A Proposal of final year project on
Prefeasibility study of Katti Khola small hydropower plant
MID WESTERN UNIVERSITY
CENTRAL CAMPUS OF ENGINEERING
HYDRO POWER INSTRUCTION COMMITTEE
BIRENDRA NAGAR, SURKHET
By:
1. Barmesh Raut Chandrawamsi (03)
2. Dipak Raut (14)
3. Madan Prasad Acharya (22)
4. Surya Paudel (43) ‘C’
5. Umesh Baduwal (46)
1
CONTENTS:
1. Introduction 1
1.1. Background 1
1.2. Introduction 2
1.3. Specification &Location of Project 4
1.3. Objective 5
2.Literature Review 6
3.Methodology 7
3.1. Methodology I 7
3.2. Survey and data collection Methodology 7
3.3. Design and Drafting framework 7
3.4. Project Planning Methodology 8
3.5. GANTT Chart 8
4.Expected Output 8
5.Require Instruments and software’s 9
References 9
2
3
1. Introduction
1.1. Background:
Nepal being water rich country has huge potentiality to hydropower energy production
Since 1911AD, 500 kW power generation at Pharping(chandra jyoti)
Dr. Hari Man Shrestha
The theoretical hydropower potential of Nepal is 83,000 MW
Economically=42,000 mw
Technically =43000mw
According to NEA 2018/19 annual report
Nepal has developed only around 1,182.215MW
Economical
Sapta koshi =10860 mw
Sapta Gandaki =5270 mw
Karnali and mahakali =25125 mw
Southern rivers = 878 mw
Total generated capacity of small HPP=563394KW
Isolated capacity=4536
4
1. Introduction
1.2. Introduction
Small Hydropower plant: Although definitions vary, DOE defines small hydropower as projects that
generate 10 MW or less of power.
Types of hydropower project
Storage HPP
Diversion HPP
Run of River (RoR) HPP
Peak Run of River (PRoR) HPP
Pumped Storage HPP
Classification of hydropower according to generation capacity
Pico <5kw
Micro 5-10 kw
Mini 100kw-1000kw(1mw)
Small 1mw-10mw
Medium 10mw-100mw
Larger above 100mw
5
1. Introduction
Why small hydropower plant?
 Easy to find developer due to its low initial cost
 Involves less social, economical, political, and technical issues
 Easily available project
 Less man power and technology required
 Less chances of failure and hazard risk
 Low construction time
 More effective in operation and maintenance
 Useful in isolated areas
6
1. Introduction
1.3 Specification &Location of Project.
Title of project: Prefeasibility study of katti Khola
hydropower Project
According to DOED:
Category: Small hydropower Project
Type: Run of River hydropower Project (RoR)
Potentiality: 2.978 MW
Location: katti khola Dailekh , Nepal
Probable discharge :4 m3/s
probable Head: 100m
Intake : 28o 48' 41“N , 81o 48' 06“E
Outlet: 28o 47’ 00”N, 81o 45' 28“E
above data is according to DOED
7
1. Introduction
1.3. Objective:
 To fulfill the requirements of the final year project of BE Hydropower
 To gain theoretical and practical knowledge of hydropower engineering.
 To learn detail design, estimation and structural analysis of small hydropower project.
 To analysis geology, hydrology and hydraulic of small HPP.
 To learn to various software’s such as GIS, CAD, STAAD PRO, SAP.
 To learn a good sense of ethics and team work.
8
2.Literature Review:
The project is prepare in complete conformity with various stipulation in Indian Standards, Code of
practice for plain and reinforced concrete IS 456:2000, Design Aids for reinforced concrete to IS
456:2000(SP-16), Criteria Earthquake Resistant design structures IS 1893:2016, Ductile detailing of
reinforced Concrete Structures subjected to seismic forces- code of practice IS 13920:1993, steel code
IS 800:2000.
The following literature are being followed:
1.For civil design
 Micro hydropower manual (Adam Hanry)
 Fundamental of hydropower(Sanjiv Baral)
 Manual on barrage and weirs(central board of irrigation )
 Guideline for design oh HPP (DOED)
2.For Hydraulics
