Ch.8 Project Quality
Management
Pages 226 - 254 of PMBOK Guide 5th
Edition
Ch.8 Project Quality Management
Quality Management includes creating and following policies and procedures to
ensure that a project meet the defined needs (from the customer’s perspective).
Quality definitions and concepts
Prevention is the better than control. Do it right the
first time. Zero Defects is the goal of quality. Philip
Crosby
Quality is defined as the degree to which the project
fulfills requirements. Or quality means fitness for
use. Joseph Juran
Quality relates to continues improvement of people
and procedures. Kaizan
Quality relates to processes
and procedures not people. Or
quality is the management’s
problem. Management needs
to provide the procedures and
resources for the employees
to produce quality product.
Edwards Deming
Quality Management is
applying the processes that
will ensure the project will
meet the needs for which it
was undertaken
Quality Vs Grade Vs Gold Plating?
Quality is the degree to which
a set of inherent characteristics fulfill
requirements” (ISO 9000)
Quality definitions and concepts Quality Management is
applying the processes that
will ensure the project will
meet the needs for which it
was undertaken
Quality is defined as the degree to which the project
fulfills requirements. Or quality means fitness for
use. Joseph Juran
Quality is the degree to which
a set of inherent characteristics fulfill
requirements” (ISO 9000) Quality relates to processes
and procedures not people. Or
quality is the management’s
problem. Management needs
to provide the procedures and
resources for the employees
to produce quality product.
Edwards Deming
Prevention is the better than control. Do it right the
first time. Zero Defects is the goal of quality. Philip
Crosby
Quality relates to continues improvement of people
and procedures. Kaizan
Quality Vs Grade Vs Gold Plating?
Ch.8 Processes of Quality Management
8.1 Plan Quality Management
• The process of identifying project’s quality requirements and how the
these requirements will be met.
8.2 Perform Quality Assurance
• Here we apply the quality requirements and audit results from quality
control process to ensure proper procedures are applied.
• In this process we measure and record quality requirements to ensure
quality is achieved and recommend changes if needed.
8.3 Control Quality
8.1 Plan Quality Management: ITTOs
1.Project Management
Plan
2. Stakeholder register
3. RiskRegister
4.Requirements
documentation
6. EEF/OP
A
1. Costbenefit analysis
2. Costof Quality (CoQ)
3. Benchmarking
4. Designof experiments
5. Statistical sampling
6.Additional quality planning tools
7. Meetings
8. Sevenbasicquality techniques
1.Quality
management plan
2. Quality metrics
3. Quality checklists
4.Process
improvement plan
5.Project document
updates
The process of identifying quality requirement and/or standards for the
project and product and documenting how the project will demonstrate
compliance.
What is quality for this project ? How will we ensure it?
Input Tools & Techniques Output
8.1 Plan Quality Management: Data Flow Diagram
8.1.1.1 Project Management Plan
• Scope Baseline: The Scope Statement of Scope Baseline gives us important
information related to project quality. The scope statements contains
project deliverables and acceptance criteria for these deliverable.
• The acceptance criteria can greatly affect the project quality requirements
hence cost of quality or cost of project as a whole.
• Other elements of the PMP used for planning the quality are the Schedule
Baseline and Cost Baseline which tells us when the work is needed to be
done and when the money is going to be spent.
• It tells us about the stakeholder that are concerned with quality aspect of
the project
8.1.1.2 Stakeholder Register
8.1 Plan Quality Management: Inputs
• It contains information about the risks that may affect the quality of the
project
8.1.1.3 Risk Register
8.1.1.4 Requirements Documentation
• The requirements documentation includes stakeholder requirements about the
project, product, and quality of the product.
