SlideShare a Scribd company logo
1 of 51
KATHMANDU UNIVERSITY
DHULIKHEL , KAVRE
DEPARTMENT OF CIVIL ENGINEERING
PRESENTATION OF INTERNSHIP ON:
SUPERMADI HYDROELECTRIC PROJECT [44 MW]
GROUP MEMBERS:
ARUN KATUWAL
KIMILSUNG LIMBU
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Introduction to the site
• Super Madi Hydroelectric Project is located in Kaski District , Gandaki Zone of
Western Development Region of Nepal.
• The Project lies in the Namarjun and Parche Village Development Committees of
Kaski District about 23 km North-East of Pokhara.
• The project is a simple Run-off-river scheme that utilizes the flow in Madi River
which is one of the major tributaries of the Narayani River .
• The proposed project has installed Capacity of 44 MW, design discharge of 18
m3/s and net head of 295 m .
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• A simple boulder riprap diversion weir across the Madi Khola will divert the water
into the side intake .
• A gravel trap settles gravels and takes water to the head pound.
• 2 underground settling basins will be fed with the discharge by two inlet tunnels from
head pound.
• An outlet pond will feed water into the headrace tunnel of length 5.9 km and finish
diameter of 4.2 m.
• Steel penstock of average diameter 2.6 m and length 1.38 km will feed water to 3
vertical axis Pelton turbines installed in semi-surface power house to generate 44 MW
of electricity.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Salient Features
General
• Name of river : Madi Khola
• Nearest Town : Pokhara , 23 km
• Type of Scheme : Run-of-River
• Type of Scheme : Run-of-River
• Gross Head : 305m
• Installed Capacity : 44000 kW
Hydrology
• Catchment area : 284.1 km2
• Mean annual Discharge : 30.29 m3/s
• Design Discharge : 18m3/s
• Probability of Exceedance : 40.96 %
• Design Flood Discharge : 1288 m3/s (100 Yr. Flood)
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Diversion Weir
• Type of Weir : Free Overflow with Spillway
• Total Length of Weir : 60m
• Height of overflow Weir from River bed : 5m
• Crest elevation : 1362 masl
• Design Flood Level : 1368 masl
Inlet Tunnel
• Shape : Inverted D
• Numbers : 2
• Length : 52m
• Size (W*H) : 3m*3m
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Side Intake
• Type of Intake: Side Intake ( Orifice Type)
• Size of Orifice (W * H) = 2.4m*1.6m , 6 Nos.
• Intake Sill Level: 1360m
Underground Desanding Basin
• No of Chamber: 2
• Size: 172m*7.5m*14.75m (parallel section 160m)
• Particle size to be settled: 0.20mm @ 90 % efficiency
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Headrace Tunnel
• Type: Inverted D Type Tunnel
• Finish Diameter: 4.2m
• Length: 5905m
• Support: Fully concrete Lined ( 800m ) Shotcrete Lined (5105m)
Surge Tank
• Type: Circular, Underground
• Height: 37 m
• Finish Diameter: 9m
Penstock Tunnel
• Type: Inverted- D Type Tunnel
• Finish Diameter: 2.8 circular penstock
• Length: 38m
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Objectives
• To get exposure to engineering duties and responsibilities.
• To develop the proficiency to function in diverse engineering and managerial
settings based on core knowledge, skills, attitudes and aptitudes acquired during
the in-campus semesters.
• To be aware of engineering norms, values and ethical practices.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Task Performed
Task
Performed
Site Reconnaissance
Drawings Study
Site Supervision
Interactions with diverse Professionals
Daily Observation Log Preparation
Weekly & Monthly Progress Report Preparation
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Tunnel Cycle
Due to the abundance of tunnels in our site we had the opportunity to observe a
complete tunneling cycle which consists of the following sequence of processes: -
1. Drilling
2. Loading & Stemming
3. Blasting
4. Ventilation
5. Mucking & Scaling
6. Geological Mapping and Surveying
7. Rock support Installation
8. Shotcreting
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
1. Drilling
• This is the first process in the tunnel cycle.
• We observed the drilling process being carried out manually using jack hammer with
pushers’ leg mostly in the Inspection tunnel and Kalbandi Headrace tunnels.
• The length of drill holes varying up to 2 meters (mostly 1.5m and 1.7m) depending
upon the pull required.
• Drilling was also carried out for Rock Bolt installation.
• Drilling was carried out by Boomer in Adit II tunnel.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• For the drilling process , we found out the average time taken for the jack hammer
and boomer to drill a hole of 1.7 m diameter as shown in the table below :
Equipment Avg. Time taken(s) Rock Class Manpower Required for operation
Jack Hammer 187 III At least 3
Boomer 130 I At least 2
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: Jack Hammer Fig : Boomer
Fig : Drilling by Boomer
Fig: Drilling by Jack Hammer
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
2. Loading & Stemming
• Packing or insertion of the explosives into the holes for the purpose of blasting is known
as Loading.
• The Process of sealing drill hole and retaining the explosive gases within it is called
Stemming.
• Loading was carried out manually in the site.
• Emulsions Explosives were mainly used in the site while loading.
• The energy released as a result of explosion is much higher in compared to other
emulsion explosives.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• The following observations were made in the site during the loading phase of the tunnel
cycle: -
Explosive Type: Emulsion Explosives
Explosive Brand Name: Superpower 90
Explosive Cartridge Size & weight: 32 mm dia., 200 gm
Average Time Taken to load a hole: 57 sec (Including Detonator placement &
stemming, Manually)
Materials used for stemming: Clay and Sand
