SlideShare a Scribd company logo
1 of 14
Estimation and Costing
RATE ANALYSIS
Submitted By Submitted to
Vansheika (202601) Er. Akash Bhardwaj
RATE ANALYSIS
“ The determination of rate per unit of a particular item of work, from the
cost of quantities of materials, the cost of labourers and other miscellaneous
petty expenses required for its completion is known as the analysis of rates.”
In order to determine the rate of a particular item, the factors affecting
the rate of that item are studied carefully and then finally a rate is
decided for that item.
PURPOSE OF RATE ANALYSIS
•To work out the actual cost of per unit of the items.
•To work out the economical use of materials and processes in completing a
particular item.
•To work out the cost of extra items which are not provided in the contract bond,
but are to be done as per the directions of the department.
•To revise the schedule of rates due to increase in the cost of material and labour
or due to change in technique.
FACTORS AFFECTING RATE ANALYSIS
1. Specification of works and material, quality of materials, proportion of mortar
method of construction and operation.
2. Quantities of materials and their rates
3. Number of different types of labourer and their rates.
4. Location of site of work and its distance from the sources of materials and the
rates of transport, availability of water.
5. Profit and miscellaneous and overhead expenses of contractor.
How is a new unit rate defined?
The starting point to define the new unit rate, is to run a careful analysis of
the elements and resources that build up to form the new work item.
The elementary components, or resources, are generally the following:
• workforce
• materials
• hired equipment
• overheads
• company profits
Labor & Materials
The cost of labor is defined by the type of workers (specialized, qualified operators)
and the hours of work necessary per quantity unit.
To define the cost of the necessary materials, you need to determine the following:
• the purchase price
• on-site transport costs
• unloading
• stacking and storage
• waste (an excess percentage of unwanted material due to the production
processes)
OVERHEAD COSTS
• It includes general office expense, rents, taxes, supervision and other costs which are indirect
expense and not productive expense of job.
• The miscellaneous expense on overheads may be under the following heads;
A.General overheads
1. Establishment (office staff)
2. Stationary, printing, postages etc.
3. Travelling expense
4. Telephone
5. Rent and Taxes
OVERHEAD COSTS
B. Job overheads
1. Supervision (salary of Engg., Overseers, Supervision etc.)
2. Handling of materials
3. Repairs, carriage and depreciation of T&P
4. Amenities of labour
5. Workmen’s compensation and insurance
6. Interest on investment
7. Losses on advances
Note*
• The contractor may allowed to have a net profit of 6%-8%
• The miscellaneous overheads expenses may come to about 5%-10%
• Total 15% of the actual cost may be reasonable amount but it is usually practice to add
10%.
• 1.5% of water charges is also added
• If material has to be transported from more than 8km than transportation cost should
be calculated separately.
• 10% should be extra added to contractors profit if cement and steel has to be arranged
by him.
Lead statement
• The distance between the source of availability of material and construction site is
known as "Lead " and is expected in Km.
• The cost of conveyance of material depends on lead.
• This statement will give the total cost of materials per unit item. It includes first
cost, conveyance loading, unloading stacking, charges etc.
TASK OR TURN-OUT WORK
• Task : the capacity of doing work by an artisan or skilled labour in the form of quantity of work
per day.
• It varies to some extent according to the nature, size, height, situation, location etc.
example
For the excavation of foundation of a building. 4 labours worked out for 2 days and total quantity of
earthwork was 24cu.mt.
So total labours worked = 2 x 4 = 8 Nos
Task of one labour = 24/8 = 3 cu.mt.
Calculations of Quantities
Concrete work
For 1 m3 of wet concrete, dry volume is taken about 52% more
That is 1 m3 of wet concrete = 1.52 m3 of dry concrete
Quantity of materials for 1: 2 : 4 cement concrete
Proportion 1: 2 : 4 C : S : A Total = 7
Cement 1/7x 1.52 0.21714/0.035 6.204 say 7nos. of bags
Sand 2/7 x 1.52 0.434 m3
Aggregate 4/7 x 1.52 0.868 m3
Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3
(A) Material required
Sr Type of material Quantity Rate Per Amount
1 Cement
Q=1/7 x 10 x 1.52 = 2.17 / 0.035
62 280 bags 17360
2 Sand
Q= 2/7 x 10 x 1.52
4.34 1200 m3 5208
3 Course Agg.
Q= 4/7 x 10 x 1.52
8.68 1100 m3 9548
4 Steel (1%) 785 50 Kg 39250
5 Binding wire 8 35 Kg 280
4 Miscellaneous - - Lump sum 100
Total (A) 71,746
Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3
(B) Labour required
Sr Type Quantity Rate Per Amount
1 Head mason 1 500 day 500
2 Mason (Mixing, Trans., Placement) 10 350 day 3500
3 Mason (binding, bending) 9 250 day 2250
4 Mason (centering ,shuttering) Lump sum 5000
6 Rent for Equp. (2000 Rs) Lump sum 2000
Total (B) 13,250
Total ( A + B ) = Rs. 84,996
Add 1.5% of water charges = Rs. 1275
Add 10% of contractor’s profit = Rs. 8500
Rate for 10.0 m3 = Rs. 94,771
Rate for 1.0 m3 = Rs. 9,477

