SlideShare a Scribd company logo
1 of 13
TRENCHING & EXCAVATION
SHIVANANDA ROY
B.TECH, M.TECH, AMIE
Trenching
ā€¢ Trenching is a construction method that involves digging a trench in the ground to
install, maintain or inspect pipes, conduits or cables underground. When the
installation of the pipe, conduit or cable is completed, the trench is backfilled and
disturbed grounds are returned to their original state, insofar as possible.
ā€¢ The main methods of the execution of trenches are:
ā€¢ 1. Conventional methods: excavators +/- rock breakers
ā€¢ 2. Drill & Blast
ā€¢ 3. Trenching
DIFFERENCE BETWEEN EXCAVATION AND
TRENCHING
ā€¢ EXCAVATION
An excavation is any opening or depression in
the earthā€™s surface. It can be as narrow as a
backhoe bucket or as wide as an open pit mine.
All excavations are manmade and have
unsupported walls of earth or rock as its
borders.
ā€¢ TRENCH
An excavation in which material removal forms a
narrow opening in the ground. Unlike large
excavations, a trench is generally deeper than it
is wide.
OSHA considers an excavation to be a trench if
it is 15 feet wide or less at the bottom of the
excavation.
All trenches are excavations, but not all excavations are trenches.
METHOD OF TRENCHING
DRILL & BLAST
HYDRAULIC ROCK BREAKERS AND
BACKHOES (+/- RIPPING)
CHAIN TRENCHERS
Application
ļ± In very strong, abrasive, massive rock.
ļ± Not suitable for rock masses composed of small,
loose blocks.
ļ± Relatively easy to set up and execute.
ļ± Backhoes and dump trucks required to remove
blasted material.
ļ± Particularly useful on steep slopes.
Application
ļ±In rock masses composed of small, loose blocks.
ļ±Not suitable in very strong, abrasive, massive rock.
ļ±Easy to set up but can be very time consuming.
ļ±Useful for tight curves.
ļ±Useful where the ground changes from soil to rock
over short distances.
Application
ļ±In weak to strong rocks.
ļ±Generally not economic in very strong, abrasive,
massive rock.
ļ±Unsuitable for rock masses containing loose cobbles
and boulders or those containing pockets of wet
clay.
ļ±Larger machines require considerable lateral
working space and operate most efficiently over
long distances in relatively homogeneous rocks.
Excavation effects
ļ±Significant over-excavation effect.
ļ±Very irregular, possibly unstable trench walls and
floor.
ļ±Sidecast spoil causes ecological damage and
increases risk of sediment release to watercourses.
ļ±Alternatively, spoil transported to temporary or
permanent disposal sites.
Excavation effects
ļ±Moderate over-excavation.
ļ±Irregular trench walls and floor.
ļ±Sidecast spoil may cause ecological damage locally.
ļ±Some spoil may have to be transported to
temporary or permanent disposal sites.
Excavation effects
ļ±Minimal over-excavation.
ļ±Regular trench walls and floor.
ļ±Spoil is deposited in a continuous windrow
alongside the trench.
ļ±Where space is limited, spoil must be discharged to
dump trucks and transported to temporary sites for
processing: no sidecast spoil.
Security Issues
ļ±Potential restrictions on use of explosives.
ļ±Cannot be used in built-up areas or in proximity to
utilities, structures and other pipelines.
Security Issues
ļ±Suitable for use in built up areas or in proximity to
utilities, structures and other pipelines
Security Issues
ļ±Smaller machines.
ļ±Suitable for use in built-up areas or in proximity to
utilities, structures and other pipelines.
SELECTION OF TRENCHING METHOD
Examples of
rock type
Appropriate trenching
method
Chain trencher
tooth Wear
Potential Reuse
of spoil
Limestone Chain trencher Moderate Good to fair
Dolomite Chain trencher Moderate Good to fair
Sandstone Chain trencher Moderate - Severe Fair
Basalt Gneiss
Chain trencher
(may need hydraulic breaker for high spots)
Severe Fair to minimal
Granite Andesite
Hydraulic breaker + Backhoe Blasting.
(Note: Chain trencher economically marginal)
Extreme Fair to minimal
Chert Ryolithe
Hydraulic breaker + Backhoe.
Blasting
Does not apply Minimal to zero