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig : An Emulsion Explosive Cartridge Fig: Loading and Stemming of a Hole manually
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
3. Blasting
• The Blasting or detonating procedure was performed with the means of detonator
which charged the emulsion explosives.
• The Blasting procedure was allowed to be carried out by an only authorized personnel
like a Blaster in the site.
• The detonators used for the purpose of blasting was Electrical type Short Period Delay
(SPD)detonators with the variance of milli second detonation delay from one another.
• The major milliseconds delay detonators used in the site varied from 1 millisecond
delay detonator to 10 milliseconds delay detonators.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: A 10 millisecond delay detonator Fig: A detonator trigger and ohm meter
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Video of blast in the inspection tunnel
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
4. Ventilation
• The site was cleared for few minutes for the explosive gases to disperse.
• Since the Kalbandi Headrace Tunnels, Inspection Tunnel and Headrace Tunnel outlet
were in the initial stages of excavation there were no provisions for mechanical
ventilators in those sites.
• The explosives gasses were allowed to disperse through the flow of natural air without
any external means for about 10 - 15 minutes before mucking process commenced.
• Ventilation in the Adit II Tunnels at Bagalethar was carried out by a single fan
ventilator. The ventilation time varying from 20 minutes to 30 minutes.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: A single Fan Longitudinal Ventilator used in Adit II Tunnel
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
5. Mucking & Scaling
• Mucking refers to the process of removing the muck after blasting and throwing outside the
tunnel.
• Mucking was carried out by a loader in our site.
• Major used wheel loaders in our site were XCMG LW 300kN and XCMG ZL 50 GN.
• Scaling refers to the process of removal of the muck that sticks to the tunnel face after the
Mucking process.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• Scaling was carried out in the site manually by hitting the tunnel face with the pressurized
jet of water and by hitting the tunnel face rocks by loading sticks.
• In average the time taken for mucking and scaling was about 2 hours.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: A loader used for mucking Fig: A tipper used for muck disposal
Fig: Scaling process carried out Fig: Mucking in tunnel by a loader
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
6. Geological Mapping and Surveying
• After the process of scaling the geologists work was to make the geological log sheet of the
rock class type of joints and faults and other aspects relating to the geological mapping of
the tunnel face.
• The Rock Class of the tunnel face is found out after the determination of Rock Tunneling
Quality Index (Q-value).
• The process of geological mapping is simultaneously followed by surveying.
• Along with the alignment fixing of tunnel, surveying was carried out to determine the
chainage and pull from the recent Blast.
• Resection is carried out to fix the tunnel alignment, the steps followed to carry out
Resection is explained in detail in Daily Observation Log.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: A surveyor conducting alignment
survey of tunnel
Fig: Face mapping by a Geologist
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
7. Rock Support Installation
• After the geologists identify the the rock support class than the supports pertaining to
the suitable tunnel face and the rock mass was installed which was either spot bolt ,
Rock Bolt or in worst cases Ribs which was done in accordance with the rock class
determined as per the approved design drawings.
Fig: Rock bolts Fig : Rib Installation
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Short Description on the type of supports used
• Spot Bolt
These are the bolts which are locally installed at sites that appear to be prone to failure
,may be on the roof or floor.
Spot bolts are used at certain spots to prevent failure of individual blocks and wedges.
The observed dimension of the rock bolt used in our site was 2m length and 20mm
diameter.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• Rock Bolt
 Is generally a long anchor bolt.
Used for stabilizing rock excavations in the tunnels and rock cuts.
It transfers load from the unstable exterior to the confined (and much stronger) interior of the
rock mass.
Dimensions of rock bolt used in the site were 2-2.5m length with 20 mm diameter.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig : Rock Bolt Fig : Installed Rock Bolt
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• Rib Installation
Ribs were installed in the excavation sites of the tunnels specifically, pertaining to the particular
rock classes with low stability.
Ribs of IS standard I – section (IS 808, ISMB 150, 15kg/m) in combination with high strength
concrete were used.
In our site the rib was of arc and post type with two pieces of each component.
The arc and post were attached to each other by plates and nut bolts.
The dimension of the plate was 18cm * 15cm and of the diameter of bolt was 16mm.
There were 4 holes and bolts in the plate with the diameter of holes 2mm greater than of bolts.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Then the backfilling was performed which was done in the form of boulder packing.
The boulders were then bind with cement mixture of M25 strength.
The backfilling were held by wire mesh with dimension of 2.1m*1.1m and 4.75mm diameter
,usually six number of wire mesh were used per rib.