 Fluid Mechanics and Hydraulics (PN Modi & S.M Seth)
 Flow in open channel (K Subramanya)
 Fluid Mechanics and Hydraulics (R.K Bansal)
3.For Hydrology
 Engineering Hydrology (S.Baral & K.N. Dulal)
4.For Geology
 Engineering and Hydrology (Tribhuvan University)
5.For Estimation
 Estimating and Costing (B.N Dutta)
6.For Surveying
 A Text Book of surveying and levelling (R.Agor)
For further required data we will concern with respective department & their web sites.
9
Literature Review Algorithm
10 3.Methodology
Project site selection
Definition of the problem &
setting objectives.
Design calculation of the structural
components from the data collected
Review of the theoretical aspects of
the project
Preparation of the drawings of the
components based on design calculation.Discussion with experts & supervisor
Preparation of the final report.
3.1. Methodology I:
11 3.Methodology
3.2. Survey and data collection Methodology
1. Detailed desk study and collection of requires maps
2. Detailed field survey of area about 3-4 km as per DOED guidelines
3. Estimation of optimum head available
4. Plotting of topo map using survey data
5. Hydrological data collection from (DHM)
6. Basic geological study in field as per requirement's
7. Discharge measurement of river as per guidelines
8. Estimation of optimum discharge available.
9. Collection of Hydrological data from DHM and calculating hydrological components.
12
3.3 Design and drafting framework
Design and Drafting
framework
3
Discussion
with experts &
supervisor
2
Collection of
requires
software’s
5
Preparing Detail
Drawing and
reporting it in
well manner
4
Design of head
work ,convey
system ,penstock
, powerhouse &
tailrace
1
Collection of
Required
data
13 3.Methodology
3.4. Project Planning
Distribution of work
 Group discussion
 Topic selection
 Topic submission
 Proposal writing
 Surveying and data collection
 Drawing of topo maps
 Design and drawing using computer aided software’s
 Analysis and design of structures (any one)
 Estimation of project
 Preparation of detailed drawing
 Rate and quality analysis
 Preparation of project Report
14 3.4. GANTT Chart:
Works
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15
Group discussion
Topic selection
Topic submission
Proposal writing
Surveying and data collection
Drawing of topo maps
Design and drawing using
computer aided software’s
Analysis and design of
structures (any one)
Estimation of project
Preparation of detailed drawing
Rate and quality analysis
Preparation of project Report
Periods
15 4.Require Instruments and software’s
1.Survey instruments:
 Total station
 Measuring tape
 Reflector
 Ranging rod
 Staff
 Pegs
 GPS
 Tripod stand etc.
2.Other instrument:
 Current meter
 Geological compass (Brunton compass)
 Mallet hammer
 Hydrochloric acid(Hcl)/sulfuric acid(H2So4)
 First aid kit
3.Software’s:
 Auto Cad
 Sap
 Excel
 MS-word
 STAAD Pro
 SW DTM
5.Expected Outcomes
It is expected to conduct a complete prefeasibility study of katti
khola hydropower project by following proper guidelines and data.
16
17 References:
 Topo maps Nepal //www.pahar.in/downloads/2881 03D Dailekh.
 www.googlemaps.com
 https://www.doed.gov.np/license/48
 https://www.nea.org.np/annual_report
 https://www.slideshare.net/YaqoobAli2/final-year-project-44097819
 Engineering Hydrology (S.Baral & K.N. Dulal)
 Fundamental of hydropower (Sanjiv Baral)
 https://www.google.com/search?q=nepal+dirstic+map&tbm=isch&ved=2ahUKEwjO
iav4g5zoAhXzXHwKHT2YAJ4Q2-
cCegQIABAA&oq=nepal+dirstic+map&gs_l=img.3...4813.10095..10550...0.0..0.182.1
958.0j12......0....1..gws-wiz-
img.......35i39j0i67j0i131j0j0i8i30j0i24.NYChRNNVGwA&ei=IuNtXs7wFPO58QO9sIL
wCQ&rlz=1C1CHNY_enNP741NP741#imgrc=yX396FIIchMVjM (district Map)
18

