SlideShare a Scribd company logo
1 of 10
CASE TAKEN BIHAR NEW GANGA RIVER PROJECT
AND
TECHNICAL RISK IDENTIFIED
• UNPREDICTED RIVER FLOW AND SOIL CONDITIONS DELAY CONSTRUCTION
• BRIDGE MAINTENANCE IS NOT SUSTAINABLE, AND FUTURE CAPACITY FOR BRIDGE OPERATION AND MANAGEMENT IS WEAK
• PROJECT START UP IS DELAYED AND DISBURSEMENT IS SLOW
• IMPLEMENTATION CAPACITY IS NOT ADEQUATE
• PROCUREMENT (MANPOWER & MATERIALS)
• IMPROVEMENTS TO COMPLEMENTARY NATIONAL AND STATE HIGHWAYS ARE DELAYED
• INADEQUATE AND INCOMPLETE DESIGN
• INACCURATE ASSUMPTIONS ON TECHNICAL ISSUES IN THE PLANNING STAGE
RISK PARAMETER TABLE
P o i n t s I m p a c t L i k e l i h o o d
1 0 - 8 C r i t i c a l H i g h
7 - 4 M o d e r a t e M e d i u m
3 - 1 M i n o r L o w
PRIORITIZE THE RISK WITH RESPECT TO
IMPACT AND LIKELIHOOD
Risk Factor Impac
t
Likelihood
a Unpredicted river flow and soil conditions delay construction 10 8 80
b Bridge maintenance is not sustainable 6 6 36
c Inaccurate assumptions on technical issues in the planning stage 9 7 63
d Inadequate and incomplete design 8 6 48
e Improvements to complementary national and state highways are
delayed
2 2 4
f Project start up is delayed and disbursement is slow 4 5 20
g Decision implementation capacity is not adequate 7 3 21
h Procurement (Manpower & Materials) 6 5 30
ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP =
environmental management plan, PMAE = project management and authority engineering, TA = technical assistance.
Source: Asian Development Bank.
RISK MATRIX
Likelihood
I
m
p
a
c
t
10 20 30 40 50 60 70 80(a) 90 100
9 18 27 36 45 54 63(c) 72 81 90
8 16 24 32 40 48(d) 56 64 72 80
7 14 21(g) 28 35 42 49 56 63 70
6 12 18 24 30(h) 36(b) 42 48 54 60
5 10 15 20 25 30 35 40 45 50
4 8 12 16 20(f) 24 28 32 36 40
3 6 9 12 15 18 21 24 27 30
2 4(e) 6 8 10 12 14 16 18 20
1 2 3 4 5 6 7 8 9 10
60-100 High, 20-59 Medium, 1-19 Low
S.No
.
Risk Factor Priority Mitigation Measures
1 Unpredicted river flow and soil
conditions delay construction
(a)
High Historical hydrological data collected by the
Central Water Commission and supplemented
with information available in the past reports and
literature.
2 Bridge maintenance is not
(b)
Medium The TA will strengthen the institutional capacity
of the Government of Bihar and BSRDCL to
effectively manage and maintain major bridges in
Bihar and develop sustainable operation and
maintenance plans for bridges in Bihar.
3 Inaccurate assumptions on technical
issues in the planning stage
(c)
Medium Value Engineering and Effective Planning team
with experienced members will conduct meetings
and review decision at Design stage.
ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP =
environmental management plan, PMAE = project management and authority engineering, TA = technical assistance.
Source: Asian Development Bank.
S.
N
o.
Risk Factor Priority Mitigation Measures
4 Inadequate and incomplete design
(d)
Medium Collaborating Software use for proper
feedback and communication at various
stages of construction
5 Improvements to complementary national
state highways are delayed
(e)
Low National Highway Development Project
(NHDP) appointed to look after the
construction of Roads
6 Decision implementation capacity is not
adequate
(g)
Medium The PMAE team will to support BSRDCL by
providing overall project management
assistance and monitoring the
implementation of safeguards, including
the EMP and other measures related to
environmental protection.
ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP =
environmental management plan, PMAE = project management and authority engineering, TA = technical assistance.
Source: Asian Development Bank.
S.N
o.
Risk Factor Priority Mitigation Measures
7 Project start up is delayed and
disbursement is slow (f)
Medium Taking EMP and EIA prior to project.
Taking Approvals with considering the
schedule and appropriate time.
8 Procurement (Manpower & Materials)
(h)
Medium Procuring from local availability and
appointing the best logistic company for
material procurement.
ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP =
environmental management plan, PMAE = project management and authority engineering, TA = technical assistance.
Source: Asian Development Bank.
THANK YOU
REFERENCES
• HTTPS://WWW.DESIGNINGBUILDINGS.CO.UK/WIKI/RISK_IN_BUILDING_DESIGN_AND_CONSTRUCTION#TE
CHNICAL_RISKS
• HTTPS://WWW.ADB.ORG/PROJECTS/DOCUMENTS/IND-BIHAR-NEW-GANGA-BRIDGE-PROJECT-RRP
• LI, QING-FU, ZHANG, PENG & FU, YAN-CHAO. (2013). RISK IDENTIFICATION FOR THE CONSTRUCTION PHASES OF
THE LARGE BRIDGE BASED ON WBS-RBS. RESEARCH JOURNAL OF APPLIED SCIENCES, ENGINEERING AND
TECHNOLOGY . [ONLINE]. 6(9), 1523-1530. [22 JANUARY 2018]. HTTP://PAKACADEMICSEARCH.COM/PDF-
FILES/ENG/392/1523-1530%202013(VOL.%206,%20ISSUE%2009).PDF

