Department of Veterans Affairs 
Office of Construction and Facilities Management (CFM) 
SRE Program Training – March 2013 
Commissioning Standards 
Institutionalizing Best Practices 
in Project Delivery 
Presented by 
Jerry Bauers, PE – Sebesta Blomberg 
Lam Vu, PE – CFM (003C2B) 
1
Definition 
“Systematic process of assuring by 
verification and documentation, from 
the design phase to a minimum of one 
year after construction, that all 
building facility systems perform 
interactively in accordance with the 
design documentation and intent, and 
in accordance with the owner’s 
operational needs, including 
preparation of operation personnel.” 
2
Objectives 
3 
“…I guess…it is a little late to bring in 
the commissioning agent!” 
“…and you said that we did not need 
commissioning???”
Objectives 
* Understand Tasks/Deliverables/ 
Responsibilities 
* Understand the Standard Documents – where 
& what? 
http://www.cfm.va.gov/TIL/ 
* Understand the Team Members, 
Responsibilities and Individual Objectives 
4
Objectives 
* Best Practices for Collaborative 
Commissioning 
* Management Strategies for Oversight 
* Responsibility of VA to Support and 
Encourage Commissioning 
5
Objectives 
Deliver a Buildings and Building Systems 
6 
that Work 
Deliver Operations Team to Sustain 
Performance
Cx – Mandated Process 
• Executive Order13423: Strengthening Federal 
Environmental, Energy & Transportation Management 
• Executive Order 13514: Federal Leadership in 
Environment, Energy and Economic Performance 
• VA Directive 0056 – VA Sustainable Building Program 
• VA Sustainable Design & Energy Reduction Manual 
• Memorandum of Understanding - Federal Leadership in 
High Performance and Sustainable Buildings – Guiding 
Principles for Fed Leadership in High Performance and 
Sustainable Buildings 
7
Value Propositions 
• Reduce Total Ownership Costs 
• Improve Energy & Water Efficiency 
• Safe, Healthy & Productive Built 
Environment 
• Promote Sustainable Stewardship 
8
Corollary Values 
• Improved Operator Knowledge 
• Upgraded Infrastructure 
• Simplified Repair/Upgrade Process 
• Energy Master Planning 
9
Results – National Studies 
NEW BUILDING COMMISSIONING 
•First Cost Avoidance * 
•13% Energy Savings * 
•4.2 Year Payback on Investment * 
* 
Building Commissioning , A Golden Opportunity for Reducing Energy Costs and 
Greenhouse Gas Emissions , Mills, Lawrence Berkley National Laboratories, 2009 
10
Results – National Studies 
NEW BUILDING COMMISSIONING 
* First Cost Avoidance 
 Reduce change orders 
 Reduce Requests for Information (RFIs) 
 Proper system/component selection 
 Reduce contractor callbacks 
* Building Commissioning , A Golden Opportunity for Reducing Energy Costs and Greenhouse 
Gas Emissions , Mills, Lawrence Berkley National Laboratories, 2009 
11
Design Phase Cx Values 
Commissioning 
Plan 
Design Intent 
Document 
Design Reviews 
Commissioning 
Specification 
Responsibility 
• OPR/BOD (Performance) 
• Cx Plan 
• Cx Specification 
• Construction Documents 
Review 
• Training Plan 
Delivered Value 
• Quality Enhancement 
• Operations Perspective 
• Accessibility/ 
Maintainability 
• Commission-ability 
• Best Practice 
12
Commissioning Plan 
Commissioning Plan: A document 
that outlines the scope and defines 
responsibilities, processes, 
schedules, and the documentation 
requirements of the Commissioning 
Process 
Management Tool 
Commissioning Agent 
VA PM 
13
Commissioning Plan 
 Plan Evolves as a Management Tool 
 Reviewed at Each Cx Meeting 
 Sections that Change 
 Commissioning Team Contacts 
 Elapsed Time Schedule 
 Pre Functional/Functional Tests 
 Integrated Systems Tests 
14
Commissioning Specifications 
Specification Features 
 Trending & Alarming 
 Documentation 
 Training 
15
Commissioning Scheduling 
Requirement Specified 
1.13 A The Commissioning Agent will be 
responsible for the overall management of the 
commissioning process as well as coordinating 
scheduling of commissioning tasks with the VA 
and the Contractor. 
1.15 B Scheduling: The Contractor will work 
with the Commissioning Agent and the VA to 
incorporate the commissioning activities into the 
