Cost Forecasting of Construction Materials: A review
Cyril Thomas1, Jenson Jose2
1M.Tech student, Dept. of civil Engineering, St. Joseph’s college of Engineering and Technology,
Palai, Kerala, India
2Assistant Professor, Dept. of civil Engineering, St. Joseph’s college of Engineering and Technology,
Palai, Kerala, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Large-scale building projects are increasing
day by day and because of that their construction costs
become a matter of great concern, especially because of
their lengthy construction periods. In particular, recent
fluctuations of construction material prices have fueled
problems like cost forecasting. This paper reviews the
incorporation of artificial neural network for predicting the
future cost construction materials. The main benefit of this
study is providing construction stakeholders with a very
reliable tool for expecting prices of coming projects,
especially with the existing Rates of Inflation.
Key Words: Future cost, construction, materials, artificial
networks.
1.INTRODUCTION
Large scale construction projects have recently increased
in number of residential, commercial and government
facilities worldwide. A lot of high rise buildings are being
constructed or planned as urban land marks. The
construction costs are dynamic. Prices of different
materials, human resources, and other costs varies
continuously. This economic uncertainty could have a
major impact on the business especially on long term and
mega projects. There are many traditional methods for
predicting future construction costs in India. A forecasting
method based on Artificial neural networks would be a
great benefit for contractors, project owners etc.
1.1 5D BIM
For a construction project perspective three phases can be
classified such as the pre-construction, the construction
and the maintenance and operation phases.5D BIM adds to
the third and fourth dimensions with the ability to link
costing information to the digital model and the project
schedules to allow for better cost management. BEXEL
Manager is software that integrates the most important
3D/4D/5D uses of BIM technology changing the
perspective of integrated project management and
allowing you to optimize your digital workflows and take
advantage of advanced open BIM technologies.
1.2 Possibility of Artificial Intelligence
In India traditional methods are followed to forecast the
prices of construction materials. But in foreign countries
several methods incorporating Artificial Intelligence are
widely used to forecast the construction material prices.
By incorporating artificial intelligence much more
accuracy can be achieved and the values will have more
accuracy compared to the ordinary methods of
forecasting. Prediction using Artificial intelligence is a
faster method and it has world wide recognition. If such
methods are used in India, greater accuracy can be
achieved and it will be very helpful for the contractors,
project owners etc. in evaluating ,pricing and bidding
construction projects.
2. COST FORECASTING METHODS
Different approaches have been analyzed to determine the
best fitting model for forecasting construction costs. These
several methods are analyzed here. They are mainly
Vector error-correction model, Time series models like
Automated time series cost forecasting system,
Interrupted time series forecasting model,5D BIM and
Artificial Neural Network approach. They are discussed
below.
2.1 Vector Error -Correction model
Forecasting the short and long-term movement of
construction material prices can be advantageous to
various project stakeholders. By improving accuracy of
their cost forecasts, contractors can avoid bidding or profit
losses. In 2015 Shanhandashti and Ashuri used VEC
models for forecasting construction material prices.
Commonly used univariate and multivariate time series
models, such as Box Jenkis and VAR models can be used to
produce short-term material price forecasts.
Cointegration, an econometric property of the time series
variables,is generally used to characterize the long term
relationships between non-stationary variables. In cases
where two or more time series are cointegrated, VEC
models can be used to develop short and long term
forecasts. VEC model development includes different
steps. First one is to identify candidate explanatory
variables and collect corresponding data. Time series
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 904
analysis includes there are transit subset and testing
subset. First step is followed by the check for stationarity.
The augmented Dicky fuller test can be used to test the
stationarity. The three main versions of augmented Dicky
fuller test use the following models. They are mainly
Woolridge model 2009,Gujarati 1995 and Dickey fuller
1979.
This step is followed by a casualty test. Cointegration test
is used to examine the existence of a long term
relationship between explained and explanatory variables.
Diagnostic tests are conducted to check for the existence
of serial correlation and constant variances among
residuals, which implies a lack of heteroscedasticity, and
determine the goodness of models. Using the testing
subset the prediction accuracy of the constructed VEC
models can be evaluated. In this step, the values predicted
by the model are compared against the actual values. After
the predictability evaluation process has completed, the
candidate VEC model that passes the diagnostics and has
the better prediction performance among the candidate
models is chosen to dynamically forecast the future levels
of the explained variable using the explanatory variables.
But there are several drawbacks for this model. The VEC
models are incapable of predicting future shocks caused
by extreme events and disruptive changes in technology,
different practices, regulations, market dynamics,
inflation, exchange rates etc.
Forecasting Nord Pool day-ahead prices with an
autoregressive model was carried out by Tarjei
Kristiansen in 2012.Auto regressive model predicts the
future behavior based on past behavior.
Hemanta Doloi tried to unfold the industry wide
perception of cost performance being heavily relient on
the contractors performance alone. Doloi’s findings are
expected to conclude a significant knowledge gap by
shifting the priorities in cost estimation and management
across all industry sectors.
2.2 Time -Series Models
The ATMF system is composed of four modules. They are
mainly time series data input, parameter estimation , GOF