More Related Content

What's hot

Drafting a project proposal
Drafting a project proposalDrafting a project proposal
Drafting a project proposalVidyavinutha
 
PMO Performance Measurement and Metrics - Kendrick
PMO Performance Measurement and Metrics - KendrickPMO Performance Measurement and Metrics - Kendrick
PMO Performance Measurement and Metrics - KendrickJim Kendrick
 
project Scope management
project Scope management project Scope management
project Scope management Mohamed , PMP
 
Dhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptxDhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptxZunayet Shibly
 
Program Management and Leadership
Program Management and LeadershipProgram Management and Leadership
Program Management and Leadershiptltiede
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
Ekvator prensipleri
Ekvator prensipleriEkvator prensipleri
Ekvator prensipleriEmre Aydın
 
Project Management Playbook
Project Management PlaybookProject Management Playbook
Project Management PlaybookDemand Metric
 
Cpec( m.ehsan)
Cpec( m.ehsan)Cpec( m.ehsan)
Cpec( m.ehsan)Ahsan Rao
 
China Pakistan Economic Corridor
China Pakistan Economic CorridorChina Pakistan Economic Corridor
China Pakistan Economic CorridorMalik Younis
 
Project Scope Management Plan Template
Project Scope Management Plan TemplateProject Scope Management Plan Template
Project Scope Management Plan TemplateMelanieRos
 
PMP Study Notes
PMP Study NotesPMP Study Notes
PMP Study NotesMike Burch
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)Tony
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...Edureka!
 
Environmental feasibility
Environmental feasibility Environmental feasibility
Environmental feasibility azizmambli
 

What's hot (20)

Drafting a project proposal
Drafting a project proposalDrafting a project proposal
Drafting a project proposal
 
PMO Performance Measurement and Metrics - Kendrick
PMO Performance Measurement and Metrics - KendrickPMO Performance Measurement and Metrics - Kendrick
PMO Performance Measurement and Metrics - Kendrick
 
Establishing an effective epmo
Establishing an effective epmoEstablishing an effective epmo
Establishing an effective epmo
 
Metro rail
Metro railMetro rail
Metro rail
 
project Scope management
project Scope management project Scope management
project Scope management
 
Dhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptxDhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptx
 
Program Management and Leadership
Program Management and LeadershipProgram Management and Leadership
Program Management and Leadership
 
A Strategy to conquer CBAP examination
A Strategy to conquer CBAP examinationA Strategy to conquer CBAP examination
A Strategy to conquer CBAP examination
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
Ekvator prensipleri
Ekvator prensipleriEkvator prensipleri
Ekvator prensipleri
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
Project Management Playbook
Project Management PlaybookProject Management Playbook
Project Management Playbook
 
Cpec( m.ehsan)
Cpec( m.ehsan)Cpec( m.ehsan)
Cpec( m.ehsan)
 
China Pakistan Economic Corridor
China Pakistan Economic CorridorChina Pakistan Economic Corridor
China Pakistan Economic Corridor
 
Project Scope Management Plan Template
Project Scope Management Plan TemplateProject Scope Management Plan Template
Project Scope Management Plan Template
 
PMP Study Notes
PMP Study NotesPMP Study Notes
PMP Study Notes
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Environmental feasibility
Environmental feasibility Environmental feasibility
Environmental feasibility
 

Similar to Technical risk identification and analysis of river bridge project

Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channelsmirzaqadeer
 
Sardar Sarovar Project - 56 Years of Controversary
Sardar Sarovar Project - 56 Years of ControversarySardar Sarovar Project - 56 Years of Controversary
Sardar Sarovar Project - 56 Years of ControversarySelf-employed
 
Tamil nadu wb review tn_hpii_delhi_may2014
Tamil nadu wb review tn_hpii_delhi_may2014Tamil nadu wb review tn_hpii_delhi_may2014
Tamil nadu wb review tn_hpii_delhi_may2014hydrologyproject0
 
