Follow this simple step-by-step guide to develop a project management
playbook that aligns with the traditional phased approach.
PROJECT MANAGEMENT
Playbook & Toolkit
Table of Contents PROJECT MANAGEMENT
Introduction 04
Conclusion 30
Framework 03
About This Playbook 31
Initiate 09
12Plan
20Execute
23Control
27Close
stage
stage
stage
stage
stage
1
2
3
4
5
Issue Log TemplateStrategy Scorecards
Key Success Factors
Tool
Responsibility
Assignment Matrix
Earned Value
Analysis Template
Lessons Learned
Template
Post-Project
Evaluation
Project Change
Request Log
Work Breakdown
Structure Template
Business Case
Template
Project Management
Maturity Assessment
Change Management
Plan Template
Project Approval Form
Project Plan Template
Feasibility Study
Template
Project Management
Office Charter
Stakeholder Analysis
Matrix
Project Portfolio
Template
Project Charter
Template
Project Management
Template
Project Budget
Template
Risk Management
Plan Template
PROJECT MANAGEMENT
Framework
Leverage the framework below to quickly empower
your organization’s project management strategy.
Click the buttons below to access all related
training, tools, templates, and other resources.
Project Change
Request Form
Project Status Report
Template
Project Acceptance
Document
Project Milestones
Template
Deliverable Approval
Template
Risk Assessment Tool
Project Closure
Checklist
Quality Log Template
PLAN2 CONTROL4 CLOSE5EXECUTE31 INITIATE
4PROJECT MANAGEMENT
Initiate Plan Execute Control Close
1 2 3 4 5
Introduction
How to Use this Playbook
Our playbook consists of five stages, each with a description,
steps and action items. Action items include using our premium
tools & templates. Our intention with this playbook is to support
you in achieving your project management goals. This will be
accomplished by helping you:
Improve the effectiveness & efficiency of project
management in your organization
Organize and support your project management office
Standardize the templates used by your project
managers
Before You Get Started…
A Project Management Office (PMO) is a group or department within
a business that defines and maintains standards for project manage-
ment within the organization. Among other things, tasks may include
monitoring and reporting on active projects and reporting prog-
ress to top management for strategic decisions on what projects to
continue or cancel. The next few pages will help you:
1. Understand the key functions of a PMO
2. Benchmark your current capabilities
3. Build a PMO Charter and formalize your process using our
time-saving tools & templates
Do you currently have a Project Management Office?
Have you been asked to build one?
5PROJECT MANAGEMENT
Functions of a Project Management Office
The Project Management Institute (PMI) sponsored Dr. Brian Hobbs
of the University of Québec to research the current state of practice
for the Project Management Office. One of the key findings involved
categorizing the functions performed by PMOs into the following five
broad groups:
Organizational Leadership
Development of Project Management
Competencies and Methodologies
Strategic Management
Multi-Project Management
Monitoring and Controlling Project Performance
Initiate Plan Execute Control Close
1 2 3 4 5
Introduction
What Is the Purpose of This Playbook?
To help you develop a Project Management Playbook &
Toolkit of your own. This guide contains tools & templates
that can be used a starting point and then customized
according to your needs.
There are a number of different approaches to managing
projects. For the purpose of this playbook, we will be using
the traditional phased approach as outlined below:
Initiate
Control
Close
Plan
Execute
6PROJECT MANAGEMENT
Use our Project Management Maturity Assessment to
evaluate your organization’s current project management
capabilities.
Use our Project Management Office Charter to establish
the purpose for the PMO’s existence, its primary functions,
its sponsors , its customers and its structure.
Areas of evaluation include: Sections covered in the PMO Charter Template include:
Benchmark Your Current Capabilities Project Management Office Charter
V I E W R E S O U R C E
Scope
Time
Cost
Scope
Vision
Mission
Goals
Quality
Human Resources
Integrations
Metrics
Reporting
Services
Communications
Risk Management
Procurement
KSFs
Governance
Approval
Based on the assessment, decide how you would like to proceed. If
you identify the need to create and/or formalize a Project Manage-
ment Office, use the next section to get started. If you decide against
creating a PMO, proceed directly to the section “Next Steps” on the
following page.
Now that you have created your PMO Charter, proceed to the next
page.
V I E W R E S O U R C E
Initiate Plan Execute Control Close
1 2 3 4 5
Introduction
7PROJECT MANAGEMENT
Use our Project Portfolio Template, otherwise known as a
PMO dashboard, to help organize your PMO by managing
projects in the most efficient way possible.
This template will allow you to:
Use our Project Prioritization Tool to rank projects based
on their strategic fit, economic impact and feasibility.
Project Management Portfolio Next Steps
V I E W R E S O U R C E
Monitor individual tasks
Identify the optimal resource mix
Effectively manage and document new project ideas
PRINCE2
PRISM
Agile
Critical Chain Project Management
Event Chain Project Management
Process-Based Management
Creating a simple system for managing all projects in the department
will increase the chances of project success and facilitate reporting
on critical business priorities with senior management.
Now, it’s time to start building your own project management meth-
odology using the Project Management resources.
The remainder of this guide will focus on the traditional phased
approach to project management. A few other popular approaches
to project management include:
If decide to use another approach, feel free to customize the
templates accordingly.
Initiate Plan Execute Control Close
1 2 3 4 5
Introduction
8PROJECT MANAGEMENT
Outputs from This Playbook
Stage 1 - Initiate
Business Case, Feasibility Study, Stakeholder Analysis,
Project Charter
Stage 4 - Control
Project Milestones, Earned Value Management, Project
Change Log, Quality Control Log, Risk Mitigation Checklist
Stage 5 - Close
Project Acceptance, Post-Project Evaluation, Lessons
Learned, Project Closure Checklist
Stage 3 - Execute
Issue Log, Project Change Request Form, Status Report
Template, Deliverable Approval
Stage 2 - Plan
Project Goals & Objectives, Identify Key Success Factors,
Work Breakdown Structure, Project Team, Project Schedule,
Project Budget, Risk & Communications Plan, Project Approval
Initiate Plan Execute Control Close
1 2 3 4 5
Introduction
Initiate
STAGE 1
PROJECT MANAGEMENT
During this stage, you’ll examine the nature and scope of the project. If this stage is not performed
well, it is unlikely that the project will be successful in meeting the businesses needs.
The initiation stage includes the following action items:
STEP 1:	Build a Business Case
STEP 2:	Conduct a Feasibility Study
STEP 3:	Identify and Analyze Stakeholders
STEP 4:	Create a Project Charter
10PROJECT MANAGEMENT
Introduction
Initiate
1
Cost savings
Revenue growth
Other business benefits
Technical
Economic
Legal
Operational
Scheduling
Build a Business Case Conduct a Feasibility Study
STEP 1 STEP 2
Action Item Action Item
Use the Business Case Template to obtain buy-in from key
stakeholders.
Use the Feasibility Study Template to conduct an objective
and rational analysis of the strengths and weaknesses of a
proposed project.
This template was created for the purpose of providing a brief
description of the problems and opportunities in a particular
business case. Your business case should identify relevant
elements such as opportunities, key success factors, risk and
sensitivity analysis.
This tool will help you identify the following:
This template will help you to check your assumptions and to eval-
uate the following areas of feasibility:
V I E W R E S O U R C E V I E W R E S O U R C E
Plan Execute Control Close
2 3 4 5
11PROJECT MANAGEMENT
Project Overview
Project Description
Key Success Factors
Stakeholders
Communication Plan
Decision Rights
Approval
Identify and Analyze Stakeholders Create a Project Charter
STEP 3 STEP 4
Action Item Action Item
Use the Stakeholder Analysis Matrix to identify key stake-
holders, and evaluate their interest, power, support level and
flexibility.
Use the Project Charter Template to organize resources for
the new project by establishing a clear project scope, deci-
sion rights, and executive sponsorship.
This tool will automatically generates a Decision Support Quotient.
The Stakeholder Analysis Map provides a graphical representa-
tion of each stakeholder’s position.
Create a mitigation plan and identify key success factors for each
of the stakeholders that do not support the project.
This tool will help you to outline the following:
Introduction
Initiate
1
V I E W R E S O U R C E
Helpful Hint – For background info, read our Executive
Summary: Examine Buy In with Stakeholder Analysis