More Related Content

What's hot

Micro hydro power plant
Micro hydro power plantMicro hydro power plant
Micro hydro power plant
Rajesh Kumar
 
Training report on server THDC(Tehri hydro dam coorporation)
Training report on server THDC(Tehri hydro dam coorporation)Training report on server THDC(Tehri hydro dam coorporation)
Training report on server THDC(Tehri hydro dam coorporation)
Vineet Pokhriyal
 
SMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTSMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANT
vikaspanch
 

What's hot (20)

Energy project report on hydropower
Energy project report on hydropowerEnergy project report on hydropower
Energy project report on hydropower
 
Hydroelectric powerplant
Hydroelectric powerplantHydroelectric powerplant
Hydroelectric powerplant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Feasibility Report of Small Hydroelectric Power Plant
Feasibility Report of Small Hydroelectric Power PlantFeasibility Report of Small Hydroelectric Power Plant
Feasibility Report of Small Hydroelectric Power Plant
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plant
 
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Micro hydro power plant
Micro hydro power plantMicro hydro power plant
Micro hydro power plant
 
Performance Analysis of FC-TCR
Performance Analysis of FC-TCRPerformance Analysis of FC-TCR
Performance Analysis of FC-TCR
 
Micro hydro power plant
Micro hydro power plantMicro hydro power plant
Micro hydro power plant
 
Hydroelectric power plant
Hydroelectric power plant Hydroelectric power plant
Hydroelectric power plant
 
HYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANTHYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANT
 
Hydro POWER PLANT
Hydro POWER PLANTHydro POWER PLANT
Hydro POWER PLANT
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Tidal Energy
Tidal EnergyTidal Energy
Tidal Energy
 
Training report on server THDC(Tehri hydro dam coorporation)
Training report on server THDC(Tehri hydro dam coorporation)Training report on server THDC(Tehri hydro dam coorporation)
Training report on server THDC(Tehri hydro dam coorporation)
 
Design of Tesla coil - Report
Design of Tesla coil - ReportDesign of Tesla coil - Report
Design of Tesla coil - Report
 
Wave energy technologies
Wave energy technologiesWave energy technologies
Wave energy technologies
 
SMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTSMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANT
 

Similar to Final year project proposal on feasibility study of small hydro power

1st phase analysis
1st phase analysis1st phase analysis
1st phase analysis
Rohit Sahai
 

Similar to Final year project proposal on feasibility study of small hydro power (20)

Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
 
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
 
IT6511 Networks Laboratory
IT6511 Networks LaboratoryIT6511 Networks Laboratory
IT6511 Networks Laboratory
 
Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channels
 
Project Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG MineProject Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG Mine
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
Saeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer UtilitiesSaeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer Utilities
 
GSU-RF-2013-Reddy-4
GSU-RF-2013-Reddy-4GSU-RF-2013-Reddy-4
GSU-RF-2013-Reddy-4
 
Vivek Resume
Vivek Resume Vivek Resume
Vivek Resume
 
ACHMAD FHADILAH_118130230_SKRIIPSI (BAB III & IV).pdf
ACHMAD FHADILAH_118130230_SKRIIPSI (BAB III & IV).pdfACHMAD FHADILAH_118130230_SKRIIPSI (BAB III & IV).pdf
ACHMAD FHADILAH_118130230_SKRIIPSI (BAB III & IV).pdf
 
Preparation of 3 d model of international space station
Preparation of 3 d model of international space stationPreparation of 3 d model of international space station
Preparation of 3 d model of international space station
 
RESUME_RAJENDRA PRAJAPAT
RESUME_RAJENDRA PRAJAPATRESUME_RAJENDRA PRAJAPAT
RESUME_RAJENDRA PRAJAPAT
 
Guidelines for Final Year Engineering & Technology Project.ppt
Guidelines for Final Year Engineering & Technology  Project.pptGuidelines for Final Year Engineering & Technology  Project.ppt
Guidelines for Final Year Engineering & Technology Project.ppt
 
1.8 project management
1.8 project management1.8 project management
1.8 project management
 
A heuristic project buffer management algorithm in the scheduling phase of a...
A heuristic project buffer management algorithm in the  scheduling phase of a...A heuristic project buffer management algorithm in the  scheduling phase of a...
A heuristic project buffer management algorithm in the scheduling phase of a...
 
