Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101
www.ijera.com 95 | P a g e
Construction Time Analysis For Different Steps In Drill-And-
Blast Method Of Hydro Power Tunnel Excavation
Erion Periku1
, Algest Aga2
1
Department of Civil Engineering, Epoka University, Tirana, Albania
1
Fan River Hydro Power Project, Aydiner Construction Co., Lezhe, Albania
2
Department of Mineral Resources Engineering, Tirana Polytechnic University, Tirana, Albania
ABSTRACT
One of the most important factors influencing the decision whether and how a tunnel is to be built are the
estimated time and costs of construction. This study is based on construction time analysis for different steps in
drill-and-blast method of hydro power tunnel excavation in working phase of 6.256,00 meters of tunnels which
have different diameters varying from 4,20 to 7,60. There are made 737 field measurements and it is seen that
many of the machinery and workmanship productions rates per unit time are significantly lower, varying from
35% to 50%, of that defined in their technical specifications, measurements indicate that highest performance is
reached in 7,60m diameter tunnel excavation. It is believed that these data will be helpful for planning and
management process of tunnel construction projects, especially those planned to be built in Albania where labor
market carries similar features.
Keywords –Albania, drill and blast, construction time, tunnel excavation
I. INTRODUCTION
Technological developments of XX and XXI
century have set tunnels as an integral part of roads,
hydropower works, mines etc. They are among the
most complicated structures that require in-depth
engineering studies and updated data. Although
preliminary analysis of tunnel opening methods are
based on geological studies, geological maps and
survey of the tunnel axis terrain, decisions are
strongly based on previous experiences. In
hydropower works energy tunnels are structural
elements, which are constructed to divert the natural
flow of water. They are built to utilize the water
potential energy; hence the hardness of the rock,
through which the energy tunnel passes, is not the
main selection criteria. The rock hardness effects
directly the tunnel excavation time therefore
uncertainties of the soil structure and inability to
pass the tunnel through hard rock makes time
prediction difficult, this difficulty is mostly solved
by previous experiences.
Albanian tunnel engineers and tunnel labor
market had a valuable experience in design,
construction and strengthening of the energy
tunnels, which reached its peak around the year
1985 [1]. After this period, as many sectors of
Albanian industry, there was a stagnation of more
than 25 years in construction of energy tunnels
which made it difficult the use of gained experience
and updating of energy tunnel construction data,
especially time and cost ones. Therefore this study
attempts to provide an overview of tunnel
construction time necessary for any particular
excavation process based on the construction of
tunnels on the Fan river hydropower projects, which
can be helpful for the Albanian tunnel managers and
engineers to reduce uncertainties and estimate more
realistic time and cost of construction.
Results of this study are based on analysis of
6.256,00 meters of tunnel excavation which have
different diameters varying from 4,20 to 7,60
meters. The data were selected such as to present in
the best way all excavation phases of drill-and-blast
method. In this study it was concluded that the time
required to complete an excavation processes is
almost two times higher than that provided in
technical specifications.
II. PREVIOUS WORKS
One of the most important factors influencing
the decision whether and how a tunnel is to be built
are the estimated time and costs of construction [2].
The construction time significantly influences the
tunnel construction costs, because substantial part of
the costs comprises of the labor and machinery
costs, which are time dependent [3]. As the labor
and machinery costs are time dependent researchers
have worked to collect statistical data for the
consumption of time during various different
working steps within a drill-and-blast method, such
as excavation, mucking out and the installation of
rock bolts and steel arches support [4]. Several
reports states that cost and time, estimated by the
early design phases, overruns commonly in
infrastructure projects that include tunnels [5].
Statistical and updated data for Albanian labor and
RESEARCH ARTICLE OPEN ACCESS
Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101
www.ijera.com 96 | P a g e
machinery time consumption in tunnel construction
projects could not be found [1] therefore this study
tend to contribute in creation of a realistic database
which can be successfully implanted in existing
tunnel construction time and cost models.
III. DRILL AND BLAST METHOD
Tunnel excavation can be seen as a cyclic
process with the main activities executed in series
[6]. The unit of each cycle in drill and blast method
is named round and consists of four successive
operations, namely: drill, blast, muck and
installation of primary support [7]. Drill is the first
operation of a single round and consists of rock
quality decision done by geological engineer,
application of holes and tunnel face done by survey
engineer, drilling the holes in the tunnel face done
by drilling jumbo. Blasting consist of charging the
holes with explosive, blasting them and provide
fresh air via ventilation. Pieces of loosened rock
remaining on the tunnel roof and walls during
blasting process have to be removed after mucking
machines and materials handling equipment are
mobilized, and the muck is hauled out of the tunnel
face. The primary support is directly related with
quality of rock and it is in reverse proportion of it,
as the hardness of rock increases the amounts of
primary support decreases, types of primary support
and round length of tunnels on the Fan river
hydropower projects are shown in Table 1.
Table 1. Primary Support of Tunnels on the Fan River Hydropower Projects [1]
Project
Value
