1. Managing the P6 Schedule
From An Owner’s Perspective
April 23, 2012
Raquel Speers Shohet, PSP, Vice President
Hill International
2. Raquel Speers Shohet, PSP
• Degree: BS – Civil Engineering
• University: University of Nevada, Las Vegas
• Years of Experience: 22
• Professional Field: Construction
• Something you do not know about me: I was
goalkeeper for University of California, Irvine
Women’s Soccer Team
Speaker Biography
3. 7 Challenges for Enterprise
Software Rollout
• Understanding the Technology
• Getting past the Software Sales Pitch
• Re-thinking Processes
• Standardizing the Processes
• Training New Processes
• Executive Buy-in
• Commitment
4. 4 Steps for a Successful Rollout
of Best Practices
• Define the Processes
• Design the Processes
• Develop the Processes
• Deliver the Processes
5.
6. 1. Process Definition and Current Environment Analysis
a. System Definition
Scheduling Specification at Implementation
Scheduling Appendix
Schedule Department Roles and Responsibilities (SOP)
b. Enterprise Database Configuration
System Installation
License Purchase Recommendation
CM – approx $2500/license including maintenance
PM Web – approx $3,300/license including maintenance
Phase 1
11. State DOT Specification
1.6 Baseline Construction Schedule
C. Schedule Submission
Notice of
Award
Within 14
cd of Notice
of Award
Submit
Baseline Plan
CPM
Engineer
review &
return
Within
7 cd of
Receipt
Complete
Baseline
Schedule and
Obtain
Engineer
Acceptance
Within 30 cd
of Notice of
Award
4. “No progress payments are made
Before the Engineer accepts the
baseline
Construction schedule.”
12. 2. Process Design and System Access
a. Corporate Wide access to scheduling system
Database set up and Installation Process Flow Charts
Consideration for EPS Project Grouping
Security Profiles and Privilege Definitions
User Assignments and Security Profiles
b. Web Access and Dashboard Analytics
User List
Phase 2
14. Security Profiles
GS-01 Users by Global Security Profile
Admin Superuser
Administrator
View Global Data
PS-01 Project Security Profile Privileges
SUPERUSER, MANAGER, VIEW DATA
Edit details, WBS, Expenses,
Schedule Project
Maintain Baselines
Run Global Changes
Etc,
Phase 2
15. 3. System Integration of Oracle Project Management/
Contract Management
a. Integration and Functional Testing
b. Training Documentation
c. Dashboard Analytics
d. Visible Contract Management Data
Phase 3
21. All projects reside in
one database to allow
for cross project
analysis and reporting
MASTER SCHEDULE
P6 Enterprise Scheduling
22. Project Management is a secure system and requires users to have a login name and password to both
read and write to each database. Each user has certain access rights to allow database modification at
the project level as well as the database or global level. (The user login name and password are
assigned by the system administrator.)
P6 Enterprise Scheduling
23. The hierarchical structure starts with the enterprise at
its highest level and the activity at its lowest level
P6 Enterprise Scheduling
25. • Scheduling System Integration Considerations
– Import Templates
– Integration with Primavera P3™
– Integration with Microsoft Project™
– Integration with other Primavera P6™
P6 Enterprise Scheduling
26. • Calendar Types
– Global
– Resource
– Project
• Work Periods
– Important – P6 is always calculating to
the minute.
26
P6 Enterprise Scheduling
29. • Documentation
• Thorough understanding of contract
requirements
• DOCUMENTATION
• Well thought out procedures
• D-O-C-U-M-E-N-T-A-T-I-O-N
• Good working relationship between all parties
• D-O-C-U-M-E-N-T-A-T-I-O-N
Keys to Success
30. P6 Implementation Benefits
• Corporate Standardized Processes
• Consistent Project Roadmaps
• Consistent Tracking and Analysis
• Effective Risk Management
• Enhanced Executive Oversight
• Enterprise Reports and Metrics
• Early Issue Identification and Resolution
32. Questions & Answers
Hoping that you can use these implementation and
execution lessons learned outlined in this presentation to
develop schedules quickly and efficiently using
Primavera P6™
Thank you
Raquel Shohet