Railway Track Gauge
Mr MANIVEL M
FACULTY,CIVIL ENGINEERING
SCHOOL OF TECHNOLOGY
PANDIT DEENDAYAL PETROLEUM UNIVERSITY
GANDHINAGAR
Introduction
• Gauge is defined as the minimum distance
between inner face two rails. Indian Railways
follows this standard practice and the gauge is
measured as the clear minimum distance
between the running faces of the two rails as
shown in Fig. 2.1.
TYPES OF GAUGES IN INDIA
The different gauges in India are of the following
these types :-
1. Broad gauge (1676),
2. Meter gauge (1000),
3. Narrow gauge (762 mm & 610 mm).
In India, efforts are being made to convert all N.G. and M.G. lines
to B.G. lines on important sections as and when funds are
available.
Permanent Way
Permanent way: The combination of rails, fitted
on sleepers with the help of fixtures and
fastenings and resting on ballast and subgrade
is called the railway track or permanent way.
Choice of Gauge
• The choice of gauge is very limited, as each
country has a fixed gauge and all new railway
lines are constructed to adhere to the
standard gauge. However, the following
factors theoretically influence the choice of
the gauge.
1.Cost Considerations:
There is only a marginal increase in the cost of the track if
a wider gauge is adopted. In this connection, the
following points are important.
(a) There is a proportional increase in the cost of
acquisition of land, earthwork, rails, sleepers, ballast,
and other track items when constructing a wider gauge.
(b) The cost of building bridges, culverts, and tunnels
increases only marginally due to a wider gauge.
(c) The cost of constructing station buildings, platforms,
staff quarters, level crossings, signals, etc. associated
with the railway network is more or less the same for all
gauges.
(d) The cost of rolling stock is independent of the gauge of
the track for carrying the same volume of traffic.
2. Traffic Considerations:
The volume of traffic depends upon the size of
wagons and the speed and hauling capacity of the
train.
(a) As a wider gauge can carry larger wagons and
coaches, it can theoretically carry more traffic.
(b) A wider gauge has a greater potential at higher
speeds, because speed is a function of the
diameter of the wheel, which in turn is limited by
the width of the gauge.
(c) The type of traction and signalling equipment
required are independent of the gauge.
3. Physical Features of the Country:
It is possible to adopt steeper gradients and
sharper curves for a narrow gauge a compared
to a wider gauge.
4. Uniformity of Gauge:
The existence of a uniform gauge in a country
enables smooth, speedy, and efficient
operation of trains. Therefore a single gauge
should be adopted irrespective of the minor
advantages of a wider gauge and the few
limitations of a narrower gauge.
Problems Caused by Change of Gauge
The need for uniformity of gauge has been
recognized by all the advanced countries of
the world. A number of problems have
cropped up in the operation of Indian Railways
because of the use of three gauges. The ill
effects of change of gauge (more popularly
known as break of gauge) are numerous;
some of these are enumerated here.
1.Inconvenience to Passengers:
Due to change of gauge, passengers have to change
trains mid-journey along with their luggage, which
causes inconvenience such as the following.
(a) Climbing stairs and crossing bridges
(b) Finding seats in the compartments of the later
trains
(c) Missing connections with the later trains in case
the earlier train is late
(d) Harassment caused by porters
(e) Transporting luggage
(f) Uncertainty and delay in reaching the destination
2. Difficulty in Trans-shipment of Goods:
Goods have to be trans-shipped at the point where
the change of gauge takes place. This causes the
following problems.
(a) Damage to goods during trans-shipment.
(b) Considerable delay in receipt of goods at the
destination.
(c) Theft or misplacement of goods during trans-
shipment and the subsequent claims.
(d) Non-availability of adequate and specialized
trans-shipment labour and staff, particularly
during strikes.
3. Inefficient Use of Rolling Stock:
As wagons have to move empty in the direction
of the trans-shipment point, they are not fully
utilized. Similarly, idle wagons of one gauge
cannot be moved on another gauge.
4. Hindrance to Fast Movement of Goods and
Passenger Traffic:
Due to change in the gauge, traffic cannot move
fast which becomes a major problem
particularly during emergencies such as war,
floods, and accidents.
5. Additional Facilities at Stations and Yards:
(a) Costly sheds and additional facilities need to be
provided for handling the large volume of goods
at trans-shipment points.
(b) Duplicate equipment and facilities such as yards
and platforms need to be provided for both
gauges at trans-shipment points.
6. Difficulties in Balanced Economic Growth:
• The difference in gauge also leads unbalanced
economic growth. This happens because
industries set up near MG/NG stations cannot
send their goods economically and efficiently to
areas being served by BG stations.
7. Difficulties in Future Gauge Conversion
Projects:
Gauge conversion is quite difficult, as it requires
enormous effort to widen existing tracks.
Widening the gauge involves heavy civil
engineering work such as widening of the
embankment, the bridges and tunnels, as well
as the tracks; additionally, a wider rolling stock
is also required. During the gauge conversion
period, there are operational problems as well
since the traffic has to be slowed down and
even suspended for a certain period is order to
execute the work.
Uni-gauge Policy of Indian Railways
The multi-gauge system is not only costly and
cumbersome but also causes serious
bottlenecks in the operation of the Railways
and hinders the balanced development of the
country. Indian Railways therefore took the
bold decision in 1992 of getting rid of the
multi-gauge system and following the unigauge
policy of adopting the broad gauge (1676 mm)
uniformly.
Benefits of Adopting BG (1676 mm) as
the Uniform Gauge
The uni-gauge system will be highly beneficial to
rail users, the railway administration, as well
as to the nation as described below.
1.No Transport Bottlenecks:
There will be no transport bottlenecks after a
uniform gauge is adopted and this will lead to
improved operational efficiency resulting in
fast movement of goods and passengers.
2.No Trans-shipment Hazards:
There will no hazards of trans-shipment and as
such no delays, no damage to goods, no
inconvenience to passengers of transfer from
one train to another train.
3.Provisions of Alternate Routes:
Through a uni-gauge policy, alternate routes will
be available for free movement of traffic and
there will be less pressure on the existing BG
network. This is expected to result in long-haul
road traffic reverting to the railways.
4.Better Turn round:
There will be a better turn round of wagons and
locomotives, and their usage will improve the
operating ratio of the railway system as a whole. As a
result the community will be benefited immensely.
5.Improved Utilization of Track:
There will be improved utilization of tracks and
reduction in the operating expenses of the railway.
6.Balanced Economic Growth:
7.No Multiple Tracking Works:
The uni-gauge project will eliminate the need for
certain traffic facilities and multiple tracking
works, which will offset the cost of gauge
conversions to a certain extent.
8.Better Transport Infrastructure:
Some of the areas served by the MG have the
potential of becoming highly industrialized;
skilled manpower is also available. The uni-
gauge policy will help in providing these areas
a better transportation infrastructure.
9.Boosting Investor’s Confidence:
With the liberalization of the economic policy,
the uni-gauge projects of the Indian Railways
have come to play a significant role. This will
help in boosting the investors’ confidence that
their goods will be distributed throughout the
country in time and without any hindrance.
This will also help in setting up industries in
areas not yet exploited because of the lack of
infrastructure facilities.
Loading gauge
 A loading gauge defines the maximum
height and width for railway vehicles and
their loads to ensure safe passage through
bridges, tunnels and other structures.
 The loading gauge determines the sizes of
passenger trains and the size of shipping
containers that can be conveyed on a
section of railway line and varies across the
world and often within a single railway
system.
Loading gauge
Construction gauge.
 By adding suitable clearance at the top
side of the loading gauge construction
gauge is obtained.
 It decides the dimensions such as
height and width of structures in
bridges and tunnels along the track
so that all wagons may pass through
them without damage to the
structures
• Thanks

