SlideShare a Scribd company logo
1 of 61
• Well foundations are those types of cassion foundation that falls under
the category of deep foundation.
• The word cassion is native to French, meaning a chest or box.
• Deep foundations are opted when there is a need for resistance to
heavy loading by the structure.
• The cassion foundations are of three types.These are as follows:
• Box Cassions
• Open Cassions ( wells )
• Pneumatic Cassions
• The origin of well foundations credits back to prehistoric Indian
engineering. The use of well foundations in India hits back to
hundreds of years ago for providing deep foundation beneath the
water level for monuments, bridges and aqueducts. Most promising
example can be use of well foundation in Taj Mahal.
• Box cassions are open at top and closed at the
bottom and they are made up of timber, reinforced
concrete or steel. They are built on land, then
launched and floated to pier site where they are
sunk in position. The suitability of these
foundations is confined only to those areas where
the bearing stratum is available at shallow depth,
and where loads are not very heavy.
• Open cassion foundations are boxes of timber, metal,
reinforced concrete or masonry which is open at top
and bottom. They are used in constructing the
foundations of bridges and buildings. As they are
similar to wells, they are termed so. It is the most
widely used foundation type in India for construction
of bridges and water house abutments.
• These are bit different from the above
mentioned types because the bottom of
foundation is designed as working
chamber in which compressed air is
forced to prevent the entry of water and
thus permit excavation in dry.
The shapes of well foundation vary with the requirements
• Single Circular well foundation
• Twin Circular well foundation
• Dumb-well foundation
• Double- D well foundation
• Twin Hexagonal well foundation
• Twin Octagonal well foundation
• Rectangular well foundation
• Economics
• Minimizes pile cap needs
• Slightly less noise and reduced vibrations
• Easily adaptable to varying site conditions
• High axial and lateral loading capacity
• Extremely sensitive to construction procedures
• Not good for contaminated sites
• Lack of construction expertise
• Lack of Qualified Inspectors
1. Well Cap – It is a RCC slab. Its function is to
transmit the forces from the piers to the body of
well. It is important that the dimension of well
cap should be sufficient to accommodate pier.
2. Top Plug – Top plug is situated below the well
cap. This helps transferring the load through the
granular material into the steining.
3. Steining – Steining is a wall that is built over a
wedge shaped portion called well curb. The wall
should be designed such that it can be sunk
under its own weight. Moreover, the thickness
should be enough to overcome the skin friction
during sinking.
4. Well Curb – As mentioned earlier, the well curb supports the steining.
Well curb is made up of RCC with steel cutting edge.
5. Cutting Edge – The cutting edge is that part of the well which helps in
penetrating the strata of soil. Thus in case of hard strata such as gravels,
the flat cutting edge is used whereas in case of soft strata the sharp
edged cutting edge is used.
6. Bottom Plug – The bottom plug transmits the load to soil below and
resists uplift forces. The thickness of the plug varies from 0.5 – 1 times
the inner diameter of the well.
7.Sand Filling – Sand filling is the part that lies in between the top and
bottom plug. Its main function is to provide stability to well and reduce
the tensile stress due to the bending moment along with the
distribution of load from the superstructure.
8. Intermediate Plug - Wells resting on clayey strata, it is not preferable
to fill the space inside the well completely with sand. In such cases, sand
filling is not done or sand is filled up to the scour level. A concrete plug
covering the filling is usually provided, known as intermediate plug.
Usually, thickness of intermediate plug is taken as 500 mm.
(a) Vertical Loads:
i. Self-weight of well.
ii. Buoyancy
iii. Dead load of superstructure, substructure.
iv. Live load, and
v. Kentledge during sinking operation
(b) Horizontal Forces:
i. Braking and tractive effort of moving vehicles.
ii. Forces on account of resistance of bearings.
iii. Forces on account of water current or waves.
iv. Centrifugal force, if the bridge is situated on a curve.
v. Wind forces or seismic forces.
vi. Earth pressure.
vii. Other horizontal and uplift forces due to provision of transmission line tower (broken
wire condition) etc.
As far as possible wells shall be sunk without any tilt and shift. A tilt of 1 in
100 and shift of D/40 subject to a minimum of 150 mm shall be taken into
account in the design of well foundation (D is the width or diameter of well).
If greater tilts and shifts occur, their effects on bearing pressure on soil,