calculation, Diagnostic checking. In time series data input
first we require a material unit price database. Material
unit price data are assigned based on each type and price
.When a user selects a material price name, from the
corresponding material price database, raw-time series
data are automatically extracted and automatically
entered into the system. Then comes the important step
that is parameter estimation. This parameter estimation
module estimates parameters of all tentative ARIMA
models and then tests the significance of the parameters.
The GOF calculating module determines the suitability of
all tentative models by using five GOF criteria which
includes : root mean square error (RMSE), mean absolute
error, Akaike’s information criteria, normalized Bayesian
information criterion , and R-squared values. This step is
followed by diagnostic checking.
2.2.1 Automated Time-Series Cost Forecasting
System
This ATMF system is very useful in predicting future
trends in construction material costs. Furthermore, this
system is very helpful for cost estimation at a detailed
level . So this system can thus help decision makers in the
construction industry deal with changes in economic
conditions and design by estimating cost escalations
caused by volatile factors such as inflation.An
autoregressive and moving average(ARIMA) modeling
method , which is one of the popular univariate and time
series modeling methods suggested by Box and
Jenkis(1994) with a focus on non seasonality and trends is
analyzed.An autoregressive integrated moving average, or
ARIMA, is a statistical analysis model that uses time series
data to either better understand the data set or to predict
future trends.For a detailed and updatable material cost
estimating, an automated forecasting system is developed
on the basis of both the ARIMA modeling process and a
simplified forecasting procedure proposed by Lu and Abou
Rizk.The system focuses on usability for construction
practitioners, compatibility with existing estimation
software, and simplicity in analysis procedures..This
automated system focuses on many things like
compatibility with the existing estimation software, on
the usability for construction practitioners and the
simplicity for analysis procedures.This system also
involves the following.They are an automated input
module using a price database,a parameter estimation
module for alternative models using an optimal solution
algorithm, a GOF calculation module using a GOF score,
and a diagnostic checking module.This automated system
focuses on many things like compatibility with the
existing estimation software, on the usability for
construction practitioners and the simplicity for analysis
procedures.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 905
Fig-1: ATMF: A student centered framework for effective
implementation of alternative teaching
Rahman and co-authors in 2013 performed a study to find
out the significant factors causing cost overrun in the large
construction projects. The Relative importance index
method is adopted here for the analysis. And from the
hierarchichal assessment of factors and it was find out
that,the top three most significant factors of cost overrun
are variation of prices of material, cashflow and the
financial difficulties that may faced by the contractors and
because of poor site management and poor supervision.
The above mentioned factors belongs to mainly two
categories. They are contractor’s site management
category and contractor’s financial management category.
Cost overrun is a severe problem faced by large
construction industries.
2.2.2 Interrupted Time Series Forecasting Model
Here an interrupted time series forecasting model was
developed wherein the economic recession of 2008 was
reflected in the forecasting model, which is an outlier
identified to have significant impact in the Construction
cost index. The forecast result which is obtained using the
Interrupted time series forecasting model was better than
that of conventional forecasting models. The accurately
forecasted Construction cost index using the presented
model will help in budget and bid planning as well as
assessing the risk of business. Interrupted-time series
models provided better predictability than An
autoregressive integrated moving average (ARIMA) and
Holt-winters exponential smoothing models. An
intervention analysis was conducted using the detected
outliers to develop an interrupted time-series model
wherein the intervention effects are reflected. Through
this analysis, an interrupted time-series model was
derived.
Fig-2: Detection of CCI outliers( using ESD test).
Fig-3: Detection of CCI outliers(using likelihood ratio test).
Fig–4: Detection of CCI(Using break point estimation test)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 906
An intervention analysis was conducted using the outliers
which have detected to develop an interrupted time-series
model wherein the intervention effects are reflected. From
the analysis, an interrupted time-series model was derived
by adding the outlier effects to the ARIMA model. It is
necessary to determine the intervention timing of the
outliers that have actually occurred at the same point in
time to validate the significance of the outlier effects in the
intervention analysis. Here, the occurence-timing points of
the outliers occurring at similar points detected using the
different detection methods were defined at the earliest of
the occurrence points of the outliers. This was done
because latter points could have occurred from the
influences of a trend change or a jump in a short period.
Hence, when the occurrence point is based on the latter
points, the model can be estimated without considering
the outlier effects between the earlier and latter points.
2.3 BIM 5D
Building Information Modeling is a process supported by
several tools, technologies and contracts involving the
generation and management of digital representations of
physical and functional characteristics of places. Building
information models (BIMs) are computer files which can
be extracted, exchanged or networked to support
decision-making regarding a built asset. Government
agencies, Individuals, business. Organizations use BIM
software in their planning, designing and construction
stage, operate and maintain buildings and diverse physical
infrastructures, such as water, refuse, electricity, gas,
communication utilities, roads, railways, bridges etc. From
