A PROJECT REPORT
ON
PLANNING AND DESIGN OF TWO-STOREY RESIDENTIAL
BUILDING ALONG WITH DETAILED ESTIMATE
SUBMITTED IN PARTIAL FULFILLMENT OF THE
REQUIREMENTS FOR THE AWARD OF
DIPLOMA IN CIVIL ENGINEERING
(2018 – 2021 )
YOGESH MEENA
SPN:CE20180055/008
Mr. RA NJAN KUMAR
SUBMITTED TO
SUBMITTED BY
INDEX
Acknowledgement
Candidate Declaration
Section-1 Introduction
Introduction
Section-2 Types Of Building
Residential Building
Section-3 Planning and
Building Planning
Orientation, Principal Of Planning, Aspect, Prospect, Circulation
Roominess, Grouping, ,Elegance, Sanitation, Flexibility, Economy
Section-4 Building Bye Law
Minimum Height and Size, Lightning and Ventilation, Built Up
Area
Section-5 Plan Design
Ground Floor Design, First Floor Plan, Ground Floor Sanitary
Layout, First Floor Sanitary Layout, Ground Floor Electricity Layout,
First Floor Electricity Layout, Sectional View
Section-6 Design Of Beam
Section-7 Design Of Slab
Section-8 Design Of Column
Section-9 Rectangular Footing
Section-10 Load Calculation
Section-11 Estimation
Finish
GOVERNMENT RAMCHANDRA KHAITAN POLYTECHNIC COLLEGE, JAIPUR
ACKNOWLEDGMENT
We are really thankful to the HOD RAKESH ASWAL, CIVIL ENGINEERING,
Govt. Ram Chandra Khaitan Polytechnic, Jaipur, for their invaluable
guidance and assistance, without which the accomplishment of the task
would have never been possible.
We also want to thank DEEPAK KHANDELWAL SIR,AND RANJAN KUMAR
SIR for giving us this opportunity and help to complete our project work
within limited time f rame.
We are also thankful to our parents, friends and all staff of CIVIL
ENGINEERING for providing us relevant information, necessary
clarifications, and great support.
YOGESH MEENA
CE20180055/008
CIVIL ENGINEERING
III YEAR
CANDIDATE DECLARATION
I Yogesh Meena declares that the work
presented in this report.
In partial fulfillment of requirement for the
award of Diploma' submitted in the
Department of Civil Engineering at Govt. R.C.
Khaitan Polytechnic College Jaipur, is an
authentic record of my own work under the
supervision of Mr. Ranjan Kumar Sir.
Mr. Ranjan Kumar
Lecturer
Civil Engineering Department
YOGESH MEENA
CE20180055/008
CIVIL ENGINEERING
III YEAR
INTRODUCTION
The basics needs of human existences are food, clothing’s & shelter. From
times immemorial man has been making efforts in improving their standard
of living. The point of his efforts has been to provide an economic and
efficient shelter. The possession of shelter besides being a basic, used, gives
a feeling of security, responsibility and shown the social status of man.
Every human being has an inherent liking for a peaceful environment
needed for his pleasant living, this object is achieved by having a place of
living situated at the safe and convenient location, such a place for
comfortable and pleasant living requires considered and kept in view.
■ A Peaceful environment.
■ Safety from all natural source & climate conditions
■General facilities for community of his residential area.
The engineer has to keep in mind the municipal conditions, building
bye laws, environment, financial capacity, water supply, sewage
arrangement, provision of future, aeration, ventilation etc., in suggestion
a particular type of plan to any client.
TYPES OF BUILDING
Buildings are classified on the basis of character of occupancy and type of
use as.
1.1.1-Residential Building
1.1.2-Educational Building
1.1.3-Institutional Building
1.1.4-Industrial Building
1.1.1-RESIDENTIAL BUILDING:
In such building sleeping accommodation is provided. IT includes the living
room, bed room, kitchen, hall, toilet and bath room. It may be a single
storey building or apartments.
1.1.2-EDUCATIONAL BUILDING:
These includes any building using for school, college, assembly
for instruction, education or recreation.
1.1.3-INSTITUTIONAL BUILDING:
