LEVEL 1 – SCHEMATIC SUMMARY PROGRAM
PROGRAM TYPE: Schematic Program
REQUIRED: Tender Final Review; At Project Baseline
Establishment; Updated for Quarterly Contract Review
PROGRAM PURPOSE: Key high level document to
communicate overall project execution strategy and
critical / near critical paths as captured in the L3 IMP
PROGRAM RELATIONSHIP: Dependent on Level 3
program
RESPONSIBILITY: Planner
FORMAT: 1 Page, project specific, schematic with
annotations
TYPICALLY DEVELOPED BY: Planner
LEVEL 3 – INTEGRATED MASTER PROGRAM
PROGRAM TYPE: Integrated Master Program
REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated for Monthly Contract Review
PROGRAM PURPOSE: Cross functional strategic program to project completion. Demonstrates execution strategies
, key milestones, critical paths(s) and project wide resource requirements.
PROGRAM RELATIONSHIP: Underpins forecast final cost. Sets framework for Level 4 and Level 5
RESPONSIBILITY: Planner
FORMAT: Bar Charts using Primavera P6 and Key Production Measure S-Curves / Histograms generated using
Primavera P6 / MS Excel
TYPICALLY DEVELOPED BY: Planner in consultation with functional leads (e.g. Design, Procurement,
Construction).
LEVEL 5 – EXECUTION PROGRAMS
PROGRAM TYPE Functional Execution Program
REQUIRED: Prior to commencement of associated works; Updated Weekly
PROGRAM PURPOSE: Short term planning to enable coordination of construction activities on
site.
PROGRAM RELATIONSHIP: Detailed L5 CEP to achieve L4 CEP targets. Planning parameters
set by L4 Execution Programs.
RESPONSIBILITY: SPE / Project Engineer
FORMAT: 4 Week Look Ahead (MS-Excel)
TYPICALLY DEVELOPED BY: Project Engineer(s), Site Engineer(s), Design Team Leader(s)
LEVEL 4 – EXECUTION PROGRAMS
PROGRAM TYPE: Functional Execution Program
REQUIRED: Prior to commencement of associated works; Updated Monthly
PROGRAM PURPOSE: Package / Area level planning to support the coordination and delivery of
logistics (e.g. Approvals, design, procurement, materials, labour, etc) to enable field execution of
construction
PROGRAM RELATIONSHIP: Planning parameters set by L3 IMP. May incorporate more aggressive
targets.
RESPONSIBILITY: Execution Teams; FORMAT: Primavera P6 / MSP
TYPICALLY DEVELOPED BY: Functional leads (e.g. Design, Procurement, Construction), with
support from Planner as required.
LEVEL
4
Construction
Execution
Program
(CEP)
LEVEL
5
Construction
Execution
Program
(CEP)
LEVEL
3
Integrated
Master
Program
(IMP)
LEVEL
1
Schematic
Summary
Program
(SSP)
LEVEL
2
Summary
Reporting
Program
(SRP)
LCPL PROGRAM HIERARCHY
LEVEL 2 –SUMMARY REPORTING PROGRAM
PROGRAM TYPE: Selective Summary Program
REQUIRED: Tender Final Review; At Project Baseline
Establishment; Updated Monthly
PROGRAM PURPOSE: Reporting planned and actual
dates for project at summary level.
PROGRAM RELATIONSHIP: Dependent on Level 3
program
RESPONSIBILITY: Planner
FORMAT: Selectively Summarised L3 IMP
TYPICALLY DEVELOPED BY: Planner in consultation
with senior project team.
Required
at Tender
Required
throughout Delivery

LCPL Program hierarchy.pptx

  • 1.
    L1 &L2 SUMMARY L3 INTEGRATED MASTER PROGRAM L5 EXECUTION PROGRAMS L4 EXECUTIONPROGRAMS LEVEL 1 – SCHEMATIC SUMMARY PROGRAM PROGRAM TYPE: Schematic Program REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated for Quarterly Contract Review PROGRAM PURPOSE: Key high level document to communicate overall project execution strategy and critical / near critical paths as captured in the L3 IMP PROGRAM RELATIONSHIP: Dependent on Level 3 program RESPONSIBILITY: Planner FORMAT: 1 Page, project specific, schematic with annotations TYPICALLY DEVELOPED BY: Planner LEVEL 3 – INTEGRATED MASTER PROGRAM PROGRAM TYPE: Integrated Master Program REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated for Monthly Contract Review PROGRAM PURPOSE: Cross functional strategic program to project completion. Demonstrates execution strategies , key milestones, critical paths(s) and project wide resource requirements. PROGRAM RELATIONSHIP: Underpins forecast final cost. Sets framework for Level 4 and Level 5 RESPONSIBILITY: Planner FORMAT: Bar Charts using Primavera P6 and Key Production Measure S-Curves / Histograms generated using Primavera P6 / MS Excel TYPICALLY DEVELOPED BY: Planner in consultation with functional leads (e.g. Design, Procurement, Construction). LEVEL 5 – EXECUTION PROGRAMS PROGRAM TYPE Functional Execution Program REQUIRED: Prior to commencement of associated works; Updated Weekly PROGRAM PURPOSE: Short term planning to enable coordination of construction activities on site. PROGRAM RELATIONSHIP: Detailed L5 CEP to achieve L4 CEP targets. Planning parameters set by L4 Execution Programs. RESPONSIBILITY: SPE / Project Engineer FORMAT: 4 Week Look Ahead (MS-Excel) TYPICALLY DEVELOPED BY: Project Engineer(s), Site Engineer(s), Design Team Leader(s) LEVEL 4 – EXECUTION PROGRAMS PROGRAM TYPE: Functional Execution Program REQUIRED: Prior to commencement of associated works; Updated Monthly PROGRAM PURPOSE: Package / Area level planning to support the coordination and delivery of logistics (e.g. Approvals, design, procurement, materials, labour, etc) to enable field execution of construction PROGRAM RELATIONSHIP: Planning parameters set by L3 IMP. May incorporate more aggressive targets. RESPONSIBILITY: Execution Teams; FORMAT: Primavera P6 / MSP TYPICALLY DEVELOPED BY: Functional leads (e.g. Design, Procurement, Construction), with support from Planner as required. LEVEL 4 Construction Execution Program (CEP) LEVEL 5 Construction Execution Program (CEP) LEVEL 3 Integrated Master Program (IMP) LEVEL 1 Schematic Summary Program (SSP) LEVEL 2 Summary Reporting Program (SRP) LCPL PROGRAM HIERARCHY LEVEL 2 –SUMMARY REPORTING PROGRAM PROGRAM TYPE: Selective Summary Program REQUIRED: Tender Final Review; At Project Baseline Establishment; Updated Monthly PROGRAM PURPOSE: Reporting planned and actual dates for project at summary level. PROGRAM RELATIONSHIP: Dependent on Level 3 program RESPONSIBILITY: Planner FORMAT: Selectively Summarised L3 IMP TYPICALLY DEVELOPED BY: Planner in consultation with senior project team. Required at Tender Required throughout Delivery