SlideShare a Scribd company logo
1 of 8
Download to read offline
REPORT ON NEELUM JHELUM HYDROPOWER
PROJECT
Project & Construction Management
GROUP MEMBERS
RUBNAWAZ
2015-UET-CCET-CIVIL-02
MUHAMMAD KAMAL UD DIN ANWAR
2015-UET-CCET-CIVIL-03
MUZAMMIL HUSSAIN
2015-UET-CCET-CIVIL-04
ZOHAIB AHMAD
2015-UET-CCET-CIVIL-24
SUBMITTED TO
ENGR. USMAN ANWAR SAHIB
REPORT ON NEELUM JHELUM HYDROPOWER PROJECT
Chenab College of Engineering & Technology Gujranwala Pakistan
TABLE OF CONTENTS
 History
 Location
 Power House
 Transformer Hall
 Busbar Tunnel
 Draft Tube
 Switch Yard
 Wapda Colony
 Client
 Consultant
 Contractors
 Introduction
 Land Acquisition
 Design & Work
 Concrete Gravity Dam
 NJHEP Dam Site
 Rock Fill Dam
 Spillways
 Tunnels
 Geographic Area of NJHEP
 Nauseri Area (C1)
 MAJHOHI/THOTA (C2)
 CHATTER KALAS AREA (C3)
 Benefits of the Project
 Criticism on the Project
REPORT ON NEELUM JHELUM HYDROPOWER PROJECT
Chenab College of Engineering & Technology Gujranwala Pakistan
History:
After being approved in 1989, the design was improved, increasing the tunnel
length and generation capacity. The project was intended to begin in 2002 and be completed
in 2008 but this time-frame experienced significant delays to rising costs and funding.
Additionally, the 2005 Kashmir earthquake which devastated the region required a redesign
of the project to conform to more stringent seismic standards.
On 7 July 2007, the Chinese consortium CGGC-CMEC (Gezhouba Group and
China National Machinery Import and Export Corporation) were awarded the contract to
construct the dam and power station.
Location:
The Neelum Jhelum Hydropower Plant is part of an under construction run of the
river hydroelectric power scheme designed to
divert water from the Neelum River to a power
station on the Jhelum River. The power station is
located in Azad Kashmir, 22 km south
of Muzaffarabad and will have an installed
capacity of 968 MW. Construction on the project
began in 2008 after a Chinese consortium was
awarded the construction contract in July 2007.
The first generator is scheduled to be
commissioned in July 2017 and the entire project
was expected to be complete in December 2017.
 Power House:
The underground power station will have four units with a total
capacity of 969 MW. The power station will be connected with Gakhar grid station
through 500KV double circuit transmission line.
 Transformer Hall:
The turbines inside powerhouse will transfer electricity to the
transformer hall located adjacent power house where to a step down transformer will
transfer the electricity to the switch yard through cable tunnels.
 Busbar Tunnels:
Tunnels connecting transformer hall and power house.
 Draft Tubes:
The water after impacting the turbines will be transported to tailrace
tunnel through draft tubes passing below the busbar tunnels.
 Switch Yard:
Cable tunnels will connect transformer hall with the 500KV switch
yard located outside the tunnel.
 WAPDA Colony:
A residential colony will be built at the C3 site for the employees
of Wapda that will work at the site once it is operational
REPORT ON NEELUM JHELUM HYDROPOWER PROJECT
Chenab College of Engineering & Technology Gujranwala Pakistan
Client:
Pakistan Water and Power Development
Authority (WAPDA) was established through an act
of Parliament in 1958. It is an autonomous and
statutory body under the administrative control of
the Federal Government. The authority consist of a
chairman and three members (Water, Power, and
Finance). Wapda was unbundled in the year 2007
whereby the functions of its power wing were
redefined as Hydel power generation & operation
maintaince of power houses.
Wapda is client of NJHEP project which cost about 404 billion rupees. First
time, it’s a big diverse nature project is implemented in Pakistan to meet energy crisis.
Project initialised in 2008 and expected completion date is June, 2017. Estimated power
generation is 969MW.
Consultant:
To ensure quality of
project, NJC is consultant. NJC (Neelum
Jhelum Consultant) is basically a joint venture
of differential and international companies.
NJC is joint venture of five firms, in which