These building are used for different purposes, such as medical or other
treatment or care of a person suffering from a physical or mental
illnesses. These building includes hospital, sanatoria, jail etc.
1.1.4-INDUSTRIAL BUILDING:
These are buildings in which products or material s of all kind of
properties are fabricated, assembled, processed. For example refineries,
gas plant, mills etc.
• It is the process of thinking about and organization the activities
required to acheive desired goal.
• Building planning is the arrangement of various component or unit of a building in a systematic manner so as to form a meaningful and
homogeneous structure to meet its functional purpose.
PLANNING AND BUILDING PLANING
FACTORS AFFECTING PLANNING OF BUILDING
•
•
•
•
•
Function of building (residential, public, commercial, industrial etc.
Shape and size of the plot
Topography
Climatic condition
Buildingbye-lawetc.
Orientation
•
•
Orientation means placing so as to face East.
Proper placement of component
wind and rain which enables the
feature of nature.
Factor affecting orientation are:
of building with respect to sun,
inmates to enjoy the desirable
•
•
•
•
Temperature
Wind
Humidity
PrincipalOfPlanning
• Aspect
• Prospect
• Circulation
• Roominess
• Elegance
• Sanitation
• Flexibility
• Economy
Aspect
• Placement of different rooms of house
different hours of day.
Rooms should get enough sunlight and
in accordance with our activities at
• air, which gives,
•
•
•
Great environment
Comfort
etc
A room which receives light & air from particular direction
'aspect' of that direction.
is said to have
•
Prospect
•
•
Prospect is the view from outside of a house.
The house should have a proper prospect so that it can give a feeling
of cheerfulness to the people living in it .
• It should create a good impression on a person who views it from
outside.
• It must also possess good qualities like comfort, cheerfulness,
security, labour saving and modern outlook.
For e.g. Small Projections or bay window can have a good out-look as
well as helps in providing breeze, light and sunlight to the room.
•
Circulation
• Circulation is movement within the premises
horizontal and vertical circulation.
Horizontal circulation (room to room)
and includes both
•
•
•
•
Passage
Corridors
Lobbies etc.
• Vertical circulation (floor to floor)
• Stairs
Roominess
• Roominess means getting maximum
dimension of the room.
advantage from the minimum
• The effect
width and
The shape
of roominess depend on
height of room.
and size of the room are
the relative dimension of length,
• also very important for
more roominess then square
roominess. A rectangular room has
room •
in same area.
Grouping
• Grouping means
the convenience
the arrangement
of user.
of various rooms in the building for
• It minimizes the circulation and
comfort.
A dinning room should be close
from kitchen, but convenient to
at the same time improves the
• to kitchen ,while sanitary be away
bed rooms.
Sanitation
• It includes providing light ,ventilation, cleanliness, water supply and
sanitary amenities.
For residential building window area should not less then 1/10" of
floor area.
•
Elegance
• Elegance is grand appearance of a building attained mainly owing
the elevation which in turn depends on the plan.
It depends upon proper positioning/selection of doors, windows,
balcony, roofs, staircase etc.
For better elegance
to
•
•
• Selecting superior building material for facing as polished stone- granite,
marble or mosaic.
Providing projection like sunshades, balconies, porch with or without pergola
•
open.ng.
i
• Providing bay window, corner window, etc.
Flexibility
• Flexibility means that a
for
for
room
one
which is planned
function be used
other, if required.
• Like study room may be
planned for using guest
room. Etc ..
Economy
• The building should have minimum floor
