SlideShare a Scribd company logo
1 of 11
Prof. Tatikonda G. S.
 The determination of rate per unit of a
particular item of work, from the cost of
quantities of materials, the cost of laborers
and other miscellaneous petty expenses
required for its completion is known as the
Analysis of Rates.
 The rates of materials and labor vary from
place to place and hence the rates of
different items of works also vary from
place to place.
 To work out the actual cost of per unit of the
items.
 To work out the economical use of materials
and processes in completing the particulars
item.
 To work out the cost of extra items which are
not provided in the contract bond, but are to
be done as per the directions of the client.
 To revise the schedule of rates due to increase
in the cost of material and labour or due to
change in technique
 Details of all operations involved in carrying
out the work
 The quantities of materials and their costs
 The number of different categories of
laborers required, their working capacity
and daily wages.
1. Major Factors :-
a) Material
b) Labour
2. Minor Factors : -
a) Special Equipment
b) Place of work
c) Nature of work
d) Conditions of Contract
e) Profit of the contractor
f) Specification
g) Site Condition
h) Miscellaneous
 Lead: The horizontal distance between the
trench pit and the place where excavated
earth is placed is called as lead. The unit of
lead is 50 m for a distance up to 500 m, 500 m
for a distance exceeding 500 m up to 5 km and
1 km for distance exceeds 5 km.
 Lift: It is the depth of excavation or the
vertical movement of material. Generally
lift is taken as 1.5 m below ground level. Extra
lift shall be measured in unit of 1.5 m or part
thereof.
The capacity of a skilled labour to do the
quantity of work per day called task work. Task work
is depends on the nature, size, height, situation, location,
climate condition, techniques adopted, wages paid.
Factors Affecting Task Work:-
 Out turn of skilled labour depends on the nature, size,
height, situation, location, Climatic condition, technique
adopted, wages paid etc.
 Availability of skilled labour.
 A well-organized work increases the out turn of labour.
 Job satisfaction and working condition may increase the
out turn work. If the work is allotted on piece work
basis then the daily wages output of labour increases.
 ANALYSIS OF RATES
The analysis of rates is worked out for the unit payment of
the particular item of work under two heads.
 Materials
 Labour
 Material Cost + Labour Cost = Cost of Items of Work
Other items included are:
 Tools and Plants ( T & P ) = 2.5 to 3 % of the labour cost
 Transportation cost more than 8 km is considered
 Water charges = 1.5 to 2 % 0f total cost
 Contractor ‘ s profit = 10 %
rate analysis

More Related Content

What's hot

Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildingsSimarpreet Singh
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tendersgayu pandian
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 

What's hot (20)

Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Valuation
ValuationValuation
Valuation
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Contracts
ContractsContracts
Contracts
 
Valuation
ValuationValuation
Valuation
 

Similar to rate analysis

Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdfDeepak37004
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptTauheedKhan45
 
Estimate and Valuation by Aman Kumar
Estimate and Valuation by Aman KumarEstimate and Valuation by Aman Kumar
Estimate and Valuation by Aman Kumaraman kumar
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of EstimationMuthanna Abbu
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptxrekhat26
 
Cost Classification in Management Accountingx
Cost Classification in Management AccountingxCost Classification in Management Accountingx
Cost Classification in Management AccountingxChamodiBandara1
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
Mca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingMca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingRai University
 
Theory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even AnalysisTheory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even AnalysisKumar Pawar
 

Similar to rate analysis (20)

UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
 
Rate analysis vansheika
Rate analysis   vansheikaRate analysis   vansheika
Rate analysis vansheika
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Estimate and Valuation by Aman Kumar
Estimate and Valuation by Aman KumarEstimate and Valuation by Aman Kumar
Estimate and Valuation by Aman Kumar
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
 
Cost Classification in Management Accountingx
Cost Classification in Management AccountingxCost Classification in Management Accountingx
Cost Classification in Management Accountingx
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
Ecv
EcvEcv
Ecv
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
3.estimating
3.estimating3.estimating
3.estimating
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Mca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingMca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costing
 
Theory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even AnalysisTheory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even Analysis
 

Recently uploaded

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 

Recently uploaded (20)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 

rate analysis

  • 2.  The determination of rate per unit of a particular item of work, from the cost of quantities of materials, the cost of laborers and other miscellaneous petty expenses required for its completion is known as the Analysis of Rates.  The rates of materials and labor vary from place to place and hence the rates of different items of works also vary from place to place.
  • 3.  To work out the actual cost of per unit of the items.  To work out the economical use of materials and processes in completing the particulars item.  To work out the cost of extra items which are not provided in the contract bond, but are to be done as per the directions of the client.  To revise the schedule of rates due to increase in the cost of material and labour or due to change in technique
  • 4.  Details of all operations involved in carrying out the work  The quantities of materials and their costs  The number of different categories of laborers required, their working capacity and daily wages.
  • 5. 1. Major Factors :- a) Material b) Labour 2. Minor Factors : - a) Special Equipment b) Place of work c) Nature of work d) Conditions of Contract e) Profit of the contractor f) Specification g) Site Condition h) Miscellaneous
  • 6.  Lead: The horizontal distance between the trench pit and the place where excavated earth is placed is called as lead. The unit of lead is 50 m for a distance up to 500 m, 500 m for a distance exceeding 500 m up to 5 km and 1 km for distance exceeds 5 km.  Lift: It is the depth of excavation or the vertical movement of material. Generally lift is taken as 1.5 m below ground level. Extra lift shall be measured in unit of 1.5 m or part thereof.
  • 7. The capacity of a skilled labour to do the quantity of work per day called task work. Task work is depends on the nature, size, height, situation, location, climate condition, techniques adopted, wages paid. Factors Affecting Task Work:-  Out turn of skilled labour depends on the nature, size, height, situation, location, Climatic condition, technique adopted, wages paid etc.  Availability of skilled labour.  A well-organized work increases the out turn of labour.  Job satisfaction and working condition may increase the out turn work. If the work is allotted on piece work basis then the daily wages output of labour increases.
  • 8.
  • 9.
  • 10.  ANALYSIS OF RATES The analysis of rates is worked out for the unit payment of the particular item of work under two heads.  Materials  Labour  Material Cost + Labour Cost = Cost of Items of Work Other items included are:  Tools and Plants ( T & P ) = 2.5 to 3 % of the labour cost  Transportation cost more than 8 km is considered  Water charges = 1.5 to 2 % 0f total cost  Contractor ‘ s profit = 10 %