three belongs to Pakistan like ACE, NESPAK
and NDC one from Norway which is
NORPLAN and one from America which is
MWH.
Contractors:
In April 2006, the
Wapda had cleared three international bidders
for a contract to develop the project. The
Chinese consortium of CMEC and CGGC
emerged as the lowest bidder at $1.30 billion.
The other bidder, China International Water &
Electric Corporation (CWE), quoted $1.80 billion. CGGC and CMEG are contactors of
NJHEP, both firms belong to China. CGGC is executing Civil work and CMEG is working
for Mechanical and Electrical work.
REPORT ON NEELUM JHELUM HYDROPOWER PROJECT
Chenab College of Engineering & Technology Gujranwala Pakistan
Introduction:
NJHEP is basically a power generation project in Azad Kashmir at Neelum
Jhelum River which is made possible by puncturing Neelum River to Jhelum River through
Tunnels. Neelum River is flowing at more elevation than Jhelum River so therefore to
develop head for power generation Neelum is punctured into Jhelum. It’s ranked the 41st in
large of Hydroelectric tunnelling project in the world most modern techniques of tunnelling is
used on Neelum Jhelum which is Tunnel Boring Machine. On NJHEP there is diversity of
work so it’s divided into different sections for ease and smooth execution.
Land Acquisition:
 Project envisages acquisition of approx, 2400 canals of private and State land in the
project Area in Muzaffarabad District.
 So far WAPDA has transferred Rs.705 Million to Govt. of AJ&K as provisional cost
of the Notified Private and state land.
 WAPDA has taken possession of 80% land; and arrangements are being made to
acquire the remaining land.
Design & Work:
The Neelum–Jhelum Dam will be a 47 m tall and 125 m long gravity
dam. It will withhold a reservoir with an 8,000,000 m3 capacity of which 2,800,000 m3 is
peak storage. The dam diverts up to 280 m3/s of the Neelum southeast into a 28.5 km long
head-race tunnel, the first 15.1 km of the head-race is two tunnels which later meet into one.
The tunnel passes 380 m below the Jhelum River and through its bend. At the terminus of the
tunnel, the water reaches the surge chamber which contains a 341 m tall surge shaft (to
prevent water hammer) and an 820 m long surge tunnel. From the surge chamber, the water is
split into four different penstocks which feed each of the four 242 MW Francis turbine-
generators in the underground power house.
Concrete gravity dam:
Concrete gravity dam basically consist of different components
like concrete walls, piers, spillway, stilling basin, drainage gallery and debris channel.
It has upstream and downstream. Upstream level is more than
downstream level. On downstream level stilling basin exist. Upstream level is 963m and
downstream level is 961m.
REPORT ON NEELUM JHELUM HYDROPOWER PROJECT
Chenab College of Engineering & Technology Gujranwala Pakistan
NJHEP Dam site:
Maximum Reservoir level 1015 m
Reservoir Capacity at Maximum Reservoir level 10.2 million cumecs
Minimum Reservoir level 1008 m
Reservoir Capacity at Maximum Reservoir level 6.4 million cumecs
Useable Water 3.8 million cumecs
PMF 1018 m
Top elevation of dam 1019 m
Rock Fill Dam:
Rock fill dams are embankment of compacted free-draining
granular earth with an impervious zone. The earth utilized often contain a high percentage of
large particles, hence the term “Rock fill”. The impervious zone may be on the upstream and
made of masonry, concrete, plastic, membrane, steel sheet piles, timber and many other
materials. The impervious zone may be within the embankment in which case it is referred to
as a core.
Spillways:
There are spillways which function is
water controlling from upstream to downstream.
Three radial gates are install on spillways. All work
is carried out in different sections, therefore
different joint exist which are cold, contraction and
expansion joint but expansion joints are not at dam
site because temperature is low at due to cold
weather. These joints are grouted to avoid seepage
of water. Drainage gallery is also designed in
spillway to drain water grouting and inspection.
Spillways are generally opened when water flow is