will reduce cost of the building .hence, it
Economy can achieved by:
area with maximum
will be economical.
utility.it
•
•
•
•
Providing simple elevation.
Reducing the storey height.
Dispensing of porches, lobbies and balconie
The various aspects of building activities
bye-laws are under:
covered by
•
•
•
•
Built up area limitations.
Norms related to height or sizes of rooms.
Lighting & ventilation of rooms.
Building services.
Building Bye Law
•
•
•
•
•
HABITABLE ROOMS- 2.75 M.
KITCHEN- 2.75 M.
BATH ROOMS- 2.4 M.
W C - 2 . 4 M .
PLINTH LEVEL- 30 CM.
Minimum Height of Different Part of Building
Minimum Size of Different Part of Building
LIGHTING AND VENTILATION OF ROOMS
•
•
•
1/10 OF FLOOR AREA IN DRY HOT CLIMATE.
1/7W OF FLOOR AREA IN WET HOT CLIMATE.
AREA OF DOORS & WINDOWS IN A ROOM IS NOT
LESS THAN L/7IH OF FLOOR AREA.
BUILT UP AREA LIMITATION
• BUILTUP AREA OR COVERED AREA OF A BUILDING ON GROUND•
THE
PLOT AREA-AREA OF OPEN SPACES AROUND
BUILDING.
• F.A.R (FLOOR AREA RATIO):-
F.A.R == COVERED AREA OF ALL FLOORS
PLOT AREA
Plan Design
DESIGN OF BEAM
DESIGN OF SLAB
DESIGN OF FOOTING
LOAD CALCULATION
Estimation
 Earth work in Excavation in foundation
1.5 Lift, 50m lead
Volume of Excavation = 291.6 cu.m
Rate of Excavation = 247m/cu.m
Total Cost of Excavation
=247x291.8
=72025₹
 Concrete Work
P.C.C in foundation (1:4:8)
Depth 10m
Volume of P.C.C Work = 18cu.m
Rate Of Concrete Work = 3002.00 ₹/cu.m
=3002.00x18
=54036
Volume of Dry Concrete = 1.54x18
= 27.72 cu.m
Cement = 27.72x1/13 = 2.132 cu.m (63 Bags)
Sand = 27.72x4/13 = 8.529 cu.m
Coarse Agg. = 27.72x8/13 = 17.058
 R.C.C Work in Footing
M20 (1:1.5:3) Depth= 0.620m
Volume of R.C.C in footing = 91.660 cu.m
Rate of R.C.C in footing = 91.660cu.m
Rate of R.R.C Work = 4485 ₹/cu.m
Total Cost of R.C.C work in footing
=91.660x4485
=4.110 lakh
Volume of dry concrete = 1.54x91.660
=141.156cu.m
Cement = 141.156x1/5.5 = 25.664 cu.m (7.55 Bags)
Sand = 141x1.5/5.5 = 38.497 cu.m
Coarse Agg. = 141.156x/1.5 = 76.994 cu.m
 R.C.C. Work in Column
M25 (1:1:2)
Volume of R.C.C in column = 14.456 cu.m
Rate of R.R.C Work = 4483 ₹/cu.m
Total Cost of R.C.C work in column =
=4485x140546
=65238₹
Volume of dry concrete = 1.54x14.546
=22.400cu.m
Cement = 22.4x1/4 = 5.6 cu.m (165 Bags)
Sand = 22.4x1/4 = 5.6
Coarse Agg. = 22.4x2/4 = 11.2
 R.C.C Work In Beam
M25 (1:1:2)
Volume of R.C.C in Beam = 21.279 cu.m
Rate of R.R.C Work = 4485₹/cu.m
Total Cost of R.C.C work in Beam =
=21.279x4485
=95436₹
 R.C.C Work in Slab
M25 (1:1:2)
Volume of R.C.C in Slab = 48.072cu.m
Rate of R.R.C Work = 5099₹/ cu.m
Total Cost of R.C.C work in slab =
= 48.072x5099
=245119₹
 R.C.C Work in Tied Beam
M25 (1:1:2)
Volume of R.C.C in Beam = 5.144cu.m
Rate of R.R.C Work = 4485₹/ cu.m
Total Cost of R.C.C work in tied beam =
= 5.144x4485
=23070₹
 Brick Work
Cement Mortar (1:6), Size of Brick 919cm x 9cm x 9cm)
Volume of Brick Work = 111.546 cu.m
Rate of Brick Work = 3875.00 ₹/cu.m
Total Cost of Brick Work
=111.546x3876
432240₹
 Flooring
Area of Tile Flooring = 486.57sq.m
Rate of Tile Flooring = 493 sq.m
Cost of Tile Flooring
=436.57x493
=215229.01m
 Plastering {12mm thick (1:6) }
Area of Plastering = 847.868 sq.m
Rate of Plastering = 133₹/sq.m
Cost of Plastering
= 133x847.868
= 112766₹
 Total Cost = 1726159₹
Contengecies Charge (5%)
=5x1726159/100
=86307.95₹
 Electrification Charge (8%)
= 8x1726159/100
138092₹
 Water Supply & Sanitation (8%)
= 8x1726159/100
138092₹
 Contractor Profit (15%)
=15x1726159/100
=258923.85₹
 Work Charge (2%)
= 2x1726159/100
=34523₹
 Tools & Plants (1.5%)
=1.5x1726159/100
=25892.385
Total Cost = 2407990₹
Civil Diploma Industrial Training Report
Civil Diploma Industrial Training Report
Civil Diploma Industrial Training Report
Civil Diploma Industrial Training Report
Civil Diploma Industrial Training Report
Civil Diploma Industrial Training Report

