EIA Manual of MoEF (Sept 2006). • Groundwater Sampling Locations: 7 Locations Code Location Source Distance Direction W.r.t site GW 1 Bopal Tube-well 2.80 km West GW 2 Shilaj Tube-well 3.05 km NW GW 3 Santej Tube-well 8.49 km NNW GW 4 Sola Tube-well 5.38 km NE GW 5 Thaltej Tube-well 2.49 km NE GW 6 Sarkhej Tube-well 5.57 km SSE GW-7 Telav Tube-well 8.34 km SW
  • 20. Groundwater Quality Monitoring • Observation of Groundwater Quality: The baseline quality of groundwater based on the results of the Groundwater quality monitoring within the study area, it is observed that, • TDS is found exceeding the permissible limit more than 2000 mg/lit at Sarkhej (GW-06) and Telav (GW-07), while the range is between 1198 mg/lit (GW-04: Sola) to 1612 mg/lit (GW-01: Bopal). • Chlorides is found near to permissible limit(1000mg/lit) ~ 955 mg/lit at Telav (GW-07). • Sulphates is exceeding permissible limit more than 400 mg/lit at Sarkhej (GW-06) and Telav (GW-07). • Magnesium is also exceeding permissible limit higher than 100 mg/lit at Telav (GW-07). • Iron content are found higher than desirable limit(0.3 mg/lit) at all locations.
  • 21. Soil Quality & Characteristics • A field visit conducted to study site-specific soil quality and condition includes soil texture mineralogical content, plasticity & possible impact to the environmental setting due to project. • Soil Sampling: Randomly selected locations • The soil samples from 0-15 cm depth were collected by using spade and pawada. • samples were homogenized and about 1 Kg soil sample was collected in the polyethylene bag, labelled with sample ID & were brought to the laboratory for analysis of physical and chemical properties Sr. No. Sampling Location Soil texture Lat. & Long. From the project site Dir. Dist. ST01 Bopal village Sandy loam 23° 1'55.31"N 72°27'52.83"E W 2.4 ST02 Shilaj village Sandy loam 23˚03'18.0"N 72˚28'21.3"E NW 3.2 ST03 Santej village Loam 23˚06'24.9" N 72˚28'13.7" E NNW 8.4 ST04 Sola village Sandy loam 23˚04'05.5" N 72˚31'27.1" E NE 5.3 ST05 Thaltej village Sandy loam 23˚03'26.4" N 72˚30'15.49" E NNE 3.1 ST06 Bodkdev (At site) Loamy sand 23° 1'55.50"N 72°29'20.84"E - 0 ST07 Sarkhej village Sandy clay loam 22˚58'54.54" N 72˚30'11.32" E SE 5.7 ST08 Telav village Sandy loam 22˚59'54.28" N 72˚26'28.56" E SW 6.1
  • 22. Soil Quality & Characteristics • Soil Quality Results: • The analysis of physicochemical properties of soil samples collected from surrounding area indicated that, • Porosity ranged from 35 –56 % and WHC (Water Holding Capacity) varied from 43.17 – 62.4 %, while permeability ranged from 17.7 – 62.4 mm/hr. The high permeability was on account of sandy to sandy clay loam texture of soils. • The EC(Electrical Conductivity) ranged from 0.641 to 1.105 dS/m indicating that soils are normal (EC<1.0 dS/m) to saline (>EC<1.0 dS/m) and ESP(Exchangeable Sodium) (0.37 to 3.52) was well within the safe limit of <15. • The pH ranged from 7.13 – 7.36, indicating that soils are normal (pH = 6.5 to 7.8). • Among water soluble cations predominance of Na (0.58 to 1.78 g/kg) was seen followed by Ca (0.37 to 1.25 g/kg), Mg (0.01 to 0.45 g/kg) and K (0.16 to 0.42 g/kg).