Tie rod and anchor rod were also used for further support and stabilization of the rib.
The tie rod was 20mm diameter and 1m length whereas the anchor rod had same diameter but
the length was 2m.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig : Rib Installation Fig : Tie Rod Welding
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig : Wire Mesh
Fig : Anchor rod
Fig : Boulder Packing
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• Shotcreting:
Shotcrete refers to concrete or mortar conveyed through a hose and pneumatically projected at
high velocity onto a surface, as a construction technique.
In our Internship we only observed dry shotcreting at our site.
The materials used were cement , sand , water and aggregate of nominal max size 10mm.
The design strength of shotcrete was generally M30 .
Steel fiber Crete was used as reinforcement.
For rapid setting of shotcrete accelerating admixture for dry shotcreting was used.
Generally 25 kg admixture was used per batch of shotcreting.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig : Shotcreting Fig : Mixer for mixing of materials
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
• Slope Stabilization
This was generally performed in the early stages of the tunnel construction.
The bearing capacity of the natural slope decreases due to tunnel face excavation.
Cement grouting or shotcreting was done for stabilization in accordance with the slope
condition.
Spiling rods were also used to support the tunnel during early stages .
Spiling rod provide a protective canopy, to enable the heading of a tunnel to be advanced
without the risk of falling debris .
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig : Grouting of Slope Fig: Spiling Rod
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Rock Class Support Type Pattern Spacing
I 2m long,20mm dia. Spot Bolt with Dry Steel
Fiber Shotcrete 50mm thick
1-1 -
II 2m long,20mm dia. Rock Bolt with Dry
Steel Fiber Shotcrete 75mm thick
5-6 1.6m c/c
III 2m long,20mm dia. Rock Bolt with Dry
Steel Fiber Shotcrete 100mm thick
6-7 1.4 m c/c
IV 2m long,20mm dia. Rock Bolt with Dry
Steel Fiber Shotcrete 125mm thick
7-8 1.2m c/c
V 2.5m long,20mm dia. Rock Bolt with Dry
Steel Fiber Shotcrete 150mm thick
8-9 1m c/c
VI 3m long,20mm dia. Rock Bolt with Dry
Steel Fiber Shotcrete 200mm thick & ISMB
150 beam sets 1m c/c
8-9 1m c/c
ROCK SUPPORT TYPE
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: Steel fiber crete used as reinforcement Fig: A mixer
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Activity Time (min) Specifics [Tunnel 4.2m x 4.2m D-shape]
Drilling 220** Avg. approx. 74 holes per round, Jackhammer on pushers leg
Loading 90 Approx. 73 kg explosives loading per blast
[Gneiss/Quartz]
Blasting 20 -
Ventilation 15 -
Mucking 140 Mechanical [1 Loader, 1 tipper]
Scaling 20 Manual
Surveying and Face Mapping 50 Resection and Q-Value Evaluation
Rock Bolting 170 Tunnel Support Type III Pattern [6/7 @ 1.40m c/c]
Shot Creting 210 (Approx. 125mm – 150mm thick)
Time for one round 935 Approx. 16hours per round, Pull obtain=0.9m-1.7m
=1.3m avg
Weekly Progress 2shifts, 9hrs per shift,
14shift per week
14 shifts/week*9 hrs/week*1.3 m pull
16 hrs
=10.2 m/week
TUNNEL CYCLE TIMES OF A FULLROUND-KALBANDI KHOLSI TUNNEL SITE
** Avg. drill time found to drill a hole of 1.7m length was 3m -4m. Drilling time varies depending upon rock mass
and efficiency of workers.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Major Problems Encountered In The Worksite
Human Errors
• Not arriving in time for work.
• Lack of skill and diligence in some manpowers.
• No consideration for proper and optimum material usage.
• Mishandling of equipment.
Technical Errors
• Machine wearing due to continuous use.
• No proper maintenance of equipment.
• No availability of advance equipment in all of the sites like boomer.
• Unavailability of electricity for certain time period.
• Less consideration for safety of manpower such as no availability of safety googles etc.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Geological Problems
• Very strong rock class in Adit II tunnels due to which problems of socket holes and
under break occurred of length 30cm to 80cm due to hard rock.
• Very weak rock class in outlet tunnel due to which continuous rib installation and
also rock over break occurred.
Other Problems
• Unexpected and unscheduled problems such as continuous strikes, Banda etc.
• Untimely payment of salary which lead to strikes from man power.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
A BRIEF OVERVIEW OF OUR FIELD VISIT TO OTHER HYDRO PROJECTS
• As our major observation were based on the works of a tunnel cycle and our selected
project was in initial phase of the construction during our internship period, we asked
our supervisor Mr. Ganga Ram Maharjan for a field visit to other hydro-projects for
observation of major hydro-power related structures in which he agreed to volunteer.
• Field visit was made to Himalayan Hydroelectric project [12 MW] located d/s to our
project.
• Similarly, field visit was made to the Middle Modi Hydro project [15.1 MW] as per
the course of study of our internship period. The report of this field visit is briefly
discussed in the Daily Observation logs of date (15-16)/02/2076.
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: ongoing Anchor block and Saddle Support construction of Himalayan Hydro project
Fig: ongoing construction of powerhouse and saddle supports of Himalayan Hydro Project
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: Headworks of Middle Modi hydro project [MMHP]
Fig: Headrace canal of MMHP Fig: Settling basin of MMHP
Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
Fig: Headrace Tunnel outlet Fig: Ongoing Powerhouse construction
Picture with supervisor