More Related Content

What's hot

training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th sem
Rajat kashv
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
Abhishek Singh
 

What's hot (20)

PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
PPT on Commerical building
PPT on Commerical buildingPPT on Commerical building
PPT on Commerical building
 
final year civil engineering training report
final year civil engineering training report final year civil engineering training report
final year civil engineering training report
 
Industrial Training report Civil Engineering.
Industrial Training report Civil Engineering.Industrial Training report Civil Engineering.
Industrial Training report Civil Engineering.
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th sem
 
training report on commercial building
training report on commercial buildingtraining report on commercial building
training report on commercial building
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
PPT on industrial summer training in civil engineer
PPT  on industrial summer training in civil engineer PPT  on industrial summer training in civil engineer
PPT on industrial summer training in civil engineer
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
Apartment building construction project report
Apartment building construction project reportApartment building construction project report
Apartment building construction project report
 
Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”
 

Similar to Civil Diploma Industrial Training Report

Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
Rai University
 

Similar to Civil Diploma Industrial Training Report (20)

principles of Building planning (BTP) (ECE)
principles of Building planning (BTP) (ECE)principles of Building planning (BTP) (ECE)
principles of Building planning (BTP) (ECE)
 
Ch 8 building planning
Ch 8 building planningCh 8 building planning
Ch 8 building planning
 
Building planning
Building planningBuilding planning
Building planning
 
Architectural Aspects Of Building Planning
Architectural Aspects Of Building Planning Architectural Aspects Of Building Planning
Architectural Aspects Of Building Planning
 
Planning for the built environment ppt
Planning for the built environment  pptPlanning for the built environment  ppt
Planning for the built environment ppt
 
Basic Civil and Environmental Engineering (BCEE)_Unit 5_SPPU_Planning for the...
Basic Civil and Environmental Engineering (BCEE)_Unit 5_SPPU_Planning for the...Basic Civil and Environmental Engineering (BCEE)_Unit 5_SPPU_Planning for the...
Basic Civil and Environmental Engineering (BCEE)_Unit 5_SPPU_Planning for the...
 