PARTS OF A TRENCH
ā€¢ WALL: (FACE, SIDES) The sides of the trench.
ā€¢ BOTTOM: (BASE, FLOOR) The bottom of the trench.
ā€¢ SPOIL: The pile of excavated earth that was removed to
form the trench. The leading edge of this pile is called the
TOE.
ā€¢ SURCHARGE LOAD: Any weight on top of the surface of
the soil, which would add extra stress to the walls of the
trench. Spoil piles, backhoes, rocks, vehicles, buildings, or
other loads placed near the trench opening would be
surcharge loads.
ā€¢ BEDDING: A material that is usually placed around a pipe
prior to backfilling. In most cases, bedding is gravel, sand,
or fine crushed rock, and it extends from 5 inches below
the pipe to 6 inches above the pipe.
SHAPE OF THE TRENCH
ā€¢ The shape of a trench is determined by:
ļ±Purpose of the trench
ļ±The type of soil the trench is being dug in
ļ±The size of pipe or conduit that is going into the trench
ļ±Availability of shielding or shoring
ļ±Location of buildings, utilities, etc.
ļ±Location of the trench (roadway, open field, etc.)Ķ¾ Conduit loading
requirements.
SHAPE OF THE TRENCH
ā€¢ STRAIGHT TRENCH
A trench where the sides are parallel
and at right angles to the base.
Straight trenches are usually used in
areas where there is limited surface
area to disturb, such as a roadway or
near buildings. Protection systems such
as shoring or trench boxes would be
required.
ā€¢ SLOPED TRENCH
A trench where the sides have been
angled to prevent cave in.
The angle of the slope is determined
by the soil type, trench depth, and
in some cases, the time that the
trench will remain open.
SHAPE OF THE TRENCH
ā€¢ BENCHED TRENCH
A trench where the sides have been cut away
to form steps. Vertical distances (height of
step) are determined by soil type. Multiple
bench or single bench systems can be used
ā€¢ BELLBOTTOM PIER HOLE
A trench which is usually used in footing
placement.
Its top is usually narrower than its bottom,
thus giving it a bell shape in cross-section.
With the sides sloping inward over the floor
of the hole, the possibility of collapse is
much greater than in other styles of
trenches.
Additional protection systems are required
for those who work in this type of
excavation.
TRENCHERS
ā€¢ Trenchers or Trenching machines are used to
excavate trenches in soil.
ā€¢ These trenches are generally used for pipeline
laying, cable laying, drainage purposes etc.
ā€¢ Trenching machines are available in two types
namely chain trenchers and wheeled trenchers.
ā€¢ Chain trenchers contains a fixed long arm around
which digging chain is provided. Wheeled trenchers
contains a metal wheel with digging tooth around it.
ā€¢ To excavate hard soil layers, wheeled trenchers are
more suitable. Both types of trenchers are available
in tracked as well as wheeled vehicle forms
EXCAVATORS
ā€¢ Excavators are heavy construction equipment
consisting of a boom, dipper (or stick), bucket
and cab on a rotating platform known as the
"house".
ā€¢ The house sits atop an undercarriage with tracks
or wheels. All movement and functions of a
hydraulic excavator are accomplished through
the use of hydraulic fluid, with hydraulic cylinders
and hydraulic motors.
ā€¢ Due to the linear actuation of hydraulic cylinders,
their mode of operation is fundamentally
different from cable-operated excavators which
use winches and steel ropes to accomplish the
movements.
Usage
ā€¢ Digging of trenches, holes, foundations
ā€¢ Material handling
ā€¢ Brush cutting with hydraulic saw and mower attachments
ā€¢ Forestry work
ā€¢ Forestry mulching
ā€¢ Construction
ā€¢ Demolition with hydraulic claw, cutter and breaker attachments
ā€¢ General grading/landscaping
ā€¢ Mining, especially, but not only open-pit mining
ā€¢ River dredging
ā€¢ Driving piles, in conjunction with a pile driver
ā€¢ Drilling shafts for footings and rock blasting, by use of an
auger or hydraulic drill attachment
ā€¢ Snow removal with snowplow and snow blower attachments
This is the last page
Thank You
RISE & BELIEVEā€¦

