This document describes the design and analysis of the electrical distribution system for a typical large-scale chemical industry plant using ETAP software. The existing 11kV distribution network is analyzed and found to be insufficient for current load demands. A new optimized distribution network is proposed, including three 11kV/415V distribution transformers, duplicate and sectionalized main buses, motor control centers, and backup diesel generators. Load flow analysis is performed on the proposed network under normal and abnormal conditions. The results show improvements in voltage profile, losses, and power factor compared to the existing network.