Building Bye-laws
Building  Bye-lawsBuilding  Bye-laws
Building Bye-laws
 
MODULE 2 Introduction and Town Planning.pptx
MODULE 2 Introduction and Town Planning.pptxMODULE 2 Introduction and Town Planning.pptx
MODULE 2 Introduction and Town Planning.pptx
 
Building planning
Building planningBuilding planning
Building planning
 
Niharika Jain,Residential Designer
Niharika Jain,Residential DesignerNiharika Jain,Residential Designer
Niharika Jain,Residential Designer
 
BPD Unit 1 to 6 ppt.pptx
BPD Unit 1 to 6 ppt.pptxBPD Unit 1 to 6 ppt.pptx
BPD Unit 1 to 6 ppt.pptx
 
Principles of planning 1.pptx
Principles of planning 1.pptxPrinciples of planning 1.pptx
Principles of planning 1.pptx
 
unit-1.pdf
unit-1.pdfunit-1.pdf
unit-1.pdf
 
A Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingA Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment Building
 
functional requirement of building
functional requirement of buildingfunctional requirement of building
functional requirement of building
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
 
Green Building Index
Green Building IndexGreen Building Index
Green Building Index
 
Lecture5 principles of planning
Lecture5 principles of planningLecture5 principles of planning
Lecture5 principles of planning
 

More from Department of Management Studies, Malaviya National Institute of Technology Jaipur

Investment Avenues in India
Investment Avenues in IndiaInvestment Avenues in India

More from Department of Management Studies, Malaviya National Institute of Technology Jaipur (16)

Consumer Protection and Consumers Rights
Consumer Protection and Consumers RightsConsumer Protection and Consumers Rights
Consumer Protection and Consumers Rights
 
Sample Resume Freshers - Business Analytics/Business Consultant
Sample Resume Freshers - Business Analytics/Business ConsultantSample Resume Freshers - Business Analytics/Business Consultant
Sample Resume Freshers - Business Analytics/Business Consultant
 
We Care For You- Sample Pitch Deck
We Care For You- Sample Pitch DeckWe Care For You- Sample Pitch Deck
We Care For You- Sample Pitch Deck
 
Social Media Marketing- Conceptual Study
Social Media Marketing- Conceptual StudySocial Media Marketing- Conceptual Study
Social Media Marketing- Conceptual Study
 
An Analysis on Union Budget
An Analysis on Union BudgetAn Analysis on Union Budget
An Analysis on Union Budget
 
Business Analytics For Managers Brochure
Business Analytics For Managers BrochureBusiness Analytics For Managers Brochure
Business Analytics For Managers Brochure
 
Derivatives - Payoff
Derivatives - Payoff Derivatives - Payoff
Derivatives - Payoff
 
Investment Avenues in India
Investment Avenues in IndiaInvestment Avenues in India
Investment Avenues in India
 
Case- Uber vs. Didi
Case- Uber vs. DidiCase- Uber vs. Didi
Case- Uber vs. Didi
 
Bad Boy Billionaries
Bad Boy BillionariesBad Boy Billionaries
Bad Boy Billionaries
 
Report: Tips to Make Your Resume and Interview Performance Stand Out
Report: Tips to Make Your Resume and Interview Performance Stand OutReport: Tips to Make Your Resume and Interview Performance Stand Out
Report: Tips to Make Your Resume and Interview Performance Stand Out
 
Case Study- Times have Changed
Case Study- Times have ChangedCase Study- Times have Changed
Case Study- Times have Changed
 
Dabbawala's Management Practices
Dabbawala's Management PracticesDabbawala's Management Practices
Dabbawala's Management Practices
 
Introduction to Management Accounting
Introduction to Management AccountingIntroduction to Management Accounting
Introduction to Management Accounting
 
The Power Of Your Subconscious Mind
The Power Of Your Subconscious MindThe Power Of Your Subconscious Mind
The Power Of Your Subconscious Mind
 
24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA
24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA
24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA
 