• Requirements documentation will help us better plan Control Quality Process
• Government Regulations, Industry Standards, Policies and Procedures, Historical
Information etc
8.1.1.5 EEF/OPA
8.1 Plan Quality Management: Inputs
8.1.2.1 Cost Benefit Analysis
• Themainreasonbehindmaintaining qualityisto havelessrework, lowercosts, higher
productivity
, andhighercostumer satisfaction
• In CostBenefitAnalysis wecompare benefitsversusthe costof meeting qualityrequirements
8.1.2.1 Cost of Quality
• Lookingatwhatthe costof conformanceandnonconformanceto qualityandcreatingan
appropriate balance
Should be
less than
8.1.2 Plan Quality Management: T&Ts
<
8.1.2.3 Seven basic quality tools
• The 7QC tools as they are called, are used in within the context of Plan-Do-
Check-Act (PDCA) cycle to solve quality related problems
8.1.2 Plan Quality Management: T&Ts
Theproblem(theEffect) isplacedat theheadof
fishandthepossiblesourceof theproblem(the
Cause)issought after inthefour factors
(Machine, Man, Methods, andMaterials).
Thewholeprocessisconduct inbrainstorming
sessions.Thestepsinvolvedareasfollow:
1. Identifytheproblem.
2. W
orkout themajor factors involved.
3. Identifypossiblecauses.
4. Analyzeyour diagram
Y
oucanalsoaddfactors suchasEnvironment,
andMaterialsor anyotherfactor deemed
related.
Major causesarefurther investigated.Attheendthewhole
diagramis analyzedandpossiblecauseorcausesareidentified.
1. Cause-and-effect Diagram: Cause-and-effect diagram or fishbone diagram
or Ishikawa diagram is used to find possible causes of a problem or failure
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
Flowchart showslogicalrelationship
betweendifferent process.
Flowchart helpsusinbetter
understandingtheprocess
Flowchart isalsoagood
communicationwhichshowswhat
reallyhappensinprocessorwhat
shouldhappen.
Flowchartsalsoshowsdecision
pointsinaprocess
Flowchart will helpusinbetter
understandingthecostsrelatedto
qualityrequirements
2. Flowcharts: Also called process maps, because flowcharts display sequence
of steps. The flowchart transforms one or more input to one or more outputs.
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
2. Flowcharts: Also called process maps, because flowcharts display sequence
of steps. The flowchart transforms one or more input to one or more outputs.
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
2. Flowcharts: Also called process maps, because flowcharts display sequence
of steps. The flowchart transforms one or more input to one or more outputs.
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
Checksheets
tellsusabout a
problemandits
frequencyof
occurrence.
Diagrams.
Dataobtained
through
Checksheetsare
oftenusedfor
generating
Pareto
Diagrams.
3. Checksheet: Checksheets or tally sheet are used to collect used to collect
useful data about a problem or its attributes when performing inspections.
Cheeksheets can also be used checklist.
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
ParetoDiagram
isaspecial type
of vertical bar
chart that shows
frequencyof the
sourcesof a
problemand
cumulative
percentageof all
vital sources
Thebarsshow
eachsourceand
thelineshows
commutative
total
4. Pareto Diagrams: Pareto thought 80 percent of the quality related problems
are effects of 20 percent of the causes.
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
Inthisexamplethe
distributionof datais
basedonabell curve.
Thenamecomesfrom
it shapewhichlikea
bell.
Inthisexamplethe
highest frequencyof
themeasurementwas
between20and22.
The
occurrence/frequency
for thismeasurement
iscloseto28times.
5. Histograms: Histograms are special types of bar charts that show central
tendency, dispersion, and shape of statistical distribution.
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
If weget 7resultsonthe
eithersideof themean, we
concludethat theprocessis
out of control, see4.Alsoif a
measurement isout of control
limitsweconcludethat the
processisout of control, see
3.
Control Chartsarealsoused
todetermineif amanagement
processisincontrol by
measuringfactors like
scheduleor cost variances, or
thefrequencyof changesinto
scopeetc.
