1. Partnership To Advance Clean Energy-Deployment (PACE-D)
Technical Assistance Program
Presented by
USAID PACE-D TA Program
Apr-18
Solar PV Rooftop Training Program For Entrepreneurs
Session:
Balance of System (BoS) Components
4. Array Mounting Structure – Design & Materials
Thermal Aspects
Expansion /
Contraction of
modules /
Structure
Mechanical
Loads on PV
Structures
To comply with
related standards
Wind
To be rated for
maximum
expected wind
speeds
Material
Accumulation on
PV Array
Snow, ice, others
Corrosion
Mounting to be
made from
corrosion resistant
materials
Support structures and module
mounting arrangements should
comply with
Applicable building codes
regulations and
Standards and module
manufacturer’s mounting
requirements
Aspects to be considered
while designing array
mounting structure
IEC 62548
10. Key Balance of System (BoS) Components
PV Modules
Mounting
frame
Junction Box
DC Cabling
Solar Array Isolator
Inverter AC Cabling
Main Switch
Solar Supply
Meter
Switchboard
Power Grid
11. Key Balance of System (BoS) Components
Balance of
System (BoS)
Components
DC cables and AC cables
Array Junction Box / DC combiner box
Over current protection device / circuit breaker
Disconnection devices
Plugs, sockets, and connectors
Lightning protection device
Earthing and bonding arrangement
Energy meters
System monitoring
Marking and signage
12. DC Cables
Use of DC cables:
String cables connecting
the modules in series and
to the array junction box
Array cables connecting the
array junction box to the
SPVRT array
DC isolator
DC inverter cables
connecting the SPVRT array
DC isolator to the inverter
For a system with battery storage:
Connecting battery to
inverter
Battery interconnection
14. Array Junction Box / DC Combiner Box
SPVRT strings are
connected in a junction
/ combiner box which
also contains
overcurrent protection
devices and / or switch-
disconnectors
SPVRT array and SPVRT
string combiner boxes
shall be at least IP 54
compliant in accordance
with IEC 60529, and
shall be UV resistant.
Shall be capable of being
reached for inspection,
maintenance or repairs
There should be segregation
between positive and
negative conductors within
combiner boxes to minimize
the risks of DC arcs
15. Over Current Protection Device / Circuit Breakers
Requirement of OCPD in SPVRT array
shall be determined as per section 6.3 of
IEC62548
String OCP shall be located at the string
in the sub-array or array cables in the
string combiner box
Sub-array OCPD shall be installed in the
sub-array cables in the array combiner
box
Array OCPD shall be installed at the
array cables in the application circuit or
the inverter
OCPD shall be certified to either IEC
60898-2 or IEC 60947-2
16. Disconnection Devices
Circuit Breakers used for overcurrent
protection in SPVRT array shall be
Certified to IEC 60898 or IEC
60947-2 (IS 13947)
Not polarity sensitive
Rated to interrupt full load and
prospective fault current
Rated for overcurrent as per IEC
62548 section 6.3.5.
All circuit breakers used, need to be
rated for DC
17. According to CEA (Technical Standards for Connectivity of the Distributed Generation
Resources) Regulations, 2013, a manual isolating switch shall be installed between the
inverter and the electricity grid. It is recommended to place that on the inverter side of the
PV metering device in the switchboard.
It must Interrupt the active conductor
Be capable of being locked in open position
Be located at a height of at least 2.44m above the ground level
May not be rated for load break nor may have feature of over-current protection
Comply with all other specifications as per CEA Regulations
Disconnection Devices
18. Plugs, Sockets & Connectors
Be rated for DC use
Have a voltage and current rating as per section 7 of IEC-62548
Require a deliberate force to disconnect
If accessible by untrained people then shall be of the locking type where two
independent actions are required to disconnect
Be rated for outdoor use, be UV-resistant and be of an IP rating suitable for the
location
Plugs and socket outlets normally used for the connection of household
equipment to low voltage AC power shall not be used in PV arrays
19. Lightning Protection System
The need for a lightning protection
system shall be assessed and installed in
accordance with IEC 62305-2, IEC 62305-
3 or IS2309
If a lightning protection system (LPS) is
already installed on the building, the
SPVRT system should be integrated into
the LPS as appropriate in accordance
with
IEC 62305-3
In the case where no lightning system is
required on a building or in a case of a
free-standing array, overvoltage
protection may still be required to
protect the array and the inverter and all
20. Earthing & Bonding Arrangement
Functional
earthing of
conductive
non-current
carrying parts
Earthing for
lightning
protection
Equipotential
bonding to avoid
uneven potentials
across an installation
Functional earthing
of one current
carrying pole of the
SPVRT array for
selected SPVRT array
The following options for earthing or
bonding of parts of a SPVRT array exist:
22. System Monitoring
Most inverters are equipped with
data module and communication
system which sends daily energy
generation
An independent energy generation
and performance monitoring system
can also be installed
When required, a residual current
monitoring and earth fault alarm
system shall be installed
23. Marking & Signage
For safety of maintenance personnel, inspectors,
DISCOM personnel, and emergency aid services
it is essential to indicate markings of SPVRT
installation. IEC 62548 indicates the following
signs using local language or using appropriate
local warning symbols
Sign at the origin of the electrical
installation
Sign at the metering position, if remote
from the origin
Sign at the consumer unit or distribution
board to which the supply from the inverter
is connected
Sign at all points of isolation of all sources
of supply
24. What are the major components of a SPVRT system?
What are the balance of system (BoS) components of a SPVRT system?
How do you qualify PV modules for grid-connected SPVRT system?
How is a grid connected inverter different from a UPS inverter?
How do you identify an isolated or non-isolated grid-connected inverter?
What are the advantages and disadvantages of micro inverter?
Why does the SPVRT system require earthing?
Why should marking and signage be installed in an SPVRT system?
Recapturing the Session
25. 25
Anurag Mishra
Senior Clean Energy Specialist
USAID/India
Email: amishra@usaid.gov
Disclaimer:
This training material is made possible by the support of the American
People through the United States Agency for International
Development (USAID). The contents of this material are the sole
responsibility of Nexant, Inc. and do not necessarily reflect the views of
USAID or the United States Government. This material was prepared
under Contract Number AID-386-C-12-00001.
Editor's Notes
Note to presenter:
1. Get familiar with the specified section of IEC 62548