a construction project perspective three phases can be
classified such as; the pre-construction, the construction,
and the maintenance and operation phases. The pre-
construction stage includes the concept, definition and
design stages. Planning, designing, site preparation,
foundation plinth construction, column, beam and slab
construction, plastering, and finishing work are the
different stages in construction. Finally in the maintenance
and operation phase there are build and commission
stages and hand over stage.5D BIM adds to the third and
fourth dimensions with the ability to link costing
information to the digital model and the project’s schedule
to allow for the better cost management.
The cost estimating features of most 5D BIM tools allow
the creation of cost estimates that represent with more
precision the actual cost of a project and overall cost
reduction. There are five steps. Mainly the step one
includes the following. they are: clarify scope, search for
information, develop a framework and validate the frame
work. The second step also was divided into three levels.
They are mainly; the identification of available BIM 5D
solutions, evaluation of solution’s functionalities, and
finally the synthesis of solution’s functionalities The
framework includes three levels. They are pre-
construction, construction and post construction. The top
three solutions have been identified for each 5D BIM level.
For the first level, top three solutions are CostX, Vico
office,iTWO. And for the second level top three solutions
are mainly in the order Vico office, iTWO,CostX.In BIM 5D
solutions there are mainly BIM readable solutions and BIM
non-readable solutions. BIM readable solutions denote the
tools that can both import data from and export data to
the main 5D BIM software used on a project .BIM non -
readable solutions have only the ability to import data
from the main 5D software used without the ability to
export data.
2.4 Artificial Neural Network Approach
Artificial neural network approach is a machine learning
method. This method can be effectively used for cost
estimation. In this method first thing is to identify the
input variables. The various input variables identified are;
scale of work, project phases, project duration, scope of
work, type of work, level of experience on client side, the
scope definition, size project team,multi disciplinary, type
of client, main market type, attitude towards design
changes etc. In order to determine the cost influencing
factor that are used in the estimation process interviews
are done with 13 employees. After the database has been
developed methodology was applied to build and train the
cost estimating model. In this approach there are different
phases. In first phase, best training function is defined. The
correlation coefficient and mean absolute percentage
error(MAPE) were used for assessment of model
performance. After identifying the best model, next
training algorithm was selected until all the training
algorithms were tested.
Fig-5: Structure of deep neural network.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 907
Phase two defines the feature selection. Here the
irrelevant input variables are eliminated. Connection
Weights Algorithm was used to determine the relative
importance of variables. Variables with lowest relative
importance are eliminated from the best model identified
in the earlier phase. These variables are used to train the
variables. There are Connection Weights Algorithm(CWA)
and Multiple Linear Regression (MLR) method. In phase
three, there is determining the model scope/range. Since
the accuracy of the model depends on the size of the input
data, three different scenarios were identified.
Here the possibility of developing an accurate ML-based
cost estimation method for tendering of engineering
services has been done using neural network model to
estimate the preliminary cost of engineering services. This
research applied a systematic methodology that provides
a guideline for developing and optimizing an Artificial
Neural Network for cost estimation. It is found to efficient
in improving the performance of the model. ANN can be
used t0 obtain a fairly accurate cost estimate, even with
minimum data that is available during the tendering
phase.
3.CONCLUSION
Here different methods were analyzed to determine the
best fitting model. Time series models like Automated
Time Series Cost Forecasting systems, Interrupted time
series forecasting model, Vector error correction
model,5D BIM and Artificial Neural Network model were
used for determine the best method for cost forecasting.
And it is identified that the Artificial Neural Network
approach is much more capable for predicting the
accurate results. Forecasting using ANN is a more realistic
approach than others.
REFERENCES
[1] Sayid Amir Mohsen Faghih, Hamed Kashani
(2021)“Forecasting Construction Material Prices Using
Vector Error Correction Model” Journal of Construction
Engineering and Management(ASCE)
[2] Marc -Antoine Vigneault,Conrad Boton,Heap-Yih
Chong,Barry Cooper Cooke(2019)”An Innovative
Framework of 5D BIM Solutions for Construction Cost
Management: A Systematic Review” Archievs of
Computational Methods in Engineering(CIMNE)
[3] Moon,Taenam,Shin,Do Hyoung(2018)”R. Nicole,
“Forecasting Construction cost index using interrupted
time series,” Journal of Civil Engineering(KSCE)
[4] Abdul Rahman I, Hameed Memon A, Tarmizi Abd
Karim A (2013)”Signifcant factors causing cost overruns in
large construction projects in Malaysia.” Journal of Applied
Sciences(ANSI)
[5] Hemanta Doloi(2013)” Cost Overruns and Failure in
Project Management: Understanding the Roles of Key
Stakeholders in Construction Projects” Journal of
Construction Engineering and Management(ASCE)
[6] Xuequing Zhang(2013)“Concessionaire’s
Financial Capability in Developing Build-Operate-Transfer
Type Infrastructure Projects.” Journal of Construction
Engineering and Management(ASCE)
[7] Tarjei Kristiansen(2012)”Forecasting Nord Pool day
Ahead prices using auto regressive model” Energy Policy
“(ELSEVIER)
[8] Sungjoo Hwang,Moonseo Park,Hyun-Soo Lee,Hyunsoo
Kim;(2012) “Automated Time Series Cost Forecasting for
cost forecasting” Construction Engineering and
Management(ASCE)
[9] AntonioConejo,JavierContreras,RosaEspinola(2005)”F
orecasting electricity prices for a day-ahead pool-based
electric energy market”. International Journal of
Forecasting”(ELSEVIER)
[10] H.Ahuja. Successful construction cost control. Wiley,
New York,1980