exceeded than reservoir capacity and flood
occurred. Spillway bottom level is 959 m and top
level is 1019 m.
Tunnels:
A six gate tunnel intake structure of 280
cumecs capacity will be connected three conventional
flushing surface basins installed at their end for taking
sediment back into the river.
The total length of headrace tunnel is
almost 48 Km. A 9.54 stretch of the tunnel from the
REPORT ON NEELUM JHELUM HYDROPOWER PROJECT
Chenab College of Engineering & Technology Gujranwala Pakistan
Nauseri site will be constructed as twin tunnel system each with cross sectional area varying
from 52-58 meter per square.
Batching plant:
A batching plant, is equipment that combines various ingredient
to form concrete. Some of these inputs includes water, air, admixture sand aggregate, fly ash,
silica fume, slag and cement. There are two main types of concrete plants: Dry mix plant and
wet mix plant.
Geographic areas of NJHEP:
The Neelum Jhelum Hydroelectric project is split into following three main geographic areas.
 Nauseri Area (C1):
A 60m
high Composite diversion dam and
sedimentation basin near Nauseri is
on the Neelum River. The dam has 3
Radial gates & 2 flap gates designed
to pass floods of 1000 years
recurrence period and also allow the
reservoir to be drawn down for
sediment flushing.
 Majhohi/Thota (C2):
The headrace tunnel is 48 km long including twin tunnel
and convey the water from the intake area at Nauseri to the Powerhouse area near Chatter
Kalas. The tunnel crosses under high ground and also across the Muzaffarabad fault zone. A
19.54 Km stretch of the tunnel from the Nauseri be constructed as a twin tunnel system each
with x-sectional area ranging from 52-58 m2 and the rest of the route, a single tunnel of x-
section area 100 m2 approx, has been proposed. The tunnel portion to be excavated & Tunnel
Boring Machine (TBM) will be shortcrete lined with a concrete invert while the drill and
blast portion of the tunnel will have full face concrete lining.
 Chatter Kalas Area (C3):
The headrace will feed four vertical-shafts Francis turbines
with an installed capacity of 969 MW housed in an underground powerhouse. The water is
discharged back into the Jhelum River near Zamainabad through a 3.54km tailrace tunnel.
Associated facilities include a transformer hall, surge shafts, access tunnels, a 500 KV
switchyard and housing facilities for the operations and maintenance personal.
REPORT ON NEELUM JHELUM HYDROPOWER PROJECT
Chenab College of Engineering & Technology Gujranwala Pakistan
 Benefits of the project:
 Reduction of dependent on thermal power.
 Saving in foreign exchange.
 Employment opportunity during construction and operation.
 Improved standard of living infrastructure.
 Social-economic uplift of the area.
 The generation of cheap electricity will help to reduce existing tariff.
 Reduction in Load sheding.
 Project will create an enhance tourism opportunities.
 Opportunities of new jobs for local people during construction & operation of
project.
 Overall growth in economy due to induction of cheap Electricity. This will help
reduction in production cost of goods used locally and especially export goods to
make them more competitive with other countries.
 Social & Economic development of local area and population.
 Reduction of floods in Jhelum River.
 Criticism on the project:
 Beauty of this area is enhanced by this river; and this diversion will have serious
effect on wild life, weather and beauty of the area.
 The river and the beauty of the area attract tourists and provide clean water to the
local people and citizens of Muzaffarabad; and this diversion of water will deprive
the area of clean water and reduce the Neelum River to ‘Nalah Lahi' in
Rawalpindi which has dirty water and creates enormous problems for the citizens.
 This project, once completed will benefit Pakistan, but local people will not
benefit from it in any form or shape. There will be serious economic and
environmental consequences for the local people; and their future generations will
face very serious economic and environmental problems.

