SlideShare a Scribd company logo
1 of 7
Download to read offline
What level Programme do 
you need, when & why?
L1
&L2
SUMMARY
L3
INTEGRATED
MASTER PROGRAM
L5
EXECUTION PROGRAMS (short term lookaheads)
L4
EXECUTION PROGRAMS
LEVEL 1 – SCHEMATIC SUMMARY PROGRAM
PROGRAM TYPE: Schematic Program
REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated for
Quarterly Contract Review
PROGRAM PURPOSE: Key high level document to communicate overall project
execution strategy and critical / near critical paths as captured in the L3 IMP
PROGRAM RELATIONSHIP: Dependent on Level 3 program
RESPONSIBILITY: Planner
FORMAT: 1 Page, project specific, schematic with annotations
TYPICALLY DEVELOPED BY: Planner
LEVEL 3 – INTEGRATED MASTER PROGRAM
PROGRAM TYPE: Integrated Master Program
REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated for Monthly Contract Review
PROGRAM PURPOSE: Cross functional strategic program to project completion. Demonstrates execution strategies , key milestones, critical paths(s) and project wide
resource requirements.
PROGRAM RELATIONSHIP: Underpins forecast final cost. Sets framework for Level 4 and Level 5
RESPONSIBILITY: Planner
FORMAT: Bar Charts using Asta and MSP Key Production Measure S-Curves / Histograms generated using MSP & MS Excel
TYPICALLY DEVELOPED BY: Planner in consultation with functional leads (e.g. Design, Procurement, Construction).
LEVEL 5 – EXECUTION PROGRAMS
PROGRAM TYPE Functional Execution Program
REQUIRED: Prior to commencement of associated works; Updated Weekly
PROGRAM PURPOSE: Short term planning to enable coordination of construction activities on site.
PROGRAM RELATIONSHIP: Detailed L5 CEP to achieve L4 CEP targets. Planning parameters set by L4 Execution Programs.
RESPONSIBILITY: PM / Project Engineer
FORMAT: 4 Week Look Ahead (MS-Excel or MSP)
TYPICALLY DEVELOPED BY: Project Engineer(s), Site Engineer(s), Design Team Leader(s)
LEVEL 4 – EXECUTION PROGRAMS
PROGRAM TYPE: Functional Execution Program
REQUIRED: Prior to commencement of associated works; Updated Monthly
PROGRAM PURPOSE: Package / Area level planning to support the coordination and delivery of logistics (e.g. Approvals, design, procurement,
materials, labour, etc) to enable field execution of construction
PROGRAM RELATIONSHIP: Planning parameters set by L3 IMP. May incorporate more aggressive targets.
RESPONSIBILITY: Execution Teams; FORMAT: Asta / MSP
TYPICALLY DEVELOPED BY: Functional leads (e.g. Design, Procurement, Construction), with support from Planner as required.
LEVEL 4 Construction Execution Program (CEP)
LEVEL 5 Construction Execution Program (CEP)
LEVEL 3  
Integrated Master Program (IMP)LEVEL 1 Schematic Summary Program (SSP)
LEVEL 2 Summary Reporting Program (SRP)
RPL PROGRAMME LEVELS
LEVEL 2 –SUMMARY REPORTING PROGRAM
PROGRAM TYPE: Selective Summary Program
REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated Monthly
PROGRAM PURPOSE: Reporting planned and actual dates for project at summary
level.
PROGRAM RELATIONSHIP: Dependent on Level 3 program
RESPONSIBILITY: Planner
FORMAT: Selectively Summarised L3 IMP
TYPICALLY DEVELOPED BY: Planner in consultation with senior project team.
Required
at Tender
Required 
throughout Delivery
L6 ‐ Reporting & As‐
built’s
• Critical Steps
• Its recommend you submit a draft 
programme at the start of the works to 
the CA for their approval
• Extensions of Time; applications for 
EOT should be made as close as 
possible to the delay event
• All record referencing relied upon 
within the programme should be 
contemporaneous
• *If the information is made available 
at the time the parties can analyse 
methods of mitigation and acceleration 
to avoid prospective delays
Its critical regardless of Contract Form or 
custom and practice to report as‐built’s 
accurately externally at the required contract 
intervals
As‐planned vs as‐built and impacted as‐
planned* are generally the cheapest forms of 
analysis.
Its advisable to agree the method of as‐built 
in advance with your Client and or CA
Its recommended the parties should deal 
with the effect of delay events in terms of 
compensation and time as close as possible 
to the event
Ability to 
influence 
risk 
exposure
Planning & Design
“Above the 
Line”
Site Field Pack, 
Induction
Daily Pre 
Start
Method 
Statements,
Site & Ground 
Investigations
Project 
Controls
Site Controls
Monitor & 
Review
Time
Incident 
Response
Tender 
R&O 
Analysis
Your ability to influence risk reduces with 
time
“Construction Safety 
Essentials” ITP, 
Auditing 
PCP,
Procurement Closeout 
Review
Time
Ability to influence risk
What good & bad looks like; which are you?
• Good • Bad 
Within any one Business control processes already in existence will tend to lean towards individual strengths. There will 
however always be correlations between good Project and Business Controls to secure the Business Plan
Project  Business
Performance Management;
• Control of quality, time & cost
• Analyse and adjust to variances
Quality Management
• Quality control within the project supported by quality assurance 
from the Business
• Validate the continuous use of procedures and standards
• Continuous improvement
Risk Management 
• Reduce the effects of threats
• Maximise the potential of opportunities
Life Cycle Management
• A gate system for release, rejection ore review of Projects eg Tender 
Adjudication, Dispute Avoidance, Business reporting on statutory 
duties
Issue Management
• Manage routine problems within the Team
• Elevate major problems to Business support
Continuous Improvement
• Filter lessons learnt to new Projects
• Improved procurement when volumes or risk changes
Review
• Report on the previous 3 matters including H&S to the Business 
manager 
Portfolio Management
• Resources including funding managed across the Business to 
maximise the profit
Change Management
• Adjust within the Project to required changes or errors in the plan
• Respond to Client changes; firstly in line with the Contract and then 
to the maximum impact on performance
Governance
• Performance to achieving the Business goals properly and regularly 
reported to the Board
• Statutory deliverables managed to ensure continence of the 
Projects 
The Business Case for Effective Programmes
Project Phase Process Effect on Profit Why
Tendering Continuous 
Improvement
Positive Use internal Business Intelligence to allow higher outputs
Innovation Positive The project may not see the benefit but the Business will 
overall once recycled
Implementation Monitoring Positive Make proactive and reactive decisions quickly and in harmony 
with the Business
Risk 
Management
Positive Adjust to negative and positive risk
Close Out Continuous 
Improvement
Positive Feedback lop to Business process; inform selection of future 
Clients and Projects
Repeat 
Business or not
‐ Whether the Project has been successful or not the parties 
may decide to repeat the agreement as the Business to 
Business learning curve has been improved. Share the learning 
up and down the supply chain