construction schedule. 
More Later 
16
Responsibility 
• Submittal Review 
• Cx Schedule 
• Site Inspections 
• Pre Functional Test 
Support 
Construction Phase Cx Values 
Delivered Value 
• Scheduling Support 
(Turnover Activities) 
• System Documentation 
(History) 
• Operational Inspection 
(Installed Components) 
• Early Issue Identification 
/Resolution 
17
Commissioning Team: Construction 
Commissioning Team 
Construction Phase 
Paragraph 7.2 Commissioning Team 
Agency/Professional/ 
Contractor 
Description 
VA RE Department of Veterans 
Affairs Resident Engineer(s) 
Technical Representative of 
the VA Contracting Officer 
responsible for project 
delivery 
VAMC VA Medical Center Facilities 
Management and/or using 
agency 
Representatives of the local 
VA Medical Center 
responsible for Facilities 
Operation & Maintenance, 
Construction Coordination 
and/or other VAMC 
departments. 
A/E Architect/Engineer Design 
Team 
Representatives of the A/E 
Design Team responsible for 
Construction Administration 18
Commissioning Team: Construction 
Commissioning Team 
Construction Phase 
Agency/Professional/ 
Contractor 
Description 
CxA Commissioning Agent Representatives of the 
independent 3rd Party 
Commissioning Contractor 
Contractor Prime Contractor Representatives of the Prime 
Contractor responsible for 
project construction. 
SC Installing Sub-Contractors 
and Service Providers, to 
include but not necessarily 
be limited to 
Representatives of the 1st- 
Tier subcontractors 
responsible for installing 
systems and equipment 
TAB Test and Balance Agency Representatives of the Test 
and Balance contractor 
responsible for air and water 
balance of HVAC systems 
19
Commissioning Team: Construction 
Commissioning Team 
Construction Phase 
Agency/Professional/ 
Contractor 
Description 
DDCC Direct Digital Control System 
contractor 
Representatives of the 
Control System contractor 
responsible for installing and 
programming the Direct 
Digital Control system 
SpC Specialty Contractors Representatives of the ower 
tier specialty contractors 
responsible for installation 
and programming of special 
systems that interface with 
the DDC system, HVAC 
and/or Electrical systems. 
This can include independent 
3rd-Party Test Agencies (e.g., 
NETA Qualified Testing 
Agents) 20
Commissioning Team: Construction 
Division of Responsibility 
Section 7.3 Commissioning Agent Tasks 
21
Commissioning Meetings 
 Kick Off Meeting 
 Controls Integration Meeting 
 Commissioning Team Meetings 
22
Commissioning Meetings 
Kick Off Meeting 
1.Process, Goals & Objectives and Plan 
2.Performance Objectives & Verification 
Strategies 
3.Documentation Requirements 
23
Commissioning Meetings 
Kick Off Meeting 
4. Team Members 
5.Communication Protocols 
6.Project and Commissioning Schedules 
7.Shop Drawing/Submittal Review 
Process 
24
Commissioning Meetings 
Controls Integration Meeting 
1. Facilitate Review of Sequences 
2. Review Component Selections 
3. Verify Common Understanding – 
Operational Strategies 
25
Commissioning Meetings 
Commissioning Team Meetings 
1.Commissioning Plan Review 
2.Documentation Requirements/Outstanding 
Issues 
3.Current Commissioning Issues 
4.Review Project & Commissioning Schedule 
a.Progress to Date 
b.Upcoming 30 Day Schedule 
c.Schedule Inspections/Tests as Appropriate 
26
Commissioning Meetings 
Commissioning Team Meetings 
Estimating Required Meetings 
27
Commissioning Scheduling Activities 
Responsibility 
• Submittal Review 
• Cx Schedule 
• Site Inspections 
• Pre Functional Test 
Support 
Delivered Value 
• Scheduling Support 
(Turnover Activities) 
• Sub Contractor Support 
• Early Issue Identification 
/Resolution 
28
Commissioning Scheduling Activities 
VALUES 
Integrate Start Up Activities into Schedule 
Influence Brick & Mortar Construction to 
Support Infrastructure 
Plan System Start Up Activities 
Initiate Functional Testing as Early As 
Possible 
29
Commissioning Scheduling Activities 
Commissioning Team Roles and Responsibilities 
Construction Phase (Section 7.4) 
Project 
Phase/ 
Cx Task 
Commissioning Team Member Responsibilities 
VA RE 
Commis 
sioning 
Agent 