Recently uploaded

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 

Recently uploaded (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 

Civil Diploma Industrial Training Report

  • 1. A PROJECT REPORT ON PLANNING AND DESIGN OF TWO-STOREY RESIDENTIAL BUILDING ALONG WITH DETAILED ESTIMATE SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF DIPLOMA IN CIVIL ENGINEERING (2018 – 2021 ) YOGESH MEENA SPN:CE20180055/008 Mr. RA NJAN KUMAR SUBMITTED TO SUBMITTED BY
  • 2. INDEX Acknowledgement Candidate Declaration Section-1 Introduction Introduction Section-2 Types Of Building Residential Building Section-3 Planning and Building Planning Orientation, Principal Of Planning, Aspect, Prospect, Circulation Roominess, Grouping, ,Elegance, Sanitation, Flexibility, Economy Section-4 Building Bye Law Minimum Height and Size, Lightning and Ventilation, Built Up Area Section-5 Plan Design Ground Floor Design, First Floor Plan, Ground Floor Sanitary Layout, First Floor Sanitary Layout, Ground Floor Electricity Layout, First Floor Electricity Layout, Sectional View Section-6 Design Of Beam Section-7 Design Of Slab Section-8 Design Of Column Section-9 Rectangular Footing Section-10 Load Calculation Section-11 Estimation Finish
  • 3. GOVERNMENT RAMCHANDRA KHAITAN POLYTECHNIC COLLEGE, JAIPUR ACKNOWLEDGMENT We are really thankful to the HOD RAKESH ASWAL, CIVIL ENGINEERING, Govt. Ram Chandra Khaitan Polytechnic, Jaipur, for their invaluable guidance and assistance, without which the accomplishment of the task would have never been possible. We also want to thank DEEPAK KHANDELWAL SIR,AND RANJAN KUMAR SIR for giving us this opportunity and help to complete our project work within limited time f rame. We are also thankful to our parents, friends and all staff of CIVIL ENGINEERING for providing us relevant information, necessary clarifications, and great support. YOGESH MEENA CE20180055/008 CIVIL ENGINEERING III YEAR
  • 4. CANDIDATE DECLARATION I Yogesh Meena declares that the work presented in this report. In partial fulfillment of requirement for the award of Diploma' submitted in the Department of Civil Engineering at Govt. R.C. Khaitan Polytechnic College Jaipur, is an authentic record of my own work under the supervision of Mr. Ranjan Kumar Sir. Mr. Ranjan Kumar Lecturer Civil Engineering Department YOGESH MEENA CE20180055/008 CIVIL ENGINEERING III YEAR
  • 5. INTRODUCTION The basics needs of human existences are food, clothing’s & shelter. From times immemorial man has been making efforts in improving their standard of living. The point of his efforts has been to provide an economic and efficient shelter. The possession of shelter besides being a basic, used, gives a feeling of security, responsibility and shown the social status of man. Every human being has an inherent liking for a peaceful environment needed for his pleasant living, this object is achieved by having a place of living situated at the safe and convenient location, such a place for comfortable and pleasant living requires considered and kept in view. ■ A Peaceful environment. ■ Safety from all natural source & climate conditions ■General facilities for community of his residential area. The engineer has to keep in mind the municipal conditions, building bye laws, environment, financial capacity, water supply, sewage arrangement, provision of future, aeration, ventilation etc., in suggestion a particular type of plan to any client.