More Related Content

What's hot

Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundationsKHUSHBU SHAH
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkAshwiniChaudhari13
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildingsAshar Gill
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specificationsSimran Vats
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1ArunRavi43
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Design of Concrete Structure 1
Design of Concrete Structure 1Design of Concrete Structure 1
Design of Concrete Structure 1SHARIQUE AHMAD
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of RatesRaj Shah
 

What's hot (20)

Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Item rate contract
Item rate contractItem rate contract
Item rate contract
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Limit state method
Limit state methodLimit state method
Limit state method
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
 
Bar chart
Bar chartBar chart
Bar chart
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Design of Concrete Structure 1
Design of Concrete Structure 1Design of Concrete Structure 1
Design of Concrete Structure 1
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Earthwork
EarthworkEarthwork
Earthwork
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
specification of Rcc
specification of Rccspecification of Rcc
specification of Rcc
 

Similar to Rate analysis for RCC slab construction

Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptxrekhat26
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.pptashoklalwani6
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfsuchitamantry2002
 
Lecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfhLecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfh2cd
 
PPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxPPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxAravind Ra
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONDJAGADEESH1
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxNSHYAMANANDASINGH
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONSathishkumarM89
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptxDJAGADEESH1
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Padmasinh Patil
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing bookSubash Pathak
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptBALAMURUGANR53
 

Similar to Rate analysis for RCC slab construction (20)

UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
 
CEE 6.pptx
CEE 6.pptxCEE 6.pptx
CEE 6.pptx
 
Section 3-2.pptx
Section 3-2.pptxSection 3-2.pptx
Section 3-2.pptx
 
3.estimating
3.estimating3.estimating
3.estimating
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
 
Lecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfhLecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfh
 
Unit 3
Unit 3Unit 3
Unit 3
 
PPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxPPCE UNIT- 3.pptx
PPCE UNIT- 3.pptx
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing book
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 