More Related Content

What's hot

Hydro power plants
Hydro power plants Hydro power plants
Hydro power plants FAHAD KHAN
 
Ghazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship ReportGhazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship ReportIhtisham Saeed
 
Nandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain KhosoNandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain KhosoWajid Hussain Khoso
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plantSuresh Rathore
 
4. Generator Step Up Transformer
4. Generator Step Up Transformer4. Generator Step Up Transformer
4. Generator Step Up TransformerChinedu Isiadinso
 
DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)Haseeb Ahsan
 
Water for Hydroelectric Generation
Water for Hydroelectric GenerationWater for Hydroelectric Generation
Water for Hydroelectric Generationharoldtaylor1113
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantpparth004
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction siteUmair Ali
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Aniket Raj
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant vishal patel
 
BHEL SUMMER TRAINING REPORT
BHEL SUMMER TRAINING REPORTBHEL SUMMER TRAINING REPORT
BHEL SUMMER TRAINING REPORTBhupendra Shukla
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship reportMd Mohsin Mohsin
 

What's hot (20)

Hydro power plants
Hydro power plants Hydro power plants
Hydro power plants
 
Hydro ppt
Hydro pptHydro ppt
Hydro ppt
 
Ghazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship ReportGhazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship Report
 
Nandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain KhosoNandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain Khoso
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
 
4. Generator Step Up Transformer
4. Generator Step Up Transformer4. Generator Step Up Transformer
4. Generator Step Up Transformer
 
DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)
 
Water for Hydroelectric Generation
Water for Hydroelectric GenerationWater for Hydroelectric Generation
Water for Hydroelectric Generation
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
 
Summer Training Presentation
Summer Training PresentationSummer Training Presentation
Summer Training Presentation
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Energy project report on hydropower
Energy project report on hydropowerEnergy project report on hydropower
Energy project report on hydropower
 
Tidal Power in India
Tidal Power in IndiaTidal Power in India
Tidal Power in India
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant
 
BHEL SUMMER TRAINING REPORT
BHEL SUMMER TRAINING REPORTBHEL SUMMER TRAINING REPORT
BHEL SUMMER TRAINING REPORT
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 

Similar to Report on Neelum Jhelum Hydropower Project Construction and Management

Punasa report on indra sagar Dam, 9608684800
Punasa  report on indra sagar Dam, 9608684800Punasa  report on indra sagar Dam, 9608684800
Punasa report on indra sagar Dam, 9608684800PRIYANSHU KUMAR
 
Presentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaPresentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaSaikat Ghosh
 
Yogesh 8th sem project report
Yogesh 8th sem project reportYogesh 8th sem project report
Yogesh 8th sem project reportYogesh Thakur
 
IVRCL - Company Profile.
IVRCL - Company Profile.IVRCL - Company Profile.
IVRCL - Company Profile.Gitanjali Singh
 
Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019HasnatAmin1
 
Warsak Hydro Power Plant
Warsak Hydro Power PlantWarsak Hydro Power Plant
Warsak Hydro Power PlantMoiz Rao
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam JunaidAshraf31
 
121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station Presentation121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station PresentationEngrAsimRaza2
 
Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)lochan Shrestha
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuVishweshwar Rao Narla
 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower projectMuhammad Aqeel
 
Top 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas PipelinesTop 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas PipelinesNES Global Talent
 
Baglihar hydro electric power plant
Baglihar hydro electric power plantBaglihar hydro electric power plant
Baglihar hydro electric power plantRaja Katoch
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Mohammed wahab
 

Similar to Report on Neelum Jhelum Hydropower Project Construction and Management (20)

Project report
Project reportProject report
Project report
 
Punasa report on indra sagar Dam, 9608684800
Punasa  report on indra sagar Dam, 9608684800Punasa  report on indra sagar Dam, 9608684800
Punasa report on indra sagar Dam, 9608684800
 
Presentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaPresentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in india
 
Yogesh 8th sem project report
Yogesh 8th sem project reportYogesh 8th sem project report
Yogesh 8th sem project report
 
IVRCL - Company Profile.
IVRCL - Company Profile.IVRCL - Company Profile.
IVRCL - Company Profile.
 
Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019
 
Warsak Hydro Power Plant
Warsak Hydro Power PlantWarsak Hydro Power Plant
Warsak Hydro Power Plant
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
 
121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station Presentation121 MW Allai Khwar Hydel Power Station Presentation
121 MW Allai Khwar Hydel Power Station Presentation
 
Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)
 
Srisailam project final
Srisailam project finalSrisailam project final
Srisailam project final
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower project
 
The report on ghazi brotha dam
The report on ghazi brotha damThe report on ghazi brotha dam
The report on ghazi brotha dam
 
Top 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas PipelinesTop 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas Pipelines
 
Baglihar hydro electric power plant
Baglihar hydro electric power plantBaglihar hydro electric power plant
Baglihar hydro electric power plant
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 
NTPC
NTPCNTPC
NTPC
 
My Cv 05-2014
My Cv 05-2014My Cv 05-2014
My Cv 05-2014
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
 

More from Rubnawaz Bhatti

Hydro Power Plants of Pakistan
Hydro Power Plants of PakistanHydro Power Plants of Pakistan
Hydro Power Plants of PakistanRubnawaz Bhatti
 
