OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
Sbhep vivek kumar
1. Internship Presentation on
Singoli-Bhatwari Hydro Electric Project, 3x33 MW
(Rudraprayag, U.K.)
by
VIVEK KUMAR
R680216055
University of Petroleum and Energy studies
Dehradun, Uttarakhand
2. Introduction
• Project Name: Singoli Bhatwari
Hydroelectric Project
• Place : Rudraprayag, Uttarakhand
• First hydel project in Uttarakhand
which is being developed by Larsen
and Toubro.
• The project was awarded in 2006 on
build, own, operate and transfer
(BOOT) basis.
• Capacity- 3X33 MW
29/18/2019
3. Organizational Structure of L&T construction limited
9/18/2019 3
Head
Office
North South
PM
Planning Store
PM
East
Time office
Plant &
Machinery
Safety Quality Site
West
PM-Project Manager
7. Specifications of Barrage in the Project:
• Average River Bed Level : 998.50m
• Elevation of top : 1020.00m
• Full Reservoir Level : 1017.00m
• Width of Barrage : 59m
• Dimension of Barrage
in the direction of flow : 30m
• No. of Bays : 5
• No. of Abutments : 2
• No. of Piers : 4
• Pier thickness : 3.5 m
9/18/2019 7
12. Head Race Tunnel
9/18/2019 12
Types of HRT
On the basis of flow
Pressure flow
tunnel
Gravity flow
tunnel
On the basis of shapes
Semi
circular
Circular Elliptical Hourseshoe
14. Pressure Shaft
9/18/2019 14
• Pressure shafts are underground circular
openings like tunnels in which fully
pressurized flow of water is expected like in
pipes.
• Depending on the water pressure and rock
cover above the pressure shaft, they can be
either lined with concrete or steel linings.
16. Surge Shaft
9/18/2019 16
Surge tank is an open tank used to
reduce the distance between the free
water surface and turbine in order to
reduce water hammering effect.
20. Approach ADITs
9/18/2019 20
• ADITs are made to access the HRT,
take equipments and construction
material
• They are used to execute work from
both directions
23. Shotcrete = Cement+ aggregate+ water + accelerators
9/18/201923
•Used to protect and support rock
surfaces after excavation and rock bolting
•Fill the cavities caused by weathering.
Fig 15. View of Drop shaft from the top
24. Power House
• The location where the required head is achieved for the generation
of electricity is selected for the construction of the Power House.
9/18/2019 24
Fig. 16 Location of Power House in the plan of the project Fig 17. View of Power House from the NH 109
25. Power House (Machine Hall)
9/18/2019 25
Fig. 18 View of Machine Hall
•Turbines were placed in the
Machine Hall
•Francis turbines are used in the
project
31. Working of Aggregate processing plant
• Boulders greater than 300m are broken by broker machine.
• After primary crushing, the sizes of broken stone are converted into 80mm to
100mm.
• The crushed stone materials are conveyed by belt conveyor for secondary
crushing .
• After secondary crushing the crushed stone are sent to vibrating screens for
separation of coarse and fine aggregates.
• There are two deck vibrating screens, on top 40mm sieve size and in bottom 24
mm sieves placed. The crushed stone retaining on 40mm sieve is sent back to the
impact crushing by conveyor belt and passing by 40mm sieve is sent for further
separation until to achieve required aggregate sizes.
• The crushed stone passing by 4.75mm is sent by conveyor belt into spiral clarifier
for separating the sand and silt.
9/18/2019 31
34. Plant And Machinery
9/18/2019 34
Typical data-
Self-weight- Less than 26 tonnes
Vertical Reach- 35.6 m
Horizontal reach- 31.4 m
Depth of reach- 23.9 m
Delivery rate- 60 cum/hr.
Fig 17. Boom Placer