Rock Quality [8] Round Length
(m)
Primary Support
RQD(%) Description
5 0-20 Very Poor 1,00-1,50
5+15 cm shotcrete, wire mesh, systematic rock bolts,
I steel arch profile
4 21-40 Poor 2,00-2,50 5+5 cm shotcrete, wire mesh, systematic rock bolts
3 41-60 Fair 2,50-3,00 5+5 cm shotcrete, wire mesh, systematic rock bolts
2 61-80 Good 3,50-4,00 5 cm shotcrete, local rock bolts
1 81-100 Very Good 3,50-4,00 no primary support
Rock quality in this project is presented in five
main classes and based on this there is given the
support system shown in Table 1, although there can
be different rates that include more than five rock
quality types which recommends different support
systems [8]. Shotcrete is the element that is used in
every tunnel where prime support is needed, wire
mesh is an element mainly used where the tension
stresses occur in order to reinforce the concrete, now
days it is mostly replaced with steel or plastic fibers.
Rock bolt is an anchor used for stabilizing rock
excavations and transfers load from the unstable
exterior, to the confined interior rock mas, mainly
used in fair, poor and very poor rocks. Steel arch
supports are used in poor or very poor rocks and for
this project it is chosen to be I section rib but it can be
wide flange rib, TH section rib, 3 bar lattice girder or
4 bar lattice girder.
Installation of primary support is the last
operation done within a single round. Depending upon
project types it is determined either making the
primary support within the round or not [1]. Technical
specification of Fan river hydropower projects has
determined it as follows: for very poor rocks the next
round can start only when primary support is
completed, for poor and fair rocks there can be at
most one round without primary support before the
next round starts and for good rocks there can be at
most two rounds without primary support before ne
next round starts.
IV. PROCESS TIME ASSESSMENT
Four successive operations drill, blast, muck and
installation of primary support are analyzed
separately, like shown in Table 2. For these operations
there is analyzed velocity of operating vehicles, time
of engineering decisions and workmanship in tunnel
construction phase.
The vehicles are; jumbo, which is used to drill the
holes in tunnel face as well as to drill the holes for
rock bolt and forepolings; excavator, which is used to
remove pieces of loosened rock remaining on the
tunnel roof and walls during blasting, loader is used to
load the muck in trucks which haul it out of the tunnel
face, shotcrete pump is used to spray the shotcrete,
sent there by mixer, into tunnel walls, pick-up trucks
which is used for technical staff transport within the
tunnel, cement injection pump, which is used to inject
cement into rock bolt holes, is moved in tunnel fixed
over pick-up truck.
Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101
www.ijera.com 97 | P a g e
Table 2. Time effecting work processes
Process Work Done Time effecting
Drill
- Rock quality decision
- Application of holes
- Drilling the holes
1. Pick-up track forward and backward velocity.
2. Geological engineer time to sketch the tunnel face.
3. Survey engineer time to apply the holes and tunnel
face.
4. Jumbo forward and backward velocity.
5. Workmanship time to drill the holes.
Blast
- Charge the holes
- Blats
- Ventilation
1. Pick-up track forward and backward velocity.
2. Workmanship time to charge the holes with explosive.
3. Blasting time
4. Ventilation time
Muck
- Remove pieces of
loosened rock
- Load the muck in
trucks
- Haul the muck out of
tunnel
1. Excavator forward and backward velocity.
2. Workmanship time to remove pieces of loosened rock
3. Loader forward and backward velocity.
4. Workmanship time to load the muck in trucks
5. Truck forward and backward velocity.
Primary Support
- Application of
shotcrete
- Installation of wire
mesh
- Topographic
measurements
- Installation of steel
arch profile
- Installation of rock
bolts
1. Shotcrete pump forward and backward velocity.
2. Mixer forward and backward velocity.
3. Workmanship time to spray shotcrete
4. Pick-up track forward and backward velocity.
5. Workmanship time to install wire mesh
6. Survey engineer time to set steel arch profile
7. Loader forward and backward velocity.
8. Workmanship time to install steel arch profile
9. Jumbo forward and backward velocity
10. Workmanship time to drill rock bolt holes
11. Workmanship to install rock bolts
Time effecting processes are defined in detail in
Table 2, for all them there are done measurements in
the faces of the tunnel which have different distances
from the entrance of it. The measurement are done in
time interval of about five months in the excavation
process of 6.256,00 m tunnel with diameter varying
from 4,20 m to 7,60 m. The geological formation of
the analyzed tunnel segments is mainly composed of
basalt, serpentine, kaolin, diabase, dunite and there
are 0% very good rock (class 1), 24% good rock
(class 2), 36% fair rock (class 3), 23% poor rock
(class 4), 17% very poor rock (class 5).
0,0 500,0 1.000,0 1.500,0 2.000,0 2.500,0
Distance From Tunnel Enterance (m)
0,0
1,0
2,0
3,0
4,0
5,0
Velocity(m/s)
Fig. 1, Pick-up track and jumbo velocity measurements; (a) Pick-up track and jumbo forward velocity, (b) Pick-
up track and jumbo backward velocity.
For drilling process there are done 163
measurements in tunnel faces which have different
distance from tunnel entrance. From these
measurements 117 are done to calculate the forward
velocity and 46 are done to calculate the backward
velocity of pick up tracks and jumbo. All the work
machines used in tunnel construction run backward
till the nearest tunnel adit, which in this project are
designed to be every 250 meters. In the same way
there are measured geological and survey engineers
time needed for their work described in Table 2 in
105 different points. Workmanship time to drill the
holes is calculated in 56 tunnel faces which consist
of four different rock qualities (class). The average
forward velocity of the pick-up track is measured to
be 3,41 m/s or 12,28 km/h as shown in Fig. 1 (a),
*Pick Up Track *Jumbo
*Pick Up Track *Jumbo