Characteristics of effective technical communication
Characteristics of effective technical communicationCharacteristics of effective technical communication
Characteristics of effective technical communicationRubnawaz Bhatti
 
Hydropower plants of pakistan
Hydropower plants of pakistanHydropower plants of pakistan
Hydropower plants of pakistanRubnawaz Bhatti
 
Seasonal calendar Sindh Pakistan
Seasonal calendar Sindh PakistanSeasonal calendar Sindh Pakistan
Seasonal calendar Sindh PakistanRubnawaz Bhatti
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industryRubnawaz Bhatti
 
Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)Rubnawaz Bhatti
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
Religious Extremism in Pakistan
Religious Extremism in PakistanReligious Extremism in Pakistan
Religious Extremism in PakistanRubnawaz Bhatti
 

More from Rubnawaz Bhatti (11)

BRT.pptx
BRT.pptxBRT.pptx
BRT.pptx
 
Hydro Power Plants of Pakistan
Hydro Power Plants of PakistanHydro Power Plants of Pakistan
Hydro Power Plants of Pakistan
 
Characteristics of effective technical communication
Characteristics of effective technical communicationCharacteristics of effective technical communication
Characteristics of effective technical communication
 
Hydropower plants of pakistan
Hydropower plants of pakistanHydropower plants of pakistan
Hydropower plants of pakistan
 
Seasonal calendar Sindh Pakistan
Seasonal calendar Sindh PakistanSeasonal calendar Sindh Pakistan
Seasonal calendar Sindh Pakistan
 
Rivers of Pakistan
Rivers of PakistanRivers of Pakistan
Rivers of Pakistan
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
 
Al bairaj al bait
Al bairaj al bait  Al bairaj al bait
Al bairaj al bait
 
Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
Religious Extremism in Pakistan
Religious Extremism in PakistanReligious Extremism in Pakistan
Religious Extremism in Pakistan
 