steining stresses, change in span etc. should be examined individually.
The depth of well foundation is mainly influenced by two factors:
a) Minimum grip length below the depth of maximum scour
b) Base pressure at permissible limit
The well need to embedded or sunk below the maximum scour level to a required
depth in order that the resistance from the sides of well is able to withstand the
lateral forces acting on the well. The depth of the bottom portion of well from the
scour level is called the grip length. While the selection of depth of foundation we
require to consider the grip length and bearing capacity of soil strata. The
maximum and minimum base pressures during the drastic or critical loading
conditions have to remain under the permissible range.
• Length of Bridge : 559.60 Mt.
• Numbers of Piers : 17 Nos. (With Abutments)
• Type of Foundation : Well & Pile Foundation
• Sub- Structure : Pier, Pier Cap
• Super-Structure : RCC Girder & PSC Girder
• Number of Span : 10 Nos. of 40m.span with PSC Girder &; 6 Nos. of 26.60mt. Span
with RCC Girder
• Total Width of Bridge : 15.00 Mt. (With Foot Path)
• Carriage Width of Bridge : 10.50 Mt. (2 Lanes)
PROJECT OBJCTIVE
• For connecting magarwada, moti daman and kachigam, nani daman. For connectivity travelling was done
through vapi-daman road.
• The distance between this two areas is 12 Kms and after the construction of this bridge it will decrease to
just 3 Kms.
1. WELL CAP
3. SAND FILLINF
4(A). CURB
4(B). CUTTING EDGE
5. BOTTOM PLUG
6. SOIL
2(A). TOP PLUG
2(B). STEINING
PLAN 1. EXCAVATION OF CIRCULAR
AREA
EDGE CENTRE CENTRELINE
OF ISMB
300
3. HEAVY PCC OF 300 MM
FOUNDATION OF PLATFORM
PCC
2. STONE AND BRICKS FILLED
• TESTING OF JOINTS
• In this initially paste of white cement is
cement is applied all over the joints of
joints of well. After drying of it, spraying
spraying of kerosene is done. Due to
Due to which if there is a void there will
there will be bubble formation of cement
of cement coming out. This will give idea
give idea about wherever welding space
welding space is there and must be filled.
must be filled.
• For well foundation sinking it is always necessary to know the
high tide and low tide, i.e. height of water. For this the
engineer takes the data of Mumbai online as the data for
daman is just available for one week. So seeing the chart of
Bombay, water level of daman is known as daman is 2hrs
later in water flow. Hence the same tide of almost same
height strikes daman after 2 hrs of its strike in Bombay.
DATA OF WATER LEVEL
SINKING
METHDOLOG
Y
CRANE GRABBING AND CHISELING
LABOUR WORKING AND GRABBING
BLASTING AND GRABBING
POCLAIN AND GRABBING USING TWO CRANE
POCLAIN AND GRABING USIG ONE CRANE
DIVERS AND GRABBING
1. WOODEN BLOCKS for creating a
joint.
50 × 100 mm
2. Blocks removed after initial set.
(30 Minutes)
3. SCRATCHING on surface is done
before second layer of concrete.
4. CONSTRUCTION JOINT is created.
DEWATERING Initially the dewatering is done of water which has been gathered below
during high tides.
DRILLING OF
ANCHOR BARS
The drilling is done in the hard rock strata using drill for inserting 6 bar of
25 mm dia rebar of 3000mm ht for anchoring of well inorder to hold it
properly . The bars may be anchored in minimum 65Ø boreholes and
grouted.
DEWATERING
(If Required)
If there is time between anchoring and concreting, water may have blowed
in and it is important to do the dewatering.
CONCRETING Concreting (PCC) is done of M15 grade of proportion 1:1.5 Cement mortar
of total height 3150 mm.
TRANSFER TO
PONTOON
The crushed sand is transferred on pontoon and the pontoon is then
moved near the well where fiiling will take place.
SAND FILLING The sand is filled in layers of 5 mt. using crane of total height 9.169
mt.
WATER FILL The water is filled in the sand upto 2.5 height of sand filled. Natural
compaction method is used.
COMPACTION For compaction chisel is used.
SAND
LEVELLING
The sand is levelled properly to ensure finish surface of top plug.
CURING OF
SAND
Before starting of concreting the curing of sand using water is
dne for proper bonding.
CONCRETING The laying of concrete of grade M25 is done in the top plug of
500 mm height.
SURVEYING The leveling and tilt and shift is continously checked in order for proper
alignment of well
REINFORCEME
NT
The rebar of 10 mm and 16 mm diameter are used.Those are
connected in form of links.
FORMWORK The 20 mm M S Plate are used for formwork which are erected by
welding it to rebar and the below steining.
CONCRETE The conrete of grade M35 is transferred from miller to well cap
through the pump and concrete pipes.
CURING The curing is done by wet jute bags and by the method of water filling.
DESHUTTERIN
G
The deshutterinf is done after 14 days.The support with rebars is
chipped of above the concrete surface using gas cutting.
Well Foundation
Well Foundation
Well Foundation