V I E W R E S O U R C E
Plan Execute Control Close
2 3 4 5
Plan
STAGE 2
PROJECT MANAGEMENT
This stage will help you to estimate the work needed and to manage risk during project execution
by planning time, cost and resources effectively.
The final deliverable of this stage will consist of a formal Project Plan:
STEP 1:	Identify Goals & Objectives
STEP 2:	Document Key Success Factors
STEP 3:	Define a Work Breakdown Structure
STEP 4:	Build your Project Team
STEP 5:	Create a Project Schedule
STEP 6:	Assemble a Project Budget
STEP 7:	Build a Risk Management Plan
STEP 8:	 Create a Change Management Plan
STEP 9:	 Finalize a Communications Plan
STEP 10:	Outline the Procurement Plan
STEP 11:	 Create a Quality Management Plan
STEP 12:	Obtain Project Approval
STEP 13:	Finalize the Project Plan
13PROJECT MANAGEMENT
Introduction
2
Plan
Social Media
Website
Content Marketing
CRM
Brand Strategy
Product Marketing
Project goals – agreement between key stakeholders
Scope creep – scope changes are defined and managed
properly
Communication – project status reports are communicated
effectively
Support – senior management supports the project
Lead Generation
Marketing Strategy
Partnership Marketing
Product Development
Sales Operations
Public Relations
Identify Goals & Objectives Document Key Success Factors
STEP 1 STEP 2
Action Item Action Item
Depending on the nature of the project, use one of our
Strategy Scorecards to identify the project’s high-level
goals, objectives, KPIs and target timeframes over the
course of its duration.
Use the Key Success Factors Tool to identify and docu-
ment key success factors, risks and contingency plans so
you can ensure that your project goes smoothly without
any major issues.
A few examples of strategy scorecards in the Demand Metric
library include:
A key success factor is a performance area of critical importance
in achieving consistently high productivity. A few examples of
KSFs include:
V I E W R E S O U R C E V I E W R E S O U R C E
Initiate Execute Control Close
1 3 4 5
14PROJECT MANAGEMENT
STEP 3 STEP 4
What needs to happen in order to complete the project
Who needs to contribute to the task
What they need to contribute to the task.
Define a Work Breakdown Structure Build your Project Team
Action Item Action Item
Use the Work Breakdown Structure Template to help you
build a work breakdown structure (WBS) by organizing the
project’s deliverables into manageable tasks.
Use the Responsibility Assignment Matrix to clarify roles and
responsibilities in cross-functional/departmental projects and
processes.
The “WBS Outline” tab will help you to identify the work break-
down structure by WBS number, Phase, Deliverable and Task.
The “WBS Diagram” tab will help you to create a visual represen-
tation of the WBS outline. When you have identified the tasks,
proceed to the next step.
Customize the matrix provided using the work breakdown struc-
ture so that each of the project’s tasks are clearly outlined.
Next, customize the drop lists in the responsibility assignment
according to your team structure and identify the following:
V I E W R E S O U R C E V I E W R E S O U R C E
Helpful Hint – You can also use our Project Work Breakdown
Structure in Word to communicate with key stakeholders.
Introduction
2
Plan
Initiate Execute Control Close
1 3 4 5
15PROJECT MANAGEMENT
STEP 5 STEP 6
Project Name
Start Date/End Date
Project Team
Time Off
Estimated Cost Vs. Actual Cost by Title
Sum of Variance by Deliverable
Sum of Hours by Owner
Create a Project Schedule Assemble a Project Budget
Action Item Action Item
Use the Project Management Template to create a project
schedule that lists individual tasks, assigns ownership and
outlines start/end dates.
Use the Project Budget Template to set and track your
project budget.
This template can also be used to track project status. Start by
indicating the following:
Start by entering the Phases, Deliverables and Tasks associated
with the project (from your Work Breakdown Structure).
Use the pivot tables provided in the “Report” tab to generate high
level reports such as:
V I E W R E S O U R C E V I E W R E S O U R C E
Introduction
2
Plan
Initiate Execute Control Close
1 3 4 5
16PROJECT MANAGEMENT
STEP 7 STEP 8
Avoid
Accept Change Management Readiness Assessment
Change Management Strategy Scorecard
Transfer
Control
Build a Risk Management Plan Create a Change Management Plan
Action Item Action Item
Use the Risk Management Plan Template to help you
define how risks associated with the project will be identified,
analyzed and managed throughout the project’s lifecycle.
Use the Change Management Plan Template to determine
readiness for the proposed changes and to build a project
plan for delivery.
The risk management plan contains an analysis of likely risks with
both catastrophic and insignificant consequences, as well as miti-
gation strategies. Four common mitigation strategies include:
Projects don’t always unfold according to plan. In order to increase
the likelihood of success, any change to project deliverables
should be maintained and continuously managed. Other useful
change management templates include:
V I E W R E S O U R C E V I E W R E S O U R C E
Introduction
2
Plan
Initiate Execute Control Close
1 3 4 5
Helpful Hint – Use our Risk Analysis (Fishbone) Tool to
identify the root causes that expose your project to risk.
17PROJECT MANAGEMENT
STEP 9 STEP 10
Communication Type
Audience
Timing
Distribution
Items to be procured
Information gathering
Contracts
Competitive Bids
Approval Process
Deliverable
Budget
Contributor
Owner
Evaluation Criteria
Vendor Management
Metrics
Sponsor Acceptance
Finalize a Communications Plan Outline the Procurement Plan
Action Item Action Item
Use the Project Communications Matrix to define the
communication requirements for the project and identify
how information will be distributed.
Use the Procurement Management Plan Template to
serve as a guide for managing procurement throughout the
project’s lifecycle.
This template can be used to identify the following information: This plan identifies and defines the following:
Helpful Hint – Use our Meeting Agenda and Meeting
Minutes templates to help you plan & document discussions.
V I E W R E S O U R C E V I E W R E S O U R C E
Introduction
2
Plan
Initiate Execute Control Close
1 3 4 5
18PROJECT MANAGEMENT
STEP 11 STEP 12
Purpose
Approach
Quality Assurance
Overview
Strategic Goals & Objectives
Impact of Non-Completion
Stakeholders
Quality Control
Problem Tracking
Project Timelines
Anticipated Resources
Results Measurement
Project Approval
Create a Quality Management Plan Obtain Project Approval
Action Item Action Item
Use the Quality Management Plan Template to help ensure
that this project will meet its quality objectives by utilizing
an integrated quality approach to define quality standards,
measure quality and continuously improve quality.
Use the Project Approval Form to formalize project approval
by obtaining sign off from the Project Sponsor, the Project
Manager, the department head and other key stakeholders.
Sections covered in this document include the following: This template includes the following sections:
V I E W R E S O U R C E V I E W R E S O U R C E
Introduction
2
Plan
Initiate Execute Control Close
1 3 4 5
19PROJECT MANAGEMENT
STEP 13
Identifying Project Milestones
Formalizing the Project Scope
Outlining the Deliverable Acceptance Process
Finalize the Project Plan
Action Item
Use the Project Plan Template to help you create a formal
document that can be used to guide both project execution
and project control.
Many of the previous steps will feed directly into the project plan.
Other important sections of the project plan include:
V I E W R E S O U R C E
Introduction
2
Plan
Initiate Execute Control Close
1 3 4 5
Execute
STAGE 3
PROJECT MANAGEMENT
In general, the execution stage involves coordinating people and resources, as well as integrating
and performing the activities of the project in accordance with the project plan.
This can vary greatly from one project to the next. As a result, the steps in this stage will require
further customization depending on the type of project that you are executing.
In order to increase project execution efficiency, you will find a series of time-saving templates
that will help you manage the execution activities more effectively.
STEP 1:	Log the Project’s Issues
STEP 2:	Formalize Project Change Requests
STEP 3:	Create a High-Level Status Report
STEP 4:	Standardize Deliverable Approval
21PROJECT MANAGEMENT
Update the project plan (budget, timelines, schedule, etc.)
Communicate with the project team (status report, commu-
nications matrix)
Log the Project’s Issues Formalize Project Change Requests
STEP 1 STEP 2
Action Item Action Item
Use the Issue Log Template to keep track of the project’s
open and closed issues.
Use the Project Change Request Form to document project
change requests to ensure scope changes are approved
and timelines/budgets are adjusted accordingly.
Effective issue management can dramatically simplify the process of