More Related Content

What's hot

Alexander Joy Cartwright Iv Cpa V4
Alexander  Joy Cartwright Iv Cpa V4Alexander  Joy Cartwright Iv Cpa V4
Alexander Joy Cartwright Iv Cpa V4mrbaseball
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyRobert Doig
 
A2) CV - July 2016 incl. EXXON & NES-BHP
A2) CV - July 2016 incl. EXXON & NES-BHP A2) CV - July 2016 incl. EXXON & NES-BHP
A2) CV - July 2016 incl. EXXON & NES-BHP Robert Romero
 
Managing the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner pptManaging the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner pptp6academy
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvkGlenn Van_kooijk
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
5.project scopemanagement
5.project scopemanagement5.project scopemanagement
5.project scopemanagementNiranjana K.R.
 
It projects austria
It projects austriaIt projects austria
It projects austriahappiashi
 
WJ White Resume_July15_Functional
WJ White Resume_July15_FunctionalWJ White Resume_July15_Functional
WJ White Resume_July15_FunctionalWm White
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 

What's hot (20)

Alexander Joy Cartwright Iv Cpa V4
Alexander  Joy Cartwright Iv Cpa V4Alexander  Joy Cartwright Iv Cpa V4
Alexander Joy Cartwright Iv Cpa V4
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
 
101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)
 
Shahzad Sikandaruk
Shahzad SikandarukShahzad Sikandaruk
Shahzad Sikandaruk
 
A2) CV - July 2016 incl. EXXON & NES-BHP
A2) CV - July 2016 incl. EXXON & NES-BHP A2) CV - July 2016 incl. EXXON & NES-BHP
A2) CV - July 2016 incl. EXXON & NES-BHP
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Managing the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner pptManaging the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner ppt
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvk
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
Cv 201503 eng_short
Cv 201503 eng_shortCv 201503 eng_short
Cv 201503 eng_short
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
5.project scopemanagement
5.project scopemanagement5.project scopemanagement
5.project scopemanagement
 