(a) (b)
Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101
www.ijera.com 98 | P a g e
and its backward velocity is measured to be 1,97
m/s or 7,10 km/h as shown in Fig. 1 (b),. Similarly
the forward velocity of the jumbo is measured to be
1,87 m/s or 6,74 km/h and its backward velocity is
measured to be 1,15 m/s or 4,12 km/h. As it is seen
from Fig. 1 the velocity of pick up track and jumbo
are not related with the distance of tunnel face from
its entrance. The average time needed from
geological engineer to make rock quality decision
and sketch the tunnel face is 16,34 minutes as
shown in Fig. 2, and that of survey engineer to apply
the holes and tunnel face is 25,44 minutes, as shown
in Fig. 2, Similarly to the vehicles velocity,
geological and survey engineer times are not related
to the distance of tunnel face from its entrance. It is
important to emphasize that these engineering teams
can work simultaneously in the same tunnel face.
VAR_5
VAR_3
0,0 20,0 40,0 60,0 80,0 100,0 120,0
Number of Measurements (times)
0,0
10,0
20,0
30,0
40,0
Time(min)
Fig. 2, Time needed by, geological engineer to make
rock quality decision and sketch the tunnel face and
survey engineer to apply the holes and tunnel face.
Workmanship to drill the holes is directly
related to the quality of rock. For every rock quality
(class) there exists a pattern which specifies the
number of holes per each tunnel face as well as their
depth. For this reason the best way to measure the
drilling process is time per unit length. In Fig. 3 the
drilling process of different rock quality is drown,
the data are collected from 100 measurements in 4
different rock quality, and the average time to drill 1
meter rock is 28,52 sec. Time in minutes to drill
holes in different tunnel faces can be calculated as
(28,52/60) x (number of holes per tunnel face) x
(round length).
0,0 20,0 40,0 60,0 80,0 100,0 120,0
Number ofMeasurements (times)
15,0
25,0
35,0
45,0
DrillinTime(Sec/meter)
Fig. 3, Drilling time that is needed to drill 1 meter
rock measured in four different rock quality.
Blasting is measured similarly to drilling process, as
there exists five rock qualities there would be five
different times. The measurements could be done
based either on time needed to charge 1 meter hole,
or the time needed to charge 1 mete cube rock to be
blasted, for this study it was chosen to make the
measurements per one meter cube rock that would
be blasted. There are done 97 measurements as
shown in Fig. 4 and the average time to charge the
holes of 1 meter cube blasted rock is 0,63 minutes,
and the time in minutes to charge a different tunnel
face can be calculated as (0,63) x (tunnel face area)
x (round length). The velocity of the pick-up track
that carries the explosive material to the tunnel face
is same with that measured in drilling process. The
blasting time is in the range of some seconds and it
does not have any effect in the entire time.
Ventilation system of this project is face
concentration, air supply system. The time needed to
supply air to tunnel face after blasting is in the range
of 40 to 50 minutes.
0,0 20,0 40,0 60,0 80,0 100,0
Number of Measurments (Times)
0,4
0,5
0,6
0,7
0,8
0,9
ChargingTime(min/m3)
Fig. 4, Charging time that is needed to blast 1 cubic
meter rock measured in four different rock quality.
Mucking process is described in detailed in
Table 2. There are done 50 measurements for the
excavator velocity and 95 measurements for
workmanship time to remove pieces of loosened
rock as shown in Fig 5. It is measured that the
forward and backward velocity of the excavators is
approximately the same for this reason it is defined
only as excavator velocity. The average velocity of
the excavator is measured to be 1,25 m/s or 4,32
km/h as shown in Fig 5 (a). Workmanship time to
remove pieces of loosened rock is measured in 4
different rock quality and it has an average time of
24,56 minutes for very poor (Class V) rock, 18,77
minutes for poor (Class IV) rock, 15,59 minutes for
fair (Class III) rock and 14,71 minutes for good
(Class II) rock, data of this measurements are
presented in Fig 5 (b).
* Geological engineer * Survey engineer
Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101
www.ijera.com 99 | P a g e
0,0 10,0 20,0 30,0 40,0 50,0 60,0
Number of Measurments (Times)
0,5
1,0
1,5
2,0
Velocity(m/s)
0,0 10,0 20,0 30,0
NumberofMeasurments(Times)
5,0
10,0
15,0
20,0
25,0
30,0
35,0
Time(min)
Fig. 5, Excavator velocity and workmanship time to remove pieces of loosened rock measurements; (a) Forward
and backward velocity of excavator, (b) Workmanship time to remove pieces of loosened rock in four different
rock quality (Class II to Class V).
It is measured that loader and material
transporting trucks have very closed average velocity,
for these reason the data are put in the same graph.
There are done 77 measurements as shown in Fig. 6
and the average forward velocity of the loader and
track is measured to be 3,34 m/s or 12,03 km/h and
the backward speed of them is 1,62 m/s or 5,83 km/h.
0,0 20,0 40,0 60,0 80,0
NumberofMeasurements(Times)
0,0
1,0
2,0
3,0
4,0
5,0
6,0
Velocity(m/s)
Fig. 6, Loader and track forward and backward
velocity measurements.
Time needed to load the muck in truck is
measured in 65 tunnel faces which have different
distance from tunnel adit. The truck that hauls the
material out of tunnel stays on tunnel adit and the
material is transported from tunnel face to nearest
tunnel adit by loader. Results are shown in Fig. 7 and
have a parabolic shape, the time needed to load the
material increases exponentially with distance and it
best fits with Equation 1, where L is the unit time in
minutes needed to load 1 meter cube muck and D is
the distance in meters of tunnel face from nearest
tunnel adit. As it is shown in Fig. 7 as the distance
changes from 150 meters to 250 meters the time
needed to load one cubic meter material increases
twice.
L = 0,50 e (0,005 x D)
(Eq. 1)
0,0 50,0 100,0 150,0 200,0 250,0
Distance from Tunnel Face to Adit (m)
0,0
0,5
1,0
1,5
2,0
LoadingTime(min/m3)
Fig. 7, Time needed to load one cubic meter material
in track.