evaluating issues, assessing their impact and deciding on a course
of action.
The Issue Log Template can be used to organize issues by priority,
severity and type to help provide justification for the order of
resolution.
The main purpose of issue management is to create a comprehen-
sive plan to deal with all issues quickly and effectively.
After you have conducted an assessment of the change request’s
possible effects on all aspects of the project, decide if you should
implement the change.
If you decide to move forward, be sure to conduct the
following activities:
Introduction
Execute
3
V I E W R E S O U R C E V I E W R E S O U R C E
Initiate Plan Control Close
1 2 4 5
22PROJECT MANAGEMENT
Project Summary
Project Vital Signs
Project Cost & Schedule
State the reasons why
Describe a corrective course of action
Create a High-Level Status Report Standardize Deliverable Approval
STEP 3 STEP 4
Action Item Action Item
Use the Project Status Report Template to help you create
a reporting tool that you can use to communicate project
status with stakeholders and management.
Use the Deliverable Approval Template to ensure that the
requirements and expectations of the project deliverables
are met, approved and accepted.
The project status report should highlight specific items that key
stakeholders need to know about without getting into too much
detail. The three broad areas this template covers are:
Review the deliverable acceptance process and criteria outlined
in the Project Plan. If a deliverable is deemed “not acceptable” be
sure to conduct the following actions:
V I E W R E S O U R C E V I E W R E S O U R C E
Helpful Hint – Use the “Status Report” tab in the Project
Management Template to create a high-level progress report.
Helpful Hint – In signing this document, the signatory agrees
that the company should continue to invest in the project.
Introduction
Execute
3Initiate Plan Control Close
1 2 4 5
Control
STAGE 4
PROJECT MANAGEMENT
Project control is the element of a project that keeps it on-track, on-time and within budget. It gener-
ally consists of a series of processes that are performed to observe project execution so that potential
problems can be identified in a timely manner and corrective action can be taken if necessary.
The primary objective of this stage is to maintain schedule, budget, and scope.
STEP 1:	Control the Project Schedule
STEP 2:	Control the Project Budget
STEP 3:	Control the Project Scope
STEP 4:	Control Quality
STEP 5:	Control Risks
24PROJECT MANAGEMENT
Introduction
Control
4
Only showing progress on the critical path
Ignoring non-critical activities
Cost Performance Index - greater than 1 is good (under
budget).
Cost Variance - greater than 0 is good (under budget).
Schedule Performance Index - greater than 1 is good (shows
that the project is on track can meet the required goals).
Control the Project Schedule Control the Project Budget
STEP 1 STEP 2
Action Item Action Item
Use the Project Milestones Template to monitor project
deliverables and ensure that the project schedule stays on
track.
Use the Earned Value Analysis Template to help you
measure project performance and progress by scope,
schedule and cost.
Milestones are commonly used to monitor progress, but the limita-
tions of using milestones to track progress can include:
A few important earned value management acronyms include:
V I E W R E S O U R C E V I E W R E S O U R C E
Helpful Hint – Set milestones before the end of a phase so
that corrective actions can be taken to address issues.
Initiate Plan Execute Close
1 2 3 5
25PROJECT MANAGEMENT
WBS ID
Status
Priority
Owner
Date
Quality Assurance: Focused on monitoring of processes.
Attempts to improve and stabilize processes to avoid issues
that lead to defects.
Quality Control: Focused on outputs. Attempts to uncover
defects and reports to management.
Description
Impact
Action Steps
Resolution
Notes
Control the Project Scope Control Quality
STEP 3 STEP 4
Action Item Action Item
Use the Project Change Request Log to help you keep track
of project changes so that you can mitigate risks and ensure
the success of your project.
Use the Quality Log Template to help you itemize, docu-
ment, and track items reported through quality management
activities.
When you receive a new Project Change Request Form, add the
following information into the Project Change Request Log:
The Quality Log Template includes the following two tabs:
V I E W R E S O U R C E V I E W R E S O U R C E
Introduction
Control
4Initiate Plan Execute Close
1 2 3 5
26PROJECT MANAGEMENT
Classification
Status
Consequence
Likelihood
Risk Rating
Course of Action
Expected Outcome
Mitigation
Other
Control Risks
STEP 5
Action Item
Use the Risk Assessment Tool to document risks, assess
their consequence & likelihood and to prioritize your risk
mitigation efforts based on their corresponding risk rating.
The goal of this step is to reduce the extent of exposure to a risk
and to reduce the likelihood of the risks occurrence. The risk assess-
ment includes the following sections:
V I E W R E S O U R C E
Helpful Hint – Use the Risk Mitigation Checklist to help you
mitigate risks and ensure the success of your project.
Introduction
Control
4Initiate Plan Execute Close
1 2 3 5
Close
STAGE 5
PROJECT MANAGEMENT
Closing includes the formal acceptance of the project and the ending thereof. Administrative
activities include archiving the files and documenting lessons learned.
This stage consists of the following steps:
STEP 1:	Project Acceptance Document
STEP 2:	Post-Project Evaluation Template
STEP 3:	Lessons Learned Knowledge Base
STEP 4:	Project Closure Checklist
28PROJECT MANAGEMENT
Introduction
Close
5
Overall Project Assessment
Scope Management
Quality of Deliverables
Key Accomplishments
Lessons Learned
Opportunities for Improvement
Future Considerations
Best Practices
Project Acceptance Document Post-Project Evaluation Template
STEP 1 STEP 2
Action Item Action Item
Use the Project Acceptance Document to establish formal
acceptance that all of the project’s deliverables have been
accepted as complete and to state whether or not the project
has achieved its goal.
Use the Post-Project Evaluation Template to facilitate the
evaluation of completed or failed projects with the intention
of building on strengths and learning from mistakes.
Conduct a project audit to verify that all deliverables meet the
requirements by entering the deliverable name, the person the
deliverable was approved by and the date of approval.
The Project Manager should only be authorized to continue with the
formal close out of this project after the project has been accepted.
This template covers the following sections:
V I E W R E S O U R C E V I E W R E S O U R C E
Initiate Plan Execute Control
1 2 3 4
29PROJECT MANAGEMENT
STEP 3 STEP 4
Category
Issue Name
Problem/Success
Description of task
Status: Completed, On Track, At Risk, On Hold, Overdue
Date completed
Notes
Recommendation
Impact
Lessons Learned Knowledge Base Project Closure Checklist
Action Item Action Item
Use the Lessons Learned Template to keep track of
lessons learned from individual projects and bring together
any insights gained that can be usefully applied on future
projects.
Use the Project Closure Checklist to ensure that project
tasks have been completed and the project can be closed.
Information captured for individual projects includes:
This information will be rolled up into a knowledge base that
consists of lessons learned from all projects so that best practices
can be shared across the organization.
Columns in this checklist include:
V I E W R E S O U R C E V I E W R E S O U R C E
Introduction
Close
5Initiate Plan Execute Control
1 2 3 4
Conclusion
At the end of any business process, it’s always a good idea to review it
and identify areas for improvement.
Demand Metric has the tools and expertise to help you with the
following:
Setting up a project management office
Creating or auditing your project management playbook
Assisting with using any of the tools referenced in this playbook
Providing hands-on assistance to accelerate achieving your goals.
To learn more, simply contact Demand Metric: info@demandmetric.com
PROJECT MANAGEMENT
About This Playbook
PROJECT MANAGEMENT
Demand Metric is a marketing research and advisory
firm serving a membership community of over 106,000
marketing professionals and consultants in 75 countries.
Offering consulting playbooks, advisory services, and
500+ premium marketing tools and templates, Demand
Metric resources and expertise help the marketing
community plan more efficiently and effectively, answer
the difficult questions about their work with authority and
conviction, and complete marketing projects more quickly
and with greater confidence — thus boosting the respect
of the marketing team and making it easier to justify
resources the team needs to succeed.
To learn more about Demand Metric, please visit
www.demandmetric.com
© Demand Metric Research Corporation.
All Rights Reserved.
www.demandmetric.com
Follow us on Twitter
Like us on Facebook
Join Linkedin Group