More Related Content

What's hot (20)

Power shovel
Power shovelPower shovel
Power shovel
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Placing of concrete
Placing of concretePlacing of concrete
Placing of concrete
 
Dredging equipment
Dredging equipmentDredging equipment
Dredging equipment
 
Tunnelling Methods.pdf
Tunnelling Methods.pdfTunnelling Methods.pdf
Tunnelling Methods.pdf
 
Casting yard
Casting yardCasting yard
Casting yard
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Excavating Equipments
Excavating EquipmentsExcavating Equipments
Excavating Equipments
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Dragline ppt
Dragline pptDragline ppt
Dragline ppt
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
1.2.2.front end loaders
1.2.2.front end loaders1.2.2.front end loaders
1.2.2.front end loaders
 
Tunnel Engineering.pptx
Tunnel Engineering.pptxTunnel Engineering.pptx
Tunnel Engineering.pptx
 
A presentation of transportation of concrete
A presentation of transportation of concreteA presentation of transportation of concrete
A presentation of transportation of concrete
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating Equipment
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
Excavation in hard rock
Excavation in hard rockExcavation in hard rock
Excavation in hard rock
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 

Similar to A brief overview of drilling and blasting process for tunnel excavation used in Supermadi HEP .pptx

blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf20JE0369GAURAVKUMAR
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...IJERA Editor
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniquesKrishna Deo Prasad
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
High level cancer institute,
High level cancer institute,High level cancer institute,
High level cancer institute,Krishan Kumar
 
PPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptxPPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptxPawanSharma565262
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)engineeringwatch
 