Shotcrete pump and mixer have the same
velocity as loader which is shown in Fig. 7, there are
done 71 measurements on shotcrete pump velocity
and 64 on mixer velocity ant it is noted that the
average velocity of them is almost the same and very
closed to that of loader. There are different shotcrete
thicknesses as shown in Table 1 for these reason the
measurements are done per meter cube of sprayed
material. The data are collected in 117 tunnel faces
and the average time needed to spray a meter cube
shotcrete is 11,40 minutes as shown in Fig. 8. The
time needed to spray the shotcrete increases slightly
as the tunnel face goes deeper, although there is
measured only the time that shotcrete pump sprays
the material.
0,0 25,0 50,0 75,0 100,0 125,0
Number of Measurements (Times)
5,0
10,0
15,0
TimetoSprayShotcrete(min/m3)
Fig. 8, Time needed to spray one cubic meter
shotcrete in tunnel.
* Class V, * Class IV,* Class III, * Class II
(a) (b)
* Forward Velocity, * Backward Velocity
Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101
www.ijera.com 100 | P a g e
Installation of steel wire mesh changes from
significantly from Class V to other rock qualities. In
the Class V rock the steel profile is installed and after
that the wire mesh, so steel arches are used as support
in other cases there must be anchored some steel ribs,
generally 12mm in diameter, which works as steel
wire mash support. Time needed to anchor those steel
ribs is some times greater than that of wire mesh
installation its self. There are done 46 measurements
in Class V rock and 46 measurements in other rock
qualities. Time needed to install one square meter
steel wire mesh in Class V is approximately 0,68
minutes, and time needed to install one square meter
steel wire mesh in other rock qualities is 1,29 minutes
as shown in Fig. 9.
0,0 10,0 20,0 30,0 40,0 50,0
Number of Measurements (Times)
0,0
0,5
1,0
1,5
2,0
TimeofWireMeshInstallation(min/m2)
Fig. 9, Time needed to install one square meter wire
mesh in tunnel.
0,0 10,0 20,0 30,0 40,0 50,0
Number ofMeasurements(Times)
30,0
50,0
70,0
90,0
TimetoInstallaSteelArch(min)
Fig. 10, Time needed to spray one cubic meter
shotcrete in tunnel
Steel arches are installed only in Class V rocks
as shown in Table 2. There are done 44
measurements of steel arch installation, and the
average time to install a single arch is 56,01 minutes
as shown in Fig. 10. Steel arch installation consumes
a large amount of time at tunnel excavation process.
The rock bolt installation mainly consists of three
steps, drilling rock bolt holes, injecting cement paste,
inserting rock bolt. Drilling process is done by jumbo
and has the same velocity of that showing in Fig. 2,
so for bolt installation only cement injection ant rock
bolt inserting time are measured. There are done 84
measurements on three different rock bolt length 3, 4
and 6 meters. Both cement injection time and rock
bolt inserting time is measured in term of rock bolt
length. The average time needed to inject cement in 1
meter hole is 1,12 minutes and that of inserting the
rock bolt and threading the nut is 0,62 minutes as
shown in Fig. 11. The total time needed to inject
cement paste and install rock bolt in minutes is 1,74 x
L, where L is length of rock bolt in meters.
0,0 20,0 40,0 60,0 80,0 100,0
Number ofMeasurements (Times)
0,0
0,5
1,0
1,5
2,0
Time(min/m)
Fig. 11, Time needed to spray one cubic meter
shotcrete in tunnel
V. CONCLUSIONS
In this study 737 field measurements were made
to define the time needed for any particular process in
drill and blast tunnel excavation method. Generally it
is seen that many of the machinery and workmanship
productions rates per unit time are significantly lower
than them defined in their technical specifications.
Measured velocity of heavy machineries is almost
35%, and their production rates are nearly 50% of
that defined and programed by project developers,
similar observation are done in workmanship
processes. The results obtained in different tunnel
diameters, from 4,20m to 7,60m, indicate that highest
performance is reached in 7,60m diameter tunnel
excavation although the differences are not
significant and for this study there is not a good
correlation between tunnel diameter and construction
time. It is measured that best construction
performance is reached when distance from tunnel
adit and tunnel face is smaller than 200 meters.
These measurements are very important in practical
use and it is also believed that they will be helpful for
planning and management process of tunnel
construction projects, especially those planned to be
built in Albania where labor market carries similar
features.
REFERENCES
[1] A. Aga, Calculation of cycle time in hydro
power tunnel excavation and effect of
decision makers in construction cost, Case
study of Fan river hydropower projects (In
Albanian language), Master thesis, Tirana
Polytechnic University, Tirana, 2014.
[2] J. Reilly, The management process for
complex underground and tunneling
* Class V, * Class II - IV
* Rock bolt inserting, * Cement paste injection
Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101
www.ijera.com 101 | P a g e
projects. Tunneling and Underground Space
Technology 15(1), 2000, 31–44.
[3] O. Spackova, Risk management of tunnel
construction projects, Doctoral Thesis,
Czech Technical University in Prague,
Prague, 2012.
[4] T. Isaksson, Model for estimation of time
and cost based on risk evaluation applied on
tunnel projects, Doctoral Thesis, Royal
Institute of Technology, Stockholm, 2002.
[5] T. Isaksson, H. Stille, Models for Estimation
of Time and Cost for tunnels Projects Based
on Risk Evaluation, Rock Mechanics and
Rock Engineering, 38(5), 2005, 373-398.
[6] S. Bagherian, Application of Important
Factors in Tunnel Projects, Research
Journal of Applied Sciences, Engineering
and Technology 6(2), 2013, 181-186.
[7] M. Messinella, Models for the analysis of
tunneling construction processes, Master
Thesis, Concordia University, Montreal,
2010.
[8] E. Karahan, Design of excavation and
support systems for the Çubukbeli tunnel in
Antalya, Master Thesis, Middle East
Technical University, Ankara, 2010.