It projects austria
It projects austriaIt projects austria
It projects austria
 
WJ White Resume_July15_Functional
WJ White Resume_July15_FunctionalWJ White Resume_July15_Functional
WJ White Resume_July15_Functional
 
Qa plan1
Qa plan1Qa plan1
Qa plan1
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 

Similar to What Programme do you need, when and why

LCPL Program hierarchy.pptx
LCPL Program hierarchy.pptxLCPL Program hierarchy.pptx
LCPL Program hierarchy.pptxsisay831210
 
Controls___Planning_Management_Plan_Short_Form_v4.pptx
Controls___Planning_Management_Plan_Short_Form_v4.pptxControls___Planning_Management_Plan_Short_Form_v4.pptx
Controls___Planning_Management_Plan_Short_Form_v4.pptxkhalidalkhudhir
 
A Planning Process
A Planning ProcessA Planning Process
A Planning Processpipmonck
 
Project planning
Project planningProject planning
Project planningShaikh Zain
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkitsIT-Toolkits.org
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management reqGlen Alleman
 
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docxPLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docxstilliegeorgiana
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11Robert (Bob) Owens
 
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docxPLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docxinfantsuk
 
Project management 101
Project management 101 Project management 101
Project management 101 Expoco
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
ROPMS - Results-Oriented Project Management System
ROPMS - Results-Oriented Project Management SystemROPMS - Results-Oriented Project Management System
ROPMS - Results-Oriented Project Management Systemrexcris
 
Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01David Eagle
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 

Similar to What Programme do you need, when and why (20)

LCPL Program hierarchy.pptx
LCPL Program hierarchy.pptxLCPL Program hierarchy.pptx
LCPL Program hierarchy.pptx
 
Controls___Planning_Management_Plan_Short_Form_v4.pptx
Controls___Planning_Management_Plan_Short_Form_v4.pptxControls___Planning_Management_Plan_Short_Form_v4.pptx
Controls___Planning_Management_Plan_Short_Form_v4.pptx
 
A Planning Process
A Planning ProcessA Planning Process
A Planning Process
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Project planning
Project planningProject planning
Project planning
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
 
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docxPLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
 
Asgkit prog2
Asgkit prog2Asgkit prog2
Asgkit prog2
 
notes_Lecture7.ppt
notes_Lecture7.pptnotes_Lecture7.ppt
notes_Lecture7.ppt
 
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docxPLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME, COS.docx
 
Project management 101
Project management 101 Project management 101
Project management 101
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
ROPMS - Results-Oriented Project Management System
ROPMS - Results-Oriented Project Management SystemROPMS - Results-Oriented Project Management System
ROPMS - Results-Oriented Project Management System
 
Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 

What Programme do you need, when and why

  • 2. L1 &L2 SUMMARY L3 INTEGRATED MASTER PROGRAM L5 EXECUTION PROGRAMS (short term lookaheads) L4 EXECUTION PROGRAMS LEVEL 1 – SCHEMATIC SUMMARY PROGRAM PROGRAM TYPE: Schematic Program REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated for Quarterly Contract Review PROGRAM PURPOSE: Key high level document to communicate overall project execution strategy and critical / near critical paths as captured in the L3 IMP PROGRAM RELATIONSHIP: Dependent on Level 3 program RESPONSIBILITY: Planner FORMAT: 1 Page, project specific, schematic with annotations TYPICALLY DEVELOPED BY: Planner LEVEL 3 – INTEGRATED MASTER PROGRAM PROGRAM TYPE: Integrated Master Program REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated for Monthly Contract Review PROGRAM PURPOSE: Cross functional strategic program to project completion. Demonstrates execution strategies , key milestones, critical paths(s) and project wide resource requirements. PROGRAM RELATIONSHIP: Underpins forecast final cost. Sets framework for Level 4 and Level 5 RESPONSIBILITY: Planner FORMAT: Bar Charts using Asta and MSP Key Production Measure S-Curves / Histograms generated using MSP & MS Excel TYPICALLY DEVELOPED BY: Planner in consultation with functional leads (e.g. Design, Procurement, Construction). LEVEL 5 – EXECUTION PROGRAMS PROGRAM TYPE Functional Execution Program REQUIRED: Prior to commencement of associated works; Updated Weekly PROGRAM PURPOSE: Short term planning to enable coordination of construction activities on site. PROGRAM RELATIONSHIP: Detailed L5 CEP to achieve L4 CEP targets. Planning parameters set by L4 Execution Programs. RESPONSIBILITY: PM / Project Engineer FORMAT: 4 Week Look Ahead (MS-Excel or MSP) TYPICALLY DEVELOPED BY: Project Engineer(s), Site Engineer(s), Design Team Leader(s) LEVEL 4 – EXECUTION PROGRAMS PROGRAM TYPE: Functional Execution Program REQUIRED: Prior to commencement of associated works; Updated Monthly PROGRAM PURPOSE: Package / Area level planning to support the coordination and delivery of logistics (e.g. Approvals, design, procurement, materials, labour, etc) to enable field execution of construction PROGRAM RELATIONSHIP: Planning parameters set by L3 IMP. May incorporate more aggressive targets. RESPONSIBILITY: Execution Teams; FORMAT: Asta / MSP TYPICALLY DEVELOPED BY: Functional leads (e.g. Design, Procurement, Construction), with support from Planner as required. LEVEL 4 Construction Execution Program (CEP) LEVEL 5 Construction Execution Program (CEP) LEVEL 3   Integrated Master Program (IMP)LEVEL 1 Schematic Summary Program (SSP) LEVEL 2 Summary Reporting Program (SRP) RPL PROGRAMME LEVELS LEVEL 2 –SUMMARY REPORTING PROGRAM PROGRAM TYPE: Selective Summary Program REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated Monthly PROGRAM PURPOSE: Reporting planned and actual dates for project at summary level. PROGRAM RELATIONSHIP: Dependent on Level 3 program RESPONSIBILITY: Planner FORMAT: Selectively Summarised L3 IMP TYPICALLY DEVELOPED BY: Planner in consultation with senior project team. Required at Tender Required  throughout Delivery
  • 3. L6 ‐ Reporting & As‐ built’s • Critical Steps • Its recommend you submit a draft  programme at the start of the works to  the CA for their approval • Extensions of Time; applications for  EOT should be made as close as  possible to the delay event • All record referencing relied upon  within the programme should be  contemporaneous • *If the information is made available  at the time the parties can analyse  methods of mitigation and acceleration  to avoid prospective delays Its critical regardless of Contract Form or  custom and practice to report as‐built’s  accurately externally at the required contract  intervals As‐planned vs as‐built and impacted as‐ planned* are generally the cheapest forms of  analysis. Its advisable to agree the method of as‐built  in advance with your Client and or CA Its recommended the parties should deal  with the effect of delay events in terms of  compensation and time as close as possible  to the event
  • 6. Within any one Business control processes already in existence will tend to lean towards individual strengths. There will  however always be correlations between good Project and Business Controls to secure the Business Plan Project  Business Performance Management; • Control of quality, time & cost • Analyse and adjust to variances Quality Management • Quality control within the project supported by quality assurance  from the Business • Validate the continuous use of procedures and standards • Continuous improvement Risk Management  • Reduce the effects of threats • Maximise the potential of opportunities Life Cycle Management • A gate system for release, rejection ore review of Projects eg Tender  Adjudication, Dispute Avoidance, Business reporting on statutory  duties Issue Management • Manage routine problems within the Team • Elevate major problems to Business support Continuous Improvement • Filter lessons learnt to new Projects • Improved procurement when volumes or risk changes Review • Report on the previous 3 matters including H&S to the Business  manager  Portfolio Management • Resources including funding managed across the Business to  maximise the profit Change Management • Adjust within the Project to required changes or errors in the plan • Respond to Client changes; firstly in line with the Contract and then  to the maximum impact on performance Governance • Performance to achieving the Business goals properly and regularly  reported to the Board • Statutory deliverables managed to ensure continence of the  Projects 
  • 7. The Business Case for Effective Programmes Project Phase Process Effect on Profit Why Tendering Continuous  Improvement Positive Use internal Business Intelligence to allow higher outputs Innovation Positive The project may not see the benefit but the Business will  overall once recycled Implementation Monitoring Positive Make proactive and reactive decisions quickly and in harmony  with the Business Risk  Management Positive Adjust to negative and positive risk Close Out Continuous  Improvement Positive Feedback lop to Business process; inform selection of future  Clients and Projects Repeat  Business or not ‐ Whether the Project has been successful or not the parties  may decide to repeat the agreement as the Business to  Business learning curve has been improved. Share the learning  up and down the supply chain