Recently uploaded

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 

Recently uploaded (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 

Report on Neelum Jhelum Hydropower Project Construction and Management

  • 1. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Project & Construction Management GROUP MEMBERS RUBNAWAZ 2015-UET-CCET-CIVIL-02 MUHAMMAD KAMAL UD DIN ANWAR 2015-UET-CCET-CIVIL-03 MUZAMMIL HUSSAIN 2015-UET-CCET-CIVIL-04 ZOHAIB AHMAD 2015-UET-CCET-CIVIL-24 SUBMITTED TO ENGR. USMAN ANWAR SAHIB
  • 2. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Chenab College of Engineering & Technology Gujranwala Pakistan TABLE OF CONTENTS  History  Location  Power House  Transformer Hall  Busbar Tunnel  Draft Tube  Switch Yard  Wapda Colony  Client  Consultant  Contractors  Introduction  Land Acquisition  Design & Work  Concrete Gravity Dam  NJHEP Dam Site  Rock Fill Dam  Spillways  Tunnels  Geographic Area of NJHEP  Nauseri Area (C1)  MAJHOHI/THOTA (C2)  CHATTER KALAS AREA (C3)  Benefits of the Project  Criticism on the Project
  • 3. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Chenab College of Engineering & Technology Gujranwala Pakistan History: After being approved in 1989, the design was improved, increasing the tunnel length and generation capacity. The project was intended to begin in 2002 and be completed in 2008 but this time-frame experienced significant delays to rising costs and funding. Additionally, the 2005 Kashmir earthquake which devastated the region required a redesign of the project to conform to more stringent seismic standards. On 7 July 2007, the Chinese consortium CGGC-CMEC (Gezhouba Group and China National Machinery Import and Export Corporation) were awarded the contract to construct the dam and power station. Location: The Neelum Jhelum Hydropower Plant is part of an under construction run of the river hydroelectric power scheme designed to divert water from the Neelum River to a power station on the Jhelum River. The power station is located in Azad Kashmir, 22 km south of Muzaffarabad and will have an installed capacity of 968 MW. Construction on the project began in 2008 after a Chinese consortium was awarded the construction contract in July 2007. The first generator is scheduled to be commissioned in July 2017 and the entire project was expected to be complete in December 2017.  Power House: The underground power station will have four units with a total capacity of 969 MW. The power station will be connected with Gakhar grid station through 500KV double circuit transmission line.  Transformer Hall: The turbines inside powerhouse will transfer electricity to the transformer hall located adjacent power house where to a step down transformer will transfer the electricity to the switch yard through cable tunnels.  Busbar Tunnels: Tunnels connecting transformer hall and power house.  Draft Tubes: The water after impacting the turbines will be transported to tailrace tunnel through draft tubes passing below the busbar tunnels.  Switch Yard: Cable tunnels will connect transformer hall with the 500KV switch yard located outside the tunnel.  WAPDA Colony: A residential colony will be built at the C3 site for the employees of Wapda that will work at the site once it is operational
  • 4. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Chenab College of Engineering & Technology Gujranwala Pakistan Client: Pakistan Water and Power Development Authority (WAPDA) was established through an act of Parliament in 1958. It is an autonomous and statutory body under the administrative control of the Federal Government. The authority consist of a chairman and three members (Water, Power, and Finance). Wapda was unbundled in the year 2007 whereby the functions of its power wing were redefined as Hydel power generation & operation maintaince of power houses. Wapda is client of NJHEP project which cost about 404 billion rupees. First time, it’s a big diverse nature project is implemented in Pakistan to meet energy crisis. Project initialised in 2008 and expected completion date is June, 2017. Estimated power generation is 969MW. Consultant: To ensure quality of project, NJC is consultant. NJC (Neelum Jhelum Consultant) is basically a joint venture of differential and international companies. NJC is joint venture of five firms, in which three belongs to Pakistan like ACE, NESPAK and NDC one from Norway which is NORPLAN and one from America which is MWH. Contractors: In April 2006, the Wapda had cleared three international bidders for a contract to develop the project. The Chinese consortium of CMEC and CGGC emerged as the lowest bidder at $1.30 billion. The other bidder, China International Water & Electric Corporation (CWE), quoted $1.80 billion. CGGC and CMEG are contactors of NJHEP, both firms belong to China. CGGC is executing Civil work and CMEG is working for Mechanical and Electrical work.
  • 5. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Chenab College of Engineering & Technology Gujranwala Pakistan Introduction: NJHEP is basically a power generation project in Azad Kashmir at Neelum Jhelum River which is made possible by puncturing Neelum River to Jhelum River through Tunnels. Neelum River is flowing at more elevation than Jhelum River so therefore to develop head for power generation Neelum is punctured into Jhelum. It’s ranked the 41st in large of Hydroelectric tunnelling project in the world most modern techniques of tunnelling is used on Neelum Jhelum which is Tunnel Boring Machine. On NJHEP there is diversity of work so it’s divided into different sections for ease and smooth execution. Land Acquisition:  Project envisages acquisition of approx, 2400 canals of private and State land in the project Area in Muzaffarabad District.  So far WAPDA has transferred Rs.705 Million to Govt. of AJ&K as provisional cost of the Notified Private and state land.  WAPDA has taken possession of 80% land; and arrangements are being made to acquire the remaining land. Design & Work: The Neelum–Jhelum Dam will be a 47 m tall and 125 m long gravity dam. It will withhold a reservoir with an 8,000,000 m3 capacity of which 2,800,000 m3 is peak storage. The dam diverts up to 280 m3/s of the Neelum southeast into a 28.5 km long head-race tunnel, the first 15.1 km of the head-race is two tunnels which later meet into one. The tunnel passes 380 m below the Jhelum River and through its bend. At the terminus of the tunnel, the water reaches the surge chamber which contains a 341 m tall surge shaft (to prevent water hammer) and an 820 m long surge tunnel. From the surge chamber, the water is split into four different penstocks which feed each of the four 242 MW Francis turbine- generators in the underground power house. Concrete gravity dam: Concrete gravity dam basically consist of different components like concrete walls, piers, spillway, stilling basin, drainage gallery and debris channel. It has upstream and downstream. Upstream level is more than downstream level. On downstream level stilling basin exist. Upstream level is 963m and downstream level is 961m.