Industrial training at DMRC Underground Station
Industrial training at DMRC Underground StationIndustrial training at DMRC Underground Station
Industrial training at DMRC Underground StationAkshay Sharma
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
1st phase analysis
1st phase analysis1st phase analysis
1st phase analysisRohit Sahai
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET Journal
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report muhammad khurram
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectRubnawaz Bhatti
 

Similar to A brief overview of drilling and blasting process for tunnel excavation used in Supermadi HEP .pptx (20)

Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniques
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
High level cancer institute,
High level cancer institute,High level cancer institute,
High level cancer institute,
 
JUNDEE MAR TEJEDO
JUNDEE MAR TEJEDOJUNDEE MAR TEJEDO
JUNDEE MAR TEJEDO
 
PPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptxPPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptx
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)
 
Industrial training at DMRC Underground Station
Industrial training at DMRC Underground StationIndustrial training at DMRC Underground Station
Industrial training at DMRC Underground Station
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
SDP Presentation.pptx
SDP Presentation.pptxSDP Presentation.pptx
SDP Presentation.pptx
 
1st phase analysis
1st phase analysis1st phase analysis
1st phase analysis
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 
Summer Training Presentation
Summer Training PresentationSummer Training Presentation
Summer Training Presentation
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic project
 

Recently uploaded

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

A brief overview of drilling and blasting process for tunnel excavation used in Supermadi HEP .pptx