More Related Content

Similar to Cost Forecasting of Construction Materials: A review

Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...IRJET Journal
 
IRJET- Speech and Hearing
IRJET- Speech and HearingIRJET- Speech and Hearing
IRJET- Speech and HearingIRJET Journal
 
'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management' 'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management' Alan Martin Redmond, PhD
 
IRJET - Customer Churn Analysis in Telecom Industry
IRJET - Customer Churn Analysis in Telecom IndustryIRJET - Customer Churn Analysis in Telecom Industry
IRJET - Customer Churn Analysis in Telecom IndustryIRJET Journal
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewIRJET Journal
 
IRJET- Logistics Network Superintendence Based on Knowledge Engineering
IRJET- Logistics Network Superintendence Based on Knowledge EngineeringIRJET- Logistics Network Superintendence Based on Knowledge Engineering
IRJET- Logistics Network Superintendence Based on Knowledge EngineeringIRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Integration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance systemIntegration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance systemLaurent Carlander
 
A TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRY
A TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRYA TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRY
A TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRYIRJET Journal
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET Journal
 
Insights on Research Techniques towards Cost Estimation in Software Design
Insights on Research Techniques towards Cost Estimation in Software Design Insights on Research Techniques towards Cost Estimation in Software Design
Insights on Research Techniques towards Cost Estimation in Software Design IJECEIAES
 
Visualizing and Forecasting Stocks Using Machine Learning
Visualizing and Forecasting Stocks Using Machine LearningVisualizing and Forecasting Stocks Using Machine Learning
Visualizing and Forecasting Stocks Using Machine LearningIRJET Journal
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
IRJET- The Evaluation of Payback period for Formwork system
IRJET-  	  The Evaluation of Payback period for Formwork systemIRJET-  	  The Evaluation of Payback period for Formwork system
IRJET- The Evaluation of Payback period for Formwork systemIRJET Journal
 