More Related Content

What's hot

Excavations ppt
Excavations pptExcavations ppt
Excavations pptColleen True
Ā 
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...A Makwana
Ā 
Rippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentRippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentshalomjudit3
Ā 
DRAG-LINE CONSTRUCTION EQUIPMENT
DRAG-LINE CONSTRUCTION EQUIPMENTDRAG-LINE CONSTRUCTION EQUIPMENT
DRAG-LINE CONSTRUCTION EQUIPMENTvikas verma
Ā 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Construction Tech. and Mgmt., VNIT Nagpur
Ā 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling EquipmentsRajarshi Patty
Ā 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt1971995
Ā 
CLAMPSHELL- CONSTRUCTION EQUIPMENT.pptx
CLAMPSHELL- CONSTRUCTION EQUIPMENT.pptxCLAMPSHELL- CONSTRUCTION EQUIPMENT.pptx
CLAMPSHELL- CONSTRUCTION EQUIPMENT.pptxAkankshaPendharkar1
Ā 
Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating EquipmentKiran Goswami
Ā 
Excavating Equipments
Excavating EquipmentsExcavating Equipments
Excavating EquipmentsTulsi Makwana
Ā 
earth moving equipments
earth moving equipmentsearth moving equipments
earth moving equipmentsrafiyaparveen1994
Ā 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls Manvinder Kingra
Ā 
Scraper ripper-grader-dozer
Scraper ripper-grader-dozerScraper ripper-grader-dozer
Scraper ripper-grader-dozerSATYANARAYANA I
Ā 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumitSuMitt MaNdla
Ā 
Techniques of Controlled Blasting
Techniques of Controlled BlastingTechniques of Controlled Blasting
Techniques of Controlled Blastingpartha sharma
Ā 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blastingJyoti Khatiwada
Ā 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)Suhaa Chine
Ā 

What's hot (20)

Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
Ā 
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Ā 
Rippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentRippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipment
Ā 
DRAG-LINE CONSTRUCTION EQUIPMENT
DRAG-LINE CONSTRUCTION EQUIPMENTDRAG-LINE CONSTRUCTION EQUIPMENT
DRAG-LINE CONSTRUCTION EQUIPMENT
Ā 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
Ā 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Ā 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling Equipments
Ā 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
Ā 
CLAMPSHELL- CONSTRUCTION EQUIPMENT.pptx
CLAMPSHELL- CONSTRUCTION EQUIPMENT.pptxCLAMPSHELL- CONSTRUCTION EQUIPMENT.pptx
CLAMPSHELL- CONSTRUCTION EQUIPMENT.pptx
Ā 
Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating Equipment
Ā 
Draglines
DraglinesDraglines
Draglines
Ā 
Excavating Equipments
Excavating EquipmentsExcavating Equipments
Excavating Equipments
Ā 
earth moving equipments
earth moving equipmentsearth moving equipments
earth moving equipments
Ā 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls
Ā 
Scraper ripper-grader-dozer
Scraper ripper-grader-dozerScraper ripper-grader-dozer
Scraper ripper-grader-dozer
Ā 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
Ā 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
Ā 
Techniques of Controlled Blasting
Techniques of Controlled BlastingTechniques of Controlled Blasting
Techniques of Controlled Blasting
Ā 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
Ā 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)
Ā 