VAMC A/E Team Contractor 
Duration 
Schedule 
for 
Commissio 
ning 
Activities 
Review 
Duration 
Schedule 
and 
Comment 
as 
Appropriate 
Refine 
Duration 
Schedule 
Review 
Schedule 
and 
Comment 
as 
Appropriate 
Review 
Duration 
Schedule and 
Comment as 
Appropriate 
Review 
Commissioning 
Agent Duration 
Schedule and 
Comment as 
Appropriate 
Confirm & 
Incorporate 
Commissioning 
Activities into 
Project CPM 
Schedule. 
30
Commissioning Submittal Reviews 
Submittals: Commissioned Systems 
Purpose: Conformance with Performance Req’ts 
Accessibility/Maintainability 
Clarity (Prepare PFT/FPT/IST’s) 
Timing: Coincident with A/E 
Comments: Forward to A/E with Copy to VA PM 
Additional 
Distribution: Approved Submittals to CxA 
31
Commissioning Site Observations 
Visits Should 
“identify issues early … to allow the Contractor to 
devote sufficient time and resources to correct….” 
Verify Pre Functional Checklist Completion 
Provide Technical Support for Issue 
Identification/Resolution to Construction Team 
32
Commissioning Site Observations 
Visits Should Not 
Be perceived as Quality Control Activities 
Replace Inspection and Demonstration Req’ts of 
Contractors/Sub contractors 
A/E Team 
33
Commissioning Site Observations 
Documentation 
Field Visit Report * 
Commissioning Issues Log * 
34
Pre Functional Testing 
OBJECTIVE 
 Systems & Components Properly 
Installed 
 Quality Control Processes Effectively 
Implemented 
 Identify Issues for Early Resolution 
 Prepare for Functional Performance & 
Integrated Systems Testing 35
Pre Functional Testing 
 Pre Functional Tests 
 Developed by CxA – Contractor Collaboration 
 Static Inspections 
 Equipment Start Up Testing/Documentation 
36
Commissioning Collaboration 
 Control System Provider 
 Testing and Balancing Professional 
 Fire Alarm Contractor 
 General Contractor 
– Overall Coordination 
– Envelope Commissioning 
37
Design/Construction Phase 
Best Practices 
Early & Consistent Involvement 
Technical Support for Construction Team 
Infrastructure Scheduling 
Collaboration 
38
Responsibility 
• Performance 
Testing 
• Issue Resolution 
• Training 
• Documentation 
Systems 
Training 
Contractor 
Training 
Functional 
Testing 
Final 
Commissioning 
Report 
Deficiency 
Correction 
Acceptance Phase Cx Values 
Delivered Value 
•Systems that Work 
•Operational Clarity 
•Trained Operators 
•Building Acceptance 
•Documented History 
39
Acceptance Phase Cx Values 
Objectives 
 Achieve Performance Compliant with OPR 
 Establish System Operating Strategies 
 Support/Accountability for Performance 
 Systems Documentation for Future Ops 
40
Acceptance Phase Cx Values 
Best Practices 
 Identify Performance Issues Early 
 Technical Support for Resolution 
 Scheduling Support 
Commissioning Schedule 
Section XIII – Sample Cx Plan 
Project 
Phase 
Task Duration Schedule Predecessors 
Construction TAB Report 
Review 
2 weeks Comment log 
issued 2 weeks 
after receiving TAB 
Report 
Receive TAB 
Report 
Construction Review O & M 
Manuals 
3 weeks Comment log 
issued 3 weeks 
after receiving O&M 
Manuals 
Receive O&M 
Manuals 
41
Acceptance Phase Cx Team 
Commissioning Team 
Acceptance and Testing Phase 
Designation Agency/Professional/Contractor 
VA RE Department of Veterans Affairs Resident 
Engineer(s) 
VAMC VA Medical Center Facilities Management 
and/or using agency 
A/E Architect/Engineer Design Team 
CxA Commissioning Agent 
Contractor Prime Contractor 
SC Installing Sub-Contractors and Service 
Providers, to include but not necessarily be 
limited to 
TAB Test and Balance Agency 
DDCC Direct Digital Control System contractor 
SpC Specialty Contractors 
42
Acceptance Phase Activities 
Commissioning Team Task/Deliverables Description 
Acceptance and Testing Phase (Section 8.2) 
Project Phase/ 
Cx Task 
Commissioning Deliverables 
Functional 
Performance & 
Integrated 
Systems Testing 
Executed Functional Performance 
Tests and support documentation. 
Long Term Trend Data and Analysis 
Prepare Systems 
Manuals 
Project Systems Manual 
43
Acceptance Phase Activities 
Commissioning Team Task/Deliverables Description 
Acceptance and Testing Phase (Section 8.2) 