  • 6. TYPES OF BUILDING Buildings are classified on the basis of character of occupancy and type of use as. 1.1.1-Residential Building 1.1.2-Educational Building 1.1.3-Institutional Building 1.1.4-Industrial Building 1.1.1-RESIDENTIAL BUILDING: In such building sleeping accommodation is provided. IT includes the living room, bed room, kitchen, hall, toilet and bath room. It may be a single storey building or apartments. 1.1.2-EDUCATIONAL BUILDING: These includes any building using for school, college, assembly for instruction, education or recreation. 1.1.3-INSTITUTIONAL BUILDING: These building are used for different purposes, such as medical or other treatment or care of a person suffering from a physical or mental illnesses. These building includes hospital, sanatoria, jail etc. 1.1.4-INDUSTRIAL BUILDING: These are buildings in which products or material s of all kind of properties are fabricated, assembled, processed. For example refineries, gas plant, mills etc.
  • 7. • It is the process of thinking about and organization the activities required to acheive desired goal. • Building planning is the arrangement of various component or unit of a building in a systematic manner so as to form a meaningful and homogeneous structure to meet its functional purpose. PLANNING AND BUILDING PLANING FACTORS AFFECTING PLANNING OF BUILDING • • • • • Function of building (residential, public, commercial, industrial etc. Shape and size of the plot Topography Climatic condition Buildingbye-lawetc.
  • 8. Orientation • • Orientation means placing so as to face East. Proper placement of component wind and rain which enables the feature of nature. Factor affecting orientation are: of building with respect to sun, inmates to enjoy the desirable • • • • Temperature Wind Humidity
  • 9. PrincipalOfPlanning • Aspect • Prospect • Circulation • Roominess • Elegance • Sanitation • Flexibility • Economy
  • 10. Aspect • Placement of different rooms of house different hours of day. Rooms should get enough sunlight and in accordance with our activities at • air, which gives, • • • Great environment Comfort etc A room which receives light & air from particular direction 'aspect' of that direction. is said to have •
  • 11. Prospect • • Prospect is the view from outside of a house. The house should have a proper prospect so that it can give a feeling of cheerfulness to the people living in it . • It should create a good impression on a person who views it from outside. • It must also possess good qualities like comfort, cheerfulness, security, labour saving and modern outlook. For e.g. Small Projections or bay window can have a good out-look as well as helps in providing breeze, light and sunlight to the room. •
  • 12.
  • 13. Circulation • Circulation is movement within the premises horizontal and vertical circulation. Horizontal circulation (room to room) and includes both • • • • Passage Corridors Lobbies etc. • Vertical circulation (floor to floor) • Stairs
  • 14. Roominess • Roominess means getting maximum dimension of the room. advantage from the minimum • The effect width and The shape of roominess depend on height of room. and size of the room are the relative dimension of length, • also very important for more roominess then square roominess. A rectangular room has room • in same area.
  • 15. Grouping • Grouping means the convenience the arrangement of user. of various rooms in the building for • It minimizes the circulation and comfort. A dinning room should be close from kitchen, but convenient to at the same time improves the • to kitchen ,while sanitary be away bed rooms. Sanitation • It includes providing light ,ventilation, cleanliness, water supply and sanitary amenities. For residential building window area should not less then 1/10" of floor area. •
  • 16. Elegance • Elegance is grand appearance of a building attained mainly owing the elevation which in turn depends on the plan. It depends upon proper positioning/selection of doors, windows, balcony, roofs, staircase etc. For better elegance to • • • Selecting superior building material for facing as polished stone- granite, marble or mosaic. Providing projection like sunshades, balconies, porch with or without pergola • open.ng. i • Providing bay window, corner window, etc.
  • 17. Flexibility • Flexibility means that a for for room one which is planned function be used other, if required. • Like study room may be planned for using guest room. Etc ..