Rate analysis for RCC slab construction

  • 1. Estimation and Costing RATE ANALYSIS Submitted By Submitted to Vansheika (202601) Er. Akash Bhardwaj
  • 2. RATE ANALYSIS “ The determination of rate per unit of a particular item of work, from the cost of quantities of materials, the cost of labourers and other miscellaneous petty expenses required for its completion is known as the analysis of rates.” In order to determine the rate of a particular item, the factors affecting the rate of that item are studied carefully and then finally a rate is decided for that item.
  • 3. PURPOSE OF RATE ANALYSIS •To work out the actual cost of per unit of the items. •To work out the economical use of materials and processes in completing a particular item. •To work out the cost of extra items which are not provided in the contract bond, but are to be done as per the directions of the department. •To revise the schedule of rates due to increase in the cost of material and labour or due to change in technique.
  • 4. FACTORS AFFECTING RATE ANALYSIS 1. Specification of works and material, quality of materials, proportion of mortar method of construction and operation. 2. Quantities of materials and their rates 3. Number of different types of labourer and their rates. 4. Location of site of work and its distance from the sources of materials and the rates of transport, availability of water. 5. Profit and miscellaneous and overhead expenses of contractor.
  • 5. How is a new unit rate defined? The starting point to define the new unit rate, is to run a careful analysis of the elements and resources that build up to form the new work item. The elementary components, or resources, are generally the following: • workforce • materials • hired equipment • overheads • company profits
  • 6. Labor & Materials The cost of labor is defined by the type of workers (specialized, qualified operators) and the hours of work necessary per quantity unit. To define the cost of the necessary materials, you need to determine the following: • the purchase price • on-site transport costs • unloading • stacking and storage • waste (an excess percentage of unwanted material due to the production processes)
  • 7. OVERHEAD COSTS • It includes general office expense, rents, taxes, supervision and other costs which are indirect expense and not productive expense of job. • The miscellaneous expense on overheads may be under the following heads; A.General overheads 1. Establishment (office staff) 2. Stationary, printing, postages etc. 3. Travelling expense 4. Telephone 5. Rent and Taxes
  • 8. OVERHEAD COSTS B. Job overheads 1. Supervision (salary of Engg., Overseers, Supervision etc.) 2. Handling of materials 3. Repairs, carriage and depreciation of T&P 4. Amenities of labour 5. Workmen’s compensation and insurance 6. Interest on investment 7. Losses on advances
  • 9. Note* • The contractor may allowed to have a net profit of 6%-8% • The miscellaneous overheads expenses may come to about 5%-10% • Total 15% of the actual cost may be reasonable amount but it is usually practice to add 10%. • 1.5% of water charges is also added • If material has to be transported from more than 8km than transportation cost should be calculated separately. • 10% should be extra added to contractors profit if cement and steel has to be arranged by him.
  • 10. Lead statement • The distance between the source of availability of material and construction site is known as "Lead " and is expected in Km. • The cost of conveyance of material depends on lead. • This statement will give the total cost of materials per unit item. It includes first cost, conveyance loading, unloading stacking, charges etc.
  • 11. TASK OR TURN-OUT WORK • Task : the capacity of doing work by an artisan or skilled labour in the form of quantity of work per day. • It varies to some extent according to the nature, size, height, situation, location etc. example For the excavation of foundation of a building. 4 labours worked out for 2 days and total quantity of earthwork was 24cu.mt. So total labours worked = 2 x 4 = 8 Nos Task of one labour = 24/8 = 3 cu.mt.
  • 12. Calculations of Quantities Concrete work For 1 m3 of wet concrete, dry volume is taken about 52% more That is 1 m3 of wet concrete = 1.52 m3 of dry concrete Quantity of materials for 1: 2 : 4 cement concrete Proportion 1: 2 : 4 C : S : A Total = 7 Cement 1/7x 1.52 0.21714/0.035 6.204 say 7nos. of bags Sand 2/7 x 1.52 0.434 m3 Aggregate 4/7 x 1.52 0.868 m3
  • 13. Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3 (A) Material required Sr Type of material Quantity Rate Per Amount 1 Cement Q=1/7 x 10 x 1.52 = 2.17 / 0.035 62 280 bags 17360 2 Sand Q= 2/7 x 10 x 1.52 4.34 1200 m3 5208 3 Course Agg. Q= 4/7 x 10 x 1.52 8.68 1100 m3 9548 4 Steel (1%) 785 50 Kg 39250 5 Binding wire 8 35 Kg 280 4 Miscellaneous - - Lump sum 100 Total (A) 71,746
  • 14. Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3 (B) Labour required Sr Type Quantity Rate Per Amount 1 Head mason 1 500 day 500 2 Mason (Mixing, Trans., Placement) 10 350 day 3500 3 Mason (binding, bending) 9 250 day 2250 4 Mason (centering ,shuttering) Lump sum 5000 6 Rent for Equp. (2000 Rs) Lump sum 2000 Total (B) 13,250 Total ( A + B ) = Rs. 84,996 Add 1.5% of water charges = Rs. 1275 Add 10% of contractor’s profit = Rs. 8500 Rate for 10.0 m3 = Rs. 94,771 Rate for 1.0 m3 = Rs. 9,477