SlideShare a Scribd company logo
1 of 25
Download to read offline
Prof.Tatikonda G. S.
Detailed estimates are prepared by carefully and
separately calculating in detail the costs of various
items of the work that constitute the whole project
from the detailed working drawings after the design
has been finalized.
Detailed estimates are submitted to the competent
authorities for obtaining technical sanction.
 In Government Organisation, a detailed estimate is required
for obtaining technical sanction from the competent
authorities for the proposed work.
 A detailed estimate is also required for the preparation of
contract (agreement) document.
 The detailed estimates serve as a guide during the execution
of the work.
 It helps in computing the quantities of materials required
and labour to be employed for the completion of various
items of construction.
 It is very useful in the efficient planning and programming of
all activities required for the speedy completion of the work.
 Drawings - Quantities of various items are calculated
on the basis of given drawing
 Specifications - Specification gives description of
material to be used, mode of execution quality of
work etc.The rates are varies according to
specification
 Rates-The rates of various materials used in the
construction and the wages of different categories of
labour should be available for preparing estimate.
 Mode of Measurement - Mode of measurement for
different item of work are taken with reference to IS
1200.
 Taking out quantities
 Squiring
 Abstracting
 The complete work is divided into various
items of work such as earth work concreting,
brick work, R.C.C. Plastering etc.,The details
of measurements are taken from drawings
and entered in respective columns of
prescribed proforma
 The quantities are calculated by multiplying
the values that are in numbers to Depth,
length, width.
 The cost of each item of work is worked out
from the quantities that already computed in
the details measurement form at workable
rate. But the total cost is worked out in the
prescribed form is known as abstract of
estimated form.
Abstract Sheet
Measurement Sheet
 Unit Quantity Method
In the unit quantity method, the work is divided
into as many operations or items as are required.
A unit of measurement is decided.The total
quantity of work under each item is taken out in
the proper unit of measurement.The total cost
per unit quantity of each item is analyzed and
worked out.Then the total cost for the item is
found by multiplying the cost per unit quantity
by the number of units.
 Total Quantity Method
In the total quantity method, an item of work is
divided into the following five subdivisions:
(I) Materials
(II) Labor
(III) Plant
(IV) Overheads
(V) Profit
 The total quantities of each kind or class of material or
labor are found and multiplied by their individual unit
cost. Similarly, the cost of plant, overhead expenses
and profit are determined.
 Long wall Short wall method or PWD method
or in to in and out to out method.
 Centre line method.
 In this method, the wall along the length of room is considered to
be long wall while the wall perpendicular to long wall is said to be
short wall.
 To get the length of longwall or shortwall, calculate first the centre
line lengths of individual walls.Then the length of long wall, (out
to out) may be calculated after adding half breadth at each end to
its centre line length.
 Length of long wall = centre line length of long wll + width of
item
 Thus the length of short wall measured into in and may be found
by deducting half breadth from its centre line length at each end.
 Length of Short wall = centre line length of short wall - width of
item
 The length of long wall usually decreases from earth work to brick
work in super structure while the short wall increases.These
lengths are multiplied by breadth and depth to get quantities.
 This method is suitable for walls of similar cross
sections. Here the total centre line length is multiplied
by breadth and depth of respective item to get the
total quantity at a time.
 When cross walls or partitions or verandah walls join
with main wall, the centre line length gets reduced by
half of breadth for each junction.
 Such junction or joints are studied carefully while
calculating total centre line length.The estimates
prepared by this method are most accurate and quick.
 Length of Item = total centre line length – (1/2 *
Number of junction *width of item)
 Bar Bending Schedule, commonly referred to as
“BBS” is a comprehensive list that describes the
location, mark, type, size, length and number, and
bending details of each bar or fabric in
a Reinforcement Drawing of a Structure.
 This process of listing the location, type and size,
number of and all other details is called “Scheduling”.
In context of Reinforcement bars, it is called bar
scheduling. In short, Bar Bending Schedule is a way of
organizing rebars for each structural unit, giving
detailed reinforcement requirements.
Contingencies :-
 The miscellaneous incidental expenses which
cannot approximately be classified under any
distinct sub head are called as contingencies.
 Some items of work might have been omitted
from the detailed estimate due to oversight or
some miscellaneous items do not form under
any sub head.To meet such expenses, provision
of contingencies is done in detailed estimate.
Normally it is 3 to 5% of estimated cost.
Work charge establishment :-
 The work charge establishment are the
establishment which is directly connected with
work.
 During the construction of a project/work some
supervisory staff such as supervisors, watchman,
store clerk etc. are appointed on temporary
basis.
 To meet this expenditure a provision is made in
the estimate of every work, which is known as
work charged establishment. It is about 2 to 2.5
% of the estimated cost of the work
 Water supply charges :-for the construction if water is
taken from street pipe line 5m from the property line
and to be stored in an overhead tank an amount of 4
to 5 % of estimated cost may be considered in
estimate.
 Electrification Charges:- For electrification wiring and
installation an amount of 8% of the cost of work is
added.
 Sanitary Charges :- An amount of 4 to 5 % of the
estimated cost of work is provided if sewer line is
within 12m from building line.
 Provisional Sum - Provisional sum is an amount
provided in the estimate for some specialized
work to be done by specialist firm.Whose details
are not known at the time of preparing estimate.
The work like installation of A.C, Lift etc. are
comes under provisional sum whose full
information and details may not be known at the
time of preparing estimate.The amount paid to
the contractor will not necessarily be the exact
amount of provisional sum.
 Prime cost :- Prime Cost is the net cost or purchase cost of articles
at shop and refers to the supply of articles only and not to the
carrying out of work. It is not always possible at the time of
preparing estimate to specify the exact requirement of articles
such as water supply fittings, sanitary fittings,door &window etc.
The same has to be decided while actual fitting of articles, for the
execution of such item a reasonable amount is kept in estimate as
Prime Cost.The price paid to the contractor for prime cost article
will be the actual cost paid by him, he is not allowed to take some
profit on that material.
 Provisional Quantity :- When the quantities of particular items
are uncertain due to unavailability of data, provisional quantities
of those items are called provisional items and corresponding
quantities are called provisional quantities.
 Day work :- The procedure of costing or
valuing an item of work on the basis of actual
labors and materials required, is called day
work.This method is used in certain items
where it is difficult to take measurement for
e.g Architectural elevation of building,
preparation of statue and under water
construction etc. Contractor have to maintain
the record of daily consummation of material
and labour engaged.