More Related Content

What's hot

100 Day Plan for Directing a PMO
100 Day Plan for Directing a PMO100 Day Plan for Directing a PMO
100 Day Plan for Directing a PMOJack Brown
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmocrmackenzie
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
PMO Presentation
PMO PresentationPMO Presentation
PMO PresentationTURKI , PMP
 
The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)CliffordEgbomeade
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardJavid Hamdard
 
Want to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notesWant to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notesMohammed Shafeea Haddad
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingJustAcademy
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project managementMohamed Amin
 

What's hot (20)

PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
100 Day Plan for Directing a PMO
100 Day Plan for Directing a PMO100 Day Plan for Directing a PMO
100 Day Plan for Directing a PMO
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Project management
Project managementProject management
Project management
 
PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
Want to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notesWant to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notes
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project management
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
Project governance
Project governanceProject governance
Project governance
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Pmo
PmoPmo
Pmo
 

Similar to Project Management Playbook

MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMdAliMujawar1
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager PrimerTom Cremins
 
Guid to implement initiating and planning processes
Guid to implement initiating and planning processesGuid to implement initiating and planning processes
Guid to implement initiating and planning processesmohamed fawzy
 
Project Management Control
Project Management ControlProject Management Control
Project Management Controlahmad bassiouny
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Optimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and PrioritizationOptimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and PrioritizationInfo-Tech Research Group
 
Project Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsProject Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsSowmak Bardhan
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Managementhatemk
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionDivya Malik
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptxAtulBhagwat6
 
Project Management Methodology_rFmAt0BhU0dwihA.pdf
Project Management Methodology_rFmAt0BhU0dwihA.pdfProject Management Methodology_rFmAt0BhU0dwihA.pdf
Project Management Methodology_rFmAt0BhU0dwihA.pdfFaisalAziz831398
 
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...May Wong, PMP
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 
Project management assignment help
Project management assignment helpProject management assignment help
Project management assignment helpassignmenthelpp
 

Similar to Project Management Playbook (20)

MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptx
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 
Day 2 scope
Day 2 scopeDay 2 scope
Day 2 scope
 
Guid to implement initiating and planning processes
Guid to implement initiating and planning processesGuid to implement initiating and planning processes
Guid to implement initiating and planning processes
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
 
Optimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and PrioritizationOptimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and Prioritization
 
Project Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsProject Management Professional (PMP) Fundamentals
Project Management Professional (PMP) Fundamentals
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases Introduction
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 
Project Management Methodology_rFmAt0BhU0dwihA.pdf
Project Management Methodology_rFmAt0BhU0dwihA.pdfProject Management Methodology_rFmAt0BhU0dwihA.pdf
Project Management Methodology_rFmAt0BhU0dwihA.pdf
 
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
Project management assignment help
Project management assignment helpProject management assignment help
Project management assignment help
 

More from Demand Metric

The Impact of COVID-19 in B2B Marketing
The Impact of COVID-19 in B2B MarketingThe Impact of COVID-19 in B2B Marketing
The Impact of COVID-19 in B2B MarketingDemand Metric
 
Infographic Return Path Email Engagement
Infographic Return Path Email EngagementInfographic Return Path Email Engagement
Infographic Return Path Email EngagementDemand Metric
 
Infographic Vidyard Video Marketing 2018
Infographic Vidyard Video Marketing 2018Infographic Vidyard Video Marketing 2018
Infographic Vidyard Video Marketing 2018Demand Metric
 
Digital Marketing Best Practices Guide
Digital Marketing Best Practices GuideDigital Marketing Best Practices Guide
Digital Marketing Best Practices GuideDemand Metric
 
Content Marketing Solution Study
Content Marketing Solution StudyContent Marketing Solution Study
Content Marketing Solution StudyDemand Metric
 
SEO Technology Overview
SEO Technology OverviewSEO Technology Overview
SEO Technology OverviewDemand Metric
 
State of Video Marketing 2017
State of Video Marketing 2017State of Video Marketing 2017
State of Video Marketing 2017Demand Metric
 
Sales Enablement Maturity Model
Sales Enablement Maturity ModelSales Enablement Maturity Model
Sales Enablement Maturity ModelDemand Metric
 
Public Relations Maturity Model
Public Relations Maturity ModelPublic Relations Maturity Model
Public Relations Maturity ModelDemand Metric
 
Email Marketing Maturity Model
Email Marketing Maturity ModelEmail Marketing Maturity Model
Email Marketing Maturity ModelDemand Metric
 
Customer Engagement Maturity Model
Customer Engagement Maturity ModelCustomer Engagement Maturity Model
Customer Engagement Maturity ModelDemand Metric
 
Formalizing the Sales Support Function How-To Guide
Formalizing the Sales Support Function How-To GuideFormalizing the Sales Support Function How-To Guide
Formalizing the Sales Support Function How-To GuideDemand Metric
 
How to Launch a Mobile App Guide How-To Guide
How to Launch a Mobile App Guide How-To GuideHow to Launch a Mobile App Guide How-To Guide
How to Launch a Mobile App Guide How-To GuideDemand Metric
 
Getting Started with Agile Marketing How-To Guide
Getting Started with Agile Marketing How-To GuideGetting Started with Agile Marketing How-To Guide
Getting Started with Agile Marketing How-To GuideDemand Metric
 
Entering the European Market Successfully How-To Guide
Entering the European Market Successfully How-To GuideEntering the European Market Successfully How-To Guide
Entering the European Market Successfully How-To GuideDemand Metric
 
Driving SEO with Press Releases How-To Guide
Driving SEO with Press Releases How-To GuideDriving SEO with Press Releases How-To Guide
Driving SEO with Press Releases How-To GuideDemand Metric
 
Calculating Customer Lifetime Value How-To Guide
Calculating Customer Lifetime Value How-To GuideCalculating Customer Lifetime Value How-To Guide
Calculating Customer Lifetime Value How-To GuideDemand Metric
 
Lead Scoring: Five Steps to Getting Started How-To Guide
Lead Scoring: Five Steps to Getting Started How-To GuideLead Scoring: Five Steps to Getting Started How-To Guide
Lead Scoring: Five Steps to Getting Started How-To GuideDemand Metric
 
Social CRM Best Practices How-To Guide
Social CRM Best Practices How-To GuideSocial CRM Best Practices How-To Guide
Social CRM Best Practices How-To GuideDemand Metric
 
Marketing Resource Management How-To Guide
Marketing Resource Management How-To GuideMarketing Resource Management How-To Guide
Marketing Resource Management How-To GuideDemand Metric
 

More from Demand Metric (20)

The Impact of COVID-19 in B2B Marketing
The Impact of COVID-19 in B2B MarketingThe Impact of COVID-19 in B2B Marketing
The Impact of COVID-19 in B2B Marketing
 
Infographic Return Path Email Engagement
Infographic Return Path Email EngagementInfographic Return Path Email Engagement
Infographic Return Path Email Engagement
 
Infographic Vidyard Video Marketing 2018
Infographic Vidyard Video Marketing 2018Infographic Vidyard Video Marketing 2018
Infographic Vidyard Video Marketing 2018
 
Digital Marketing Best Practices Guide
Digital Marketing Best Practices GuideDigital Marketing Best Practices Guide
Digital Marketing Best Practices Guide
 
Content Marketing Solution Study
Content Marketing Solution StudyContent Marketing Solution Study
Content Marketing Solution Study
 
