SlideShare a Scribd company logo
1 of 25
Partnership To Advance Clean Energy-Deployment (PACE-D)
Technical Assistance Program
Presented by
USAID PACE-D TA Program
Apr-18
Solar PV Rooftop Training Program For Entrepreneurs
Session:
Grid Interconnection & Commissioning Test Procedures
Contents
Interconnection and metering – What are the deciding
factors?
Single Line Diagrams for different types of interconnections
Applicable standards and regulations for grid connectivity
Interconnection technical specification and requirements
Contents
Interconnection test specification and requirements
Commissioning tests
Unintentional islanding functionality test
Interconnection & Metering – Deciding Factors
1
 State regulation by SERC
2
 Distribution utility whose grid would be utilized
3
 Capacity of SPVRT plant
4
5
 Program framework – gross or net metering
 Voltage levels where energy to be injected
Interconnection & Metering – Examples of 3 States
Supply
Voltage
Madhya Pradesh Rajasthan Maharashtra
230V, 1 phase Up to 3kW Up to 5kW Up to 8 kW / 40 A
415V, 3 phase >3kW to 112 kW >5kW to 18.65 kW >8 kW to 150 kW
>8 kW to 80 kW
11kV, 3 phase > 112kW to 300kW >18.65kW to 50kW >150 kW to 1000
kVA
>80 kW to 1000 kVA
33kV, 3 phase >300kW to
10,000kW
>50 kW
Single Line Diagram – Gross Metering: Grid Tied LT
Single Line Diagram – Gross Metering: Grid Tied HT
Single Line Diagram – Net Metering: Grid Tied LT
Single Line Diagram – Net Metering: Grid Tied HT
Single Line Diagram – Gross Metering Using 2
Meters
This is typically a gross metered connection and Meter 2 is export meter
Single Line Diagram – Net Metering Using 1 Meter
This is typically a net metered connection and Meter 1 is net meter (bi-directional)
Single Line Diagram – Net Metering Using 2 Meters
This is typically a net metered connection as mandated in many state regulations and
Meter 1 is net meter (bi-directional) whereas Meter 2 is Solar (Generation) Meter
Single Line Diagram – Net Metering for Multiple
Buildings
This is typically a colony of buildings with number of installations with net metered
connection and all meters are net meters (bi-directional)
Single Line Diagram – Gross Metering for Multiple
Buildings
This is typically a gross metered connection and Meter 1 is consumer meter and Meter
2 is Solar (Generation) meter
 Central Electricity Authority (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations 2013
 IEEE 1547 – Standard for Interconnecting Distributed Resources with Electric
Power System, 2003
 Central Electricity Authority (Measures Relating to Safety and Electricity
Supply) Regulations, 2010
 Central Electricity Authority (Technical Standards for Connectivity to the grid)
Regulations 2007
 IEEE 519: Recommended Practice and Requirements for Harmonic Control in
Electric Power Systems, 2014
Applicable Standards & Regulations for Grid
Connectivity
Interconnection Technical Specifications &
Requirements
General Requirements (IEEE 1547 / CEA Regulation 2013)
Voltage Regulations
The distributed resources shall
not actively regulate the
voltage at the point of
interconnection
Synchronization
The distributed resource
synchronized with electric
system shall not cause a
voltage fluctuation at the
point of interconnection
greater than ±5%
Monitoring Provision
Each distributed resource of
250 kVA or more at a single
point of interconnection shall
have provisions for monitoring
its connections status, real
power output, reactive power
output and voltages at the
point of interconnection
Interconnection Technical Specifications &
Requirements
General Requirements (IEEE 1547 / CEA Regulation 2013)
Isolation Device
There should be a manually operating isolating switch between distributed generation resource
and electric system, which meets the following requirements:
 Allow visible verification that separation has been established
 Indicators to show clearly closed and open position
 Be readily accessible and be capable of being locked in open position