Similar to TRENCHING & EXCAVATION GUIDE

u1t4tunneling.pptx
u1t4tunneling.pptxu1t4tunneling.pptx
u1t4tunneling.pptxMagudeaswaranP
Ā 
Tunneling
TunnelingTunneling
TunnelingSafdar Ali
Ā 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundationSourabh Jain
Ā 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling explorationjamali husain
Ā 
tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdfBalpreetSingh47890
Ā 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Mayur Rahangdale
Ā 
Drilling in Surface Mine.pdf
Drilling in Surface Mine.pdfDrilling in Surface Mine.pdf
Drilling in Surface Mine.pdfBIT Sindri
Ā 
Tunnel Engineering.pptx
Tunnel Engineering.pptxTunnel Engineering.pptx
Tunnel Engineering.pptxPriya Sarita Mane
Ā 
Underground mining method
Underground mining methodUnderground mining method
Underground mining methodSafdar Ali
Ā 
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTUVATSAL PATEL
Ā 
Heavy construction equipment
Heavy construction equipmentHeavy construction equipment
Heavy construction equipmentPritesh Parmar
Ā 
Percussion drilling
Percussion drillingPercussion drilling
Percussion drillingshaxee ali
Ā 
Exploratory Drilling
Exploratory Drilling Exploratory Drilling
Exploratory Drilling BIT Sindri
Ā 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundationashishcivil098
Ā 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
Ā 
Tunnel and Underground Excavation Presentation
Tunnel and Underground Excavation PresentationTunnel and Underground Excavation Presentation
Tunnel and Underground Excavation PresentationChandan Pradhan
Ā 
Offshore mining
Offshore miningOffshore mining
Offshore miningAbhiRam152
Ā 

Similar to TRENCHING & EXCAVATION GUIDE (20)

u1t4tunneling.pptx
u1t4tunneling.pptxu1t4tunneling.pptx
u1t4tunneling.pptx
Ā 
Tunneling
TunnelingTunneling
Tunneling
Ā 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
Ā 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
Ā 
tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdf
Ā 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
Ā 
Drilling in Surface Mine.pdf
Drilling in Surface Mine.pdfDrilling in Surface Mine.pdf
Drilling in Surface Mine.pdf
Ā 
Tunnel Engineering.pptx
Tunnel Engineering.pptxTunnel Engineering.pptx
Tunnel Engineering.pptx
Ā 
Underground mining method
Underground mining methodUnderground mining method
Underground mining method
Ā 
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
Ā 
Heavy construction equipment
Heavy construction equipmentHeavy construction equipment
Heavy construction equipment
Ā 
Percussion drilling
Percussion drillingPercussion drilling
Percussion drilling
Ā 
Square set stoping
Square set stopingSquare set stoping
Square set stoping
Ā 
Exploratory Drilling
Exploratory Drilling Exploratory Drilling
Exploratory Drilling
Ā 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundation
Ā 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
Ā 
Presentation tos
Presentation tosPresentation tos
Presentation tos
Ā 
Tunnel and Underground Excavation Presentation
Tunnel and Underground Excavation PresentationTunnel and Underground Excavation Presentation
Tunnel and Underground Excavation Presentation
Ā 
Offshore mining
Offshore miningOffshore mining
Offshore mining
Ā 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
Ā 

More from Shivananda Roy

PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSShivananda Roy
Ā 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONShivananda Roy
Ā 
UNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESUNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESShivananda Roy
Ā 
Construction Equipments
Construction EquipmentsConstruction Equipments
Construction EquipmentsShivananda Roy
Ā 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGEShivananda Roy
Ā 

More from Shivananda Roy (6)

PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
Ā 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATION
Ā 
UNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESUNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUES
Ā 
Construction Equipments
Construction EquipmentsConstruction Equipments
Construction Equipments
Ā 
Green concrete
Green concreteGreen concrete
Green concrete
Ā 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
Ā 

Recently uploaded

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
Ā 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
Ā 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
Ā 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
Ā 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
Ā 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
Ā 

Recently uploaded (20)

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
Ā 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
Ā 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Ā 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
Ā 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
Ā 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
Ā 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
Ā 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
Ā 
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Serviceyoung call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
Ā 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
Ā 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
Ā 