Project Phase/ 
Cx Task 
Commissioning Deliverables 
Training Plan 
Review 
Compiled Training Plan 
Individual Training Agendas 
Training Attendance Sign In Sheets 
Systems Training Systems Training Presentations 
(electronic) 
Final 
Commissioning 
Report 
Final Commissioning Report 
44
Acceptance Phase Scheduling 
Commissioning Schedule 
Section XIII – Sample Cx Plan 
Project Phase Task Duration Schedule Predecessors 
Construction TAB 
Report 
Review 
2 weeks 2 weeks after 
TAB Report 
Receive TAB 
Report 
Construction Review O 
& M 
Manuals 
3 weeks 3 weeks after 
O&M Manuals 
Receive O&M 
Manuals 
Construction Prepare 
Systems 
Manuals 
8 weeks 8 weeks after 
O&M Manuals 
Receive O&M 
Manuals 
Construction Review 
Training 
Plans 
3 weeks 3 weeks after 
Training Plans 
Receive Training 
Plans 
45
Acceptance Phase Scheduling 
Schedule Development 
46
Acceptance Phase 
Systems Functional Testing 
Objective 
 Test a Complete System 
 Validate System Performance 
 Test Criteria 
o Steady State 
o Transitions 
o Failure Conditions/Return to Normal 
47
Acceptance Phase Pre Requisites 
Functional Performance Testing 
 Pre Functional Checklists Complete 
 Third Party Testing Complete 
 Control Systems Fully Functional 
 TAB Complete 
48
Acceptance Phase Pre Requisites 
Integrated Systems Testing 
 Functional Performance Testing Complete 
 Long Term Trending Complete 
Both EX fans 
OFF 
Decon 
Isolation 
Only EF 14A 
ON 
Both EF 
14A, B ON 
Only EF 14B 
ON 
49
Acceptance Phase Pre Requisites 
Integrated Systems Testing 
Mechanical Systems 
IST: Integrated Operations FPT’s Complete & 
Accepted – All Units 
FPT’s Complete – Base 
Utilities (Chilled Water, 
Hot Water, etc.) 
Testing: Impose State Changes – All Units 
50
Acceptance Phase 
Integrated Systems Testing 
Objective 
 Test Building as a Complete System 
 Validate System Interactions 
 Test Criteria 
o Steady State 
o Transitions 
o Failure Conditions/Return to Normal 
51
Acceptance Phase 
Integrated Systems Testing 
Typical Integrated System Tests 
Leaks at window 
jamb trim 
Building Envelope Air Leak Testing 
Loss of Power Testing 
Fire Alarm Testing 
Long Term Trending – Environmental Control Systems 
52
Acceptance Phase Pre Requisites 
Training Activities 
 Training Agenda Approvals Complete 
 O&M Manuals Submitted and Approved 
 Systems or OMSI Manuals Submitted and 
Approved 
 Operators Engaged in FPT Execution (Optional 
– Recommended) 
53
Acceptance Phase Training 
Training Activities 
 Training Agenda 
 System Manuals 
 Systems Training 
54
Acceptance Phase Training 
Training Agenda 
Training Modules Learning Objective & 
Teaching Outline 
Documentation Manuals 
Emergencies Emergency Response 
Operations Procedures Start up, Shut Down, etc. 
Adjustments Setpoints, Timers, etc. 
Troubleshooting 
Maintenance PM’s 
Repairs Repair Procedures, 
Emergency Repairs, etc. 
55
Acceptance Phase 
Best Practices 
Early & Consistent Involvement 
Technical Support for Construction Team 
Operator Involvement in Testing 
Effective Training/Turnover Processes 
56
Post Occupancy Phase Cx Values 
Responsibility 
• Deferred Testing 
• Performance 
Checkup 
• Reinforce Training 
• Warranty Support 
10-Month 
Check-up 
Amend Final 
Commissioning 
Report 
Deferred 
Testing 
Reinforce 
Training 
Delivered Value 
•Performance 
Confirmation 
•Reinforced Training 
•Issue Identification/ 
Resolution 
•Warranty Support 
57
Post Occupancy Phase Activities 
Commissioning Team Task/Deliverables Description 
Warranty Phase 
Project Phase/ Cx Task Commissioning Deliverables 
Deferred and/or 
Seasonal Testing 
Executed Functional Performance Test 
and Support Documents 
Commissioning Issues Log 
Warranty Period Site 
Visits (Up to 4) 
Warranty Site Visit Reports 
Post-Occupancy 
Inspection 
Post Occupancy Field Visit Report 
Commissioning Issues Log 
Warranty Issues Report 
Systems Energy Review Report 
Final Commissioning 
Report Amendment 
Final Report Amendment 
58
Post Occupancy Phase 
Best Practices 
 System Adjustments to Operating 
Realities 
 Technical Support for Operations Team 
 Operator Involvement in Testing 
 Effective Training Reinforcement 
59
60

