SlideShare a Scribd company logo
1 of 39
Download to read offline
Independent expertise in depth
Guidance for good practice in bored pile and diaphragm wall
design and construction for marine structures
Contents
• Introduction
• Recent developments
• Diaphragm wall finish
• Cage detailing practice
• Tremie concreting practice
• Panel stability
• Improvements in safety
• conclusions
Introduction
Introduction
Introduction
Introduction
Introduction
Why concrete at London Gateway ?
• Illustrative design based on combi
wall
• Safer installation of DWall on dry land
• Risk of driving into very dense Thanet
Sand mitigated
• Dwalls will act as foundations for the
gantry cranes
• Steel prices high and volatile in 2007
• Much reduced steel content in DWall
Design of Diaphragm Wall
• Key challenges
• Relatively high retained height (ca.
28m lowest dredge)
• Changing ground conditions
• Complex soil-structure interaction
• Tight displacement criteria - limit
permanent change of gauge ca. 14.75
mm
• Complex load cases involving tidal lag,
crane, vessel berthing and mooring
• Crack widths limited to 0.24 mm (SLS)
in the splash zone
Thanet Sand Section
Soil Model One
London Clay Section
Soil Model Three
W E
Transition
Soil Model Two
London Gateway Port – Typical Section
Recent developments - deeper CFA
Soil Mech SF50 Fundex F3500
CFA pile reach limited by mast
height and pull back winch capacity
• Dia. 300 to 1500mm
• Length max 32 metres
Recent developments – cased CFA secant walls
Cased CFA Rotary
CFA
CFA - Secant wall examples
Cased CFA - Secant wall examples
Diaphragm walls – new horizons
100m+ wall depth
1800mm thickness
Verticality 1 in 300
C60 concrete
Rotary drum cutters
Mud Pump
Inclinometer
Guide Frame
Mud to the
desanding
plant
Mud return into the trench
after treatment
Diaphragm wall - Hydrofraise
Excavation verticality control
Hydraulically
operated
verticality
control pads
Adjust alignment
as excavation
proceeds
Diaphragm wall – Grab versus Hydrofraise comparison
Theoretical position
of wall
Re-excavate to
correct
alignment
Grab Hydrofraise
Specified limits of
deviation
Diaphragm wall – What does a finished Dwall look like?
Diaphragm wall – What does a finished Dwall look like ?
Diaphragm wall – What can a finished Dwall look like ?
Bleed channels Mud inclusion Mattressing
Diaphragm wall – Latest design and execution practice?
• Careful mix design
• Pre-start concrete trials
• Monitor concrete
production facility
• Observe good cage
detailing practice
• Follow good tremie
practice
• Slump and strength are
not sufficient testing eg.
bleed and stability tests
Diaphragm wall – latest guidance on cage detailing
Diaphragm wall – Latest guidance on cage detailing
• Final clear horizontal distance on vertical
bars at least 100 mm
• Can be reduced at laps to 80 mm
• Multiple layers of vertical bars to be lined
up behind eachother
• Final clear vertical distance on horizontal
bars at least 150 mm provided max
aggregate is 20 mm
• 3D model may be required in areas of high
congestion to avoid clashes
• Minimum distance between cages 200 mm
• Ensure nominal cover is sufficient to
achieve required design cover, to satisfy
durability requirements, allowing for
construction tolerances
Diaphragm wall – Latest guidance on tremie practice
Diaphragm wall – Latest guidance on tremie practice
• At start of pour tremie to the panel bottom and raise <200 mm
• Prior to first discharge install effective separator ie. ball or vermiculite volume
to create plug length at least 2x tremie diameter
• Discharge to all tremies simultaneously until at least 3 m depth of concrete
• Thereafter keep difference in concrete level to a minimum
• Avoid repeated raising and lowering of the tremie (surging)
• Minimum tremie embedment 3 m (may be reduced to 2 m if concrete level
accurately known)
• Excessive tremie embedment to be avoided (preferably less than 10m)
• Remember the first concrete which enters the tremie will not usually reach the
top of the pour
Trench instability
How do we check trench stability?
OVERALL STABILITY
• Limit Equilibrium Method
• Finite Element Model
• Limit Analysis
T
T
G
θ
E
Ls
H
Y
X
Z
q
σy,surcharge
q‘K0
σy,poids
Q
φ
Ls
Z Z
Fc
dS
FoS required:
1.1 to 1.3
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00
Pressure (KPa)
Depth
(m)
Active Pressure Bentonite Pressure
Trench stability example
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00
Pressure (KPa)
Depth
(m) Active Pressure Bentonite Pressure
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00
Pressure (KPa)
Depth
(m)
Active Pressure Bentonite Pressure
Add 20KPa
surcharge I.0m drop in
bentonite
level
Guidewall
depth
Potentially
unstable
Trench stability considerations
How to improve trench stability in poor ground
Standard measures
• Slurry level min 1.5m higher than
groundwater level
• Reinforcement continuity along guide
wall sections
• L-shaped guide walls
• Careful consideration of where to
position the plant
• Use short panels (single bite)
Additional measures
• Elevated guide walls (no more than 500mm)
• Increased density of support fluid
• Lower groundwater
• Ground improvement
Horizontal to vertical - Tandem lift D-wall
Temporary works rebar – very important
Additional rebar to ensure safe:
• Fabrication
• Transportation
• On and off loading
• Storage
• Lifting from horizontal to vertical
• Hanging
• splicing
All elements require design e.g. bars,
welds and connectors
Horizontal to vertical lift – tandem lift
Tandem lifting points
@ top of z bars and cathedral bar
• Were developed to splice ropes, not
reinforcement bars
• Must use lowest tested strength and
robust procedure due to high
variation of tensile strength results
Cage splicing - Bulldog grips
New cage splicing systems - SuperlatchTM
• Size of
superlatch
varies with cage
weight
• No fingers in
cage
• Expensive but
safe
Improvements in safe working – platforms and barriers
Conclusions
• Cast in situ concrete diaphragm and secant pile walls have many potential
applications in marine works
• Diaphragm walls in particular have been used on many quay wall projects
• Plant and material developments have brought opportunities and risks
• Recently published industry guidance designed to achieve better outcomes
in terms of quality and safety
• Good practice should be shared by all