Local Government Management Processes
Local Government Management ProcessesLocal Government Management Processes
Local Government Management ProcessesDanee McGee
 
Final year project proposal on feasibility study of small hydro power
Final year project proposal on feasibility study of small hydro powerFinal year project proposal on feasibility study of small hydro power
Final year project proposal on feasibility study of small hydro powersurya paudel
 
AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2Ashwin Beosumbar
 
RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)apwacoachellavalley
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L NBasavaraj L N
 
CV for Nyquist rev bob 2
CV for Nyquist rev bob 2CV for Nyquist rev bob 2
CV for Nyquist rev bob 2Michael Nyquist
 
2013.03.12_HillStPublicMeeting_ppt
2013.03.12_HillStPublicMeeting_ppt2013.03.12_HillStPublicMeeting_ppt
2013.03.12_HillStPublicMeeting_pptDanee McGee
 
K Horner_RESUME_20161103
K Horner_RESUME_20161103K Horner_RESUME_20161103
K Horner_RESUME_20161103Kenneth Horner
 
Project formulation slstl-iesl - 25th oct 2018 - to be published
Project formulation   slstl-iesl - 25th oct 2018 - to be publishedProject formulation   slstl-iesl - 25th oct 2018 - to be published
Project formulation slstl-iesl - 25th oct 2018 - to be publishedNamalie Siyambalapitiya
 
RESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINSRESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINSarchith sanker
 
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docxNEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docxhenrymartin15260
 

Similar to Technical risk identification and analysis of river bridge project (20)

Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channels
 
Sardar Sarovar Project - 56 Years of Controversary
Sardar Sarovar Project - 56 Years of ControversarySardar Sarovar Project - 56 Years of Controversary
Sardar Sarovar Project - 56 Years of Controversary
 
Tamil nadu wb review tn_hpii_delhi_may2014
Tamil nadu wb review tn_hpii_delhi_may2014Tamil nadu wb review tn_hpii_delhi_may2014
Tamil nadu wb review tn_hpii_delhi_may2014
 
Hemant_CV
Hemant_CVHemant_CV
Hemant_CV
 
Local Government Management Processes
Local Government Management ProcessesLocal Government Management Processes
Local Government Management Processes
 
Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20
 
Final year project proposal on feasibility study of small hydro power
Final year project proposal on feasibility study of small hydro powerFinal year project proposal on feasibility study of small hydro power
Final year project proposal on feasibility study of small hydro power
 
AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2AHBeosumbarPrTechEngCV2013Vol2
AHBeosumbarPrTechEngCV2013Vol2
 
RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L N
 
CV for Nyquist rev bob 2
CV for Nyquist rev bob 2CV for Nyquist rev bob 2
CV for Nyquist rev bob 2
 
PPM presentation
PPM presentation PPM presentation
PPM presentation
 
2013.03.12_HillStPublicMeeting_ppt
2013.03.12_HillStPublicMeeting_ppt2013.03.12_HillStPublicMeeting_ppt
2013.03.12_HillStPublicMeeting_ppt
 
PM Resume 9_30_15
PM Resume 9_30_15PM Resume 9_30_15
PM Resume 9_30_15
 
K Horner_RESUME_20161103
K Horner_RESUME_20161103K Horner_RESUME_20161103
K Horner_RESUME_20161103
 
Project formulation slstl-iesl - 25th oct 2018 - to be published
Project formulation   slstl-iesl - 25th oct 2018 - to be publishedProject formulation   slstl-iesl - 25th oct 2018 - to be published
Project formulation slstl-iesl - 25th oct 2018 - to be published
 
RESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINSRESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINS
 
Whitington 2016-10
Whitington 2016-10Whitington 2016-10
Whitington 2016-10
 
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docxNEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
 
QPR-1 draft.pptx
QPR-1 draft.pptxQPR-1 draft.pptx
QPR-1 draft.pptx
 

Recently uploaded

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Recently uploaded (20)

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Technical risk identification and analysis of river bridge project