More Related Content

What's hot

CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
Robert Doig
 
Local Government Management Processes
Local Government Management ProcessesLocal Government Management Processes
Local Government Management Processes
Danee McGee
 

What's hot (20)

Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Building services planning manual 2007
Building services planning manual 2007Building services planning manual 2007
Building services planning manual 2007
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
ACH 216 Lecture 02 (Project Format)
ACH 216 Lecture 02 (Project Format)ACH 216 Lecture 02 (Project Format)
ACH 216 Lecture 02 (Project Format)
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Local Government Management Processes
Local Government Management ProcessesLocal Government Management Processes
Local Government Management Processes
 

Similar to VA Cx Presentation_SRE Training 2013 Final_v2

Table of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docxTable of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docx
ssuserf9c51d
 
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanhVGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
Vietnam Green Building Council
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
jitendra kumar biswas
 

Similar to VA Cx Presentation_SRE Training 2013 Final_v2 (20)

Qa qc-waste unit4
Qa qc-waste unit4Qa qc-waste unit4
Qa qc-waste unit4
 
EA credit 3
EA credit 3EA credit 3
EA credit 3
 
Ray-Goodfellow.ppt
Ray-Goodfellow.pptRay-Goodfellow.ppt
Ray-Goodfellow.ppt
 
Table of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docxTable of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docx
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioning
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
 
Commissioning Best Practices to Follow during the Turnover Phase
Commissioning Best Practices to Follow during the Turnover PhaseCommissioning Best Practices to Follow during the Turnover Phase
Commissioning Best Practices to Follow during the Turnover Phase
 
Construction Commissioning Best Practices during Turnover
Construction Commissioning Best Practices during TurnoverConstruction Commissioning Best Practices during Turnover
Construction Commissioning Best Practices during Turnover
 
Project Delivery Education Program
Project Delivery Education ProgramProject Delivery Education Program
Project Delivery Education Program
 
Quality_Management_Plan Template.docx
Quality_Management_Plan Template.docxQuality_Management_Plan Template.docx
Quality_Management_Plan Template.docx
 
Commissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdfCommissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdf
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 
Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21
 
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanhVGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioning
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 