More Related Content

What's hot

TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSMaharshi Dave
 
Tremie concreting
Tremie concretingTremie concreting
Tremie concretingpriyank 59
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentationSevar Dilkhaz
 
Analysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundationAnalysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundationMonojit Mondal
 
Presuremeter presentation
Presuremeter presentationPresuremeter presentation
Presuremeter presentationSarfraz Abro
 
Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures kamariya keyur
 
Introduction to Foundation Engineering
Introduction to Foundation EngineeringIntroduction to Foundation Engineering
Introduction to Foundation EngineeringLatif Hyder Wadho
 
Shallow foundation(by indrajit mitra)01
Shallow   foundation(by indrajit mitra)01Shallow   foundation(by indrajit mitra)01
Shallow foundation(by indrajit mitra)01Indrajit Ind
 
Geotechnical engineering 2
Geotechnical engineering   2Geotechnical engineering   2
Geotechnical engineering 2R VIJAYAKUMAR
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)S M Rahat Rahman
 
Factors affecting the strenght of concrete
Factors affecting the strenght of concreteFactors affecting the strenght of concrete
Factors affecting the strenght of concreteMUBARAKALI111
 
shallow foundation
shallow foundationshallow foundation
shallow foundationJNTUK
 

What's hot (20)

TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONS
 
Tremie concreting
Tremie concretingTremie concreting
Tremie concreting
 
Shallow Foundation
Shallow FoundationShallow Foundation
Shallow Foundation
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
 
Analysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundationAnalysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundation
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
 
Presuremeter presentation
Presuremeter presentationPresuremeter presentation
Presuremeter presentation
 
