SlideShare a Scribd company logo
1 of 15
Faculty of Engineering
Construction Management Course
Scheduling project for
bader-waset road
Prepared by:
JALAL TAHSIEN RASHIED TANATRAH
Material professor:
Dr. Akram Suleiman
•For this project a lot of assumptions are made because we
don’t have project drawings, so we don’t know on what
station does the box and pipe culvert s exist and how many.
•We considered there is only one box culvert and pipe culverts
two crossings of 1000mm, and three crossings of 800mm
considering each crossing 100m long.
•Another thing we considered once the activity is started it
will remain till it finish no matter the long time of it and this is
actually not right because in road construction we make it as a
milestones for example 10km or 5km or less or larger
depending on the availability of resources and manpower .
•So you can find activity duration of 300 days for example but
if we split this activity to milestones of 10km each, this will be
300/6=50 days and so on for the other activities.
Assumptions made to determine activities times
• For site clearance and temp. facilities this will depend mainly on
surveyor and helper and some times a grader to remove all radish
to fix center line and accordingly make road cross sections which is
estimated as 45 days and for the surveyor could at least make 2km
per day.
• For structural excavation which is 1000 cubic meters. Excavator
could accomplish 100 m3/day = 10 days and 4 days for submission,
and this is mainly for box and pipe culverts.
• For road excavation we are going to use dozer (D10) which could
excavate 1000m3/day means 200days and 10 days for bad weather.
• For laying of pipe culverts we estimated to lay pipes 10l.m/day so it
needs 50days.
• For erecting of box culvert for ordinary carpenter could finish
5m3/day and with 3 of them they will finish 15m3/day so 400 by 15
= 26.7days and for steel fixer could finish 1.0 ton/day and with 3 of
them could finish 3.0ton/day so 60 by 3 = 20 days another 10 days
extra for submission, pouring of concrete and possibility of bad
weather.
•For backfilling we used the resources of dozer (D10), grader, water tank
(2), Roller (2), and trucks (10). For the dozer it can backfill 2500 cubic
meter per day easily depending on the availability of material that is why
we used 10 trucks of 30 cubic meter loading and with 12 runs per day
30*10*12=3600 m3/day , and this needs water and grader to finish the
top of each layer and a roller for compaction. So 600000/2500=240 days
the other 60 days for submission and bad weather.
•For base coarse layers we need 13200*1.5=19800m3 of loose material
and with 10 trucks of 30m3 loading we need 66 days if each truck brings
one hit because source is too far, but the key factor here is the grader
which can finish 50m3/ day and we have two of them so we need 132
days the rest of days for submission and bad weather.
•For MC spraying each thnier could spray 20000m2/day so 582000/20000
so we need 29.1 days.
•For asphalt layer we need two finishers with 5000m2/day each so we
can achieve 10000m2/day and consequently need 58.2days and the
difference for submission and bad weather.
•For riprap protection for those workers they produce 10m3/day so we
need 50days.
•For slope protection with those workers they finish 40m2/day
consequently we need 20 days.
•For right of way signs we estimated duration of 10 days depending on the
location of 6km per day.
•For road painting we estimated 3km/day painting for each machine
resulting in 20days for the whole project.
•And last for traffic signs we estimated it of 10days depending on
accomplishing 6km/day.
CPM calculation with activities only
Bar Chart
CPM with duration, start, finish, IPA,
and resources (Bar chart)
Critical Activities Only (Bar chart)
Scheduling using AON method
Resources used and its rates
PERT analysis which begin with
allocating To,Tm,Tp
PERT calculation for critical activities
with Te=699.177days
PERT chart
Highway Project Schedule
Highway Project Schedule

More Related Content

What's hot

Road construction equipment.pptx 2
Road construction equipment.pptx 2Road construction equipment.pptx 2
Road construction equipment.pptx 2AhmedZL
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavementBhavik A Shah
 
Sums on Rigid Pavement Design
Sums on Rigid Pavement DesignSums on Rigid Pavement Design
Sums on Rigid Pavement DesignArnabKarmakar18
 