VA Cx Presentation_SRE Training 2013 Final_v2

  • 1. Department of Veterans Affairs Office of Construction and Facilities Management (CFM) SRE Program Training – March 2013 Commissioning Standards Institutionalizing Best Practices in Project Delivery Presented by Jerry Bauers, PE – Sebesta Blomberg Lam Vu, PE – CFM (003C2B) 1
  • 2. Definition “Systematic process of assuring by verification and documentation, from the design phase to a minimum of one year after construction, that all building facility systems perform interactively in accordance with the design documentation and intent, and in accordance with the owner’s operational needs, including preparation of operation personnel.” 2
  • 3. Objectives 3 “…I guess…it is a little late to bring in the commissioning agent!” “…and you said that we did not need commissioning???”
  • 4. Objectives * Understand Tasks/Deliverables/ Responsibilities * Understand the Standard Documents – where & what? http://www.cfm.va.gov/TIL/ * Understand the Team Members, Responsibilities and Individual Objectives 4
  • 5. Objectives * Best Practices for Collaborative Commissioning * Management Strategies for Oversight * Responsibility of VA to Support and Encourage Commissioning 5
  • 6. Objectives Deliver a Buildings and Building Systems 6 that Work Deliver Operations Team to Sustain Performance
  • 7. Cx – Mandated Process • Executive Order13423: Strengthening Federal Environmental, Energy & Transportation Management • Executive Order 13514: Federal Leadership in Environment, Energy and Economic Performance • VA Directive 0056 – VA Sustainable Building Program • VA Sustainable Design & Energy Reduction Manual • Memorandum of Understanding - Federal Leadership in High Performance and Sustainable Buildings – Guiding Principles for Fed Leadership in High Performance and Sustainable Buildings 7
  • 8. Value Propositions • Reduce Total Ownership Costs • Improve Energy & Water Efficiency • Safe, Healthy & Productive Built Environment • Promote Sustainable Stewardship 8
  • 9. Corollary Values • Improved Operator Knowledge • Upgraded Infrastructure • Simplified Repair/Upgrade Process • Energy Master Planning 9
  • 10. Results – National Studies NEW BUILDING COMMISSIONING •First Cost Avoidance * •13% Energy Savings * •4.2 Year Payback on Investment * * Building Commissioning , A Golden Opportunity for Reducing Energy Costs and Greenhouse Gas Emissions , Mills, Lawrence Berkley National Laboratories, 2009 10
  • 11. Results – National Studies NEW BUILDING COMMISSIONING * First Cost Avoidance  Reduce change orders  Reduce Requests for Information (RFIs)  Proper system/component selection  Reduce contractor callbacks * Building Commissioning , A Golden Opportunity for Reducing Energy Costs and Greenhouse Gas Emissions , Mills, Lawrence Berkley National Laboratories, 2009 11
  • 12. Design Phase Cx Values Commissioning Plan Design Intent Document Design Reviews Commissioning Specification Responsibility • OPR/BOD (Performance) • Cx Plan • Cx Specification • Construction Documents Review • Training Plan Delivered Value • Quality Enhancement • Operations Perspective • Accessibility/ Maintainability • Commission-ability • Best Practice 12
  • 13. Commissioning Plan Commissioning Plan: A document that outlines the scope and defines responsibilities, processes, schedules, and the documentation requirements of the Commissioning Process Management Tool Commissioning Agent VA PM 13
  • 14. Commissioning Plan  Plan Evolves as a Management Tool  Reviewed at Each Cx Meeting  Sections that Change  Commissioning Team Contacts  Elapsed Time Schedule  Pre Functional/Functional Tests  Integrated Systems Tests 14
  • 15. Commissioning Specifications Specification Features  Trending & Alarming  Documentation  Training 15
  • 16. Commissioning Scheduling Requirement Specified 1.13 A The Commissioning Agent will be responsible for the overall management of the commissioning process as well as coordinating scheduling of commissioning tasks with the VA and the Contractor. 1.15 B Scheduling: The Contractor will work with the Commissioning Agent and the VA to incorporate the commissioning activities into the construction schedule. More Later 16
  • 17. Responsibility • Submittal Review • Cx Schedule • Site Inspections • Pre Functional Test Support Construction Phase Cx Values Delivered Value • Scheduling Support (Turnover Activities) • System Documentation (History) • Operational Inspection (Installed Components) • Early Issue Identification /Resolution 17
  • 18. Commissioning Team: Construction Commissioning Team Construction Phase Paragraph 7.2 Commissioning Team Agency/Professional/ Contractor Description VA RE Department of Veterans Affairs Resident Engineer(s) Technical Representative of the VA Contracting Officer responsible for project delivery VAMC VA Medical Center Facilities Management and/or using agency Representatives of the local VA Medical Center responsible for Facilities Operation & Maintenance, Construction Coordination and/or other VAMC departments. A/E Architect/Engineer Design Team Representatives of the A/E Design Team responsible for Construction Administration 18