Machine Learning Approaches to Predict Customer Churn in Telecommunications I...
Machine Learning Approaches to Predict Customer Churn in Telecommunications I...Machine Learning Approaches to Predict Customer Churn in Telecommunications I...
Machine Learning Approaches to Predict Customer Churn in Telecommunications I...IRJET Journal
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET Journal
 
PERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATORPERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATORDr Ezzat Mansour
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionIJERA Editor
 
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET Journal
 

Similar to Cost Forecasting of Construction Materials: A review (20)

Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
 
IRJET- Speech and Hearing
IRJET- Speech and HearingIRJET- Speech and Hearing
IRJET- Speech and Hearing
 
'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management' 'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management'
 
IRJET - Customer Churn Analysis in Telecom Industry
IRJET - Customer Churn Analysis in Telecom IndustryIRJET - Customer Churn Analysis in Telecom Industry
IRJET - Customer Churn Analysis in Telecom Industry
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A Review
 
IRJET- Logistics Network Superintendence Based on Knowledge Engineering
IRJET- Logistics Network Superintendence Based on Knowledge EngineeringIRJET- Logistics Network Superintendence Based on Knowledge Engineering
IRJET- Logistics Network Superintendence Based on Knowledge Engineering
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Integration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance systemIntegration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance system
 
A TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRY
A TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRYA TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRY
A TECHNICAL REVIEW ON USE OF VEHICLE MONITORING SYSTEM IN CONSTRUCTION INDUSTRY
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
Insights on Research Techniques towards Cost Estimation in Software Design
Insights on Research Techniques towards Cost Estimation in Software Design Insights on Research Techniques towards Cost Estimation in Software Design
Insights on Research Techniques towards Cost Estimation in Software Design
 
Visualizing and Forecasting Stocks Using Machine Learning
Visualizing and Forecasting Stocks Using Machine LearningVisualizing and Forecasting Stocks Using Machine Learning
Visualizing and Forecasting Stocks Using Machine Learning
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
IRJET- The Evaluation of Payback period for Formwork system
IRJET-  	  The Evaluation of Payback period for Formwork systemIRJET-  	  The Evaluation of Payback period for Formwork system
IRJET- The Evaluation of Payback period for Formwork system
 
Machine Learning Approaches to Predict Customer Churn in Telecommunications I...
Machine Learning Approaches to Predict Customer Churn in Telecommunications I...Machine Learning Approaches to Predict Customer Churn in Telecommunications I...
Machine Learning Approaches to Predict Customer Churn in Telecommunications I...
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites Progress
 
PERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATORPERFORMANCE MONITORING USING EVM INDICATOR
PERFORMANCE MONITORING USING EVM INDICATOR
 
EARNED VALUE MANAGEMENT
EARNED VALUE MANAGEMENTEARNED VALUE MANAGEMENT
EARNED VALUE MANAGEMENT
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building Construction
 
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 

Recently uploaded (20)

POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 

Cost Forecasting of Construction Materials: A review

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 903 Cost Forecasting of Construction Materials: A review Cyril Thomas1, Jenson Jose2 1M.Tech student, Dept. of civil Engineering, St. Joseph’s college of Engineering and Technology, Palai, Kerala, India 2Assistant Professor, Dept. of civil Engineering, St. Joseph’s college of Engineering and Technology, Palai, Kerala, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Large-scale building projects are increasing day by day and because of that their construction costs become a matter of great concern, especially because of their lengthy construction periods. In particular, recent fluctuations of construction material prices have fueled problems like cost forecasting. This paper reviews the incorporation of artificial neural network for predicting the future cost construction materials. The main benefit of this study is providing construction stakeholders with a very reliable tool for expecting prices of coming projects, especially with the existing Rates of Inflation. Key Words: Future cost, construction, materials, artificial networks. 1.INTRODUCTION Large scale construction projects have recently increased in number of residential, commercial and government facilities worldwide. A lot of high rise buildings are being constructed or planned as urban land marks. The construction costs are dynamic. Prices of different materials, human resources, and other costs varies continuously. This economic uncertainty could have a major impact on the business especially on long term and mega projects. There are many traditional methods for predicting future construction costs in India. A forecasting method based on Artificial neural networks would be a great benefit for contractors, project owners etc. 1.1 5D BIM For a construction project perspective three phases can be classified such as the pre-construction, the construction and the maintenance and operation phases.5D BIM adds to the third and fourth dimensions with the ability to link costing information to the digital model and the project schedules to allow for better cost management. BEXEL Manager is software that integrates the most important 3D/4D/5D uses of BIM technology changing the perspective of integrated project management and allowing you to optimize your digital workflows and take advantage of advanced open BIM technologies. 1.2 Possibility of Artificial Intelligence In India traditional methods are followed to forecast the prices of construction materials. But in foreign countries several methods incorporating Artificial Intelligence are widely used to forecast the construction material prices. By incorporating artificial intelligence much more accuracy can be achieved and the values will have more accuracy compared to the ordinary methods of forecasting. Prediction using Artificial intelligence is a faster method and it has world wide recognition. If such methods are used in India, greater accuracy can be achieved and it will be very helpful for the contractors, project owners etc. in evaluating ,pricing and bidding construction projects. 2. COST FORECASTING METHODS Different approaches have been analyzed to determine the best fitting model for forecasting construction costs. These several methods are analyzed here. They are mainly Vector error-correction model, Time series models like Automated time series cost forecasting system, Interrupted time series forecasting model,5D BIM and Artificial Neural Network approach. They are discussed below. 2.1 Vector Error -Correction model Forecasting the short and long-term movement of construction material prices can be advantageous to various project stakeholders. By improving accuracy of their cost forecasts, contractors can avoid bidding or profit losses. In 2015 Shanhandashti and Ashuri used VEC models for forecasting construction material prices. Commonly used univariate and multivariate time series models, such as Box Jenkis and VAR models can be used to produce short-term material price forecasts. Cointegration, an econometric property of the time series variables,is generally used to characterize the long term relationships between non-stationary variables. In cases where two or more time series are cointegrated, VEC models can be used to develop short and long term forecasts. VEC model development includes different steps. First one is to identify candidate explanatory variables and collect corresponding data. Time series
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 904 analysis includes there are transit subset and testing subset. First step is followed by the check for stationarity. The augmented Dicky fuller test can be used to test the stationarity. The three main versions of augmented Dicky fuller test use the following models. They are mainly Woolridge model 2009,Gujarati 1995 and Dickey fuller 1979. This step is followed by a casualty test. Cointegration test is used to examine the existence of a long term relationship between explained and explanatory variables. Diagnostic tests are conducted to check for the existence of serial correlation and constant variances among residuals, which implies a lack of heteroscedasticity, and determine the goodness of models. Using the testing subset the prediction accuracy of the constructed VEC models can be evaluated. In this step, the values predicted by the model are compared against the actual values. After the predictability evaluation process has completed, the candidate VEC model that passes the diagnostics and has the better prediction performance among the candidate models is chosen to dynamically forecast the future levels of the explained variable using the explanatory variables. But there are several drawbacks for this model. The VEC models are incapable of predicting future shocks caused by extreme events and disruptive changes in technology, different practices, regulations, market dynamics, inflation, exchange rates etc. Forecasting Nord Pool day-ahead prices with an autoregressive model was carried out by Tarjei Kristiansen in 2012.Auto regressive model predicts the future behavior based on past behavior. Hemanta Doloi tried to unfold the industry wide perception of cost performance being heavily relient on the contractors performance alone. Doloi’s findings are expected to conclude a significant knowledge gap by shifting the priorities in cost estimation and management across all industry sectors. 