More Related Content

Similar to Detailed Estimate Components Guide

Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for buildingHimani762003
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfsuchitamantry2002
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptxRaniVishwakarma15
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notesDr.K.Mohan Das
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdfBSuresh26
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing2cd
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 

Similar to Detailed Estimate Components Guide (20)

Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
Ecv
EcvEcv
Ecv
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notes
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
M&R of Project
M&R of ProjectM&R of Project
M&R of Project
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 

More from Deepak37004

Summer Internship Report.pptx
Summer Internship Report.pptxSummer Internship Report.pptx
Summer Internship Report.pptxDeepak37004
 
EaseMyTrip_Investor-Presentation.pdf
EaseMyTrip_Investor-Presentation.pdfEaseMyTrip_Investor-Presentation.pdf
EaseMyTrip_Investor-Presentation.pdfDeepak37004
 
20221205043815.pdf
20221205043815.pdf20221205043815.pdf
20221205043815.pdfDeepak37004
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...Deepak37004
 
approximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfapproximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfDeepak37004
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
 
estimation-and-costing-textbook-by-bn-duttapdf_compress.pdf
estimation-and-costing-textbook-by-bn-duttapdf_compress.pdfestimation-and-costing-textbook-by-bn-duttapdf_compress.pdf
estimation-and-costing-textbook-by-bn-duttapdf_compress.pdfDeepak37004
 