  • 19. Commissioning Team: Construction Commissioning Team Construction Phase Agency/Professional/ Contractor Description CxA Commissioning Agent Representatives of the independent 3rd Party Commissioning Contractor Contractor Prime Contractor Representatives of the Prime Contractor responsible for project construction. SC Installing Sub-Contractors and Service Providers, to include but not necessarily be limited to Representatives of the 1st- Tier subcontractors responsible for installing systems and equipment TAB Test and Balance Agency Representatives of the Test and Balance contractor responsible for air and water balance of HVAC systems 19
  • 20. Commissioning Team: Construction Commissioning Team Construction Phase Agency/Professional/ Contractor Description DDCC Direct Digital Control System contractor Representatives of the Control System contractor responsible for installing and programming the Direct Digital Control system SpC Specialty Contractors Representatives of the ower tier specialty contractors responsible for installation and programming of special systems that interface with the DDC system, HVAC and/or Electrical systems. This can include independent 3rd-Party Test Agencies (e.g., NETA Qualified Testing Agents) 20
  • 21. Commissioning Team: Construction Division of Responsibility Section 7.3 Commissioning Agent Tasks 21
  • 22. Commissioning Meetings  Kick Off Meeting  Controls Integration Meeting  Commissioning Team Meetings 22
  • 23. Commissioning Meetings Kick Off Meeting 1.Process, Goals & Objectives and Plan 2.Performance Objectives & Verification Strategies 3.Documentation Requirements 23
  • 24. Commissioning Meetings Kick Off Meeting 4. Team Members 5.Communication Protocols 6.Project and Commissioning Schedules 7.Shop Drawing/Submittal Review Process 24
  • 25. Commissioning Meetings Controls Integration Meeting 1. Facilitate Review of Sequences 2. Review Component Selections 3. Verify Common Understanding – Operational Strategies 25
  • 26. Commissioning Meetings Commissioning Team Meetings 1.Commissioning Plan Review 2.Documentation Requirements/Outstanding Issues 3.Current Commissioning Issues 4.Review Project & Commissioning Schedule a.Progress to Date b.Upcoming 30 Day Schedule c.Schedule Inspections/Tests as Appropriate 26
  • 27. Commissioning Meetings Commissioning Team Meetings Estimating Required Meetings 27
  • 28. Commissioning Scheduling Activities Responsibility • Submittal Review • Cx Schedule • Site Inspections • Pre Functional Test Support Delivered Value • Scheduling Support (Turnover Activities) • Sub Contractor Support • Early Issue Identification /Resolution 28
  • 29. Commissioning Scheduling Activities VALUES Integrate Start Up Activities into Schedule Influence Brick & Mortar Construction to Support Infrastructure Plan System Start Up Activities Initiate Functional Testing as Early As Possible 29
  • 30. Commissioning Scheduling Activities Commissioning Team Roles and Responsibilities Construction Phase (Section 7.4) Project Phase/ Cx Task Commissioning Team Member Responsibilities VA RE Commis sioning Agent VAMC A/E Team Contractor Duration Schedule for Commissio ning Activities Review Duration Schedule and Comment as Appropriate Refine Duration Schedule Review Schedule and Comment as Appropriate Review Duration Schedule and Comment as Appropriate Review Commissioning Agent Duration Schedule and Comment as Appropriate Confirm & Incorporate Commissioning Activities into Project CPM Schedule. 30
  • 31. Commissioning Submittal Reviews Submittals: Commissioned Systems Purpose: Conformance with Performance Req’ts Accessibility/Maintainability Clarity (Prepare PFT/FPT/IST’s) Timing: Coincident with A/E Comments: Forward to A/E with Copy to VA PM Additional Distribution: Approved Submittals to CxA 31
  • 32. Commissioning Site Observations Visits Should “identify issues early … to allow the Contractor to devote sufficient time and resources to correct….” Verify Pre Functional Checklist Completion Provide Technical Support for Issue Identification/Resolution to Construction Team 32
  • 33. Commissioning Site Observations Visits Should Not Be perceived as Quality Control Activities Replace Inspection and Demonstration Req’ts of Contractors/Sub contractors A/E Team 33
  • 34. Commissioning Site Observations Documentation Field Visit Report * Commissioning Issues Log * 34
  • 35. Pre Functional Testing OBJECTIVE  Systems & Components Properly Installed  Quality Control Processes Effectively Implemented  Identify Issues for Early Resolution  Prepare for Functional Performance & Integrated Systems Testing 35
  • 36. Pre Functional Testing  Pre Functional Tests  Developed by CxA – Contractor Collaboration  Static Inspections  Equipment Start Up Testing/Documentation 36
  • 37. Commissioning Collaboration  Control System Provider  Testing and Balancing Professional  Fire Alarm Contractor  General Contractor – Overall Coordination – Envelope Commissioning 37
  • 38. Design/Construction Phase Best Practices Early & Consistent Involvement Technical Support for Construction Team Infrastructure Scheduling Collaboration 38
  • 39. Responsibility • Performance Testing • Issue Resolution • Training • Documentation Systems Training Contractor Training Functional Testing Final Commissioning Report Deficiency Correction Acceptance Phase Cx Values Delivered Value •Systems that Work •Operational Clarity •Trained Operators •Building Acceptance •Documented History 39
  • 40. Acceptance Phase Cx Values Objectives  Achieve Performance Compliant with OPR  Establish System Operating Strategies  Support/Accountability for Performance  Systems Documentation for Future Ops 40