  • 18. Economy • The building should have minimum floor will reduce cost of the building .hence, it Economy can achieved by: area with maximum will be economical. utility.it • • • • Providing simple elevation. Reducing the storey height. Dispensing of porches, lobbies and balconie
  • 19. The various aspects of building activities bye-laws are under: covered by • • • • Built up area limitations. Norms related to height or sizes of rooms. Lighting & ventilation of rooms. Building services. Building Bye Law
  • 20. • • • • • HABITABLE ROOMS- 2.75 M. KITCHEN- 2.75 M. BATH ROOMS- 2.4 M. W C - 2 . 4 M . PLINTH LEVEL- 30 CM. Minimum Height of Different Part of Building Minimum Size of Different Part of Building
  • 21. LIGHTING AND VENTILATION OF ROOMS • • • 1/10 OF FLOOR AREA IN DRY HOT CLIMATE. 1/7W OF FLOOR AREA IN WET HOT CLIMATE. AREA OF DOORS & WINDOWS IN A ROOM IS NOT LESS THAN L/7IH OF FLOOR AREA.
  • 22. BUILT UP AREA LIMITATION • BUILTUP AREA OR COVERED AREA OF A BUILDING ON GROUND• THE PLOT AREA-AREA OF OPEN SPACES AROUND BUILDING. • F.A.R (FLOOR AREA RATIO):- F.A.R == COVERED AREA OF ALL FLOORS PLOT AREA
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
  • 32.
  • 33.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 44.
  • 45.
  • 46.
  • 47.
  • 48.
  • 50.
  • 51.
  • 52.
  • 53.
  • 54.
  • 55.
  • 56.
  • 57.
  • 58.
  • 59.
  • 60.
  • 61.
  • 63.  Earth work in Excavation in foundation 1.5 Lift, 50m lead Volume of Excavation = 291.6 cu.m Rate of Excavation = 247m/cu.m Total Cost of Excavation =247x291.8 =72025₹  Concrete Work P.C.C in foundation (1:4:8) Depth 10m Volume of P.C.C Work = 18cu.m Rate Of Concrete Work = 3002.00 ₹/cu.m =3002.00x18 =54036 Volume of Dry Concrete = 1.54x18 = 27.72 cu.m Cement = 27.72x1/13 = 2.132 cu.m (63 Bags) Sand = 27.72x4/13 = 8.529 cu.m Coarse Agg. = 27.72x8/13 = 17.058  R.C.C Work in Footing M20 (1:1.5:3) Depth= 0.620m Volume of R.C.C in footing = 91.660 cu.m Rate of R.C.C in footing = 91.660cu.m Rate of R.R.C Work = 4485 ₹/cu.m Total Cost of R.C.C work in footing =91.660x4485 =4.110 lakh Volume of dry concrete = 1.54x91.660 =141.156cu.m Cement = 141.156x1/5.5 = 25.664 cu.m (7.55 Bags) Sand = 141x1.5/5.5 = 38.497 cu.m Coarse Agg. = 141.156x/1.5 = 76.994 cu.m  R.C.C. Work in Column M25 (1:1:2) Volume of R.C.C in column = 14.456 cu.m Rate of R.R.C Work = 4483 ₹/cu.m Total Cost of R.C.C work in column = =4485x140546 =65238₹ Volume of dry concrete = 1.54x14.546 =22.400cu.m Cement = 22.4x1/4 = 5.6 cu.m (165 Bags) Sand = 22.4x1/4 = 5.6 Coarse Agg. = 22.4x2/4 = 11.2  R.C.C Work In Beam M25 (1:1:2) Volume of R.C.C in Beam = 21.279 cu.m Rate of R.R.C Work = 4485₹/cu.m Total Cost of R.C.C work in Beam = =21.279x4485 =95436₹  R.C.C Work in Slab M25 (1:1:2) Volume of R.C.C in Slab = 48.072cu.m Rate of R.R.C Work = 5099₹/ cu.m Total Cost of R.C.C work in slab = = 48.072x5099 =245119₹
  • 64.  R.C.C Work in Tied Beam M25 (1:1:2) Volume of R.C.C in Beam = 5.144cu.m Rate of R.R.C Work = 4485₹/ cu.m Total Cost of R.C.C work in tied beam = = 5.144x4485 =23070₹  Brick Work Cement Mortar (1:6), Size of Brick 919cm x 9cm x 9cm) Volume of Brick Work = 111.546 cu.m Rate of Brick Work = 3875.00 ₹/cu.m Total Cost of Brick Work =111.546x3876 432240₹  Flooring Area of Tile Flooring = 486.57sq.m Rate of Tile Flooring = 493 sq.m Cost of Tile Flooring =436.57x493 =215229.01m  Plastering {12mm thick (1:6) } Area of Plastering = 847.868 sq.m Rate of Plastering = 133₹/sq.m Cost of Plastering = 133x847.868 = 112766₹  Total Cost = 1726159₹ Contengecies Charge (5%) =5x1726159/100 =86307.95₹  Electrification Charge (8%) = 8x1726159/100 138092₹  Water Supply & Sanitation (8%) = 8x1726159/100 138092₹  Contractor Profit (15%) =15x1726159/100 =258923.85₹  Work Charge (2%) = 2x1726159/100 =34523₹  Tools & Plants (1.5%) =1.5x1726159/100 =25892.385 Total Cost = 2407990₹