More Related Content

What's hot

Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundationSourabh Jain
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATIONaframawal
 
Type of caissons
Type of caissonsType of caissons
Type of caissonsAB MAKASANA
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Make Mannan
 
Goetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedGoetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedIrfan Malik
 
Bearing capacity_of_soil
 Bearing capacity_of_soil Bearing capacity_of_soil
Bearing capacity_of_soilShivarajteggi
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniquesNayana 54321
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.pptTarique048
 
Bearing capacity of Soil
Bearing capacity of SoilBearing capacity of Soil
Bearing capacity of SoilPirpasha Ujede
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Make Mannan
 

What's hot (20)

Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Type of caissons
Type of caissonsType of caissons
Type of caissons
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
Goetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedGoetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signed
 
Bearing capacity_of_soil
 Bearing capacity_of_soil Bearing capacity_of_soil
Bearing capacity_of_soil
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Caissons
Caissons Caissons
Caissons
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniques
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
 
Bearing capacity of Soil
Bearing capacity of SoilBearing capacity of Soil
Bearing capacity of Soil
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 

Similar to Well Foundation

Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptxAkshayGhorpade19
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1DYPCET
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructionChinnuNinan
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...Arman Hashmi
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsMitaliShelke
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptxJackRider12
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
GT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptxGT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptxAPURWAYAWALE
 
BC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptxBC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptxNisthaPathak2
 
Pile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdfPile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdfRohan Dasgupta
 
Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)Daphne Tan
 
Foundation selection
Foundation selectionFoundation selection
Foundation selectiondhara dattani
 

Similar to Well Foundation (20)

Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Presentation tos
Presentation tosPresentation tos
Presentation tos
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
pire and well.pptx
pire and  well.pptxpire and  well.pptx
pire and well.pptx
 
GT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptxGT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptx
 
BC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptxBC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptx
 
Pile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdfPile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdf
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)
 
Micropile
MicropileMicropile
Micropile
 
Foundation selection
Foundation selectionFoundation selection
Foundation selection
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