SEO Technology Overview
SEO Technology OverviewSEO Technology Overview
SEO Technology Overview
 
State of Video Marketing 2017
State of Video Marketing 2017State of Video Marketing 2017
State of Video Marketing 2017
 
Sales Enablement Maturity Model
Sales Enablement Maturity ModelSales Enablement Maturity Model
Sales Enablement Maturity Model
 
Public Relations Maturity Model
Public Relations Maturity ModelPublic Relations Maturity Model
Public Relations Maturity Model
 
Email Marketing Maturity Model
Email Marketing Maturity ModelEmail Marketing Maturity Model
Email Marketing Maturity Model
 
Customer Engagement Maturity Model
Customer Engagement Maturity ModelCustomer Engagement Maturity Model
Customer Engagement Maturity Model
 
Formalizing the Sales Support Function How-To Guide
Formalizing the Sales Support Function How-To GuideFormalizing the Sales Support Function How-To Guide
Formalizing the Sales Support Function How-To Guide
 
How to Launch a Mobile App Guide How-To Guide
How to Launch a Mobile App Guide How-To GuideHow to Launch a Mobile App Guide How-To Guide
How to Launch a Mobile App Guide How-To Guide
 
Getting Started with Agile Marketing How-To Guide
Getting Started with Agile Marketing How-To GuideGetting Started with Agile Marketing How-To Guide
Getting Started with Agile Marketing How-To Guide
 
Entering the European Market Successfully How-To Guide
Entering the European Market Successfully How-To GuideEntering the European Market Successfully How-To Guide
Entering the European Market Successfully How-To Guide
 
Driving SEO with Press Releases How-To Guide
Driving SEO with Press Releases How-To GuideDriving SEO with Press Releases How-To Guide
Driving SEO with Press Releases How-To Guide
 
Calculating Customer Lifetime Value How-To Guide
Calculating Customer Lifetime Value How-To GuideCalculating Customer Lifetime Value How-To Guide
Calculating Customer Lifetime Value How-To Guide
 
Lead Scoring: Five Steps to Getting Started How-To Guide
Lead Scoring: Five Steps to Getting Started How-To GuideLead Scoring: Five Steps to Getting Started How-To Guide
Lead Scoring: Five Steps to Getting Started How-To Guide
 
Social CRM Best Practices How-To Guide
Social CRM Best Practices How-To GuideSocial CRM Best Practices How-To Guide
Social CRM Best Practices How-To Guide
 
Marketing Resource Management How-To Guide
Marketing Resource Management How-To GuideMarketing Resource Management How-To Guide
Marketing Resource Management How-To Guide
 

Recently uploaded

BLOOM_April2024. Balmer Lawrie Online Monthly Bulletin
BLOOM_April2024. Balmer Lawrie Online Monthly BulletinBLOOM_April2024. Balmer Lawrie Online Monthly Bulletin
BLOOM_April2024. Balmer Lawrie Online Monthly BulletinBalmerLawrie
 
Brand experience Dream Center Peoria Presentation.pdf
Brand experience Dream Center Peoria Presentation.pdfBrand experience Dream Center Peoria Presentation.pdf
Brand experience Dream Center Peoria Presentation.pdftbatkhuu1
 
Aryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptxAryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptxtegevi9289
 
Local SEO Domination: Put your business at the forefront of local searches!
Local SEO Domination:  Put your business at the forefront of local searches!Local SEO Domination:  Put your business at the forefront of local searches!
Local SEO Domination: Put your business at the forefront of local searches!dstvtechnician
 
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort ServiceDelhi Call girls
 
Situation Analysis | Management Company.
Situation Analysis | Management Company.Situation Analysis | Management Company.
Situation Analysis | Management Company.DanielaQuiroz63
 
How to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail SuccessHow to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail SuccessAggregage
 
Unraveling the Mystery of Roanoke Colony: What Really Happened?
Unraveling the Mystery of Roanoke Colony: What Really Happened?Unraveling the Mystery of Roanoke Colony: What Really Happened?
Unraveling the Mystery of Roanoke Colony: What Really Happened?elizabethella096
 
Beyond Resumes_ How Volunteering Shapes Career Trajectories by Kent Kubie
Beyond Resumes_ How Volunteering Shapes Career Trajectories by Kent KubieBeyond Resumes_ How Volunteering Shapes Career Trajectories by Kent Kubie
Beyond Resumes_ How Volunteering Shapes Career Trajectories by Kent KubieKent Kubie
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...aditipandeya
 
Social Samosa Guidebook for SAMMIES 2024.pdf
Social Samosa Guidebook for SAMMIES 2024.pdfSocial Samosa Guidebook for SAMMIES 2024.pdf
Social Samosa Guidebook for SAMMIES 2024.pdfSocial Samosa
 
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO SuccessBrighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO SuccessVarn
 
Branding strategies of new company .pptx
Branding strategies of new company .pptxBranding strategies of new company .pptx
Branding strategies of new company .pptxVikasTiwari846641
 
Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...
Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...
Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...Search Engine Journal
 
The Skin Games 2024 25 - Sponsorship Deck
The Skin Games 2024 25 - Sponsorship DeckThe Skin Games 2024 25 - Sponsorship Deck
The Skin Games 2024 25 - Sponsorship DeckToluwanimi Balogun
 

Recently uploaded (20)

BLOOM_April2024. Balmer Lawrie Online Monthly Bulletin
BLOOM_April2024. Balmer Lawrie Online Monthly BulletinBLOOM_April2024. Balmer Lawrie Online Monthly Bulletin
BLOOM_April2024. Balmer Lawrie Online Monthly Bulletin
 
Brand experience Dream Center Peoria Presentation.pdf
Brand experience Dream Center Peoria Presentation.pdfBrand experience Dream Center Peoria Presentation.pdf
Brand experience Dream Center Peoria Presentation.pdf
 
Aryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptxAryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptx
 
Local SEO Domination: Put your business at the forefront of local searches!
Local SEO Domination:  Put your business at the forefront of local searches!Local SEO Domination:  Put your business at the forefront of local searches!
Local SEO Domination: Put your business at the forefront of local searches!
 
SEO Master Class - Steve Wiideman, Wiideman Consulting Group
SEO Master Class - Steve Wiideman, Wiideman Consulting GroupSEO Master Class - Steve Wiideman, Wiideman Consulting Group
SEO Master Class - Steve Wiideman, Wiideman Consulting Group
 
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
 
How to Create a Social Media Plan Like a Pro - Jordan Scheltgen
How to Create a Social Media Plan Like a Pro - Jordan ScheltgenHow to Create a Social Media Plan Like a Pro - Jordan Scheltgen
How to Create a Social Media Plan Like a Pro - Jordan Scheltgen
 
Situation Analysis | Management Company.
Situation Analysis | Management Company.Situation Analysis | Management Company.
Situation Analysis | Management Company.
 
How to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail SuccessHow to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail Success
 
Unraveling the Mystery of Roanoke Colony: What Really Happened?
Unraveling the Mystery of Roanoke Colony: What Really Happened?Unraveling the Mystery of Roanoke Colony: What Really Happened?
Unraveling the Mystery of Roanoke Colony: What Really Happened?
 
Beyond Resumes_ How Volunteering Shapes Career Trajectories by Kent Kubie
Beyond Resumes_ How Volunteering Shapes Career Trajectories by Kent KubieBeyond Resumes_ How Volunteering Shapes Career Trajectories by Kent Kubie
Beyond Resumes_ How Volunteering Shapes Career Trajectories by Kent Kubie
 
Creator Influencer Strategy Master Class - Corinne Rose Guirgis
Creator Influencer Strategy Master Class - Corinne Rose GuirgisCreator Influencer Strategy Master Class - Corinne Rose Guirgis
Creator Influencer Strategy Master Class - Corinne Rose Guirgis
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Film Nagar high-profile Call ...
 