1.Upper control limit
2. Lower
control limit
3. Out of control
5.Specification limit: is point determines by
customer, not calculated based on control chart
4. Rule of seven: Out of control if 7
measurements are above or below the mean
6. Normal and
expected variation
Usually 3 or 6 sigma
6. Control Charts: Control Charts are used to know whether a process is stable or
has the desired performance. Control Charts are used for repetitive process e.g
manufacturing
8.1.2.3 Seven basic quality tools
• The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA)
cycletosolvequalityrelated problems
8.1.2 Plan Quality Management: T&Ts
Onceweknowthat thereisa
correlationbetweenthetwo
variablesthenwecan
estimatehowchangesto
independentvariablecan
result inachangeinthe
dependent variable.
Grapha, b, c, anddshow
different correlationthat may
exist betweentwovariables.
For exampleingraphbtheY
axismayshownumberof
iterationandXaxismay
shownumber of bugsfound
inthesoftware.
7. Scatter Diagram: Scatter Diagram is used to check for correlation between
two variables
8.1.2.4 Benchmarking
• Comparingthe project in handwith similarprojectscompletedin the past in order to identify
best practices, andgenerate newideas.
8.1.2.5 Design of Experiment
• DOEis usedto identify factorsthat caninfluencedifferent variablesofthe productorprocess
• DOEis usedin PlanQualityManagementto determinethe numberandtype of tests needed
toachievetherequiredquality
8.1 Plan Quality Management: T&Ts
InDOEwecanchangemultiplevariablesat a
time.Indoingsowefindoptimalconditionfor
product or process.
Imaginetheexampleontheleft isabout
producingbrickunderdifferent conditionsorwith
aninputofdifferentproportions ofthe materials
Onceweknowthatvariousfactorscaninfluence
ourproductin various ways, wewill develop
testsor qualitychecklist for them.
8.1.2.6 Statistical Sampling
• Statistical Samplingrefers to choosingfewitemsasasamplefrom alarger groupof items.
• Herewedonot dothe actualsamplingbutdecideonhowwewill dohowsamplinginthe
comingqualityprocesses
• Thiswill helpusin correctlydetermining thecostof quality.
8.1.2.7 Other Quality Tools
• Brainstorming: Usedfor generatingideas
• ForceFieldAnalysis: Diagramsof forces for andagainstchange
• Nominal GroupTechnique: Inthis technique wevotefor ideasto befurther discussedbya
larger groupof people
• Quality ControlandManagementTools:Thistoolswill beexplainedin the next process.
Thesetoolsareusedto link andsequencethe toolsof the project.
8.1.2.8 Meetings
• Qualityrelated meetingsareattendedbytheprojectsponsor,project management,selected
projectteammember,selectedstakeholders,teammembersthatareresponsibleforqualityof
theproject.
8.1 Plan Quality Management: T&Ts
8.1 Plan Quality Management: T&Ts
Below is an example of force-field diagram
In the force-field you
basically identify the force
that will support or oppose a
planned work which usually
is something related to
change.
In the force-field you
basically identify the force
the will support or oppose
the change. This will help
you better understand the
situation and plan you
quality accordingly.
8.1.3.1 Quality Management Plan
• Qualitymanagementplansexplainshoworganizationsqualitypolicieswill beimplemented.
• Dependingonthe project,theplancanbeverydetailedorsimple.
8.1.3.2 Process Improvement Plan
• ProcessImprovement Planispart of the PMP
• Thisplandetailsthe steps that will help asin improvingvarious processin ourproject.
• Theplanis developedin the PlanQualityManagement Processandimplementedin the QA
andQCprocesses
8.1 Plan Quality Management: Outputs
Areas included in the Process Improvement Plan are as follow:
1. Process Boundaries: The propose of the process, the start and end date, the inputs
and outputs of the process
2. Process Configuration: Graphical depiction of the process
3. Process Metric: Used for measuring process efficiency
4. Targets for Improved Performance: Targets for improvement
8.1.3.3 Quality Metrics
• It describes the project orproductattributesandhowthe qualitycontrol processwill measure
it.
• Examplesof qualitymetrics are finishingthe project withinthe budgetandtime, the frequency
of defects, failure rate, etc.