  • 23. Ecology and Biodiversity • This section represents existing biodiversity status of the project site (core zone) and its surrounding environment of the project study area (buffer zone of 10 km radius). • Field Data Collection & Observation: - • After the plot survey it is found that, there is lot of diversity when it comes to the flora and fauna in and around the study area. • no rare and endangered flora was observed. • Among floral species, none of the species can be designated as threatened species. For the recorded faunal species, none of the species can be designated as an endemic.
  • 24. Socio-Economics • This section analyses the existing socio-economic conditions of the habitations as well as community residing in the project area. • It also identifies the potential issues and problems in the area. For the design of project, stakeholder views were taken through the structured questionnaires and focus group discussions.
  • 25. Potential Environmental Impacts & Mitigation Measures • Environmental impacts have been identified based on an assessment of environmental aspects associated with the project. So, both positive and negative impacts are mentioned below along with the impacting activities: • Land use/Land cover: • Impacts • Land procurement and site preparation. • Generation of earth/debris and change in topography of the site due to cutting & filling. • Betterment of overall land cover characteristics both aesthetically as well as ecologically • Mitigation measures • Establish and clearly document land usage permission. • Clearance of vegetation limited to project footprint. • Landscape development within site. • Use of excavated earth for backfilling. • Storage of top soil separately and its reuse for greenbelt within the site.
  • 26. Potential Environmental Impacts & Mitigation Measures • Air quality: • Impacts • SPM generation and emission of HC & CO due to Vehicle movement during site preparation • Dust generation during construction activities and restoration • Emission of SPM, SO2, NOx, HC & CO due to operation of DG sets. • Mitigation measures • PUC (Pollution Under Control) certified all cars /vehicles shall be allowed to enter. • Vehicular emission can be mitigated by strictly following traffic management plan at site. Also by maintaining the roads and by controlling speed limit. • Dust and air emission can be controlled by development of greenbelt / green cover. • Periodic air quality monitoring will be carried out at project site and other location within study area. • Sprinkling of water can be carried out for dust suppression. • Adequate stack height of 2.0 m will be provided for emission from DG
  • 27. Potential Environmental Impacts & Mitigation Measures • Noise: • Impacts • Noise due to Vehicle movement during site preparation and occupants • Noise during operation of construction equipment / machineries. • Mitigation measures • Use of well-maintained equipment, machinery and vehicles to avoid generation of high noise. • Provision of personnel protective equipment (PPEs) like ear plugs/muffs for all the workers at site and ensuring that the same wore by everybody during construction work. • Noise to be monitored in ambient air within the premises.
  • 28. Potential Environmental Impacts & Mitigation Measures • Surface Water: • Impacts • Water resources depletion due to water consumption due to domestic use • surface water contamination due to generation, handling & disposal of wastewater. • Mitigation measures • Separate drainage will be proposed for storm water and for sewage to avoid run off contamination as well as any contamination of surface water sources. • Care shall be taken to reduce water consumption by providing water conservation measures. • Drip irrigation system will be proposed to reduce fresh water demand for gardening.
  • 29. Potential Environmental Impacts & Mitigation Measures • Ground water: • Impacts • Ground water contamination due to storage, handling & disposal of wastewater. • Mitigation Measures • The ground water occurs under confined conditions under the alternate layers of clay and sand in study area, the proper zone of formation need to be recharge. • For which, 02 recharge wells are installed. It is further assumed that, this recharge-well will improve the present ground water conditions. • Rainwater harvesting to recharge the ground water has been proposed at site. • Such activity will reflect in improvement of ground water conditions and sustainability of recharge structure.
  • 30. Potential Environmental Impacts & Mitigation Measures • Soil: • Impacts • Soil erosion due to Clearance of vegetation during site preparation, • Loss in soil fertility due to levelling and Changes in natural topography due to excavation • Soil Contamination due to storage and handling of solid waste. • Control over soil erosion due to green belt. • spillage of solid waste may deteriorate soil quality • Mitigation Measures • Spillage of construction materials was avoided to prevent soil contamination and deterioration on soil quality. • Spillage of oil, diesel etc. was minimized to avoid soil contamination. • During excavation, top soil was reused in a stretch of 150 m long & 1.5 m wide along 18 m wide road on north side of the project site.