  • 1. KATHMANDU UNIVERSITY DHULIKHEL , KAVRE DEPARTMENT OF CIVIL ENGINEERING PRESENTATION OF INTERNSHIP ON: SUPERMADI HYDROELECTRIC PROJECT [44 MW] GROUP MEMBERS: ARUN KATUWAL KIMILSUNG LIMBU
  • 2. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Introduction to the site • Super Madi Hydroelectric Project is located in Kaski District , Gandaki Zone of Western Development Region of Nepal. • The Project lies in the Namarjun and Parche Village Development Committees of Kaski District about 23 km North-East of Pokhara. • The project is a simple Run-off-river scheme that utilizes the flow in Madi River which is one of the major tributaries of the Narayani River . • The proposed project has installed Capacity of 44 MW, design discharge of 18 m3/s and net head of 295 m .
  • 3. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • A simple boulder riprap diversion weir across the Madi Khola will divert the water into the side intake . • A gravel trap settles gravels and takes water to the head pound. • 2 underground settling basins will be fed with the discharge by two inlet tunnels from head pound. • An outlet pond will feed water into the headrace tunnel of length 5.9 km and finish diameter of 4.2 m. • Steel penstock of average diameter 2.6 m and length 1.38 km will feed water to 3 vertical axis Pelton turbines installed in semi-surface power house to generate 44 MW of electricity.
  • 4. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Salient Features General • Name of river : Madi Khola • Nearest Town : Pokhara , 23 km • Type of Scheme : Run-of-River • Type of Scheme : Run-of-River • Gross Head : 305m • Installed Capacity : 44000 kW Hydrology • Catchment area : 284.1 km2 • Mean annual Discharge : 30.29 m3/s • Design Discharge : 18m3/s • Probability of Exceedance : 40.96 % • Design Flood Discharge : 1288 m3/s (100 Yr. Flood)
  • 5. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Diversion Weir • Type of Weir : Free Overflow with Spillway • Total Length of Weir : 60m • Height of overflow Weir from River bed : 5m • Crest elevation : 1362 masl • Design Flood Level : 1368 masl Inlet Tunnel • Shape : Inverted D • Numbers : 2 • Length : 52m • Size (W*H) : 3m*3m
  • 6. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Side Intake • Type of Intake: Side Intake ( Orifice Type) • Size of Orifice (W * H) = 2.4m*1.6m , 6 Nos. • Intake Sill Level: 1360m Underground Desanding Basin • No of Chamber: 2 • Size: 172m*7.5m*14.75m (parallel section 160m) • Particle size to be settled: 0.20mm @ 90 % efficiency
  • 7. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Headrace Tunnel • Type: Inverted D Type Tunnel • Finish Diameter: 4.2m • Length: 5905m • Support: Fully concrete Lined ( 800m ) Shotcrete Lined (5105m) Surge Tank • Type: Circular, Underground • Height: 37 m • Finish Diameter: 9m Penstock Tunnel • Type: Inverted- D Type Tunnel • Finish Diameter: 2.8 circular penstock • Length: 38m
  • 8. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Objectives • To get exposure to engineering duties and responsibilities. • To develop the proficiency to function in diverse engineering and managerial settings based on core knowledge, skills, attitudes and aptitudes acquired during the in-campus semesters. • To be aware of engineering norms, values and ethical practices.
  • 9. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Task Performed Task Performed Site Reconnaissance Drawings Study Site Supervision Interactions with diverse Professionals Daily Observation Log Preparation Weekly & Monthly Progress Report Preparation
  • 10. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
  • 11. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
  • 12. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
  • 13. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering
  • 14. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Tunnel Cycle Due to the abundance of tunnels in our site we had the opportunity to observe a complete tunneling cycle which consists of the following sequence of processes: - 1. Drilling 2. Loading & Stemming 3. Blasting 4. Ventilation 5. Mucking & Scaling 6. Geological Mapping and Surveying 7. Rock support Installation 8. Shotcreting
  • 15. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering 1. Drilling • This is the first process in the tunnel cycle. • We observed the drilling process being carried out manually using jack hammer with pushers’ leg mostly in the Inspection tunnel and Kalbandi Headrace tunnels. • The length of drill holes varying up to 2 meters (mostly 1.5m and 1.7m) depending upon the pull required. • Drilling was also carried out for Rock Bolt installation. • Drilling was carried out by Boomer in Adit II tunnel.
  • 16. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • For the drilling process , we found out the average time taken for the jack hammer and boomer to drill a hole of 1.7 m diameter as shown in the table below : Equipment Avg. Time taken(s) Rock Class Manpower Required for operation Jack Hammer 187 III At least 3 Boomer 130 I At least 2
  • 17. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: Jack Hammer Fig : Boomer Fig : Drilling by Boomer Fig: Drilling by Jack Hammer
  • 18. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering 2. Loading & Stemming • Packing or insertion of the explosives into the holes for the purpose of blasting is known as Loading. • The Process of sealing drill hole and retaining the explosive gases within it is called Stemming. • Loading was carried out manually in the site. • Emulsions Explosives were mainly used in the site while loading. • The energy released as a result of explosion is much higher in compared to other emulsion explosives.
  • 19. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • The following observations were made in the site during the loading phase of the tunnel cycle: - Explosive Type: Emulsion Explosives Explosive Brand Name: Superpower 90 Explosive Cartridge Size & weight: 32 mm dia., 200 gm Average Time Taken to load a hole: 57 sec (Including Detonator placement & stemming, Manually) Materials used for stemming: Clay and Sand