More Related Content

What's hot

Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the trackT.Naga Anusha
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdfTVijayaGowri
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric designVijai Krishnan V
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationMani Vel
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of RailwaySouvik Mondal
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport EngineeringEmaan Sharma
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway EngineeringLatif Hyder Wadho
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringLatif Hyder Wadho
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringLatif Hyder Wadho
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian RailwayArbaz Kazi
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: TurnoutsVijai Krishnan V
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway EngineeringIrfan Nasir
 
Coning of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepConing of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepRAMPRASAD KUMAWAT
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD Dhruv Makadia
 

What's hot (20)

Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
 
Railway Track Maintenance
Railway Track  MaintenanceRailway Track  Maintenance
Railway Track Maintenance
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric design
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport Engineering
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
 
Railway Gauge
Railway GaugeRailway Gauge
Railway Gauge
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway Engineering
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway Engineering
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian Railway
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
 
Coning of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepConing of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail Creep
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD
 

Similar to 2.railway track gauge

Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Tushar Sonawane
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeJangid Devendra
 
Types of tracks in pakistan
Types of tracks in pakistanTypes of tracks in pakistan
Types of tracks in pakistanAYAZ AHMAD
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gaugeGaurav Jagad
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdfRESHMAFEGADE
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdfRESHMAFEGADE
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracksGowtham G
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailIRJET Journal
 
railway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptxrailway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptxRESHMAFEGADE
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieeringMani Vel
 