3140601_surveying_module-6-tacheometric-surveying.pdf
3140601_surveying_module-6-tacheometric-surveying.pdf3140601_surveying_module-6-tacheometric-surveying.pdf
3140601_surveying_module-6-tacheometric-surveying.pdfDeepak37004
 

More from Deepak37004 (9)

Summer Internship Report.pptx
Summer Internship Report.pptxSummer Internship Report.pptx
Summer Internship Report.pptx
 
Curves.pdf
Curves.pdfCurves.pdf
Curves.pdf
 
EaseMyTrip_Investor-Presentation.pdf
EaseMyTrip_Investor-Presentation.pdfEaseMyTrip_Investor-Presentation.pdf
EaseMyTrip_Investor-Presentation.pdf
 
20221205043815.pdf
20221205043815.pdf20221205043815.pdf
20221205043815.pdf
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
 
approximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfapproximateestimate-200713090343.pdf
approximateestimate-200713090343.pdf
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
estimation-and-costing-textbook-by-bn-duttapdf_compress.pdf
estimation-and-costing-textbook-by-bn-duttapdf_compress.pdfestimation-and-costing-textbook-by-bn-duttapdf_compress.pdf
estimation-and-costing-textbook-by-bn-duttapdf_compress.pdf
 
3140601_surveying_module-6-tacheometric-surveying.pdf
3140601_surveying_module-6-tacheometric-surveying.pdf3140601_surveying_module-6-tacheometric-surveying.pdf
3140601_surveying_module-6-tacheometric-surveying.pdf
 

Recently uploaded

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Detailed Estimate Components Guide