  • 20. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig : An Emulsion Explosive Cartridge Fig: Loading and Stemming of a Hole manually
  • 21. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering 3. Blasting • The Blasting or detonating procedure was performed with the means of detonator which charged the emulsion explosives. • The Blasting procedure was allowed to be carried out by an only authorized personnel like a Blaster in the site. • The detonators used for the purpose of blasting was Electrical type Short Period Delay (SPD)detonators with the variance of milli second detonation delay from one another. • The major milliseconds delay detonators used in the site varied from 1 millisecond delay detonator to 10 milliseconds delay detonators.
  • 22. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: A 10 millisecond delay detonator Fig: A detonator trigger and ohm meter
  • 23. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Video of blast in the inspection tunnel
  • 24. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering 4. Ventilation • The site was cleared for few minutes for the explosive gases to disperse. • Since the Kalbandi Headrace Tunnels, Inspection Tunnel and Headrace Tunnel outlet were in the initial stages of excavation there were no provisions for mechanical ventilators in those sites. • The explosives gasses were allowed to disperse through the flow of natural air without any external means for about 10 - 15 minutes before mucking process commenced. • Ventilation in the Adit II Tunnels at Bagalethar was carried out by a single fan ventilator. The ventilation time varying from 20 minutes to 30 minutes.
  • 25. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: A single Fan Longitudinal Ventilator used in Adit II Tunnel
  • 26. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering 5. Mucking & Scaling • Mucking refers to the process of removing the muck after blasting and throwing outside the tunnel. • Mucking was carried out by a loader in our site. • Major used wheel loaders in our site were XCMG LW 300kN and XCMG ZL 50 GN. • Scaling refers to the process of removal of the muck that sticks to the tunnel face after the Mucking process.
  • 27. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • Scaling was carried out in the site manually by hitting the tunnel face with the pressurized jet of water and by hitting the tunnel face rocks by loading sticks. • In average the time taken for mucking and scaling was about 2 hours.
  • 28. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: A loader used for mucking Fig: A tipper used for muck disposal Fig: Scaling process carried out Fig: Mucking in tunnel by a loader
  • 29. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering 6. Geological Mapping and Surveying • After the process of scaling the geologists work was to make the geological log sheet of the rock class type of joints and faults and other aspects relating to the geological mapping of the tunnel face. • The Rock Class of the tunnel face is found out after the determination of Rock Tunneling Quality Index (Q-value). • The process of geological mapping is simultaneously followed by surveying. • Along with the alignment fixing of tunnel, surveying was carried out to determine the chainage and pull from the recent Blast. • Resection is carried out to fix the tunnel alignment, the steps followed to carry out Resection is explained in detail in Daily Observation Log.
  • 30. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: A surveyor conducting alignment survey of tunnel Fig: Face mapping by a Geologist
  • 31. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering 7. Rock Support Installation • After the geologists identify the the rock support class than the supports pertaining to the suitable tunnel face and the rock mass was installed which was either spot bolt , Rock Bolt or in worst cases Ribs which was done in accordance with the rock class determined as per the approved design drawings. Fig: Rock bolts Fig : Rib Installation
  • 32. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Short Description on the type of supports used • Spot Bolt These are the bolts which are locally installed at sites that appear to be prone to failure ,may be on the roof or floor. Spot bolts are used at certain spots to prevent failure of individual blocks and wedges. The observed dimension of the rock bolt used in our site was 2m length and 20mm diameter.
  • 33. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • Rock Bolt  Is generally a long anchor bolt. Used for stabilizing rock excavations in the tunnels and rock cuts. It transfers load from the unstable exterior to the confined (and much stronger) interior of the rock mass. Dimensions of rock bolt used in the site were 2-2.5m length with 20 mm diameter.
  • 34. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig : Rock Bolt Fig : Installed Rock Bolt
  • 35. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • Rib Installation Ribs were installed in the excavation sites of the tunnels specifically, pertaining to the particular rock classes with low stability. Ribs of IS standard I – section (IS 808, ISMB 150, 15kg/m) in combination with high strength concrete were used. In our site the rib was of arc and post type with two pieces of each component. The arc and post were attached to each other by plates and nut bolts. The dimension of the plate was 18cm * 15cm and of the diameter of bolt was 16mm. There were 4 holes and bolts in the plate with the diameter of holes 2mm greater than of bolts.
  • 36. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Then the backfilling was performed which was done in the form of boulder packing. The boulders were then bind with cement mixture of M25 strength. The backfilling were held by wire mesh with dimension of 2.1m*1.1m and 4.75mm diameter ,usually six number of wire mesh were used per rib. Tie rod and anchor rod were also used for further support and stabilization of the rib. The tie rod was 20mm diameter and 1m length whereas the anchor rod had same diameter but the length was 2m.