Chapter 3&4
Chapter 3&4Chapter 3&4
Chapter 3&4EWIT
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfTVijayaGowri
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Make Mannan
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Spot speed studies.ppt .mylan nejyar
Spot speed studies.ppt .mylan nejyarSpot speed studies.ppt .mylan nejyar
Spot speed studies.ppt .mylan nejyarMalika khalil
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADkumawat123
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of pilesLatif Hyder Wadho
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gaugeMani Vel
 
Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)Ahmed Ferdous Ankon
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Make Mannan
 
Soil mechanics 2 (geotech engg) lab report
Soil mechanics 2 (geotech engg) lab reportSoil mechanics 2 (geotech engg) lab report
Soil mechanics 2 (geotech engg) lab reportMuhammad Bilal
 
History of road in Nepal
History of road in NepalHistory of road in Nepal
History of road in Nepalpnbastola
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: TurnoutsVijai Krishnan V
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 

What's hot (20)

Road construction equipment.pptx 2
Road construction equipment.pptx 2Road construction equipment.pptx 2
Road construction equipment.pptx 2
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Sums on Rigid Pavement Design
Sums on Rigid Pavement DesignSums on Rigid Pavement Design
Sums on Rigid Pavement Design
 
Chapter 3&4
Chapter 3&4Chapter 3&4
Chapter 3&4
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Spot speed studies.ppt .mylan nejyar
Spot speed studies.ppt .mylan nejyarSpot speed studies.ppt .mylan nejyar
Spot speed studies.ppt .mylan nejyar
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROAD
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Unit 1
Unit 1Unit 1
Unit 1
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gauge
 
Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
 
Soil mechanics 2 (geotech engg) lab report
Soil mechanics 2 (geotech engg) lab reportSoil mechanics 2 (geotech engg) lab report
Soil mechanics 2 (geotech engg) lab report
 
History of road in Nepal
History of road in NepalHistory of road in Nepal
History of road in Nepal
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 

Similar to Highway Project Schedule

Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChandra Mohan Lodha
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity SSudhaVelan
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSSaritaJoshi5
 
Construction of Utility Tunnel phase ll
Construction of Utility Tunnel phase  llConstruction of Utility Tunnel phase  ll
Construction of Utility Tunnel phase llRavi Bhadani
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 finaldhanapal143
 
Rmc plant
Rmc plantRmc plant
Rmc plantKp Ahm
 
J.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resourcesJ.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resourcesJ.S. Daniel
 
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptxModule-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptxSilasChaudhari
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsRavi Shankar
 
Excavation work
Excavation workExcavation work
Excavation workAmit Kumar
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningJasmeet Singh Saluja
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamMd Raijul Islam
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingAnchit Agrawal
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposalkjanand
 
CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010
CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010
CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010Chris Hutchinson
 
Ambuja Cements Ltd. Internship Project Presentation
Ambuja Cements Ltd. Internship Project PresentationAmbuja Cements Ltd. Internship Project Presentation
Ambuja Cements Ltd. Internship Project PresentationSubharaj Chakraborty
 

Similar to Highway Project Schedule (20)

Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONS
 
EQS - RATE ANALYSIS.pdf
EQS -  RATE ANALYSIS.pdfEQS -  RATE ANALYSIS.pdf
EQS - RATE ANALYSIS.pdf
 
Construction of Utility Tunnel phase ll
Construction of Utility Tunnel phase  llConstruction of Utility Tunnel phase  ll
Construction of Utility Tunnel phase ll
 
Sbhep vivek kumar
Sbhep vivek kumarSbhep vivek kumar
Sbhep vivek kumar
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
 
Rmc plant
Rmc plantRmc plant
Rmc plant
 
J.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resourcesJ.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resources
 
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptxModule-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
Excavation work
Excavation workExcavation work
Excavation work
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
 