Social Samosa Guidebook for SAMMIES 2024.pdf
Social Samosa Guidebook for SAMMIES 2024.pdfSocial Samosa Guidebook for SAMMIES 2024.pdf
Social Samosa Guidebook for SAMMIES 2024.pdf
 
Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...
Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...
Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...
 
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO SuccessBrighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
 
Branding strategies of new company .pptx
Branding strategies of new company .pptxBranding strategies of new company .pptx
Branding strategies of new company .pptx
 
Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...
Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...
Do More with Less: Navigating Customer Acquisition Challenges for Today's Ent...
 
The Future of Brands on LinkedIn - Alison Kaltman
The Future of Brands on LinkedIn - Alison KaltmanThe Future of Brands on LinkedIn - Alison Kaltman
The Future of Brands on LinkedIn - Alison Kaltman
 
The Skin Games 2024 25 - Sponsorship Deck
The Skin Games 2024 25 - Sponsorship DeckThe Skin Games 2024 25 - Sponsorship Deck
The Skin Games 2024 25 - Sponsorship Deck
 

Project Management Playbook

  • 1. Follow this simple step-by-step guide to develop a project management playbook that aligns with the traditional phased approach. PROJECT MANAGEMENT Playbook & Toolkit
  • 2. Table of Contents PROJECT MANAGEMENT Introduction 04 Conclusion 30 Framework 03 About This Playbook 31 Initiate 09 12Plan 20Execute 23Control 27Close stage stage stage stage stage 1 2 3 4 5
  • 3. Issue Log TemplateStrategy Scorecards Key Success Factors Tool Responsibility Assignment Matrix Earned Value Analysis Template Lessons Learned Template Post-Project Evaluation Project Change Request Log Work Breakdown Structure Template Business Case Template Project Management Maturity Assessment Change Management Plan Template Project Approval Form Project Plan Template Feasibility Study Template Project Management Office Charter Stakeholder Analysis Matrix Project Portfolio Template Project Charter Template Project Management Template Project Budget Template Risk Management Plan Template PROJECT MANAGEMENT Framework Leverage the framework below to quickly empower your organization’s project management strategy. Click the buttons below to access all related training, tools, templates, and other resources. Project Change Request Form Project Status Report Template Project Acceptance Document Project Milestones Template Deliverable Approval Template Risk Assessment Tool Project Closure Checklist Quality Log Template PLAN2 CONTROL4 CLOSE5EXECUTE31 INITIATE
  • 4. 4PROJECT MANAGEMENT Initiate Plan Execute Control Close 1 2 3 4 5 Introduction How to Use this Playbook Our playbook consists of five stages, each with a description, steps and action items. Action items include using our premium tools & templates. Our intention with this playbook is to support you in achieving your project management goals. This will be accomplished by helping you: Improve the effectiveness & efficiency of project management in your organization Organize and support your project management office Standardize the templates used by your project managers Before You Get Started… A Project Management Office (PMO) is a group or department within a business that defines and maintains standards for project manage- ment within the organization. Among other things, tasks may include monitoring and reporting on active projects and reporting prog- ress to top management for strategic decisions on what projects to continue or cancel. The next few pages will help you: 1. Understand the key functions of a PMO 2. Benchmark your current capabilities 3. Build a PMO Charter and formalize your process using our time-saving tools & templates Do you currently have a Project Management Office? Have you been asked to build one?
  • 5. 5PROJECT MANAGEMENT Functions of a Project Management Office The Project Management Institute (PMI) sponsored Dr. Brian Hobbs of the University of Québec to research the current state of practice for the Project Management Office. One of the key findings involved categorizing the functions performed by PMOs into the following five broad groups: Organizational Leadership Development of Project Management Competencies and Methodologies Strategic Management Multi-Project Management Monitoring and Controlling Project Performance Initiate Plan Execute Control Close 1 2 3 4 5 Introduction What Is the Purpose of This Playbook? To help you develop a Project Management Playbook & Toolkit of your own. This guide contains tools & templates that can be used a starting point and then customized according to your needs. There are a number of different approaches to managing projects. For the purpose of this playbook, we will be using the traditional phased approach as outlined below: Initiate Control Close Plan Execute
  • 6. 6PROJECT MANAGEMENT Use our Project Management Maturity Assessment to evaluate your organization’s current project management capabilities. Use our Project Management Office Charter to establish the purpose for the PMO’s existence, its primary functions, its sponsors , its customers and its structure. Areas of evaluation include: Sections covered in the PMO Charter Template include: Benchmark Your Current Capabilities Project Management Office Charter V I E W R E S O U R C E Scope Time Cost Scope Vision Mission Goals Quality Human Resources Integrations Metrics Reporting Services Communications Risk Management Procurement KSFs Governance Approval Based on the assessment, decide how you would like to proceed. If you identify the need to create and/or formalize a Project Manage- ment Office, use the next section to get started. If you decide against creating a PMO, proceed directly to the section “Next Steps” on the following page. Now that you have created your PMO Charter, proceed to the next page. V I E W R E S O U R C E Initiate Plan Execute Control Close 1 2 3 4 5 Introduction
  • 7. 7PROJECT MANAGEMENT Use our Project Portfolio Template, otherwise known as a PMO dashboard, to help organize your PMO by managing projects in the most efficient way possible. This template will allow you to: Use our Project Prioritization Tool to rank projects based on their strategic fit, economic impact and feasibility. Project Management Portfolio Next Steps V I E W R E S O U R C E Monitor individual tasks Identify the optimal resource mix Effectively manage and document new project ideas PRINCE2 PRISM Agile Critical Chain Project Management Event Chain Project Management Process-Based Management Creating a simple system for managing all projects in the department will increase the chances of project success and facilitate reporting on critical business priorities with senior management. Now, it’s time to start building your own project management meth- odology using the Project Management resources. The remainder of this guide will focus on the traditional phased approach to project management. A few other popular approaches to project management include: If decide to use another approach, feel free to customize the templates accordingly. Initiate Plan Execute Control Close 1 2 3 4 5 Introduction
  • 8. 8PROJECT MANAGEMENT Outputs from This Playbook Stage 1 - Initiate Business Case, Feasibility Study, Stakeholder Analysis, Project Charter Stage 4 - Control Project Milestones, Earned Value Management, Project Change Log, Quality Control Log, Risk Mitigation Checklist Stage 5 - Close Project Acceptance, Post-Project Evaluation, Lessons Learned, Project Closure Checklist Stage 3 - Execute Issue Log, Project Change Request Form, Status Report Template, Deliverable Approval Stage 2 - Plan Project Goals & Objectives, Identify Key Success Factors, Work Breakdown Structure, Project Team, Project Schedule, Project Budget, Risk & Communications Plan, Project Approval Initiate Plan Execute Control Close 1 2 3 4 5 Introduction
  • 9. Initiate STAGE 1 PROJECT MANAGEMENT During this stage, you’ll examine the nature and scope of the project. If this stage is not performed well, it is unlikely that the project will be successful in meeting the businesses needs. The initiation stage includes the following action items: STEP 1: Build a Business Case STEP 2: Conduct a Feasibility Study STEP 3: Identify and Analyze Stakeholders STEP 4: Create a Project Charter
  • 10. 10PROJECT MANAGEMENT Introduction Initiate 1 Cost savings Revenue growth Other business benefits Technical Economic Legal Operational Scheduling Build a Business Case Conduct a Feasibility Study STEP 1 STEP 2 Action Item Action Item Use the Business Case Template to obtain buy-in from key stakeholders. Use the Feasibility Study Template to conduct an objective and rational analysis of the strengths and weaknesses of a proposed project. This template was created for the purpose of providing a brief description of the problems and opportunities in a particular business case. Your business case should identify relevant elements such as opportunities, key success factors, risk and sensitivity analysis. This tool will help you identify the following: This template will help you to check your assumptions and to eval- uate the following areas of feasibility: V I E W R E S O U R C E V I E W R E S O U R C E Plan Execute Control Close 2 3 4 5