  • 1.
  • 2. CASE TAKEN BIHAR NEW GANGA RIVER PROJECT AND TECHNICAL RISK IDENTIFIED • UNPREDICTED RIVER FLOW AND SOIL CONDITIONS DELAY CONSTRUCTION • BRIDGE MAINTENANCE IS NOT SUSTAINABLE, AND FUTURE CAPACITY FOR BRIDGE OPERATION AND MANAGEMENT IS WEAK • PROJECT START UP IS DELAYED AND DISBURSEMENT IS SLOW • IMPLEMENTATION CAPACITY IS NOT ADEQUATE • PROCUREMENT (MANPOWER & MATERIALS) • IMPROVEMENTS TO COMPLEMENTARY NATIONAL AND STATE HIGHWAYS ARE DELAYED • INADEQUATE AND INCOMPLETE DESIGN • INACCURATE ASSUMPTIONS ON TECHNICAL ISSUES IN THE PLANNING STAGE
  • 3. RISK PARAMETER TABLE P o i n t s I m p a c t L i k e l i h o o d 1 0 - 8 C r i t i c a l H i g h 7 - 4 M o d e r a t e M e d i u m 3 - 1 M i n o r L o w
  • 4. PRIORITIZE THE RISK WITH RESPECT TO IMPACT AND LIKELIHOOD Risk Factor Impac t Likelihood a Unpredicted river flow and soil conditions delay construction 10 8 80 b Bridge maintenance is not sustainable 6 6 36 c Inaccurate assumptions on technical issues in the planning stage 9 7 63 d Inadequate and incomplete design 8 6 48 e Improvements to complementary national and state highways are delayed 2 2 4 f Project start up is delayed and disbursement is slow 4 5 20 g Decision implementation capacity is not adequate 7 3 21 h Procurement (Manpower & Materials) 6 5 30 ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP = environmental management plan, PMAE = project management and authority engineering, TA = technical assistance. Source: Asian Development Bank.
  • 5. RISK MATRIX Likelihood I m p a c t 10 20 30 40 50 60 70 80(a) 90 100 9 18 27 36 45 54 63(c) 72 81 90 8 16 24 32 40 48(d) 56 64 72 80 7 14 21(g) 28 35 42 49 56 63 70 6 12 18 24 30(h) 36(b) 42 48 54 60 5 10 15 20 25 30 35 40 45 50 4 8 12 16 20(f) 24 28 32 36 40 3 6 9 12 15 18 21 24 27 30 2 4(e) 6 8 10 12 14 16 18 20 1 2 3 4 5 6 7 8 9 10 60-100 High, 20-59 Medium, 1-19 Low
  • 6. S.No . Risk Factor Priority Mitigation Measures 1 Unpredicted river flow and soil conditions delay construction (a) High Historical hydrological data collected by the Central Water Commission and supplemented with information available in the past reports and literature. 2 Bridge maintenance is not (b) Medium The TA will strengthen the institutional capacity of the Government of Bihar and BSRDCL to effectively manage and maintain major bridges in Bihar and develop sustainable operation and maintenance plans for bridges in Bihar. 3 Inaccurate assumptions on technical issues in the planning stage (c) Medium Value Engineering and Effective Planning team with experienced members will conduct meetings and review decision at Design stage. ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP = environmental management plan, PMAE = project management and authority engineering, TA = technical assistance. Source: Asian Development Bank.
  • 7. S. N o. Risk Factor Priority Mitigation Measures 4 Inadequate and incomplete design (d) Medium Collaborating Software use for proper feedback and communication at various stages of construction 5 Improvements to complementary national state highways are delayed (e) Low National Highway Development Project (NHDP) appointed to look after the construction of Roads 6 Decision implementation capacity is not adequate (g) Medium The PMAE team will to support BSRDCL by providing overall project management assistance and monitoring the implementation of safeguards, including the EMP and other measures related to environmental protection. ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP = environmental management plan, PMAE = project management and authority engineering, TA = technical assistance. Source: Asian Development Bank.
  • 8. S.N o. Risk Factor Priority Mitigation Measures 7 Project start up is delayed and disbursement is slow (f) Medium Taking EMP and EIA prior to project. Taking Approvals with considering the schedule and appropriate time. 8 Procurement (Manpower & Materials) (h) Medium Procuring from local availability and appointing the best logistic company for material procurement. ADB = Asian Development Bank, BSRDCL = Bihar State Road Development Corporation Limited, EMP = environmental management plan, PMAE = project management and authority engineering, TA = technical assistance. Source: Asian Development Bank.
  • 10. REFERENCES • HTTPS://WWW.DESIGNINGBUILDINGS.CO.UK/WIKI/RISK_IN_BUILDING_DESIGN_AND_CONSTRUCTION#TE CHNICAL_RISKS • HTTPS://WWW.ADB.ORG/PROJECTS/DOCUMENTS/IND-BIHAR-NEW-GANGA-BRIDGE-PROJECT-RRP • LI, QING-FU, ZHANG, PENG & FU, YAN-CHAO. (2013). RISK IDENTIFICATION FOR THE CONSTRUCTION PHASES OF THE LARGE BRIDGE BASED ON WBS-RBS. RESEARCH JOURNAL OF APPLIED SCIENCES, ENGINEERING AND TECHNOLOGY . [ONLINE]. 6(9), 1523-1530. [22 JANUARY 2018]. HTTP://PAKACADEMICSEARCH.COM/PDF- FILES/ENG/392/1523-1530%202013(VOL.%206,%20ISSUE%2009).PDF