Rail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMateRail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMateCivil TechMate
 
Introduction, alignment & surveys
Introduction, alignment & surveysIntroduction, alignment & surveys
Introduction, alignment & surveysGARRE RAVI KUMAR
 
Rail yard container terminal
Rail yard container terminalRail yard container terminal
Rail yard container terminalKapilLamba6
 
Transport poster
Transport posterTransport poster
Transport posterGordon Best
 
Railway Engineering Introduction
Railway Engineering IntroductionRailway Engineering Introduction
Railway Engineering IntroductionT.Naga Anusha
 

Similar to 2.railway track gauge (20)

Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gauge
 
Types of tracks in pakistan
Types of tracks in pakistanTypes of tracks in pakistan
Types of tracks in pakistan
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gauge
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway.pdf
Railway.pdfRailway.pdf
Railway.pdf
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
 
railway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptxrailway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptx
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieering
 
Rail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMateRail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMate
 
Introduction, alignment & surveys
Introduction, alignment & surveysIntroduction, alignment & surveys
Introduction, alignment & surveys
 
Rail yard container terminal
Rail yard container terminalRail yard container terminal
Rail yard container terminal
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Transport poster
Transport posterTransport poster
Transport poster
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway Engineering Introduction
Railway Engineering IntroductionRailway Engineering Introduction
Railway Engineering Introduction
 
D012531923
D012531923D012531923
D012531923
 

Recently uploaded

UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentBharaniDharan195623
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate productionChinnuNinan
 

Recently uploaded (20)

UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managament
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate production
 