  • 6. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Chenab College of Engineering & Technology Gujranwala Pakistan NJHEP Dam site: Maximum Reservoir level 1015 m Reservoir Capacity at Maximum Reservoir level 10.2 million cumecs Minimum Reservoir level 1008 m Reservoir Capacity at Maximum Reservoir level 6.4 million cumecs Useable Water 3.8 million cumecs PMF 1018 m Top elevation of dam 1019 m Rock Fill Dam: Rock fill dams are embankment of compacted free-draining granular earth with an impervious zone. The earth utilized often contain a high percentage of large particles, hence the term “Rock fill”. The impervious zone may be on the upstream and made of masonry, concrete, plastic, membrane, steel sheet piles, timber and many other materials. The impervious zone may be within the embankment in which case it is referred to as a core. Spillways: There are spillways which function is water controlling from upstream to downstream. Three radial gates are install on spillways. All work is carried out in different sections, therefore different joint exist which are cold, contraction and expansion joint but expansion joints are not at dam site because temperature is low at due to cold weather. These joints are grouted to avoid seepage of water. Drainage gallery is also designed in spillway to drain water grouting and inspection. Spillways are generally opened when water flow is exceeded than reservoir capacity and flood occurred. Spillway bottom level is 959 m and top level is 1019 m. Tunnels: A six gate tunnel intake structure of 280 cumecs capacity will be connected three conventional flushing surface basins installed at their end for taking sediment back into the river. The total length of headrace tunnel is almost 48 Km. A 9.54 stretch of the tunnel from the
  • 7. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Chenab College of Engineering & Technology Gujranwala Pakistan Nauseri site will be constructed as twin tunnel system each with cross sectional area varying from 52-58 meter per square. Batching plant: A batching plant, is equipment that combines various ingredient to form concrete. Some of these inputs includes water, air, admixture sand aggregate, fly ash, silica fume, slag and cement. There are two main types of concrete plants: Dry mix plant and wet mix plant. Geographic areas of NJHEP: The Neelum Jhelum Hydroelectric project is split into following three main geographic areas.  Nauseri Area (C1): A 60m high Composite diversion dam and sedimentation basin near Nauseri is on the Neelum River. The dam has 3 Radial gates & 2 flap gates designed to pass floods of 1000 years recurrence period and also allow the reservoir to be drawn down for sediment flushing.  Majhohi/Thota (C2): The headrace tunnel is 48 km long including twin tunnel and convey the water from the intake area at Nauseri to the Powerhouse area near Chatter Kalas. The tunnel crosses under high ground and also across the Muzaffarabad fault zone. A 19.54 Km stretch of the tunnel from the Nauseri be constructed as a twin tunnel system each with x-sectional area ranging from 52-58 m2 and the rest of the route, a single tunnel of x- section area 100 m2 approx, has been proposed. The tunnel portion to be excavated & Tunnel Boring Machine (TBM) will be shortcrete lined with a concrete invert while the drill and blast portion of the tunnel will have full face concrete lining.  Chatter Kalas Area (C3): The headrace will feed four vertical-shafts Francis turbines with an installed capacity of 969 MW housed in an underground powerhouse. The water is discharged back into the Jhelum River near Zamainabad through a 3.54km tailrace tunnel. Associated facilities include a transformer hall, surge shafts, access tunnels, a 500 KV switchyard and housing facilities for the operations and maintenance personal.
  • 8. REPORT ON NEELUM JHELUM HYDROPOWER PROJECT Chenab College of Engineering & Technology Gujranwala Pakistan  Benefits of the project:  Reduction of dependent on thermal power.  Saving in foreign exchange.  Employment opportunity during construction and operation.  Improved standard of living infrastructure.  Social-economic uplift of the area.  The generation of cheap electricity will help to reduce existing tariff.  Reduction in Load sheding.  Project will create an enhance tourism opportunities.  Opportunities of new jobs for local people during construction & operation of project.  Overall growth in economy due to induction of cheap Electricity. This will help reduction in production cost of goods used locally and especially export goods to make them more competitive with other countries.  Social & Economic development of local area and population.  Reduction of floods in Jhelum River.  Criticism on the project:  Beauty of this area is enhanced by this river; and this diversion will have serious effect on wild life, weather and beauty of the area.  The river and the beauty of the area attract tourists and provide clean water to the local people and citizens of Muzaffarabad; and this diversion of water will deprive the area of clean water and reduce the Neelum River to ‘Nalah Lahi' in Rawalpindi which has dirty water and creates enormous problems for the citizens.  This project, once completed will benefit Pakistan, but local people will not benefit from it in any form or shape. There will be serious economic and environmental consequences for the local people; and their future generations will face very serious economic and environmental problems.