 May not be rated for load-break
 Be located at height of 2.44 m above ground level
Interconnection Technical Specifications &
Requirements
General Requirements (IEEE 1547 / CEA Regulation 2013)
Interconnect Integrity
 Interconnection system shall have the capability to withstand electromagnetic interference
 Paralleling device shall withstand 220% of interconnection system rated voltage
 Interconnection system shall have the capability to withstand voltage and current surge
Interconnection Technical Specifications &
Requirements
Response to Abnormal Conditions (IEEE 1547 / CEA Regulation 2013)
Voltage
Inverter must have over and
under voltage trip functions if
voltage reaches above 110%
or below 80% respectively with
clearing time up to two
seconds
Frequency
Inverter must have over and
under frequency trip functions
if frequency reaches 50.5 Hz
and below 47.5 Hz with a
clearing time of 0.2 seconds
Islanding
Inverter must have function to
prevent formation of
unintended island, and cease
to energise the electricity
system within 2 seconds
Interconnection Technical Specifications &
Requirements
Power Quality (IEEE 1547 / CEA Regulation 2013)
Limitation on DC Injection
The rooftop solar and its
interconnection system shall
not inject dc current greater
than 0.5% of the full rated
output current
Limitation of Flicker
The distributed resource shall
not cause objectionable flicker
on the electric system (IEC
61000)
Harmonics
The distributed resource shall
not inject harmonic current
greater than 5% at the electric
system (IEEE 519)
Commissioning Tests
 All commissioning tests shall be performed based on written test procedures of
equipment manufacturer / system integrator
 A visual inspection shall be made to ensure that the system earthing is adequate as
per standard / regulation
 A visual inspection shall be made to confirm the presence of the isolation device as
required by standard / regulation
 The following initial commissioning tests shall be performed on the installed solar PV
rooftop system and grid connected inverter prior to the initial parallel connection to
the grid:
 Operability test on the isolation device
 Unintentional islanding functionality
Unintentional Islanding Functionality Test
If there is more than
one inverter, tests
should be carried out
for each inverter
SPVR system should
produce more than
20% of the rated
output of the SPVRT
Array or the inverter
– whichever is less
This test must be
conducted during
noon time on a
sunny day
Unintentional Islanding Functionality Test – Test 1
Test 1: Inverter must cease supplying power within 0.2 seconds of loss of
mains
Step 1:
Keep DC supply from the SPVRT array connected to the inverter
Step 2:
Place the voltage probe in the inverter side of the AC main switch
Step 3:
Turn OFF the main switch, through which inverter is connected to grid
Step 4:
Measure time taken for inverter to cease attempting to export power
with a timing device and record
Unintentional Islanding Functionality Test – Test 2
Test 2: Inverter must not resume supplying power until mains have been
present for more than 60 seconds
Step 1:
Keep DC supply from the SPVRT array connected to the inverter
Step 2:
Place the current probe in the inverter side of the AC main switch
Step 3:
Turn ON the main switch, through which inverter is connected to grid
Step 4:
Measure time taken for inverter to re-energize and start exporting
power with a timing device and record
25
Anurag Mishra
Senior Clean Energy Specialist
USAID/India
Email: amishra@usaid.gov
Disclaimer:
This training material is made possible by the support of the American
People through the United States Agency for International
Development (USAID). The contents of this material are the sole
responsibility of Nexant, Inc. and do not necessarily reflect the views of
USAID or the United States Government. This material was prepared
under Contract Number AID-386-C-12-00001.