2.2 Time -Series Models The ATMF system is composed of four modules. They are mainly time series data input, parameter estimation , GOF calculation, Diagnostic checking. In time series data input first we require a material unit price database. Material unit price data are assigned based on each type and price .When a user selects a material price name, from the corresponding material price database, raw-time series data are automatically extracted and automatically entered into the system. Then comes the important step that is parameter estimation. This parameter estimation module estimates parameters of all tentative ARIMA models and then tests the significance of the parameters. The GOF calculating module determines the suitability of all tentative models by using five GOF criteria which includes : root mean square error (RMSE), mean absolute error, Akaike’s information criteria, normalized Bayesian information criterion , and R-squared values. This step is followed by diagnostic checking. 2.2.1 Automated Time-Series Cost Forecasting System This ATMF system is very useful in predicting future trends in construction material costs. Furthermore, this system is very helpful for cost estimation at a detailed level . So this system can thus help decision makers in the construction industry deal with changes in economic conditions and design by estimating cost escalations caused by volatile factors such as inflation.An autoregressive and moving average(ARIMA) modeling method , which is one of the popular univariate and time series modeling methods suggested by Box and Jenkis(1994) with a focus on non seasonality and trends is analyzed.An autoregressive integrated moving average, or ARIMA, is a statistical analysis model that uses time series data to either better understand the data set or to predict future trends.For a detailed and updatable material cost estimating, an automated forecasting system is developed on the basis of both the ARIMA modeling process and a simplified forecasting procedure proposed by Lu and Abou Rizk.The system focuses on usability for construction practitioners, compatibility with existing estimation software, and simplicity in analysis procedures..This automated system focuses on many things like compatibility with the existing estimation software, on the usability for construction practitioners and the simplicity for analysis procedures.This system also involves the following.They are an automated input module using a price database,a parameter estimation module for alternative models using an optimal solution algorithm, a GOF calculation module using a GOF score, and a diagnostic checking module.This automated system focuses on many things like compatibility with the existing estimation software, on the usability for construction practitioners and the simplicity for analysis procedures.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 905 Fig-1: ATMF: A student centered framework for effective implementation of alternative teaching Rahman and co-authors in 2013 performed a study to find out the significant factors causing cost overrun in the large construction projects. The Relative importance index method is adopted here for the analysis. And from the hierarchichal assessment of factors and it was find out that,the top three most significant factors of cost overrun are variation of prices of material, cashflow and the financial difficulties that may faced by the contractors and because of poor site management and poor supervision. The above mentioned factors belongs to mainly two categories. They are contractor’s site management category and contractor’s financial management category. Cost overrun is a severe problem faced by large construction industries. 2.2.2 Interrupted Time Series Forecasting Model Here an interrupted time series forecasting model was developed wherein the economic recession of 2008 was reflected in the forecasting model, which is an outlier identified to have significant impact in the Construction cost index. The forecast result which is obtained using the Interrupted time series forecasting model was better than that of conventional forecasting models. The accurately forecasted Construction cost index using the presented model will help in budget and bid planning as well as assessing the risk of business. Interrupted-time series models provided better predictability than An autoregressive integrated moving average (ARIMA) and Holt-winters exponential smoothing models. An intervention analysis was conducted using the detected outliers to develop an interrupted time-series model wherein the intervention effects are reflected. Through this analysis, an interrupted time-series model was derived. Fig-2: Detection of CCI outliers( using ESD test). Fig-3: Detection of CCI outliers(using likelihood ratio test). Fig–4: Detection of CCI(Using break point estimation test)
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 906 An intervention analysis was conducted using the outliers which have detected to develop an interrupted time-series model wherein the intervention effects are reflected. From the analysis, an interrupted time-series model was derived by adding the outlier effects to the ARIMA model. It is necessary to determine the intervention timing of the outliers that have actually occurred at the same point in time to validate the significance of the outlier effects in the intervention analysis. Here, the occurence-timing points of the outliers occurring at similar points detected using the different detection methods were defined at the earliest of the occurrence points of the outliers. This was done because latter points could have occurred from the influences of a trend change or a jump in a short period. Hence, when the occurrence point is based on the latter points, the model can be estimated without considering the outlier effects between the earlier and latter points. 