More Related Content

What's hot

Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINALBenjamin Kramka
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersVR M
 
Case study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONCase study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONShagun mahajan
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003Minh Bui Si
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionStefan Lammert
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignDr Mazin Alhamrany
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Hitesh Khanna
 
Construction manual chapter 2
Construction manual chapter 2Construction manual chapter 2
Construction manual chapter 2vps1968
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsgifanta
 
Geotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILLGeotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILLDr. Malek Smadi
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecturegefyra-rion
 

What's hot (20)

Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINAL
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
 
Case study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONCase study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATION
 
Report
ReportReport
Report
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel construction
 
Aoil profile 2016
Aoil  profile  2016 Aoil  profile  2016
Aoil profile 2016
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
Mtech Project_2013_ppt
Mtech Project_2013_pptMtech Project_2013_ppt
Mtech Project_2013_ppt
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
Construction manual chapter 2
Construction manual chapter 2Construction manual chapter 2
Construction manual chapter 2
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problems
 
ICDE2006, Singapore
ICDE2006, SingaporeICDE2006, Singapore
ICDE2006, Singapore
 
Geotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILLGeotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILL
 
149-Uludag[1]
149-Uludag[1]149-Uludag[1]
149-Uludag[1]
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecture
 

Similar to Construction time analysis for hydro power tunnel excavation

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsIRJET Journal
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportDivyesh Mungara
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Mohit Shukla
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET Journal
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...Mary Montoya
 
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Dr. Amarjeet Singh
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...IRJET Journal
 
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitField Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitIRJET Journal
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methodsHalim Rahman
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technologyAbhishek Paul
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...CrimsonPublishersAMMS
 

Similar to Construction time analysis for hydro power tunnel excavation (20)

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
SPE-212574-MS.pdf
SPE-212574-MS.pdfSPE-212574-MS.pdf
SPE-212574-MS.pdf
 
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 
IRTG ppt.pptx
IRTG ppt.pptxIRTG ppt.pptx
IRTG ppt.pptx
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
4880 4
4880 44880 4
4880 4
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
 
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitField Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer Bit
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
 

Recently uploaded

How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessPixlogix Infotech
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 

Recently uploaded (20)