Well Foundation

  • 1.
  • 2.
  • 3. • Well foundations are those types of cassion foundation that falls under the category of deep foundation. • The word cassion is native to French, meaning a chest or box. • Deep foundations are opted when there is a need for resistance to heavy loading by the structure. • The cassion foundations are of three types.These are as follows: • Box Cassions • Open Cassions ( wells ) • Pneumatic Cassions
  • 4. • The origin of well foundations credits back to prehistoric Indian engineering. The use of well foundations in India hits back to hundreds of years ago for providing deep foundation beneath the water level for monuments, bridges and aqueducts. Most promising example can be use of well foundation in Taj Mahal.
  • 5. • Box cassions are open at top and closed at the bottom and they are made up of timber, reinforced concrete or steel. They are built on land, then launched and floated to pier site where they are sunk in position. The suitability of these foundations is confined only to those areas where the bearing stratum is available at shallow depth, and where loads are not very heavy.
  • 6. • Open cassion foundations are boxes of timber, metal, reinforced concrete or masonry which is open at top and bottom. They are used in constructing the foundations of bridges and buildings. As they are similar to wells, they are termed so. It is the most widely used foundation type in India for construction of bridges and water house abutments.
  • 7. • These are bit different from the above mentioned types because the bottom of foundation is designed as working chamber in which compressed air is forced to prevent the entry of water and thus permit excavation in dry.
  • 8. The shapes of well foundation vary with the requirements • Single Circular well foundation • Twin Circular well foundation • Dumb-well foundation • Double- D well foundation • Twin Hexagonal well foundation • Twin Octagonal well foundation • Rectangular well foundation
  • 9. • Economics • Minimizes pile cap needs • Slightly less noise and reduced vibrations • Easily adaptable to varying site conditions • High axial and lateral loading capacity
  • 10. • Extremely sensitive to construction procedures • Not good for contaminated sites • Lack of construction expertise • Lack of Qualified Inspectors
  • 11.
  • 12. 1. Well Cap – It is a RCC slab. Its function is to transmit the forces from the piers to the body of well. It is important that the dimension of well cap should be sufficient to accommodate pier. 2. Top Plug – Top plug is situated below the well cap. This helps transferring the load through the granular material into the steining. 3. Steining – Steining is a wall that is built over a wedge shaped portion called well curb. The wall should be designed such that it can be sunk under its own weight. Moreover, the thickness should be enough to overcome the skin friction during sinking.
  • 13. 4. Well Curb – As mentioned earlier, the well curb supports the steining. Well curb is made up of RCC with steel cutting edge. 5. Cutting Edge – The cutting edge is that part of the well which helps in penetrating the strata of soil. Thus in case of hard strata such as gravels, the flat cutting edge is used whereas in case of soft strata the sharp edged cutting edge is used. 6. Bottom Plug – The bottom plug transmits the load to soil below and resists uplift forces. The thickness of the plug varies from 0.5 – 1 times the inner diameter of the well. 7.Sand Filling – Sand filling is the part that lies in between the top and bottom plug. Its main function is to provide stability to well and reduce the tensile stress due to the bending moment along with the distribution of load from the superstructure.
  • 14. 8. Intermediate Plug - Wells resting on clayey strata, it is not preferable to fill the space inside the well completely with sand. In such cases, sand filling is not done or sand is filled up to the scour level. A concrete plug covering the filling is usually provided, known as intermediate plug. Usually, thickness of intermediate plug is taken as 500 mm.
  • 15. (a) Vertical Loads: i. Self-weight of well. ii. Buoyancy iii. Dead load of superstructure, substructure. iv. Live load, and v. Kentledge during sinking operation (b) Horizontal Forces: i. Braking and tractive effort of moving vehicles. ii. Forces on account of resistance of bearings. iii. Forces on account of water current or waves. iv. Centrifugal force, if the bridge is situated on a curve. v. Wind forces or seismic forces. vi. Earth pressure. vii. Other horizontal and uplift forces due to provision of transmission line tower (broken wire condition) etc.
  • 16. As far as possible wells shall be sunk without any tilt and shift. A tilt of 1 in 100 and shift of D/40 subject to a minimum of 150 mm shall be taken into account in the design of well foundation (D is the width or diameter of well). If greater tilts and shifts occur, their effects on bearing pressure on soil, steining stresses, change in span etc. should be examined individually.