  • 11. 11PROJECT MANAGEMENT Project Overview Project Description Key Success Factors Stakeholders Communication Plan Decision Rights Approval Identify and Analyze Stakeholders Create a Project Charter STEP 3 STEP 4 Action Item Action Item Use the Stakeholder Analysis Matrix to identify key stake- holders, and evaluate their interest, power, support level and flexibility. Use the Project Charter Template to organize resources for the new project by establishing a clear project scope, deci- sion rights, and executive sponsorship. This tool will automatically generates a Decision Support Quotient. The Stakeholder Analysis Map provides a graphical representa- tion of each stakeholder’s position. Create a mitigation plan and identify key success factors for each of the stakeholders that do not support the project. This tool will help you to outline the following: Introduction Initiate 1 V I E W R E S O U R C E Helpful Hint – For background info, read our Executive Summary: Examine Buy In with Stakeholder Analysis V I E W R E S O U R C E Plan Execute Control Close 2 3 4 5
  • 12. Plan STAGE 2 PROJECT MANAGEMENT This stage will help you to estimate the work needed and to manage risk during project execution by planning time, cost and resources effectively. The final deliverable of this stage will consist of a formal Project Plan: STEP 1: Identify Goals & Objectives STEP 2: Document Key Success Factors STEP 3: Define a Work Breakdown Structure STEP 4: Build your Project Team STEP 5: Create a Project Schedule STEP 6: Assemble a Project Budget STEP 7: Build a Risk Management Plan STEP 8: Create a Change Management Plan STEP 9: Finalize a Communications Plan STEP 10: Outline the Procurement Plan STEP 11: Create a Quality Management Plan STEP 12: Obtain Project Approval STEP 13: Finalize the Project Plan
  • 13. 13PROJECT MANAGEMENT Introduction 2 Plan Social Media Website Content Marketing CRM Brand Strategy Product Marketing Project goals – agreement between key stakeholders Scope creep – scope changes are defined and managed properly Communication – project status reports are communicated effectively Support – senior management supports the project Lead Generation Marketing Strategy Partnership Marketing Product Development Sales Operations Public Relations Identify Goals & Objectives Document Key Success Factors STEP 1 STEP 2 Action Item Action Item Depending on the nature of the project, use one of our Strategy Scorecards to identify the project’s high-level goals, objectives, KPIs and target timeframes over the course of its duration. Use the Key Success Factors Tool to identify and docu- ment key success factors, risks and contingency plans so you can ensure that your project goes smoothly without any major issues. A few examples of strategy scorecards in the Demand Metric library include: A key success factor is a performance area of critical importance in achieving consistently high productivity. A few examples of KSFs include: V I E W R E S O U R C E V I E W R E S O U R C E Initiate Execute Control Close 1 3 4 5
  • 14. 14PROJECT MANAGEMENT STEP 3 STEP 4 What needs to happen in order to complete the project Who needs to contribute to the task What they need to contribute to the task. Define a Work Breakdown Structure Build your Project Team Action Item Action Item Use the Work Breakdown Structure Template to help you build a work breakdown structure (WBS) by organizing the project’s deliverables into manageable tasks. Use the Responsibility Assignment Matrix to clarify roles and responsibilities in cross-functional/departmental projects and processes. The “WBS Outline” tab will help you to identify the work break- down structure by WBS number, Phase, Deliverable and Task. The “WBS Diagram” tab will help you to create a visual represen- tation of the WBS outline. When you have identified the tasks, proceed to the next step. Customize the matrix provided using the work breakdown struc- ture so that each of the project’s tasks are clearly outlined. Next, customize the drop lists in the responsibility assignment according to your team structure and identify the following: V I E W R E S O U R C E V I E W R E S O U R C E Helpful Hint – You can also use our Project Work Breakdown Structure in Word to communicate with key stakeholders. Introduction 2 Plan Initiate Execute Control Close 1 3 4 5
  • 15. 15PROJECT MANAGEMENT STEP 5 STEP 6 Project Name Start Date/End Date Project Team Time Off Estimated Cost Vs. Actual Cost by Title Sum of Variance by Deliverable Sum of Hours by Owner Create a Project Schedule Assemble a Project Budget Action Item Action Item Use the Project Management Template to create a project schedule that lists individual tasks, assigns ownership and outlines start/end dates. Use the Project Budget Template to set and track your project budget. This template can also be used to track project status. Start by indicating the following: Start by entering the Phases, Deliverables and Tasks associated with the project (from your Work Breakdown Structure). Use the pivot tables provided in the “Report” tab to generate high level reports such as: V I E W R E S O U R C E V I E W R E S O U R C E Introduction 2 Plan Initiate Execute Control Close 1 3 4 5
  • 16. 16PROJECT MANAGEMENT STEP 7 STEP 8 Avoid Accept Change Management Readiness Assessment Change Management Strategy Scorecard Transfer Control Build a Risk Management Plan Create a Change Management Plan Action Item Action Item Use the Risk Management Plan Template to help you define how risks associated with the project will be identified, analyzed and managed throughout the project’s lifecycle. Use the Change Management Plan Template to determine readiness for the proposed changes and to build a project plan for delivery. The risk management plan contains an analysis of likely risks with both catastrophic and insignificant consequences, as well as miti- gation strategies. Four common mitigation strategies include: Projects don’t always unfold according to plan. In order to increase the likelihood of success, any change to project deliverables should be maintained and continuously managed. Other useful change management templates include: V I E W R E S O U R C E V I E W R E S O U R C E Introduction 2 Plan Initiate Execute Control Close 1 3 4 5 Helpful Hint – Use our Risk Analysis (Fishbone) Tool to identify the root causes that expose your project to risk.
  • 17. 17PROJECT MANAGEMENT STEP 9 STEP 10 Communication Type Audience Timing Distribution Items to be procured Information gathering Contracts Competitive Bids Approval Process Deliverable Budget Contributor Owner Evaluation Criteria Vendor Management Metrics Sponsor Acceptance Finalize a Communications Plan Outline the Procurement Plan Action Item Action Item Use the Project Communications Matrix to define the communication requirements for the project and identify how information will be distributed. Use the Procurement Management Plan Template to serve as a guide for managing procurement throughout the project’s lifecycle. This template can be used to identify the following information: This plan identifies and defines the following: Helpful Hint – Use our Meeting Agenda and Meeting Minutes templates to help you plan & document discussions. V I E W R E S O U R C E V I E W R E S O U R C E Introduction 2 Plan Initiate Execute Control Close 1 3 4 5
  • 18. 18PROJECT MANAGEMENT STEP 11 STEP 12 Purpose Approach Quality Assurance Overview Strategic Goals & Objectives Impact of Non-Completion Stakeholders Quality Control Problem Tracking Project Timelines Anticipated Resources Results Measurement Project Approval Create a Quality Management Plan Obtain Project Approval Action Item Action Item Use the Quality Management Plan Template to help ensure that this project will meet its quality objectives by utilizing an integrated quality approach to define quality standards, measure quality and continuously improve quality. Use the Project Approval Form to formalize project approval by obtaining sign off from the Project Sponsor, the Project Manager, the department head and other key stakeholders. Sections covered in this document include the following: This template includes the following sections: V I E W R E S O U R C E V I E W R E S O U R C E Introduction 2 Plan Initiate Execute Control Close 1 3 4 5
  • 19. 19PROJECT MANAGEMENT STEP 13 Identifying Project Milestones Formalizing the Project Scope Outlining the Deliverable Acceptance Process Finalize the Project Plan Action Item Use the Project Plan Template to help you create a formal document that can be used to guide both project execution and project control. Many of the previous steps will feed directly into the project plan. Other important sections of the project plan include: V I E W R E S O U R C E Introduction 2 Plan Initiate Execute Control Close 1 3 4 5
  • 20. Execute STAGE 3 PROJECT MANAGEMENT In general, the execution stage involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project plan. This can vary greatly from one project to the next. As a result, the steps in this stage will require further customization depending on the type of project that you are executing. In order to increase project execution efficiency, you will find a series of time-saving templates that will help you manage the execution activities more effectively. STEP 1: Log the Project’s Issues STEP 2: Formalize Project Change Requests STEP 3: Create a High-Level Status Report STEP 4: Standardize Deliverable Approval