  • 37. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig : Rib Installation Fig : Tie Rod Welding
  • 38. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig : Wire Mesh Fig : Anchor rod Fig : Boulder Packing
  • 39. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • Shotcreting: Shotcrete refers to concrete or mortar conveyed through a hose and pneumatically projected at high velocity onto a surface, as a construction technique. In our Internship we only observed dry shotcreting at our site. The materials used were cement , sand , water and aggregate of nominal max size 10mm. The design strength of shotcrete was generally M30 . Steel fiber Crete was used as reinforcement. For rapid setting of shotcrete accelerating admixture for dry shotcreting was used. Generally 25 kg admixture was used per batch of shotcreting.
  • 40. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig : Shotcreting Fig : Mixer for mixing of materials
  • 41. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering • Slope Stabilization This was generally performed in the early stages of the tunnel construction. The bearing capacity of the natural slope decreases due to tunnel face excavation. Cement grouting or shotcreting was done for stabilization in accordance with the slope condition. Spiling rods were also used to support the tunnel during early stages . Spiling rod provide a protective canopy, to enable the heading of a tunnel to be advanced without the risk of falling debris .
  • 42. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig : Grouting of Slope Fig: Spiling Rod
  • 43. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Rock Class Support Type Pattern Spacing I 2m long,20mm dia. Spot Bolt with Dry Steel Fiber Shotcrete 50mm thick 1-1 - II 2m long,20mm dia. Rock Bolt with Dry Steel Fiber Shotcrete 75mm thick 5-6 1.6m c/c III 2m long,20mm dia. Rock Bolt with Dry Steel Fiber Shotcrete 100mm thick 6-7 1.4 m c/c IV 2m long,20mm dia. Rock Bolt with Dry Steel Fiber Shotcrete 125mm thick 7-8 1.2m c/c V 2.5m long,20mm dia. Rock Bolt with Dry Steel Fiber Shotcrete 150mm thick 8-9 1m c/c VI 3m long,20mm dia. Rock Bolt with Dry Steel Fiber Shotcrete 200mm thick & ISMB 150 beam sets 1m c/c 8-9 1m c/c ROCK SUPPORT TYPE
  • 44. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: Steel fiber crete used as reinforcement Fig: A mixer
  • 45. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Activity Time (min) Specifics [Tunnel 4.2m x 4.2m D-shape] Drilling 220** Avg. approx. 74 holes per round, Jackhammer on pushers leg Loading 90 Approx. 73 kg explosives loading per blast [Gneiss/Quartz] Blasting 20 - Ventilation 15 - Mucking 140 Mechanical [1 Loader, 1 tipper] Scaling 20 Manual Surveying and Face Mapping 50 Resection and Q-Value Evaluation Rock Bolting 170 Tunnel Support Type III Pattern [6/7 @ 1.40m c/c] Shot Creting 210 (Approx. 125mm – 150mm thick) Time for one round 935 Approx. 16hours per round, Pull obtain=0.9m-1.7m =1.3m avg Weekly Progress 2shifts, 9hrs per shift, 14shift per week 14 shifts/week*9 hrs/week*1.3 m pull 16 hrs =10.2 m/week TUNNEL CYCLE TIMES OF A FULLROUND-KALBANDI KHOLSI TUNNEL SITE ** Avg. drill time found to drill a hole of 1.7m length was 3m -4m. Drilling time varies depending upon rock mass and efficiency of workers.
  • 46. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Major Problems Encountered In The Worksite Human Errors • Not arriving in time for work. • Lack of skill and diligence in some manpowers. • No consideration for proper and optimum material usage. • Mishandling of equipment. Technical Errors • Machine wearing due to continuous use. • No proper maintenance of equipment. • No availability of advance equipment in all of the sites like boomer. • Unavailability of electricity for certain time period. • Less consideration for safety of manpower such as no availability of safety googles etc.
  • 47. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Geological Problems • Very strong rock class in Adit II tunnels due to which problems of socket holes and under break occurred of length 30cm to 80cm due to hard rock. • Very weak rock class in outlet tunnel due to which continuous rib installation and also rock over break occurred. Other Problems • Unexpected and unscheduled problems such as continuous strikes, Banda etc. • Untimely payment of salary which lead to strikes from man power.
  • 48. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering A BRIEF OVERVIEW OF OUR FIELD VISIT TO OTHER HYDRO PROJECTS • As our major observation were based on the works of a tunnel cycle and our selected project was in initial phase of the construction during our internship period, we asked our supervisor Mr. Ganga Ram Maharjan for a field visit to other hydro-projects for observation of major hydro-power related structures in which he agreed to volunteer. • Field visit was made to Himalayan Hydroelectric project [12 MW] located d/s to our project. • Similarly, field visit was made to the Middle Modi Hydro project [15.1 MW] as per the course of study of our internship period. The report of this field visit is briefly discussed in the Daily Observation logs of date (15-16)/02/2076.
  • 49. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: ongoing Anchor block and Saddle Support construction of Himalayan Hydro project Fig: ongoing construction of powerhouse and saddle supports of Himalayan Hydro Project
  • 50. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: Headworks of Middle Modi hydro project [MMHP] Fig: Headrace canal of MMHP Fig: Settling basin of MMHP
  • 51. Internship Project - GROUP 11 Kathmandu University , Department of Civil Engineering Fig: Headrace Tunnel outlet Fig: Ongoing Powerhouse construction Picture with supervisor