  • 17. The depth of well foundation is mainly influenced by two factors: a) Minimum grip length below the depth of maximum scour b) Base pressure at permissible limit The well need to embedded or sunk below the maximum scour level to a required depth in order that the resistance from the sides of well is able to withstand the lateral forces acting on the well. The depth of the bottom portion of well from the scour level is called the grip length. While the selection of depth of foundation we require to consider the grip length and bearing capacity of soil strata. The maximum and minimum base pressures during the drastic or critical loading conditions have to remain under the permissible range.
  • 18.
  • 19.
  • 20. • Length of Bridge : 559.60 Mt. • Numbers of Piers : 17 Nos. (With Abutments) • Type of Foundation : Well & Pile Foundation • Sub- Structure : Pier, Pier Cap • Super-Structure : RCC Girder & PSC Girder • Number of Span : 10 Nos. of 40m.span with PSC Girder &; 6 Nos. of 26.60mt. Span with RCC Girder • Total Width of Bridge : 15.00 Mt. (With Foot Path) • Carriage Width of Bridge : 10.50 Mt. (2 Lanes) PROJECT OBJCTIVE • For connecting magarwada, moti daman and kachigam, nani daman. For connectivity travelling was done through vapi-daman road. • The distance between this two areas is 12 Kms and after the construction of this bridge it will decrease to just 3 Kms.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28. 1. WELL CAP 3. SAND FILLINF 4(A). CURB 4(B). CUTTING EDGE 5. BOTTOM PLUG 6. SOIL 2(A). TOP PLUG 2(B). STEINING
  • 29.
  • 30.
  • 31.
  • 32.
  • 33. PLAN 1. EXCAVATION OF CIRCULAR AREA EDGE CENTRE CENTRELINE OF ISMB 300 3. HEAVY PCC OF 300 MM FOUNDATION OF PLATFORM PCC 2. STONE AND BRICKS FILLED
  • 34.
  • 35. • TESTING OF JOINTS • In this initially paste of white cement is cement is applied all over the joints of joints of well. After drying of it, spraying spraying of kerosene is done. Due to Due to which if there is a void there will there will be bubble formation of cement of cement coming out. This will give idea give idea about wherever welding space welding space is there and must be filled. must be filled.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40. • For well foundation sinking it is always necessary to know the high tide and low tide, i.e. height of water. For this the engineer takes the data of Mumbai online as the data for daman is just available for one week. So seeing the chart of Bombay, water level of daman is known as daman is 2hrs later in water flow. Hence the same tide of almost same height strikes daman after 2 hrs of its strike in Bombay. DATA OF WATER LEVEL
  • 41.
  • 42.
  • 43.
  • 44.
  • 45. SINKING METHDOLOG Y CRANE GRABBING AND CHISELING LABOUR WORKING AND GRABBING BLASTING AND GRABBING POCLAIN AND GRABBING USING TWO CRANE POCLAIN AND GRABING USIG ONE CRANE DIVERS AND GRABBING
  • 46.
  • 47.
  • 48.
  • 49. 1. WOODEN BLOCKS for creating a joint. 50 × 100 mm 2. Blocks removed after initial set. (30 Minutes) 3. SCRATCHING on surface is done before second layer of concrete. 4. CONSTRUCTION JOINT is created.
  • 50.
  • 51. DEWATERING Initially the dewatering is done of water which has been gathered below during high tides. DRILLING OF ANCHOR BARS The drilling is done in the hard rock strata using drill for inserting 6 bar of 25 mm dia rebar of 3000mm ht for anchoring of well inorder to hold it properly . The bars may be anchored in minimum 65Ø boreholes and grouted. DEWATERING (If Required) If there is time between anchoring and concreting, water may have blowed in and it is important to do the dewatering. CONCRETING Concreting (PCC) is done of M15 grade of proportion 1:1.5 Cement mortar of total height 3150 mm.
  • 52.
  • 53.
  • 54. TRANSFER TO PONTOON The crushed sand is transferred on pontoon and the pontoon is then moved near the well where fiiling will take place. SAND FILLING The sand is filled in layers of 5 mt. using crane of total height 9.169 mt. WATER FILL The water is filled in the sand upto 2.5 height of sand filled. Natural compaction method is used. COMPACTION For compaction chisel is used.
  • 55. SAND LEVELLING The sand is levelled properly to ensure finish surface of top plug. CURING OF SAND Before starting of concreting the curing of sand using water is dne for proper bonding. CONCRETING The laying of concrete of grade M25 is done in the top plug of 500 mm height.
  • 56.
  • 57.
  • 58. SURVEYING The leveling and tilt and shift is continously checked in order for proper alignment of well REINFORCEME NT The rebar of 10 mm and 16 mm diameter are used.Those are connected in form of links. FORMWORK The 20 mm M S Plate are used for formwork which are erected by welding it to rebar and the below steining. CONCRETE The conrete of grade M35 is transferred from miller to well cap through the pump and concrete pipes. CURING The curing is done by wet jute bags and by the method of water filling. DESHUTTERIN G The deshutterinf is done after 14 days.The support with rebars is chipped of above the concrete surface using gas cutting.