TRENCHING & EXCAVATION GUIDE

  • 1. TRENCHING & EXCAVATION SHIVANANDA ROY B.TECH, M.TECH, AMIE
  • 2. Trenching ā€¢ Trenching is a construction method that involves digging a trench in the ground to install, maintain or inspect pipes, conduits or cables underground. When the installation of the pipe, conduit or cable is completed, the trench is backfilled and disturbed grounds are returned to their original state, insofar as possible. ā€¢ The main methods of the execution of trenches are: ā€¢ 1. Conventional methods: excavators +/- rock breakers ā€¢ 2. Drill & Blast ā€¢ 3. Trenching
  • 3. DIFFERENCE BETWEEN EXCAVATION AND TRENCHING ā€¢ EXCAVATION An excavation is any opening or depression in the earthā€™s surface. It can be as narrow as a backhoe bucket or as wide as an open pit mine. All excavations are manmade and have unsupported walls of earth or rock as its borders. ā€¢ TRENCH An excavation in which material removal forms a narrow opening in the ground. Unlike large excavations, a trench is generally deeper than it is wide. OSHA considers an excavation to be a trench if it is 15 feet wide or less at the bottom of the excavation. All trenches are excavations, but not all excavations are trenches.
  • 4. METHOD OF TRENCHING DRILL & BLAST HYDRAULIC ROCK BREAKERS AND BACKHOES (+/- RIPPING) CHAIN TRENCHERS Application ļ± In very strong, abrasive, massive rock. ļ± Not suitable for rock masses composed of small, loose blocks. ļ± Relatively easy to set up and execute. ļ± Backhoes and dump trucks required to remove blasted material. ļ± Particularly useful on steep slopes. Application ļ±In rock masses composed of small, loose blocks. ļ±Not suitable in very strong, abrasive, massive rock. ļ±Easy to set up but can be very time consuming. ļ±Useful for tight curves. ļ±Useful where the ground changes from soil to rock over short distances. Application ļ±In weak to strong rocks. ļ±Generally not economic in very strong, abrasive, massive rock. ļ±Unsuitable for rock masses containing loose cobbles and boulders or those containing pockets of wet clay. ļ±Larger machines require considerable lateral working space and operate most efficiently over long distances in relatively homogeneous rocks. Excavation effects ļ±Significant over-excavation effect. ļ±Very irregular, possibly unstable trench walls and floor. ļ±Sidecast spoil causes ecological damage and increases risk of sediment release to watercourses. ļ±Alternatively, spoil transported to temporary or permanent disposal sites. Excavation effects ļ±Moderate over-excavation. ļ±Irregular trench walls and floor. ļ±Sidecast spoil may cause ecological damage locally. ļ±Some spoil may have to be transported to temporary or permanent disposal sites. Excavation effects ļ±Minimal over-excavation. ļ±Regular trench walls and floor. ļ±Spoil is deposited in a continuous windrow alongside the trench. ļ±Where space is limited, spoil must be discharged to dump trucks and transported to temporary sites for processing: no sidecast spoil. Security Issues ļ±Potential restrictions on use of explosives. ļ±Cannot be used in built-up areas or in proximity to utilities, structures and other pipelines. Security Issues ļ±Suitable for use in built up areas or in proximity to utilities, structures and other pipelines Security Issues ļ±Smaller machines. ļ±Suitable for use in built-up areas or in proximity to utilities, structures and other pipelines.
  • 5. SELECTION OF TRENCHING METHOD Examples of rock type Appropriate trenching method Chain trencher tooth Wear Potential Reuse of spoil Limestone Chain trencher Moderate Good to fair Dolomite Chain trencher Moderate Good to fair Sandstone Chain trencher Moderate - Severe Fair Basalt Gneiss Chain trencher (may need hydraulic breaker for high spots) Severe Fair to minimal Granite Andesite Hydraulic breaker + Backhoe Blasting. (Note: Chain trencher economically marginal) Extreme Fair to minimal Chert Ryolithe Hydraulic breaker + Backhoe. Blasting Does not apply Minimal to zero