More Related Content

What's hot

Session 09 spvrt business models
Session 09   spvrt business modelsSession 09   spvrt business models
Session 09 spvrt business modelsChirag Jain
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transitionNarinporn Malasri
 
Grid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata PatnaikGrid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata PatnaikDr.Priyabrata Patnaik
 
Session 02 solar energy technologies
Session 02   solar energy technologiesSession 02   solar energy technologies
Session 02 solar energy technologiesChirag Jain
 
Agreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plusAgreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plusPrivate Consultants
 
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...IRJET Journal
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringAnil Kumar Bohra
 
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureSALMAN SAEED
 
Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field
Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field
Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field EnergyTech2015
 
Brian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerBrian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerEnergyTech2015
 
Tues.1040 am states role in protecting electric grids from emp and gmd with a...
Tues.1040 am states role in protecting electric grids from emp and gmd with a...Tues.1040 am states role in protecting electric grids from emp and gmd with a...
Tues.1040 am states role in protecting electric grids from emp and gmd with a...EnergyTech2015
 
Impact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power systemImpact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power systemMuwaf_5
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectPartha Deb
 
Hybrid Controller | Design 150KW PV with DG1:700KW
Hybrid  Controller | Design 150KW PV with DG1:700KWHybrid  Controller | Design 150KW PV with DG1:700KW
Hybrid Controller | Design 150KW PV with DG1:700KWEyad Adnan
 

What's hot (20)

Session 09 spvrt business models
Session 09   spvrt business modelsSession 09   spvrt business models
Session 09 spvrt business models
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transition
 
Grid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata PatnaikGrid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata Patnaik
 
Session 02 solar energy technologies
Session 02   solar energy technologiesSession 02   solar energy technologies
Session 02 solar energy technologies
 
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
 
Applicability of Smart Metering Technology in Sri Lanka
Applicability of Smart Metering Technology in Sri LankaApplicability of Smart Metering Technology in Sri Lanka
Applicability of Smart Metering Technology in Sri Lanka
 
Agreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plusAgreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plus
 
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
 
4.4_Micro Grid Design_Bello_EPRI/SNL Microgrid
4.4_Micro Grid Design_Bello_EPRI/SNL Microgrid4.4_Micro Grid Design_Bello_EPRI/SNL Microgrid
4.4_Micro Grid Design_Bello_EPRI/SNL Microgrid
 
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
 
Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field
Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field
Josh Long: Minimum Cyber Security Requirements for a 20 MW Photo Voltaic Field
 
Brian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerBrian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building Power
 
Tues.1040 am states role in protecting electric grids from emp and gmd with a...
Tues.1040 am states role in protecting electric grids from emp and gmd with a...Tues.1040 am states role in protecting electric grids from emp and gmd with a...
Tues.1040 am states role in protecting electric grids from emp and gmd with a...
 
Impact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power systemImpact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power system
 
12 dessai epri sandia - pge vvo pilot
12 dessai epri sandia - pge vvo pilot12 dessai epri sandia - pge vvo pilot
12 dessai epri sandia - pge vvo pilot
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot Project
 
Hybrid Controller | Design 150KW PV with DG1:700KW
Hybrid  Controller | Design 150KW PV with DG1:700KWHybrid  Controller | Design 150KW PV with DG1:700KW
Hybrid Controller | Design 150KW PV with DG1:700KW
 
17 mohit epri-sandia symposium_v1
17 mohit epri-sandia symposium_v117 mohit epri-sandia symposium_v1
17 mohit epri-sandia symposium_v1
 
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
8.1.2_PAR 2030.8_Bower_EPRI/SNL Microgrid Symposium
 

Similar to Session 10 grid interconnections & commissioning test procedures

Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...IRJET Journal
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantHarish Sharma
 
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET Journal
 
Session 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptxSession 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptxTaashish
 
IRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected SystemIRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected SystemIRJET Journal
 
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic SystemIRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic SystemIRJET Journal
 
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...IRJET Journal
 
Advancements in inverter technology
Advancements  in inverter technologyAdvancements  in inverter technology
Advancements in inverter technologyBhanu Teja
 
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...ijsrd.com
 
IRJET- A Review Paper on Power Quality Issues and Monitoring Techniques
IRJET- A Review Paper on Power Quality Issues and Monitoring TechniquesIRJET- A Review Paper on Power Quality Issues and Monitoring Techniques
IRJET- A Review Paper on Power Quality Issues and Monitoring TechniquesIRJET Journal
 
CONTROL STRATEGIES ON GRID-TIED PV INVERTERS
CONTROL STRATEGIES ON GRID-TIED PV INVERTERSCONTROL STRATEGIES ON GRID-TIED PV INVERTERS
CONTROL STRATEGIES ON GRID-TIED PV INVERTERSIRJET Journal
 