Summer training report
Summer training reportSummer training report
Summer training report
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010
CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010
CT-3000 Demo for Warsaw Local Road Authorities (ZDM), May 2010
 
Ambuja Cements Ltd. Internship Project Presentation
Ambuja Cements Ltd. Internship Project PresentationAmbuja Cements Ltd. Internship Project Presentation
Ambuja Cements Ltd. Internship Project Presentation
 
Ppt on cement grade project
Ppt on cement grade projectPpt on cement grade project
Ppt on cement grade project
 

More from Akram Suleiman

Highway Maintenance مشروع الصيانة
Highway Maintenance مشروع الصيانة Highway Maintenance مشروع الصيانة
Highway Maintenance مشروع الصيانة Akram Suleiman
 
Flixible Pavement Layers
Flixible Pavement Layers Flixible Pavement Layers
Flixible Pavement Layers Akram Suleiman
 
Earth Structure, Minerals In Earth, Physical Properties Of Minerals
Earth Structure, Minerals In Earth, Physical Properties Of Minerals   Earth Structure, Minerals In Earth, Physical Properties Of Minerals
Earth Structure, Minerals In Earth, Physical Properties Of Minerals Akram Suleiman
 
Soil formation and Types
Soil formation and TypesSoil formation and Types
Soil formation and TypesAkram Suleiman
 
Metamorphic Rocks geology
Metamorphic Rocks geologyMetamorphic Rocks geology
Metamorphic Rocks geologyAkram Suleiman
 
Site subsurface Investigation
Site subsurface InvestigationSite subsurface Investigation
Site subsurface InvestigationAkram Suleiman
 
Highway Maintenance Project
Highway Maintenance ProjectHighway Maintenance Project
Highway Maintenance ProjectAkram Suleiman
 
Paver 5.2.3 A Quick Start
Paver 5.2.3 A Quick StartPaver 5.2.3 A Quick Start
Paver 5.2.3 A Quick StartAkram Suleiman
 
أعمال الواح الجبصين
أعمال الواح الجبصينأعمال الواح الجبصين
أعمال الواح الجبصينAkram Suleiman
 

More from Akram Suleiman (20)

Highway Maintenance مشروع الصيانة
Highway Maintenance مشروع الصيانة Highway Maintenance مشروع الصيانة
Highway Maintenance مشروع الصيانة
 
Flixible Pavement Layers
Flixible Pavement Layers Flixible Pavement Layers
Flixible Pavement Layers
 
Earth Structure
Earth StructureEarth Structure
Earth Structure
 
Groundwater
GroundwaterGroundwater
Groundwater
 
Structural Geology
Structural GeologyStructural Geology
Structural Geology
 
Engineering Geology
Engineering GeologyEngineering Geology
Engineering Geology
 
CHEMICAL WEATHERING
CHEMICAL WEATHERING CHEMICAL WEATHERING
CHEMICAL WEATHERING
 
Structural geology
Structural geologyStructural geology
Structural geology
 
Igneous rocks
Igneous rocksIgneous rocks
Igneous rocks
 
Weathering
WeatheringWeathering
Weathering
 
Earthquakes
EarthquakesEarthquakes
Earthquakes
 
Metamorphic Rocks
Metamorphic RocksMetamorphic Rocks
Metamorphic Rocks
 
Earth Structure, Minerals In Earth, Physical Properties Of Minerals
Earth Structure, Minerals In Earth, Physical Properties Of Minerals   Earth Structure, Minerals In Earth, Physical Properties Of Minerals
Earth Structure, Minerals In Earth, Physical Properties Of Minerals
 
Soil formation and Types
Soil formation and TypesSoil formation and Types
Soil formation and Types
 
Earthquakes
EarthquakesEarthquakes
Earthquakes
 
Metamorphic Rocks geology
Metamorphic Rocks geologyMetamorphic Rocks geology
Metamorphic Rocks geology
 
Site subsurface Investigation
Site subsurface InvestigationSite subsurface Investigation
Site subsurface Investigation
 