How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 

Construction time analysis for hydro power tunnel excavation

  • 1. Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101 www.ijera.com 95 | P a g e Construction Time Analysis For Different Steps In Drill-And- Blast Method Of Hydro Power Tunnel Excavation Erion Periku1 , Algest Aga2 1 Department of Civil Engineering, Epoka University, Tirana, Albania 1 Fan River Hydro Power Project, Aydiner Construction Co., Lezhe, Albania 2 Department of Mineral Resources Engineering, Tirana Polytechnic University, Tirana, Albania ABSTRACT One of the most important factors influencing the decision whether and how a tunnel is to be built are the estimated time and costs of construction. This study is based on construction time analysis for different steps in drill-and-blast method of hydro power tunnel excavation in working phase of 6.256,00 meters of tunnels which have different diameters varying from 4,20 to 7,60. There are made 737 field measurements and it is seen that many of the machinery and workmanship productions rates per unit time are significantly lower, varying from 35% to 50%, of that defined in their technical specifications, measurements indicate that highest performance is reached in 7,60m diameter tunnel excavation. It is believed that these data will be helpful for planning and management process of tunnel construction projects, especially those planned to be built in Albania where labor market carries similar features. Keywords –Albania, drill and blast, construction time, tunnel excavation I. INTRODUCTION Technological developments of XX and XXI century have set tunnels as an integral part of roads, hydropower works, mines etc. They are among the most complicated structures that require in-depth engineering studies and updated data. Although preliminary analysis of tunnel opening methods are based on geological studies, geological maps and survey of the tunnel axis terrain, decisions are strongly based on previous experiences. In hydropower works energy tunnels are structural elements, which are constructed to divert the natural flow of water. They are built to utilize the water potential energy; hence the hardness of the rock, through which the energy tunnel passes, is not the main selection criteria. The rock hardness effects directly the tunnel excavation time therefore uncertainties of the soil structure and inability to pass the tunnel through hard rock makes time prediction difficult, this difficulty is mostly solved by previous experiences. Albanian tunnel engineers and tunnel labor market had a valuable experience in design, construction and strengthening of the energy tunnels, which reached its peak around the year 1985 [1]. After this period, as many sectors of Albanian industry, there was a stagnation of more than 25 years in construction of energy tunnels which made it difficult the use of gained experience and updating of energy tunnel construction data, especially time and cost ones. Therefore this study attempts to provide an overview of tunnel construction time necessary for any particular excavation process based on the construction of tunnels on the Fan river hydropower projects, which can be helpful for the Albanian tunnel managers and engineers to reduce uncertainties and estimate more realistic time and cost of construction. Results of this study are based on analysis of 6.256,00 meters of tunnel excavation which have different diameters varying from 4,20 to 7,60 meters. The data were selected such as to present in the best way all excavation phases of drill-and-blast method. In this study it was concluded that the time required to complete an excavation processes is almost two times higher than that provided in technical specifications. II. PREVIOUS WORKS One of the most important factors influencing the decision whether and how a tunnel is to be built are the estimated time and costs of construction [2]. The construction time significantly influences the tunnel construction costs, because substantial part of the costs comprises of the labor and machinery costs, which are time dependent [3]. As the labor and machinery costs are time dependent researchers have worked to collect statistical data for the consumption of time during various different working steps within a drill-and-blast method, such as excavation, mucking out and the installation of rock bolts and steel arches support [4]. Several reports states that cost and time, estimated by the early design phases, overruns commonly in infrastructure projects that include tunnels [5]. Statistical and updated data for Albanian labor and RESEARCH ARTICLE OPEN ACCESS
  • 2. Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101 www.ijera.com 96 | P a g e machinery time consumption in tunnel construction projects could not be found [1] therefore this study tend to contribute in creation of a realistic database which can be successfully implanted in existing tunnel construction time and cost models. III. DRILL AND BLAST METHOD Tunnel excavation can be seen as a cyclic process with the main activities executed in series [6]. The unit of each cycle in drill and blast method is named round and consists of four successive operations, namely: drill, blast, muck and installation of primary support [7]. Drill is the first operation of a single round and consists of rock quality decision done by geological engineer, application of holes and tunnel face done by survey engineer, drilling the holes in the tunnel face done by drilling jumbo. Blasting consist of charging the holes with explosive, blasting them and provide fresh air via ventilation. Pieces of loosened rock remaining on the tunnel roof and walls during blasting process have to be removed after mucking machines and materials handling equipment are mobilized, and the muck is hauled out of the tunnel face. The primary support is directly related with quality of rock and it is in reverse proportion of it, as the hardness of rock increases the amounts of primary support decreases, types of primary support and round length of tunnels on the Fan river hydropower projects are shown in Table 1. Table 1. Primary Support of Tunnels on the Fan River Hydropower Projects [1] Project Value Rock Quality [8] Round Length (m) Primary Support RQD(%) Description 5 0-20 Very Poor 1,00-1,50 5+15 cm shotcrete, wire mesh, systematic rock bolts, I steel arch profile 4 21-40 Poor 2,00-2,50 5+5 cm shotcrete, wire mesh, systematic rock bolts 3 41-60 Fair 2,50-3,00 5+5 cm shotcrete, wire mesh, systematic rock bolts 2 61-80 Good 3,50-4,00 5 cm shotcrete, local rock bolts 1 81-100 Very Good 3,50-4,00 no primary support Rock quality in this project is presented in five main classes and based on this there is given the support system shown in Table 1, although there can be different rates that include more than five rock quality types which recommends different support systems [8]. Shotcrete is the element that is used in every tunnel where prime support is needed, wire mesh is an element mainly used where the tension stresses occur in order to reinforce the concrete, now days it is mostly replaced with steel or plastic fibers. Rock bolt is an anchor used for stabilizing rock excavations and transfers load from the unstable exterior, to the confined interior rock mas, mainly used in fair, poor and very poor rocks. Steel arch supports are used in poor or very poor rocks and for this project it is chosen to be I section rib but it can be wide flange rib, TH section rib, 3 bar lattice girder or 4 bar lattice girder. Installation of primary support is the last operation done within a single round. Depending upon project types it is determined either making the primary support within the round or not [1]. Technical specification of Fan river hydropower projects has determined it as follows: for very poor rocks the next round can start only when primary support is completed, for poor and fair rocks there can be at most one round without primary support before the next round starts and for good rocks there can be at most two rounds without primary support before ne next round starts. IV. PROCESS TIME ASSESSMENT Four successive operations drill, blast, muck and installation of primary support are analyzed separately, like shown in Table 2. For these operations there is analyzed velocity of operating vehicles, time of engineering decisions and workmanship in tunnel construction phase. The vehicles are; jumbo, which is used to drill the holes in tunnel face as well as to drill the holes for rock bolt and forepolings; excavator, which is used to remove pieces of loosened rock remaining on the tunnel roof and walls during blasting, loader is used to load the muck in trucks which haul it out of the tunnel face, shotcrete pump is used to spray the shotcrete, sent there by mixer, into tunnel walls, pick-up trucks which is used for technical staff transport within the tunnel, cement injection pump, which is used to inject cement into rock bolt holes, is moved in tunnel fixed over pick-up truck.