  • 31. Potential Environmental Impacts & Mitigation Measures • Socio – Economic: • Impacts • Positive impact due to creation of jobs and increase in indirect income. • Mitigation Measures • The project will provide short term employment opportunities to the local people.
  • 32. Potential Environmental Impacts & Mitigation Measures • Ecology and Biodiversity: • Impacts • Negative impacts due to clearance of vegetation during site preparation • barrier to faunal movement due to construction of building structure • impact on flora & fauna due to vehicle movements • disturbance to nocturnal fauna & flying patterns of birds due to artificial illumination of project • positive impact plantation during landscaping & greenbelt development. • Mitigation Measures • Maximum trees will be included in the green belt area which will support existing faunal biodiversity. • Artificial illumination will be kept in suitable direction and light will be switched off in less time duration at night. • For the impact on flora & fauna, No immediate action required because all local species from project site would be common as reported from nearby environment and well adapted to the routine urban activities, so they would not face significant impact on their normal movements.
  • 33. Potential Environmental Impacts & Mitigation Measures • Occupational health, Community Health and Safety: • Impacts • Health & safety risk/hazard to workers due to various construction activities • Beneficiary effect on occupational health due to landscaping & Greenbelt development. • Mitigation Measures • Workers were given all the safety items such as safety helmets, safety belts, jackets, etc. to be safe from any kind of injuries while doing construction activities.
  • 34. Environmental Monitoring Programme • The regular monitoring of environmental parameters is of immense importance to assess the status of environment during project operation. • With the knowledge of baseline conditions, the monitoring program will serve as an indicator for any deterioration in environmental conditions due to operation of the project, to enable taking up suitable mitigation measures in time to safeguard the environment. • Environmental Monitoring Plan; • Air Environment- • Once in every six months • At main Gate- Readings to be taken for Ambient air quality monitoring for PM10, PM2.5, SO2, NOx in ambient and within project premises & comparing them to Permissible values. • At DG Set- Stack air monitoring for SPM, SO2, NOx, HC & CO in stack of DG set & comparing them to Permissible values
  • 35. Environmental Monitoring Programme • Noise Environment- • Once in every six months • At Project site(Various Locations)- Ambient Noise level during day and night time & comparing them to Permissible values • Water Environment- • Once in every six months • At Project site- One ground water sample of recharge well (Essential parameters as per IS: 10500:1991) & comparing them to Permissible values. • Solid & Hazardous Waste- • Once in every week • At Project site- Solid waste (MSW) Generation, handling, storage and disposal & record review for random checks for site in-charge.
  • 36. Project Benefits • During construction phase direct employment opportunity was created for contractor, laborers and workers, indirect employments in transportation and construction allied sectors • During operation phase, long-term job opportunities will be created in terms of security, housekeeping and gardening personnel which will lead to increase their living standard. • Exposure of modernized infrastructural & technological facilities due to proposed project activities will helpful to boost knowledge of employees, workers, locals • 10% of the plot area is being developed as landscape area /green belt, which will enhance the beauty and aesthetics of the project area. • Good solid waste management system consisting of proper collection, designated storage, provision of composting facility for bio degradable waste disposal. • Project will set a good example for surrounding area about good solid waste management system consisting of proper collection, storage & disposal facility. • Adequate parking space for residents and visitors.
  • 37. Conclusion • It can be concluded on a positive note that due to the adequate provision and efficient operation of proposed environmental management systems and mitigation measures, the project activities during the operation phase would have manageable & largely have reversible impacts on the environment and on balance the project would be beneficial to surrounding communities and the region.