2.railway track gauge

  • 1. Railway Track Gauge Mr MANIVEL M FACULTY,CIVIL ENGINEERING SCHOOL OF TECHNOLOGY PANDIT DEENDAYAL PETROLEUM UNIVERSITY GANDHINAGAR
  • 2. Introduction • Gauge is defined as the minimum distance between inner face two rails. Indian Railways follows this standard practice and the gauge is measured as the clear minimum distance between the running faces of the two rails as shown in Fig. 2.1.
  • 3. TYPES OF GAUGES IN INDIA The different gauges in India are of the following these types :- 1. Broad gauge (1676), 2. Meter gauge (1000), 3. Narrow gauge (762 mm & 610 mm). In India, efforts are being made to convert all N.G. and M.G. lines to B.G. lines on important sections as and when funds are available.
  • 4. Permanent Way Permanent way: The combination of rails, fitted on sleepers with the help of fixtures and fastenings and resting on ballast and subgrade is called the railway track or permanent way.
  • 5.
  • 6. Choice of Gauge • The choice of gauge is very limited, as each country has a fixed gauge and all new railway lines are constructed to adhere to the standard gauge. However, the following factors theoretically influence the choice of the gauge.
  • 7. 1.Cost Considerations: There is only a marginal increase in the cost of the track if a wider gauge is adopted. In this connection, the following points are important. (a) There is a proportional increase in the cost of acquisition of land, earthwork, rails, sleepers, ballast, and other track items when constructing a wider gauge. (b) The cost of building bridges, culverts, and tunnels increases only marginally due to a wider gauge. (c) The cost of constructing station buildings, platforms, staff quarters, level crossings, signals, etc. associated with the railway network is more or less the same for all gauges. (d) The cost of rolling stock is independent of the gauge of the track for carrying the same volume of traffic.
  • 8. 2. Traffic Considerations: The volume of traffic depends upon the size of wagons and the speed and hauling capacity of the train. (a) As a wider gauge can carry larger wagons and coaches, it can theoretically carry more traffic. (b) A wider gauge has a greater potential at higher speeds, because speed is a function of the diameter of the wheel, which in turn is limited by the width of the gauge. (c) The type of traction and signalling equipment required are independent of the gauge.
  • 9. 3. Physical Features of the Country: It is possible to adopt steeper gradients and sharper curves for a narrow gauge a compared to a wider gauge. 4. Uniformity of Gauge: The existence of a uniform gauge in a country enables smooth, speedy, and efficient operation of trains. Therefore a single gauge should be adopted irrespective of the minor advantages of a wider gauge and the few limitations of a narrower gauge.
  • 10. Problems Caused by Change of Gauge The need for uniformity of gauge has been recognized by all the advanced countries of the world. A number of problems have cropped up in the operation of Indian Railways because of the use of three gauges. The ill effects of change of gauge (more popularly known as break of gauge) are numerous; some of these are enumerated here.
  • 11. 1.Inconvenience to Passengers: Due to change of gauge, passengers have to change trains mid-journey along with their luggage, which causes inconvenience such as the following. (a) Climbing stairs and crossing bridges (b) Finding seats in the compartments of the later trains (c) Missing connections with the later trains in case the earlier train is late (d) Harassment caused by porters (e) Transporting luggage (f) Uncertainty and delay in reaching the destination
  • 12. 2. Difficulty in Trans-shipment of Goods: Goods have to be trans-shipped at the point where the change of gauge takes place. This causes the following problems. (a) Damage to goods during trans-shipment. (b) Considerable delay in receipt of goods at the destination. (c) Theft or misplacement of goods during trans- shipment and the subsequent claims. (d) Non-availability of adequate and specialized trans-shipment labour and staff, particularly during strikes.
  • 13. 3. Inefficient Use of Rolling Stock: As wagons have to move empty in the direction of the trans-shipment point, they are not fully utilized. Similarly, idle wagons of one gauge cannot be moved on another gauge. 4. Hindrance to Fast Movement of Goods and Passenger Traffic: Due to change in the gauge, traffic cannot move fast which becomes a major problem particularly during emergencies such as war, floods, and accidents.
  • 14. 5. Additional Facilities at Stations and Yards: (a) Costly sheds and additional facilities need to be provided for handling the large volume of goods at trans-shipment points. (b) Duplicate equipment and facilities such as yards and platforms need to be provided for both gauges at trans-shipment points. 6. Difficulties in Balanced Economic Growth: • The difference in gauge also leads unbalanced economic growth. This happens because industries set up near MG/NG stations cannot send their goods economically and efficiently to areas being served by BG stations.
  • 15. 7. Difficulties in Future Gauge Conversion Projects: Gauge conversion is quite difficult, as it requires enormous effort to widen existing tracks. Widening the gauge involves heavy civil engineering work such as widening of the embankment, the bridges and tunnels, as well as the tracks; additionally, a wider rolling stock is also required. During the gauge conversion period, there are operational problems as well since the traffic has to be slowed down and even suspended for a certain period is order to execute the work.
  • 16. Uni-gauge Policy of Indian Railways The multi-gauge system is not only costly and cumbersome but also causes serious bottlenecks in the operation of the Railways and hinders the balanced development of the country. Indian Railways therefore took the bold decision in 1992 of getting rid of the multi-gauge system and following the unigauge policy of adopting the broad gauge (1676 mm) uniformly.
  • 17. Benefits of Adopting BG (1676 mm) as the Uniform Gauge The uni-gauge system will be highly beneficial to rail users, the railway administration, as well as to the nation as described below. 1.No Transport Bottlenecks: There will be no transport bottlenecks after a uniform gauge is adopted and this will lead to improved operational efficiency resulting in fast movement of goods and passengers.
  • 18. 2.No Trans-shipment Hazards: There will no hazards of trans-shipment and as such no delays, no damage to goods, no inconvenience to passengers of transfer from one train to another train. 3.Provisions of Alternate Routes: Through a uni-gauge policy, alternate routes will be available for free movement of traffic and there will be less pressure on the existing BG network. This is expected to result in long-haul road traffic reverting to the railways.
  • 19. 4.Better Turn round: There will be a better turn round of wagons and locomotives, and their usage will improve the operating ratio of the railway system as a whole. As a result the community will be benefited immensely. 5.Improved Utilization of Track: There will be improved utilization of tracks and reduction in the operating expenses of the railway. 6.Balanced Economic Growth:
  • 20. 7.No Multiple Tracking Works: The uni-gauge project will eliminate the need for certain traffic facilities and multiple tracking works, which will offset the cost of gauge conversions to a certain extent. 8.Better Transport Infrastructure: Some of the areas served by the MG have the potential of becoming highly industrialized; skilled manpower is also available. The uni- gauge policy will help in providing these areas a better transportation infrastructure.
  • 21. 9.Boosting Investor’s Confidence: With the liberalization of the economic policy, the uni-gauge projects of the Indian Railways have come to play a significant role. This will help in boosting the investors’ confidence that their goods will be distributed throughout the country in time and without any hindrance. This will also help in setting up industries in areas not yet exploited because of the lack of infrastructure facilities.
  • 22. Loading gauge  A loading gauge defines the maximum height and width for railway vehicles and their loads to ensure safe passage through bridges, tunnels and other structures.  The loading gauge determines the sizes of passenger trains and the size of shipping containers that can be conveyed on a section of railway line and varies across the world and often within a single railway system.
  • 24. Construction gauge.  By adding suitable clearance at the top side of the loading gauge construction gauge is obtained.  It decides the dimensions such as height and width of structures in bridges and tunnels along the track so that all wagons may pass through them without damage to the structures