Low-voltage ride-through for a three-phase four-leg photovoltaic system using...
Low-voltage ride-through for a three-phase four-leg photovoltaic system using...Low-voltage ride-through for a three-phase four-leg photovoltaic system using...
Low-voltage ride-through for a three-phase four-leg photovoltaic system using...IJECEIAES
 
A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...
A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...
A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...IOSR Journals
 
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...ijtsrd
 
ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...
ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...
ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...IRJET Journal
 
IRJET- Mitigation Techniques of Power Quality Issues in Electrical Power System
IRJET- Mitigation Techniques of Power Quality Issues in Electrical Power SystemIRJET- Mitigation Techniques of Power Quality Issues in Electrical Power System
IRJET- Mitigation Techniques of Power Quality Issues in Electrical Power SystemIRJET Journal
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...theijes
 

Similar to Session 10 grid interconnections & commissioning test procedures (20)

file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
 
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
 
Session 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptxSession 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptx
 
IRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected SystemIRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected System
 
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic SystemIRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
 
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
 
Advancements in inverter technology
Advancements  in inverter technologyAdvancements  in inverter technology
Advancements in inverter technology
 
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
 
IRJET- A Review Paper on Power Quality Issues and Monitoring Techniques
IRJET- A Review Paper on Power Quality Issues and Monitoring TechniquesIRJET- A Review Paper on Power Quality Issues and Monitoring Techniques
IRJET- A Review Paper on Power Quality Issues and Monitoring Techniques
 
CONTROL STRATEGIES ON GRID-TIED PV INVERTERS
CONTROL STRATEGIES ON GRID-TIED PV INVERTERSCONTROL STRATEGIES ON GRID-TIED PV INVERTERS
CONTROL STRATEGIES ON GRID-TIED PV INVERTERS
 
Low-voltage ride-through for a three-phase four-leg photovoltaic system using...
Low-voltage ride-through for a three-phase four-leg photovoltaic system using...Low-voltage ride-through for a three-phase four-leg photovoltaic system using...
Low-voltage ride-through for a three-phase four-leg photovoltaic system using...
 
A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...
A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...
A Svc Light Based Technique for Power Quality Improvement for Grid Connected ...
 
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
 
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
 
ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...
ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...
ANALYTICAL STUDY OF DIFFERENT TECHNIQUES FOR ISLANDING DETECTION OF PV GRID-T...
 
IRJET- Mitigation Techniques of Power Quality Issues in Electrical Power System
IRJET- Mitigation Techniques of Power Quality Issues in Electrical Power SystemIRJET- Mitigation Techniques of Power Quality Issues in Electrical Power System
IRJET- Mitigation Techniques of Power Quality Issues in Electrical Power System
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
 

More from Chirag Jain

Session 21 preparation of techno commercial report
Session 21   preparation of techno commercial reportSession 21   preparation of techno commercial report
Session 21 preparation of techno commercial reportChirag Jain
 
Session 20 interacting with the client
Session 20   interacting with the clientSession 20   interacting with the client
Session 20 interacting with the clientChirag Jain
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluationChirag Jain
 
Session 17 project management & monitoring
Session 17   project management & monitoringSession 17   project management & monitoring
Session 17 project management & monitoringChirag Jain
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreementChirag Jain
 
Session 15 spvrt project financing
Session 15   spvrt project financingSession 15   spvrt project financing
Session 15 spvrt project financingChirag Jain
 
Session 14 market trends & business proposals
Session 14   market trends & business proposalsSession 14   market trends & business proposals
Session 14 market trends & business proposalsChirag Jain
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentivesChirag Jain
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economicsChirag Jain
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planningChirag Jain
 
Session 01 Introduction to the course
Session 01   Introduction to the courseSession 01   Introduction to the course
Session 01 Introduction to the courseChirag Jain
 

More from Chirag Jain (11)

Session 21 preparation of techno commercial report
Session 21   preparation of techno commercial reportSession 21   preparation of techno commercial report
Session 21 preparation of techno commercial report
 