  • 6. PARTS OF A TRENCH ā€¢ WALL: (FACE, SIDES) The sides of the trench. ā€¢ BOTTOM: (BASE, FLOOR) The bottom of the trench. ā€¢ SPOIL: The pile of excavated earth that was removed to form the trench. The leading edge of this pile is called the TOE. ā€¢ SURCHARGE LOAD: Any weight on top of the surface of the soil, which would add extra stress to the walls of the trench. Spoil piles, backhoes, rocks, vehicles, buildings, or other loads placed near the trench opening would be surcharge loads. ā€¢ BEDDING: A material that is usually placed around a pipe prior to backfilling. In most cases, bedding is gravel, sand, or fine crushed rock, and it extends from 5 inches below the pipe to 6 inches above the pipe.
  • 7. SHAPE OF THE TRENCH ā€¢ The shape of a trench is determined by: ļ±Purpose of the trench ļ±The type of soil the trench is being dug in ļ±The size of pipe or conduit that is going into the trench ļ±Availability of shielding or shoring ļ±Location of buildings, utilities, etc. ļ±Location of the trench (roadway, open field, etc.)Ķ¾ Conduit loading requirements.
  • 8. SHAPE OF THE TRENCH ā€¢ STRAIGHT TRENCH A trench where the sides are parallel and at right angles to the base. Straight trenches are usually used in areas where there is limited surface area to disturb, such as a roadway or near buildings. Protection systems such as shoring or trench boxes would be required. ā€¢ SLOPED TRENCH A trench where the sides have been angled to prevent cave in. The angle of the slope is determined by the soil type, trench depth, and in some cases, the time that the trench will remain open.
  • 9. SHAPE OF THE TRENCH ā€¢ BENCHED TRENCH A trench where the sides have been cut away to form steps. Vertical distances (height of step) are determined by soil type. Multiple bench or single bench systems can be used ā€¢ BELLBOTTOM PIER HOLE A trench which is usually used in footing placement. Its top is usually narrower than its bottom, thus giving it a bell shape in cross-section. With the sides sloping inward over the floor of the hole, the possibility of collapse is much greater than in other styles of trenches. Additional protection systems are required for those who work in this type of excavation.
  • 10. TRENCHERS ā€¢ Trenchers or Trenching machines are used to excavate trenches in soil. ā€¢ These trenches are generally used for pipeline laying, cable laying, drainage purposes etc. ā€¢ Trenching machines are available in two types namely chain trenchers and wheeled trenchers. ā€¢ Chain trenchers contains a fixed long arm around which digging chain is provided. Wheeled trenchers contains a metal wheel with digging tooth around it. ā€¢ To excavate hard soil layers, wheeled trenchers are more suitable. Both types of trenchers are available in tracked as well as wheeled vehicle forms
  • 11. EXCAVATORS ā€¢ Excavators are heavy construction equipment consisting of a boom, dipper (or stick), bucket and cab on a rotating platform known as the "house". ā€¢ The house sits atop an undercarriage with tracks or wheels. All movement and functions of a hydraulic excavator are accomplished through the use of hydraulic fluid, with hydraulic cylinders and hydraulic motors. ā€¢ Due to the linear actuation of hydraulic cylinders, their mode of operation is fundamentally different from cable-operated excavators which use winches and steel ropes to accomplish the movements.
  • 12. Usage ā€¢ Digging of trenches, holes, foundations ā€¢ Material handling ā€¢ Brush cutting with hydraulic saw and mower attachments ā€¢ Forestry work ā€¢ Forestry mulching ā€¢ Construction ā€¢ Demolition with hydraulic claw, cutter and breaker attachments ā€¢ General grading/landscaping ā€¢ Mining, especially, but not only open-pit mining ā€¢ River dredging ā€¢ Driving piles, in conjunction with a pile driver ā€¢ Drilling shafts for footings and rock blasting, by use of an auger or hydraulic drill attachment ā€¢ Snow removal with snowplow and snow blower attachments
  • 13. This is the last page Thank You RISE & BELIEVEā€¦