  • 41. Acceptance Phase Cx Values Best Practices  Identify Performance Issues Early  Technical Support for Resolution  Scheduling Support Commissioning Schedule Section XIII – Sample Cx Plan Project Phase Task Duration Schedule Predecessors Construction TAB Report Review 2 weeks Comment log issued 2 weeks after receiving TAB Report Receive TAB Report Construction Review O & M Manuals 3 weeks Comment log issued 3 weeks after receiving O&M Manuals Receive O&M Manuals 41
  • 42. Acceptance Phase Cx Team Commissioning Team Acceptance and Testing Phase Designation Agency/Professional/Contractor VA RE Department of Veterans Affairs Resident Engineer(s) VAMC VA Medical Center Facilities Management and/or using agency A/E Architect/Engineer Design Team CxA Commissioning Agent Contractor Prime Contractor SC Installing Sub-Contractors and Service Providers, to include but not necessarily be limited to TAB Test and Balance Agency DDCC Direct Digital Control System contractor SpC Specialty Contractors 42
  • 43. Acceptance Phase Activities Commissioning Team Task/Deliverables Description Acceptance and Testing Phase (Section 8.2) Project Phase/ Cx Task Commissioning Deliverables Functional Performance & Integrated Systems Testing Executed Functional Performance Tests and support documentation. Long Term Trend Data and Analysis Prepare Systems Manuals Project Systems Manual 43
  • 44. Acceptance Phase Activities Commissioning Team Task/Deliverables Description Acceptance and Testing Phase (Section 8.2) Project Phase/ Cx Task Commissioning Deliverables Training Plan Review Compiled Training Plan Individual Training Agendas Training Attendance Sign In Sheets Systems Training Systems Training Presentations (electronic) Final Commissioning Report Final Commissioning Report 44
  • 45. Acceptance Phase Scheduling Commissioning Schedule Section XIII – Sample Cx Plan Project Phase Task Duration Schedule Predecessors Construction TAB Report Review 2 weeks 2 weeks after TAB Report Receive TAB Report Construction Review O & M Manuals 3 weeks 3 weeks after O&M Manuals Receive O&M Manuals Construction Prepare Systems Manuals 8 weeks 8 weeks after O&M Manuals Receive O&M Manuals Construction Review Training Plans 3 weeks 3 weeks after Training Plans Receive Training Plans 45
  • 46. Acceptance Phase Scheduling Schedule Development 46
  • 47. Acceptance Phase Systems Functional Testing Objective  Test a Complete System  Validate System Performance  Test Criteria o Steady State o Transitions o Failure Conditions/Return to Normal 47
  • 48. Acceptance Phase Pre Requisites Functional Performance Testing  Pre Functional Checklists Complete  Third Party Testing Complete  Control Systems Fully Functional  TAB Complete 48
  • 49. Acceptance Phase Pre Requisites Integrated Systems Testing  Functional Performance Testing Complete  Long Term Trending Complete Both EX fans OFF Decon Isolation Only EF 14A ON Both EF 14A, B ON Only EF 14B ON 49
  • 50. Acceptance Phase Pre Requisites Integrated Systems Testing Mechanical Systems IST: Integrated Operations FPT’s Complete & Accepted – All Units FPT’s Complete – Base Utilities (Chilled Water, Hot Water, etc.) Testing: Impose State Changes – All Units 50
  • 51. Acceptance Phase Integrated Systems Testing Objective  Test Building as a Complete System  Validate System Interactions  Test Criteria o Steady State o Transitions o Failure Conditions/Return to Normal 51
  • 52. Acceptance Phase Integrated Systems Testing Typical Integrated System Tests Leaks at window jamb trim Building Envelope Air Leak Testing Loss of Power Testing Fire Alarm Testing Long Term Trending – Environmental Control Systems 52
  • 53. Acceptance Phase Pre Requisites Training Activities  Training Agenda Approvals Complete  O&M Manuals Submitted and Approved  Systems or OMSI Manuals Submitted and Approved  Operators Engaged in FPT Execution (Optional – Recommended) 53
  • 54. Acceptance Phase Training Training Activities  Training Agenda  System Manuals  Systems Training 54
  • 55. Acceptance Phase Training Training Agenda Training Modules Learning Objective & Teaching Outline Documentation Manuals Emergencies Emergency Response Operations Procedures Start up, Shut Down, etc. Adjustments Setpoints, Timers, etc. Troubleshooting Maintenance PM’s Repairs Repair Procedures, Emergency Repairs, etc. 55
  • 56. Acceptance Phase Best Practices Early & Consistent Involvement Technical Support for Construction Team Operator Involvement in Testing Effective Training/Turnover Processes 56
  • 57. Post Occupancy Phase Cx Values Responsibility • Deferred Testing • Performance Checkup • Reinforce Training • Warranty Support 10-Month Check-up Amend Final Commissioning Report Deferred Testing Reinforce Training Delivered Value •Performance Confirmation •Reinforced Training •Issue Identification/ Resolution •Warranty Support 57
  • 58. Post Occupancy Phase Activities Commissioning Team Task/Deliverables Description Warranty Phase Project Phase/ Cx Task Commissioning Deliverables Deferred and/or Seasonal Testing Executed Functional Performance Test and Support Documents Commissioning Issues Log Warranty Period Site Visits (Up to 4) Warranty Site Visit Reports Post-Occupancy Inspection Post Occupancy Field Visit Report Commissioning Issues Log Warranty Issues Report Systems Energy Review Report Final Commissioning Report Amendment Final Report Amendment 58
  • 59. Post Occupancy Phase Best Practices  System Adjustments to Operating Realities  Technical Support for Operations Team  Operator Involvement in Testing  Effective Training Reinforcement 59
  • 60. 60