2.3 BIM 5D Building Information Modeling is a process supported by several tools, technologies and contracts involving the generation and management of digital representations of physical and functional characteristics of places. Building information models (BIMs) are computer files which can be extracted, exchanged or networked to support decision-making regarding a built asset. Government agencies, Individuals, business. Organizations use BIM software in their planning, designing and construction stage, operate and maintain buildings and diverse physical infrastructures, such as water, refuse, electricity, gas, communication utilities, roads, railways, bridges etc. From a construction project perspective three phases can be classified such as; the pre-construction, the construction, and the maintenance and operation phases. The pre- construction stage includes the concept, definition and design stages. Planning, designing, site preparation, foundation plinth construction, column, beam and slab construction, plastering, and finishing work are the different stages in construction. Finally in the maintenance and operation phase there are build and commission stages and hand over stage.5D BIM adds to the third and fourth dimensions with the ability to link costing information to the digital model and the project’s schedule to allow for the better cost management. The cost estimating features of most 5D BIM tools allow the creation of cost estimates that represent with more precision the actual cost of a project and overall cost reduction. There are five steps. Mainly the step one includes the following. they are: clarify scope, search for information, develop a framework and validate the frame work. The second step also was divided into three levels. They are mainly; the identification of available BIM 5D solutions, evaluation of solution’s functionalities, and finally the synthesis of solution’s functionalities The framework includes three levels. They are pre- construction, construction and post construction. The top three solutions have been identified for each 5D BIM level. For the first level, top three solutions are CostX, Vico office,iTWO. And for the second level top three solutions are mainly in the order Vico office, iTWO,CostX.In BIM 5D solutions there are mainly BIM readable solutions and BIM non-readable solutions. BIM readable solutions denote the tools that can both import data from and export data to the main 5D BIM software used on a project .BIM non - readable solutions have only the ability to import data from the main 5D software used without the ability to export data. 2.4 Artificial Neural Network Approach Artificial neural network approach is a machine learning method. This method can be effectively used for cost estimation. In this method first thing is to identify the input variables. The various input variables identified are; scale of work, project phases, project duration, scope of work, type of work, level of experience on client side, the scope definition, size project team,multi disciplinary, type of client, main market type, attitude towards design changes etc. In order to determine the cost influencing factor that are used in the estimation process interviews are done with 13 employees. After the database has been developed methodology was applied to build and train the cost estimating model. In this approach there are different phases. In first phase, best training function is defined. The correlation coefficient and mean absolute percentage error(MAPE) were used for assessment of model performance. After identifying the best model, next training algorithm was selected until all the training algorithms were tested. Fig-5: Structure of deep neural network.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 907 Phase two defines the feature selection. Here the irrelevant input variables are eliminated. Connection Weights Algorithm was used to determine the relative importance of variables. Variables with lowest relative importance are eliminated from the best model identified in the earlier phase. These variables are used to train the variables. There are Connection Weights Algorithm(CWA) and Multiple Linear Regression (MLR) method. In phase three, there is determining the model scope/range. Since the accuracy of the model depends on the size of the input data, three different scenarios were identified. Here the possibility of developing an accurate ML-based cost estimation method for tendering of engineering services has been done using neural network model to estimate the preliminary cost of engineering services. This research applied a systematic methodology that provides a guideline for developing and optimizing an Artificial Neural Network for cost estimation. It is found to efficient in improving the performance of the model. ANN can be used t0 obtain a fairly accurate cost estimate, even with minimum data that is available during the tendering phase. 3.CONCLUSION Here different methods were analyzed to determine the best fitting model. Time series models like Automated Time Series Cost Forecasting systems, Interrupted time series forecasting model, Vector error correction model,5D BIM and Artificial Neural Network model were used for determine the best method for cost forecasting. And it is identified that the Artificial Neural Network approach is much more capable for predicting the accurate results. Forecasting using ANN is a more realistic approach than others. REFERENCES [1] Sayid Amir Mohsen Faghih, Hamed Kashani (2021)“Forecasting Construction Material Prices Using Vector Error Correction Model” Journal of Construction Engineering and Management(ASCE) [2] Marc -Antoine Vigneault,Conrad Boton,Heap-Yih Chong,Barry Cooper Cooke(2019)”An Innovative Framework of 5D BIM Solutions for Construction Cost Management: A Systematic Review” Archievs of Computational Methods in Engineering(CIMNE) [3] Moon,Taenam,Shin,Do Hyoung(2018)”R. Nicole, “Forecasting Construction cost index using interrupted time series,” Journal of Civil Engineering(KSCE) [4] Abdul Rahman I, Hameed Memon A, Tarmizi Abd Karim A (2013)”Signifcant factors causing cost overruns in large construction projects in Malaysia.” Journal of Applied Sciences(ANSI) [5] Hemanta Doloi(2013)” Cost Overruns and Failure in Project Management: Understanding the Roles of Key Stakeholders in Construction Projects” Journal of Construction Engineering and Management(ASCE) [6] Xuequing Zhang(2013)“Concessionaire’s Financial Capability in Developing Build-Operate-Transfer Type Infrastructure Projects.” Journal of Construction Engineering and Management(ASCE) [7] Tarjei Kristiansen(2012)”Forecasting Nord Pool day Ahead prices using auto regressive model” Energy Policy “(ELSEVIER) [8] Sungjoo Hwang,Moonseo Park,Hyun-Soo Lee,Hyunsoo Kim;(2012) “Automated Time Series Cost Forecasting for cost forecasting” Construction Engineering and Management(ASCE) [9] AntonioConejo,JavierContreras,RosaEspinola(2005)”F orecasting electricity prices for a day-ahead pool-based electric energy market”. International Journal of Forecasting”(ELSEVIER) [10] H.Ahuja. Successful construction cost control. Wiley, New York,1980