S I T E S E L E C T I O N A N D E V A L U A T I O N I N T H A I L A N D
S I T E  S E L E C T I O N  A N D  E V A L U A T I O N  I N  T H A I L A N DS I T E  S E L E C T I O N  A N D  E V A L U A T I O N  I N  T H A I L A N D
S I T E S E L E C T I O N A N D E V A L U A T I O N I N T H A I L A N D
 
NARESH 3+
NARESH 3+NARESH 3+
NARESH 3+
 
RESUME_RAJENDRA PRAJAPAT
RESUME_RAJENDRA PRAJAPATRESUME_RAJENDRA PRAJAPAT
RESUME_RAJENDRA PRAJAPAT
 
1st phase analysis
1st phase analysis1st phase analysis
1st phase analysis
 
Rohan_Resume (1)
Rohan_Resume (1)Rohan_Resume (1)
Rohan_Resume (1)
 

Recently uploaded

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 

Recently uploaded (20)

BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Final year project proposal on feasibility study of small hydro power

  • 1. A Proposal of final year project on Prefeasibility study of Katti Khola small hydropower plant MID WESTERN UNIVERSITY CENTRAL CAMPUS OF ENGINEERING HYDRO POWER INSTRUCTION COMMITTEE BIRENDRA NAGAR, SURKHET By: 1. Barmesh Raut Chandrawamsi (03) 2. Dipak Raut (14) 3. Madan Prasad Acharya (22) 4. Surya Paudel (43) ‘C’ 5. Umesh Baduwal (46) 1
  • 2. CONTENTS: 1. Introduction 1 1.1. Background 1 1.2. Introduction 2 1.3. Specification &Location of Project 4 1.3. Objective 5 2.Literature Review 6 3.Methodology 7 3.1. Methodology I 7 3.2. Survey and data collection Methodology 7 3.3. Design and Drafting framework 7 3.4. Project Planning Methodology 8 3.5. GANTT Chart 8 4.Expected Output 8 5.Require Instruments and software’s 9 References 9 2
  • 3. 3 1. Introduction 1.1. Background: Nepal being water rich country has huge potentiality to hydropower energy production Since 1911AD, 500 kW power generation at Pharping(chandra jyoti) Dr. Hari Man Shrestha The theoretical hydropower potential of Nepal is 83,000 MW Economically=42,000 mw Technically =43000mw According to NEA 2018/19 annual report Nepal has developed only around 1,182.215MW Economical Sapta koshi =10860 mw Sapta Gandaki =5270 mw Karnali and mahakali =25125 mw Southern rivers = 878 mw Total generated capacity of small HPP=563394KW Isolated capacity=4536
  • 4. 4 1. Introduction 1.2. Introduction Small Hydropower plant: Although definitions vary, DOE defines small hydropower as projects that generate 10 MW or less of power. Types of hydropower project Storage HPP Diversion HPP Run of River (RoR) HPP Peak Run of River (PRoR) HPP Pumped Storage HPP Classification of hydropower according to generation capacity Pico <5kw Micro 5-10 kw Mini 100kw-1000kw(1mw) Small 1mw-10mw Medium 10mw-100mw Larger above 100mw
  • 5. 5 1. Introduction Why small hydropower plant?  Easy to find developer due to its low initial cost  Involves less social, economical, political, and technical issues  Easily available project  Less man power and technology required  Less chances of failure and hazard risk  Low construction time  More effective in operation and maintenance  Useful in isolated areas
  • 6. 6 1. Introduction 1.3 Specification &Location of Project. Title of project: Prefeasibility study of katti Khola hydropower Project According to DOED: Category: Small hydropower Project Type: Run of River hydropower Project (RoR) Potentiality: 2.978 MW Location: katti khola Dailekh , Nepal Probable discharge :4 m3/s probable Head: 100m Intake : 28o 48' 41“N , 81o 48' 06“E Outlet: 28o 47’ 00”N, 81o 45' 28“E above data is according to DOED
  • 7. 7 1. Introduction 1.3. Objective:  To fulfill the requirements of the final year project of BE Hydropower  To gain theoretical and practical knowledge of hydropower engineering.  To learn detail design, estimation and structural analysis of small hydropower project.  To analysis geology, hydrology and hydraulic of small HPP.  To learn to various software’s such as GIS, CAD, STAAD PRO, SAP.  To learn a good sense of ethics and team work.