Session 20 interacting with the client
Session 20   interacting with the clientSession 20   interacting with the client
Session 20 interacting with the client
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluation
 
Session 17 project management & monitoring
Session 17   project management & monitoringSession 17   project management & monitoring
Session 17 project management & monitoring
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
Session 15 spvrt project financing
Session 15   spvrt project financingSession 15   spvrt project financing
Session 15 spvrt project financing
 
Session 14 market trends & business proposals
Session 14   market trends & business proposalsSession 14   market trends & business proposals
Session 14 market trends & business proposals
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economics
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planning
 
Session 01 Introduction to the course
Session 01   Introduction to the courseSession 01   Introduction to the course
Session 01 Introduction to the course
 

Recently uploaded

Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxLigayaBacuel1
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 

Recently uploaded (20)

Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptx
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 

Session 10 grid interconnections & commissioning test procedures

  • 1. Partnership To Advance Clean Energy-Deployment (PACE-D) Technical Assistance Program Presented by USAID PACE-D TA Program Apr-18 Solar PV Rooftop Training Program For Entrepreneurs Session: Grid Interconnection & Commissioning Test Procedures
  • 2. Contents Interconnection and metering – What are the deciding factors? Single Line Diagrams for different types of interconnections Applicable standards and regulations for grid connectivity Interconnection technical specification and requirements
  • 3. Contents Interconnection test specification and requirements Commissioning tests Unintentional islanding functionality test
  • 4. Interconnection & Metering – Deciding Factors 1  State regulation by SERC 2  Distribution utility whose grid would be utilized 3  Capacity of SPVRT plant 4 5  Program framework – gross or net metering  Voltage levels where energy to be injected
  • 5. Interconnection & Metering – Examples of 3 States Supply Voltage Madhya Pradesh Rajasthan Maharashtra 230V, 1 phase Up to 3kW Up to 5kW Up to 8 kW / 40 A 415V, 3 phase >3kW to 112 kW >5kW to 18.65 kW >8 kW to 150 kW >8 kW to 80 kW 11kV, 3 phase > 112kW to 300kW >18.65kW to 50kW >150 kW to 1000 kVA >80 kW to 1000 kVA 33kV, 3 phase >300kW to 10,000kW >50 kW
  • 6. Single Line Diagram – Gross Metering: Grid Tied LT
  • 7. Single Line Diagram – Gross Metering: Grid Tied HT
  • 8. Single Line Diagram – Net Metering: Grid Tied LT
  • 9. Single Line Diagram – Net Metering: Grid Tied HT
  • 10. Single Line Diagram – Gross Metering Using 2 Meters This is typically a gross metered connection and Meter 2 is export meter
  • 11. Single Line Diagram – Net Metering Using 1 Meter This is typically a net metered connection and Meter 1 is net meter (bi-directional)
  • 12. Single Line Diagram – Net Metering Using 2 Meters This is typically a net metered connection as mandated in many state regulations and Meter 1 is net meter (bi-directional) whereas Meter 2 is Solar (Generation) Meter
  • 13. Single Line Diagram – Net Metering for Multiple Buildings This is typically a colony of buildings with number of installations with net metered connection and all meters are net meters (bi-directional)
  • 14. Single Line Diagram – Gross Metering for Multiple Buildings This is typically a gross metered connection and Meter 1 is consumer meter and Meter 2 is Solar (Generation) meter
  • 15.  Central Electricity Authority (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013  IEEE 1547 – Standard for Interconnecting Distributed Resources with Electric Power System, 2003  Central Electricity Authority (Measures Relating to Safety and Electricity Supply) Regulations, 2010  Central Electricity Authority (Technical Standards for Connectivity to the grid) Regulations 2007  IEEE 519: Recommended Practice and Requirements for Harmonic Control in Electric Power Systems, 2014 Applicable Standards & Regulations for Grid Connectivity
  • 16. Interconnection Technical Specifications & Requirements General Requirements (IEEE 1547 / CEA Regulation 2013) Voltage Regulations The distributed resources shall not actively regulate the voltage at the point of interconnection Synchronization The distributed resource synchronized with electric system shall not cause a voltage fluctuation at the point of interconnection greater than ±5% Monitoring Provision Each distributed resource of 250 kVA or more at a single point of interconnection shall have provisions for monitoring its connections status, real power output, reactive power output and voltages at the point of interconnection