Highway Maintenance Project
Highway Maintenance ProjectHighway Maintenance Project
Highway Maintenance Project
 
Paver 5.2.3 A Quick Start
Paver 5.2.3 A Quick StartPaver 5.2.3 A Quick Start
Paver 5.2.3 A Quick Start
 
أعمال الواح الجبصين
أعمال الواح الجبصينأعمال الواح الجبصين
أعمال الواح الجبصين
 

Recently uploaded

Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.MateoGardella
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...KokoStevan
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterMateoGardella
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 

Recently uploaded (20)

Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 

Highway Project Schedule

  • 1. Faculty of Engineering Construction Management Course Scheduling project for bader-waset road Prepared by: JALAL TAHSIEN RASHIED TANATRAH Material professor: Dr. Akram Suleiman
  • 2. •For this project a lot of assumptions are made because we don’t have project drawings, so we don’t know on what station does the box and pipe culvert s exist and how many. •We considered there is only one box culvert and pipe culverts two crossings of 1000mm, and three crossings of 800mm considering each crossing 100m long. •Another thing we considered once the activity is started it will remain till it finish no matter the long time of it and this is actually not right because in road construction we make it as a milestones for example 10km or 5km or less or larger depending on the availability of resources and manpower . •So you can find activity duration of 300 days for example but if we split this activity to milestones of 10km each, this will be 300/6=50 days and so on for the other activities.
  • 3. Assumptions made to determine activities times • For site clearance and temp. facilities this will depend mainly on surveyor and helper and some times a grader to remove all radish to fix center line and accordingly make road cross sections which is estimated as 45 days and for the surveyor could at least make 2km per day. • For structural excavation which is 1000 cubic meters. Excavator could accomplish 100 m3/day = 10 days and 4 days for submission, and this is mainly for box and pipe culverts. • For road excavation we are going to use dozer (D10) which could excavate 1000m3/day means 200days and 10 days for bad weather. • For laying of pipe culverts we estimated to lay pipes 10l.m/day so it needs 50days. • For erecting of box culvert for ordinary carpenter could finish 5m3/day and with 3 of them they will finish 15m3/day so 400 by 15 = 26.7days and for steel fixer could finish 1.0 ton/day and with 3 of them could finish 3.0ton/day so 60 by 3 = 20 days another 10 days extra for submission, pouring of concrete and possibility of bad weather.
  • 4. •For backfilling we used the resources of dozer (D10), grader, water tank (2), Roller (2), and trucks (10). For the dozer it can backfill 2500 cubic meter per day easily depending on the availability of material that is why we used 10 trucks of 30 cubic meter loading and with 12 runs per day 30*10*12=3600 m3/day , and this needs water and grader to finish the top of each layer and a roller for compaction. So 600000/2500=240 days the other 60 days for submission and bad weather. •For base coarse layers we need 13200*1.5=19800m3 of loose material and with 10 trucks of 30m3 loading we need 66 days if each truck brings one hit because source is too far, but the key factor here is the grader which can finish 50m3/ day and we have two of them so we need 132 days the rest of days for submission and bad weather. •For MC spraying each thnier could spray 20000m2/day so 582000/20000 so we need 29.1 days. •For asphalt layer we need two finishers with 5000m2/day each so we can achieve 10000m2/day and consequently need 58.2days and the difference for submission and bad weather. •For riprap protection for those workers they produce 10m3/day so we need 50days. •For slope protection with those workers they finish 40m2/day consequently we need 20 days.
  • 5. •For right of way signs we estimated duration of 10 days depending on the location of 6km per day. •For road painting we estimated 3km/day painting for each machine resulting in 20days for the whole project. •And last for traffic signs we estimated it of 10days depending on accomplishing 6km/day.
  • 6. CPM calculation with activities only Bar Chart
  • 7. CPM with duration, start, finish, IPA, and resources (Bar chart)
  • 10. Resources used and its rates
  • 11. PERT analysis which begin with allocating To,Tm,Tp
  • 12. PERT calculation for critical activities with Te=699.177days