  • 2. Detailed estimates are prepared by carefully and separately calculating in detail the costs of various items of the work that constitute the whole project from the detailed working drawings after the design has been finalized. Detailed estimates are submitted to the competent authorities for obtaining technical sanction.
  • 3.  In Government Organisation, a detailed estimate is required for obtaining technical sanction from the competent authorities for the proposed work.  A detailed estimate is also required for the preparation of contract (agreement) document.  The detailed estimates serve as a guide during the execution of the work.  It helps in computing the quantities of materials required and labour to be employed for the completion of various items of construction.  It is very useful in the efficient planning and programming of all activities required for the speedy completion of the work.
  • 4.  Drawings - Quantities of various items are calculated on the basis of given drawing  Specifications - Specification gives description of material to be used, mode of execution quality of work etc.The rates are varies according to specification  Rates-The rates of various materials used in the construction and the wages of different categories of labour should be available for preparing estimate.  Mode of Measurement - Mode of measurement for different item of work are taken with reference to IS 1200.
  • 5.  Taking out quantities  Squiring  Abstracting
  • 6.  The complete work is divided into various items of work such as earth work concreting, brick work, R.C.C. Plastering etc.,The details of measurements are taken from drawings and entered in respective columns of prescribed proforma
  • 7.  The quantities are calculated by multiplying the values that are in numbers to Depth, length, width.
  • 8.  The cost of each item of work is worked out from the quantities that already computed in the details measurement form at workable rate. But the total cost is worked out in the prescribed form is known as abstract of estimated form.
  • 10.  Unit Quantity Method In the unit quantity method, the work is divided into as many operations or items as are required. A unit of measurement is decided.The total quantity of work under each item is taken out in the proper unit of measurement.The total cost per unit quantity of each item is analyzed and worked out.Then the total cost for the item is found by multiplying the cost per unit quantity by the number of units.
  • 11.  Total Quantity Method In the total quantity method, an item of work is divided into the following five subdivisions: (I) Materials (II) Labor (III) Plant (IV) Overheads (V) Profit  The total quantities of each kind or class of material or labor are found and multiplied by their individual unit cost. Similarly, the cost of plant, overhead expenses and profit are determined.
  • 12.  Long wall Short wall method or PWD method or in to in and out to out method.  Centre line method.
  • 13.  In this method, the wall along the length of room is considered to be long wall while the wall perpendicular to long wall is said to be short wall.  To get the length of longwall or shortwall, calculate first the centre line lengths of individual walls.Then the length of long wall, (out to out) may be calculated after adding half breadth at each end to its centre line length.  Length of long wall = centre line length of long wll + width of item  Thus the length of short wall measured into in and may be found by deducting half breadth from its centre line length at each end.  Length of Short wall = centre line length of short wall - width of item  The length of long wall usually decreases from earth work to brick work in super structure while the short wall increases.These lengths are multiplied by breadth and depth to get quantities.
  • 14.
  • 15.  This method is suitable for walls of similar cross sections. Here the total centre line length is multiplied by breadth and depth of respective item to get the total quantity at a time.  When cross walls or partitions or verandah walls join with main wall, the centre line length gets reduced by half of breadth for each junction.  Such junction or joints are studied carefully while calculating total centre line length.The estimates prepared by this method are most accurate and quick.  Length of Item = total centre line length – (1/2 * Number of junction *width of item)
  • 16.
  • 17.  Bar Bending Schedule, commonly referred to as “BBS” is a comprehensive list that describes the location, mark, type, size, length and number, and bending details of each bar or fabric in a Reinforcement Drawing of a Structure.  This process of listing the location, type and size, number of and all other details is called “Scheduling”. In context of Reinforcement bars, it is called bar scheduling. In short, Bar Bending Schedule is a way of organizing rebars for each structural unit, giving detailed reinforcement requirements.
  • 18.
  • 19.
  • 20. Contingencies :-  The miscellaneous incidental expenses which cannot approximately be classified under any distinct sub head are called as contingencies.  Some items of work might have been omitted from the detailed estimate due to oversight or some miscellaneous items do not form under any sub head.To meet such expenses, provision of contingencies is done in detailed estimate. Normally it is 3 to 5% of estimated cost.
  • 21. Work charge establishment :-  The work charge establishment are the establishment which is directly connected with work.  During the construction of a project/work some supervisory staff such as supervisors, watchman, store clerk etc. are appointed on temporary basis.  To meet this expenditure a provision is made in the estimate of every work, which is known as work charged establishment. It is about 2 to 2.5 % of the estimated cost of the work
  • 22.  Water supply charges :-for the construction if water is taken from street pipe line 5m from the property line and to be stored in an overhead tank an amount of 4 to 5 % of estimated cost may be considered in estimate.  Electrification Charges:- For electrification wiring and installation an amount of 8% of the cost of work is added.  Sanitary Charges :- An amount of 4 to 5 % of the estimated cost of work is provided if sewer line is within 12m from building line.
  • 23.  Provisional Sum - Provisional sum is an amount provided in the estimate for some specialized work to be done by specialist firm.Whose details are not known at the time of preparing estimate. The work like installation of A.C, Lift etc. are comes under provisional sum whose full information and details may not be known at the time of preparing estimate.The amount paid to the contractor will not necessarily be the exact amount of provisional sum.
  • 24.  Prime cost :- Prime Cost is the net cost or purchase cost of articles at shop and refers to the supply of articles only and not to the carrying out of work. It is not always possible at the time of preparing estimate to specify the exact requirement of articles such as water supply fittings, sanitary fittings,door &window etc. The same has to be decided while actual fitting of articles, for the execution of such item a reasonable amount is kept in estimate as Prime Cost.The price paid to the contractor for prime cost article will be the actual cost paid by him, he is not allowed to take some profit on that material.  Provisional Quantity :- When the quantities of particular items are uncertain due to unavailability of data, provisional quantities of those items are called provisional items and corresponding quantities are called provisional quantities.
  • 25.  Day work :- The procedure of costing or valuing an item of work on the basis of actual labors and materials required, is called day work.This method is used in certain items where it is difficult to take measurement for e.g Architectural elevation of building, preparation of statue and under water construction etc. Contractor have to maintain the record of daily consummation of material and labour engaged.