Secant pile wall for emergency dump pond
Secant pile wall for emergency dump pondSecant pile wall for emergency dump pond
Secant pile wall for emergency dump pond
 
Compaction grouting hassan
Compaction  grouting hassanCompaction  grouting hassan
Compaction grouting hassan
 
Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures
 
Underwater concrete
Underwater concreteUnderwater concrete
Underwater concrete
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Introduction to Foundation Engineering
Introduction to Foundation EngineeringIntroduction to Foundation Engineering
Introduction to Foundation Engineering
 
Shallow foundation(by indrajit mitra)01
Shallow   foundation(by indrajit mitra)01Shallow   foundation(by indrajit mitra)01
Shallow foundation(by indrajit mitra)01
 
Geotechnical engineering 2
Geotechnical engineering   2Geotechnical engineering   2
Geotechnical engineering 2
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)
 
Factors affecting the strenght of concrete
Factors affecting the strenght of concreteFactors affecting the strenght of concrete
Factors affecting the strenght of concrete
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
shallow foundation
shallow foundationshallow foundation
shallow foundation
 

Similar to D-wall Presentation - Rebar Cage.pdf

Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptVaibhavSoni742163
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptHarshKumarEname
 
D wall construction
D wall constructionD wall construction
D wall constructionanuragrikku
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technologyAnjith Augustine
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsMitaliShelke
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSjagrutib22
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTSsrinivas cnu
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologyLTDH2013
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
Materials of sewer
Materials of sewerMaterials of sewer
Materials of sewerFAISAL A
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimneyAxay Sharma
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 

Similar to D-wall Presentation - Rebar Cage.pdf (20)

Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Retaining wall (1)
Retaining wall (1)Retaining wall (1)
Retaining wall (1)
 
D wall construction
D wall constructionD wall construction
D wall construction
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technology
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Materials of sewer
Materials of sewerMaterials of sewer
Materials of sewer
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 

Recently uploaded

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 

Recently uploaded (20)

Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 

D-wall Presentation - Rebar Cage.pdf

  • 1. Independent expertise in depth Guidance for good practice in bored pile and diaphragm wall design and construction for marine structures
  • 2. Contents • Introduction • Recent developments • Diaphragm wall finish • Cage detailing practice • Tremie concreting practice • Panel stability • Improvements in safety • conclusions
  • 8. Why concrete at London Gateway ? • Illustrative design based on combi wall • Safer installation of DWall on dry land • Risk of driving into very dense Thanet Sand mitigated • Dwalls will act as foundations for the gantry cranes • Steel prices high and volatile in 2007 • Much reduced steel content in DWall
  • 9. Design of Diaphragm Wall • Key challenges • Relatively high retained height (ca. 28m lowest dredge) • Changing ground conditions • Complex soil-structure interaction • Tight displacement criteria - limit permanent change of gauge ca. 14.75 mm • Complex load cases involving tidal lag, crane, vessel berthing and mooring • Crack widths limited to 0.24 mm (SLS) in the splash zone
  • 10. Thanet Sand Section Soil Model One London Clay Section Soil Model Three W E Transition Soil Model Two
  • 11. London Gateway Port – Typical Section
  • 12. Recent developments - deeper CFA Soil Mech SF50 Fundex F3500 CFA pile reach limited by mast height and pull back winch capacity • Dia. 300 to 1500mm • Length max 32 metres
  • 13. Recent developments – cased CFA secant walls Cased CFA Rotary CFA
  • 14. CFA - Secant wall examples
  • 15. Cased CFA - Secant wall examples
  • 16. Diaphragm walls – new horizons 100m+ wall depth 1800mm thickness Verticality 1 in 300 C60 concrete
  • 17. Rotary drum cutters Mud Pump Inclinometer Guide Frame Mud to the desanding plant Mud return into the trench after treatment Diaphragm wall - Hydrofraise
  • 19. Adjust alignment as excavation proceeds Diaphragm wall – Grab versus Hydrofraise comparison Theoretical position of wall Re-excavate to correct alignment Grab Hydrofraise Specified limits of deviation
  • 20. Diaphragm wall – What does a finished Dwall look like?
  • 21. Diaphragm wall – What does a finished Dwall look like ?
  • 22. Diaphragm wall – What can a finished Dwall look like ? Bleed channels Mud inclusion Mattressing
  • 23. Diaphragm wall – Latest design and execution practice? • Careful mix design • Pre-start concrete trials • Monitor concrete production facility • Observe good cage detailing practice • Follow good tremie practice • Slump and strength are not sufficient testing eg. bleed and stability tests
  • 24. Diaphragm wall – latest guidance on cage detailing
  • 25. Diaphragm wall – Latest guidance on cage detailing • Final clear horizontal distance on vertical bars at least 100 mm • Can be reduced at laps to 80 mm • Multiple layers of vertical bars to be lined up behind eachother • Final clear vertical distance on horizontal bars at least 150 mm provided max aggregate is 20 mm • 3D model may be required in areas of high congestion to avoid clashes • Minimum distance between cages 200 mm • Ensure nominal cover is sufficient to achieve required design cover, to satisfy durability requirements, allowing for construction tolerances
  • 26. Diaphragm wall – Latest guidance on tremie practice
  • 27. Diaphragm wall – Latest guidance on tremie practice • At start of pour tremie to the panel bottom and raise <200 mm • Prior to first discharge install effective separator ie. ball or vermiculite volume to create plug length at least 2x tremie diameter • Discharge to all tremies simultaneously until at least 3 m depth of concrete • Thereafter keep difference in concrete level to a minimum • Avoid repeated raising and lowering of the tremie (surging) • Minimum tremie embedment 3 m (may be reduced to 2 m if concrete level accurately known) • Excessive tremie embedment to be avoided (preferably less than 10m) • Remember the first concrete which enters the tremie will not usually reach the top of the pour
  • 29. How do we check trench stability? OVERALL STABILITY • Limit Equilibrium Method • Finite Element Model • Limit Analysis T T G θ E Ls H Y X Z q σy,surcharge q‘K0 σy,poids Q φ Ls Z Z Fc dS FoS required: 1.1 to 1.3
  • 30. 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 Pressure (KPa) Depth (m) Active Pressure Bentonite Pressure Trench stability example
  • 31. 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 Pressure (KPa) Depth (m) Active Pressure Bentonite Pressure 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 Pressure (KPa) Depth (m) Active Pressure Bentonite Pressure Add 20KPa surcharge I.0m drop in bentonite level Guidewall depth Potentially unstable Trench stability considerations
  • 32. How to improve trench stability in poor ground Standard measures • Slurry level min 1.5m higher than groundwater level • Reinforcement continuity along guide wall sections • L-shaped guide walls • Careful consideration of where to position the plant • Use short panels (single bite) Additional measures • Elevated guide walls (no more than 500mm) • Increased density of support fluid • Lower groundwater • Ground improvement
  • 33. Horizontal to vertical - Tandem lift D-wall
  • 34. Temporary works rebar – very important Additional rebar to ensure safe: • Fabrication • Transportation • On and off loading • Storage • Lifting from horizontal to vertical • Hanging • splicing All elements require design e.g. bars, welds and connectors
  • 35. Horizontal to vertical lift – tandem lift Tandem lifting points @ top of z bars and cathedral bar
  • 36. • Were developed to splice ropes, not reinforcement bars • Must use lowest tested strength and robust procedure due to high variation of tensile strength results Cage splicing - Bulldog grips
  • 37. New cage splicing systems - SuperlatchTM • Size of superlatch varies with cage weight • No fingers in cage • Expensive but safe
  • 38. Improvements in safe working – platforms and barriers
  • 39. Conclusions • Cast in situ concrete diaphragm and secant pile walls have many potential applications in marine works • Diaphragm walls in particular have been used on many quay wall projects • Plant and material developments have brought opportunities and risks • Recently published industry guidance designed to achieve better outcomes in terms of quality and safety • Good practice should be shared by all