  • 21. 21PROJECT MANAGEMENT Update the project plan (budget, timelines, schedule, etc.) Communicate with the project team (status report, commu- nications matrix) Log the Project’s Issues Formalize Project Change Requests STEP 1 STEP 2 Action Item Action Item Use the Issue Log Template to keep track of the project’s open and closed issues. Use the Project Change Request Form to document project change requests to ensure scope changes are approved and timelines/budgets are adjusted accordingly. Effective issue management can dramatically simplify the process of evaluating issues, assessing their impact and deciding on a course of action. The Issue Log Template can be used to organize issues by priority, severity and type to help provide justification for the order of resolution. The main purpose of issue management is to create a comprehen- sive plan to deal with all issues quickly and effectively. After you have conducted an assessment of the change request’s possible effects on all aspects of the project, decide if you should implement the change. If you decide to move forward, be sure to conduct the following activities: Introduction Execute 3 V I E W R E S O U R C E V I E W R E S O U R C E Initiate Plan Control Close 1 2 4 5
  • 22. 22PROJECT MANAGEMENT Project Summary Project Vital Signs Project Cost & Schedule State the reasons why Describe a corrective course of action Create a High-Level Status Report Standardize Deliverable Approval STEP 3 STEP 4 Action Item Action Item Use the Project Status Report Template to help you create a reporting tool that you can use to communicate project status with stakeholders and management. Use the Deliverable Approval Template to ensure that the requirements and expectations of the project deliverables are met, approved and accepted. The project status report should highlight specific items that key stakeholders need to know about without getting into too much detail. The three broad areas this template covers are: Review the deliverable acceptance process and criteria outlined in the Project Plan. If a deliverable is deemed “not acceptable” be sure to conduct the following actions: V I E W R E S O U R C E V I E W R E S O U R C E Helpful Hint – Use the “Status Report” tab in the Project Management Template to create a high-level progress report. Helpful Hint – In signing this document, the signatory agrees that the company should continue to invest in the project. Introduction Execute 3Initiate Plan Control Close 1 2 4 5
  • 23. Control STAGE 4 PROJECT MANAGEMENT Project control is the element of a project that keeps it on-track, on-time and within budget. It gener- ally consists of a series of processes that are performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken if necessary. The primary objective of this stage is to maintain schedule, budget, and scope. STEP 1: Control the Project Schedule STEP 2: Control the Project Budget STEP 3: Control the Project Scope STEP 4: Control Quality STEP 5: Control Risks
  • 24. 24PROJECT MANAGEMENT Introduction Control 4 Only showing progress on the critical path Ignoring non-critical activities Cost Performance Index - greater than 1 is good (under budget). Cost Variance - greater than 0 is good (under budget). Schedule Performance Index - greater than 1 is good (shows that the project is on track can meet the required goals). Control the Project Schedule Control the Project Budget STEP 1 STEP 2 Action Item Action Item Use the Project Milestones Template to monitor project deliverables and ensure that the project schedule stays on track. Use the Earned Value Analysis Template to help you measure project performance and progress by scope, schedule and cost. Milestones are commonly used to monitor progress, but the limita- tions of using milestones to track progress can include: A few important earned value management acronyms include: V I E W R E S O U R C E V I E W R E S O U R C E Helpful Hint – Set milestones before the end of a phase so that corrective actions can be taken to address issues. Initiate Plan Execute Close 1 2 3 5
  • 25. 25PROJECT MANAGEMENT WBS ID Status Priority Owner Date Quality Assurance: Focused on monitoring of processes. Attempts to improve and stabilize processes to avoid issues that lead to defects. Quality Control: Focused on outputs. Attempts to uncover defects and reports to management. Description Impact Action Steps Resolution Notes Control the Project Scope Control Quality STEP 3 STEP 4 Action Item Action Item Use the Project Change Request Log to help you keep track of project changes so that you can mitigate risks and ensure the success of your project. Use the Quality Log Template to help you itemize, docu- ment, and track items reported through quality management activities. When you receive a new Project Change Request Form, add the following information into the Project Change Request Log: The Quality Log Template includes the following two tabs: V I E W R E S O U R C E V I E W R E S O U R C E Introduction Control 4Initiate Plan Execute Close 1 2 3 5
  • 26. 26PROJECT MANAGEMENT Classification Status Consequence Likelihood Risk Rating Course of Action Expected Outcome Mitigation Other Control Risks STEP 5 Action Item Use the Risk Assessment Tool to document risks, assess their consequence & likelihood and to prioritize your risk mitigation efforts based on their corresponding risk rating. The goal of this step is to reduce the extent of exposure to a risk and to reduce the likelihood of the risks occurrence. The risk assess- ment includes the following sections: V I E W R E S O U R C E Helpful Hint – Use the Risk Mitigation Checklist to help you mitigate risks and ensure the success of your project. Introduction Control 4Initiate Plan Execute Close 1 2 3 5
  • 27. Close STAGE 5 PROJECT MANAGEMENT Closing includes the formal acceptance of the project and the ending thereof. Administrative activities include archiving the files and documenting lessons learned. This stage consists of the following steps: STEP 1: Project Acceptance Document STEP 2: Post-Project Evaluation Template STEP 3: Lessons Learned Knowledge Base STEP 4: Project Closure Checklist
  • 28. 28PROJECT MANAGEMENT Introduction Close 5 Overall Project Assessment Scope Management Quality of Deliverables Key Accomplishments Lessons Learned Opportunities for Improvement Future Considerations Best Practices Project Acceptance Document Post-Project Evaluation Template STEP 1 STEP 2 Action Item Action Item Use the Project Acceptance Document to establish formal acceptance that all of the project’s deliverables have been accepted as complete and to state whether or not the project has achieved its goal. Use the Post-Project Evaluation Template to facilitate the evaluation of completed or failed projects with the intention of building on strengths and learning from mistakes. Conduct a project audit to verify that all deliverables meet the requirements by entering the deliverable name, the person the deliverable was approved by and the date of approval. The Project Manager should only be authorized to continue with the formal close out of this project after the project has been accepted. This template covers the following sections: V I E W R E S O U R C E V I E W R E S O U R C E Initiate Plan Execute Control 1 2 3 4
  • 29. 29PROJECT MANAGEMENT STEP 3 STEP 4 Category Issue Name Problem/Success Description of task Status: Completed, On Track, At Risk, On Hold, Overdue Date completed Notes Recommendation Impact Lessons Learned Knowledge Base Project Closure Checklist Action Item Action Item Use the Lessons Learned Template to keep track of lessons learned from individual projects and bring together any insights gained that can be usefully applied on future projects. Use the Project Closure Checklist to ensure that project tasks have been completed and the project can be closed. Information captured for individual projects includes: This information will be rolled up into a knowledge base that consists of lessons learned from all projects so that best practices can be shared across the organization. Columns in this checklist include: V I E W R E S O U R C E V I E W R E S O U R C E Introduction Close 5Initiate Plan Execute Control 1 2 3 4
  • 30. Conclusion At the end of any business process, it’s always a good idea to review it and identify areas for improvement. Demand Metric has the tools and expertise to help you with the following: Setting up a project management office Creating or auditing your project management playbook Assisting with using any of the tools referenced in this playbook Providing hands-on assistance to accelerate achieving your goals. To learn more, simply contact Demand Metric: info@demandmetric.com PROJECT MANAGEMENT
  • 31. About This Playbook PROJECT MANAGEMENT Demand Metric is a marketing research and advisory firm serving a membership community of over 106,000 marketing professionals and consultants in 75 countries. Offering consulting playbooks, advisory services, and 500+ premium marketing tools and templates, Demand Metric resources and expertise help the marketing community plan more efficiently and effectively, answer the difficult questions about their work with authority and conviction, and complete marketing projects more quickly and with greater confidence — thus boosting the respect of the marketing team and making it easier to justify resources the team needs to succeed. To learn more about Demand Metric, please visit www.demandmetric.com