  • 3. Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101 www.ijera.com 97 | P a g e Table 2. Time effecting work processes Process Work Done Time effecting Drill - Rock quality decision - Application of holes - Drilling the holes 1. Pick-up track forward and backward velocity. 2. Geological engineer time to sketch the tunnel face. 3. Survey engineer time to apply the holes and tunnel face. 4. Jumbo forward and backward velocity. 5. Workmanship time to drill the holes. Blast - Charge the holes - Blats - Ventilation 1. Pick-up track forward and backward velocity. 2. Workmanship time to charge the holes with explosive. 3. Blasting time 4. Ventilation time Muck - Remove pieces of loosened rock - Load the muck in trucks - Haul the muck out of tunnel 1. Excavator forward and backward velocity. 2. Workmanship time to remove pieces of loosened rock 3. Loader forward and backward velocity. 4. Workmanship time to load the muck in trucks 5. Truck forward and backward velocity. Primary Support - Application of shotcrete - Installation of wire mesh - Topographic measurements - Installation of steel arch profile - Installation of rock bolts 1. Shotcrete pump forward and backward velocity. 2. Mixer forward and backward velocity. 3. Workmanship time to spray shotcrete 4. Pick-up track forward and backward velocity. 5. Workmanship time to install wire mesh 6. Survey engineer time to set steel arch profile 7. Loader forward and backward velocity. 8. Workmanship time to install steel arch profile 9. Jumbo forward and backward velocity 10. Workmanship time to drill rock bolt holes 11. Workmanship to install rock bolts Time effecting processes are defined in detail in Table 2, for all them there are done measurements in the faces of the tunnel which have different distances from the entrance of it. The measurement are done in time interval of about five months in the excavation process of 6.256,00 m tunnel with diameter varying from 4,20 m to 7,60 m. The geological formation of the analyzed tunnel segments is mainly composed of basalt, serpentine, kaolin, diabase, dunite and there are 0% very good rock (class 1), 24% good rock (class 2), 36% fair rock (class 3), 23% poor rock (class 4), 17% very poor rock (class 5). 0,0 500,0 1.000,0 1.500,0 2.000,0 2.500,0 Distance From Tunnel Enterance (m) 0,0 1,0 2,0 3,0 4,0 5,0 Velocity(m/s) Fig. 1, Pick-up track and jumbo velocity measurements; (a) Pick-up track and jumbo forward velocity, (b) Pick- up track and jumbo backward velocity. For drilling process there are done 163 measurements in tunnel faces which have different distance from tunnel entrance. From these measurements 117 are done to calculate the forward velocity and 46 are done to calculate the backward velocity of pick up tracks and jumbo. All the work machines used in tunnel construction run backward till the nearest tunnel adit, which in this project are designed to be every 250 meters. In the same way there are measured geological and survey engineers time needed for their work described in Table 2 in 105 different points. Workmanship time to drill the holes is calculated in 56 tunnel faces which consist of four different rock qualities (class). The average forward velocity of the pick-up track is measured to be 3,41 m/s or 12,28 km/h as shown in Fig. 1 (a), *Pick Up Track *Jumbo *Pick Up Track *Jumbo (a) (b)
  • 4. Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101 www.ijera.com 98 | P a g e and its backward velocity is measured to be 1,97 m/s or 7,10 km/h as shown in Fig. 1 (b),. Similarly the forward velocity of the jumbo is measured to be 1,87 m/s or 6,74 km/h and its backward velocity is measured to be 1,15 m/s or 4,12 km/h. As it is seen from Fig. 1 the velocity of pick up track and jumbo are not related with the distance of tunnel face from its entrance. The average time needed from geological engineer to make rock quality decision and sketch the tunnel face is 16,34 minutes as shown in Fig. 2, and that of survey engineer to apply the holes and tunnel face is 25,44 minutes, as shown in Fig. 2, Similarly to the vehicles velocity, geological and survey engineer times are not related to the distance of tunnel face from its entrance. It is important to emphasize that these engineering teams can work simultaneously in the same tunnel face. VAR_5 VAR_3 0,0 20,0 40,0 60,0 80,0 100,0 120,0 Number of Measurements (times) 0,0 10,0 20,0 30,0 40,0 Time(min) Fig. 2, Time needed by, geological engineer to make rock quality decision and sketch the tunnel face and survey engineer to apply the holes and tunnel face. Workmanship to drill the holes is directly related to the quality of rock. For every rock quality (class) there exists a pattern which specifies the number of holes per each tunnel face as well as their depth. For this reason the best way to measure the drilling process is time per unit length. In Fig. 3 the drilling process of different rock quality is drown, the data are collected from 100 measurements in 4 different rock quality, and the average time to drill 1 meter rock is 28,52 sec. Time in minutes to drill holes in different tunnel faces can be calculated as (28,52/60) x (number of holes per tunnel face) x (round length). 0,0 20,0 40,0 60,0 80,0 100,0 120,0 Number ofMeasurements (times) 15,0 25,0 35,0 45,0 DrillinTime(Sec/meter) Fig. 3, Drilling time that is needed to drill 1 meter rock measured in four different rock quality. Blasting is measured similarly to drilling process, as there exists five rock qualities there would be five different times. The measurements could be done based either on time needed to charge 1 meter hole, or the time needed to charge 1 mete cube rock to be blasted, for this study it was chosen to make the measurements per one meter cube rock that would be blasted. There are done 97 measurements as shown in Fig. 4 and the average time to charge the holes of 1 meter cube blasted rock is 0,63 minutes, and the time in minutes to charge a different tunnel face can be calculated as (0,63) x (tunnel face area) x (round length). The velocity of the pick-up track that carries the explosive material to the tunnel face is same with that measured in drilling process. The blasting time is in the range of some seconds and it does not have any effect in the entire time. Ventilation system of this project is face concentration, air supply system. The time needed to supply air to tunnel face after blasting is in the range of 40 to 50 minutes. 0,0 20,0 40,0 60,0 80,0 100,0 Number of Measurments (Times) 0,4 0,5 0,6 0,7 0,8 0,9 ChargingTime(min/m3) Fig. 4, Charging time that is needed to blast 1 cubic meter rock measured in four different rock quality. Mucking process is described in detailed in Table 2. There are done 50 measurements for the excavator velocity and 95 measurements for workmanship time to remove pieces of loosened rock as shown in Fig 5. It is measured that the forward and backward velocity of the excavators is approximately the same for this reason it is defined only as excavator velocity. The average velocity of the excavator is measured to be 1,25 m/s or 4,32 km/h as shown in Fig 5 (a). Workmanship time to remove pieces of loosened rock is measured in 4 different rock quality and it has an average time of 24,56 minutes for very poor (Class V) rock, 18,77 minutes for poor (Class IV) rock, 15,59 minutes for fair (Class III) rock and 14,71 minutes for good (Class II) rock, data of this measurements are presented in Fig 5 (b). * Geological engineer * Survey engineer