  • 8. 8 2.Literature Review: The project is prepare in complete conformity with various stipulation in Indian Standards, Code of practice for plain and reinforced concrete IS 456:2000, Design Aids for reinforced concrete to IS 456:2000(SP-16), Criteria Earthquake Resistant design structures IS 1893:2016, Ductile detailing of reinforced Concrete Structures subjected to seismic forces- code of practice IS 13920:1993, steel code IS 800:2000. The following literature are being followed: 1.For civil design  Micro hydropower manual (Adam Hanry)  Fundamental of hydropower(Sanjiv Baral)  Manual on barrage and weirs(central board of irrigation )  Guideline for design oh HPP (DOED) 2.For Hydraulics  Fluid Mechanics and Hydraulics (PN Modi & S.M Seth)  Flow in open channel (K Subramanya)  Fluid Mechanics and Hydraulics (R.K Bansal) 3.For Hydrology  Engineering Hydrology (S.Baral & K.N. Dulal) 4.For Geology  Engineering and Hydrology (Tribhuvan University) 5.For Estimation  Estimating and Costing (B.N Dutta) 6.For Surveying  A Text Book of surveying and levelling (R.Agor) For further required data we will concern with respective department & their web sites.
  • 10. 10 3.Methodology Project site selection Definition of the problem & setting objectives. Design calculation of the structural components from the data collected Review of the theoretical aspects of the project Preparation of the drawings of the components based on design calculation.Discussion with experts & supervisor Preparation of the final report. 3.1. Methodology I:
  • 11. 11 3.Methodology 3.2. Survey and data collection Methodology 1. Detailed desk study and collection of requires maps 2. Detailed field survey of area about 3-4 km as per DOED guidelines 3. Estimation of optimum head available 4. Plotting of topo map using survey data 5. Hydrological data collection from (DHM) 6. Basic geological study in field as per requirement's 7. Discharge measurement of river as per guidelines 8. Estimation of optimum discharge available. 9. Collection of Hydrological data from DHM and calculating hydrological components.
  • 12. 12 3.3 Design and drafting framework Design and Drafting framework 3 Discussion with experts & supervisor 2 Collection of requires software’s 5 Preparing Detail Drawing and reporting it in well manner 4 Design of head work ,convey system ,penstock , powerhouse & tailrace 1 Collection of Required data
  • 13. 13 3.Methodology 3.4. Project Planning Distribution of work  Group discussion  Topic selection  Topic submission  Proposal writing  Surveying and data collection  Drawing of topo maps  Design and drawing using computer aided software’s  Analysis and design of structures (any one)  Estimation of project  Preparation of detailed drawing  Rate and quality analysis  Preparation of project Report
  • 14. 14 3.4. GANTT Chart: Works Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Group discussion Topic selection Topic submission Proposal writing Surveying and data collection Drawing of topo maps Design and drawing using computer aided software’s Analysis and design of structures (any one) Estimation of project Preparation of detailed drawing Rate and quality analysis Preparation of project Report Periods
  • 15. 15 4.Require Instruments and software’s 1.Survey instruments:  Total station  Measuring tape  Reflector  Ranging rod  Staff  Pegs  GPS  Tripod stand etc. 2.Other instrument:  Current meter  Geological compass (Brunton compass)  Mallet hammer  Hydrochloric acid(Hcl)/sulfuric acid(H2So4)  First aid kit 3.Software’s:  Auto Cad  Sap  Excel  MS-word  STAAD Pro  SW DTM
  • 16. 5.Expected Outcomes It is expected to conduct a complete prefeasibility study of katti khola hydropower project by following proper guidelines and data. 16
  • 17. 17 References:  Topo maps Nepal //www.pahar.in/downloads/2881 03D Dailekh.  www.googlemaps.com  https://www.doed.gov.np/license/48  https://www.nea.org.np/annual_report  https://www.slideshare.net/YaqoobAli2/final-year-project-44097819  Engineering Hydrology (S.Baral & K.N. Dulal)  Fundamental of hydropower (Sanjiv Baral)  https://www.google.com/search?q=nepal+dirstic+map&tbm=isch&ved=2ahUKEwjO iav4g5zoAhXzXHwKHT2YAJ4Q2- cCegQIABAA&oq=nepal+dirstic+map&gs_l=img.3...4813.10095..10550...0.0..0.182.1 958.0j12......0....1..gws-wiz- img.......35i39j0i67j0i131j0j0i8i30j0i24.NYChRNNVGwA&ei=IuNtXs7wFPO58QO9sIL wCQ&rlz=1C1CHNY_enNP741NP741#imgrc=yX396FIIchMVjM (district Map)