  • 17. Interconnection Technical Specifications & Requirements General Requirements (IEEE 1547 / CEA Regulation 2013) Isolation Device There should be a manually operating isolating switch between distributed generation resource and electric system, which meets the following requirements:  Allow visible verification that separation has been established  Indicators to show clearly closed and open position  Be readily accessible and be capable of being locked in open position  May not be rated for load-break  Be located at height of 2.44 m above ground level
  • 18. Interconnection Technical Specifications & Requirements General Requirements (IEEE 1547 / CEA Regulation 2013) Interconnect Integrity  Interconnection system shall have the capability to withstand electromagnetic interference  Paralleling device shall withstand 220% of interconnection system rated voltage  Interconnection system shall have the capability to withstand voltage and current surge
  • 19. Interconnection Technical Specifications & Requirements Response to Abnormal Conditions (IEEE 1547 / CEA Regulation 2013) Voltage Inverter must have over and under voltage trip functions if voltage reaches above 110% or below 80% respectively with clearing time up to two seconds Frequency Inverter must have over and under frequency trip functions if frequency reaches 50.5 Hz and below 47.5 Hz with a clearing time of 0.2 seconds Islanding Inverter must have function to prevent formation of unintended island, and cease to energise the electricity system within 2 seconds
  • 20. Interconnection Technical Specifications & Requirements Power Quality (IEEE 1547 / CEA Regulation 2013) Limitation on DC Injection The rooftop solar and its interconnection system shall not inject dc current greater than 0.5% of the full rated output current Limitation of Flicker The distributed resource shall not cause objectionable flicker on the electric system (IEC 61000) Harmonics The distributed resource shall not inject harmonic current greater than 5% at the electric system (IEEE 519)
  • 21. Commissioning Tests  All commissioning tests shall be performed based on written test procedures of equipment manufacturer / system integrator  A visual inspection shall be made to ensure that the system earthing is adequate as per standard / regulation  A visual inspection shall be made to confirm the presence of the isolation device as required by standard / regulation  The following initial commissioning tests shall be performed on the installed solar PV rooftop system and grid connected inverter prior to the initial parallel connection to the grid:  Operability test on the isolation device  Unintentional islanding functionality
  • 22. Unintentional Islanding Functionality Test If there is more than one inverter, tests should be carried out for each inverter SPVR system should produce more than 20% of the rated output of the SPVRT Array or the inverter – whichever is less This test must be conducted during noon time on a sunny day
  • 23. Unintentional Islanding Functionality Test – Test 1 Test 1: Inverter must cease supplying power within 0.2 seconds of loss of mains Step 1: Keep DC supply from the SPVRT array connected to the inverter Step 2: Place the voltage probe in the inverter side of the AC main switch Step 3: Turn OFF the main switch, through which inverter is connected to grid Step 4: Measure time taken for inverter to cease attempting to export power with a timing device and record
  • 24. Unintentional Islanding Functionality Test – Test 2 Test 2: Inverter must not resume supplying power until mains have been present for more than 60 seconds Step 1: Keep DC supply from the SPVRT array connected to the inverter Step 2: Place the current probe in the inverter side of the AC main switch Step 3: Turn ON the main switch, through which inverter is connected to grid Step 4: Measure time taken for inverter to re-energize and start exporting power with a timing device and record
  • 25. 25 Anurag Mishra Senior Clean Energy Specialist USAID/India Email: amishra@usaid.gov Disclaimer: This training material is made possible by the support of the American People through the United States Agency for International Development (USAID). The contents of this material are the sole responsibility of Nexant, Inc. and do not necessarily reflect the views of USAID or the United States Government. This material was prepared under Contract Number AID-386-C-12-00001.