  • 5. Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101 www.ijera.com 99 | P a g e 0,0 10,0 20,0 30,0 40,0 50,0 60,0 Number of Measurments (Times) 0,5 1,0 1,5 2,0 Velocity(m/s) 0,0 10,0 20,0 30,0 NumberofMeasurments(Times) 5,0 10,0 15,0 20,0 25,0 30,0 35,0 Time(min) Fig. 5, Excavator velocity and workmanship time to remove pieces of loosened rock measurements; (a) Forward and backward velocity of excavator, (b) Workmanship time to remove pieces of loosened rock in four different rock quality (Class II to Class V). It is measured that loader and material transporting trucks have very closed average velocity, for these reason the data are put in the same graph. There are done 77 measurements as shown in Fig. 6 and the average forward velocity of the loader and track is measured to be 3,34 m/s or 12,03 km/h and the backward speed of them is 1,62 m/s or 5,83 km/h. 0,0 20,0 40,0 60,0 80,0 NumberofMeasurements(Times) 0,0 1,0 2,0 3,0 4,0 5,0 6,0 Velocity(m/s) Fig. 6, Loader and track forward and backward velocity measurements. Time needed to load the muck in truck is measured in 65 tunnel faces which have different distance from tunnel adit. The truck that hauls the material out of tunnel stays on tunnel adit and the material is transported from tunnel face to nearest tunnel adit by loader. Results are shown in Fig. 7 and have a parabolic shape, the time needed to load the material increases exponentially with distance and it best fits with Equation 1, where L is the unit time in minutes needed to load 1 meter cube muck and D is the distance in meters of tunnel face from nearest tunnel adit. As it is shown in Fig. 7 as the distance changes from 150 meters to 250 meters the time needed to load one cubic meter material increases twice. L = 0,50 e (0,005 x D) (Eq. 1) 0,0 50,0 100,0 150,0 200,0 250,0 Distance from Tunnel Face to Adit (m) 0,0 0,5 1,0 1,5 2,0 LoadingTime(min/m3) Fig. 7, Time needed to load one cubic meter material in track. Shotcrete pump and mixer have the same velocity as loader which is shown in Fig. 7, there are done 71 measurements on shotcrete pump velocity and 64 on mixer velocity ant it is noted that the average velocity of them is almost the same and very closed to that of loader. There are different shotcrete thicknesses as shown in Table 1 for these reason the measurements are done per meter cube of sprayed material. The data are collected in 117 tunnel faces and the average time needed to spray a meter cube shotcrete is 11,40 minutes as shown in Fig. 8. The time needed to spray the shotcrete increases slightly as the tunnel face goes deeper, although there is measured only the time that shotcrete pump sprays the material. 0,0 25,0 50,0 75,0 100,0 125,0 Number of Measurements (Times) 5,0 10,0 15,0 TimetoSprayShotcrete(min/m3) Fig. 8, Time needed to spray one cubic meter shotcrete in tunnel. * Class V, * Class IV,* Class III, * Class II (a) (b) * Forward Velocity, * Backward Velocity
  • 6. Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101 www.ijera.com 100 | P a g e Installation of steel wire mesh changes from significantly from Class V to other rock qualities. In the Class V rock the steel profile is installed and after that the wire mesh, so steel arches are used as support in other cases there must be anchored some steel ribs, generally 12mm in diameter, which works as steel wire mash support. Time needed to anchor those steel ribs is some times greater than that of wire mesh installation its self. There are done 46 measurements in Class V rock and 46 measurements in other rock qualities. Time needed to install one square meter steel wire mesh in Class V is approximately 0,68 minutes, and time needed to install one square meter steel wire mesh in other rock qualities is 1,29 minutes as shown in Fig. 9. 0,0 10,0 20,0 30,0 40,0 50,0 Number of Measurements (Times) 0,0 0,5 1,0 1,5 2,0 TimeofWireMeshInstallation(min/m2) Fig. 9, Time needed to install one square meter wire mesh in tunnel. 0,0 10,0 20,0 30,0 40,0 50,0 Number ofMeasurements(Times) 30,0 50,0 70,0 90,0 TimetoInstallaSteelArch(min) Fig. 10, Time needed to spray one cubic meter shotcrete in tunnel Steel arches are installed only in Class V rocks as shown in Table 2. There are done 44 measurements of steel arch installation, and the average time to install a single arch is 56,01 minutes as shown in Fig. 10. Steel arch installation consumes a large amount of time at tunnel excavation process. The rock bolt installation mainly consists of three steps, drilling rock bolt holes, injecting cement paste, inserting rock bolt. Drilling process is done by jumbo and has the same velocity of that showing in Fig. 2, so for bolt installation only cement injection ant rock bolt inserting time are measured. There are done 84 measurements on three different rock bolt length 3, 4 and 6 meters. Both cement injection time and rock bolt inserting time is measured in term of rock bolt length. The average time needed to inject cement in 1 meter hole is 1,12 minutes and that of inserting the rock bolt and threading the nut is 0,62 minutes as shown in Fig. 11. The total time needed to inject cement paste and install rock bolt in minutes is 1,74 x L, where L is length of rock bolt in meters. 0,0 20,0 40,0 60,0 80,0 100,0 Number ofMeasurements (Times) 0,0 0,5 1,0 1,5 2,0 Time(min/m) Fig. 11, Time needed to spray one cubic meter shotcrete in tunnel V. CONCLUSIONS In this study 737 field measurements were made to define the time needed for any particular process in drill and blast tunnel excavation method. Generally it is seen that many of the machinery and workmanship productions rates per unit time are significantly lower than them defined in their technical specifications. Measured velocity of heavy machineries is almost 35%, and their production rates are nearly 50% of that defined and programed by project developers, similar observation are done in workmanship processes. The results obtained in different tunnel diameters, from 4,20m to 7,60m, indicate that highest performance is reached in 7,60m diameter tunnel excavation although the differences are not significant and for this study there is not a good correlation between tunnel diameter and construction time. It is measured that best construction performance is reached when distance from tunnel adit and tunnel face is smaller than 200 meters. These measurements are very important in practical use and it is also believed that they will be helpful for planning and management process of tunnel construction projects, especially those planned to be built in Albania where labor market carries similar features. REFERENCES [1] A. Aga, Calculation of cycle time in hydro power tunnel excavation and effect of decision makers in construction cost, Case study of Fan river hydropower projects (In Albanian language), Master thesis, Tirana Polytechnic University, Tirana, 2014. [2] J. Reilly, The management process for complex underground and tunneling * Class V, * Class II - IV * Rock bolt inserting, * Cement paste injection
  • 7. Erion Periku Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 1( Part 1), January 2015, pp.95-101 www.ijera.com 101 | P a g e projects. Tunneling and Underground Space Technology 15(1), 2000, 31–44. [3] O. Spackova, Risk management of tunnel construction projects, Doctoral Thesis, Czech Technical University in Prague, Prague, 2012. [4] T. Isaksson, Model for estimation of time and cost based on risk evaluation applied on tunnel projects, Doctoral Thesis, Royal Institute of Technology, Stockholm, 2002. [5] T. Isaksson, H. Stille, Models for Estimation of Time and Cost for tunnels Projects Based on Risk Evaluation, Rock Mechanics and Rock Engineering, 38(5), 2005, 373-398. [6] S. Bagherian, Application of Important Factors in Tunnel Projects, Research Journal of Applied Sciences, Engineering and Technology 6(2), 2013, 181-186. [7] M. Messinella, Models for the analysis of tunneling construction processes, Master Thesis, Concordia University, Montreal, 2010. [8] E. Karahan, Design of excavation and support systems for the Çubukbeli tunnel in Antalya, Master Thesis, Middle East Technical University, Ankara, 2010.