• Themetrics andthe tolerancelevelfor variation is set in PlanQuality
• Theattributesaremeasuredincontrol quality
8.1.3.4 Quality Checklists
• Basedonthe productrequirementsachecklistis developed
• Thechecklistwill list the steps to befollowed to achievethe desired qualityfor the product
• Thechecklistshouldalsocontain the productrequirements
8.1.3.5 Document Update
• RiskRegister, RequirementTraceability Matrix, andWBSdictionary are updated
8.1 Plan Quality Management: Outputs
8.2 Perform Quality Assurance: ITTOs
1. Quality Management Plan
2.ProcessImprovement
Plan
Quality metrics
3.Quality control
measurement
4. Project Documents
1.Quality Management and
Control T
ools
2. Quality audits
3. Processanalysis
1.Change Requests
2.Project management
planupdates
3.Project document
updates
4. OP
Aupdates
Input Tools & Techniques Output
In Quality Assurance we ensure the proper quality related procedures are
followed. We do this by auditing the quality requirements and results received
from Quality Control Process
8.2 Perform Quality Assurance: Data Flow
Diagram
8.2.1 Perform Quality Assurance: Inputs
8.2.1.1 Quality Management Plan
• It contains planfor quality assuranceandprocessimprovement
8.2.1.2 Process Improvement Plan
• Thiswill tell usaboutthe project’s processimprovement plan which needsto be
alignedwith quality assuranceprocess.
8.2.1.3 Quality Metrics
• Thiswill tells what weneedto measureandwhat arethe allowable variation for our
measurements.
8.2.1.4 Quality Control Measurements
• Thesearethemeasurements takenintheControl Quality Process
• Themeasurements areusedfedbackto QualityAssuranceinorder toevaluate the
effectiveness of quality assuranceprocedures/processes
8.2.2 Perform Quality Assurance: T&Ts
8.2.2.1 Quality Management and Control Tools
• Besideother available tools,in quality assuranceweusall thetools that areusedin
PlanQuality Management andControl Quality Processes
Affinity Diagram……?
• Classifying large number of ideas into groups
8.2.2 Perform Quality Assurance: T&Ts
8.2.2.1 Quality Management and Control Tools
• Besideother available tools,in quality assuranceweusall thetools that areusedin
PlanQuality Management andControl Quality Processes
Process Decision Program Chart (PDPC)
PDPC systematically identifies what might go wrong in a plan under development.
1. Y
oudivided in andsubdividea
complexplaninto more simple
steps
3
. Y
ouidentify possibleproblems that
will hinder implementing theplan.
4
. Y
ouidentify possibleproblems that
will hinder implementing theplan.
5
. Y
ouput Oinfront of thesolutions that are
practical andyouput Xinfront of the
solutions that arenot practical
Attheendyoueitherchangeyourplanwherethereisnopractical
solutionor prepareyourself accordingly
8.2.2 Perform Quality Assurance: T&Ts
8.2.2.1 Quality Management and Control Tools
• Besideother available tools,in quality assuranceweusall thetools that areusedin
PlanQuality Management andControl Quality Processes
Interrelationship Digraph
It is usedfor problemidentification andproblem solving in complex systems
Interrelationship Digraph isusually usedafter
Case-and-effect diagram, ideamindmapping,
affinitydiagram.
Hereweconstruct howdifferent problems are
relatedto eachother.
After constructingtheDigraph westart
interpreting it.
Interpretationcanbeas:
1. Anitemwith largenumberofoutputse.g“Poor
SchedulingPractice”canbecauseofmanyeffect
2. Anitemwith largenumberofinputse. g“Poor
SchedulingofTrucker”canbesourceof Quality
metrics.
8.2.2 Perform Quality Assurance: T&Ts
8.2.2.1 Quality Management and Control Tools
• Besideother available tools,in quality assuranceweusall thetools that areusedin
PlanQuality Management andControl Quality Processes
Tree Diagram
It is usedto showhowthe generalplan is related to specific parts e. gin WBS.Alsoit is usedto
seethe results of different decision that wemight bemakingin ourproject.
ThroughT
reeDiagramwelearnhowdifferent
decisioncanaffect ourproject.Howdoinga
processindifferent waycanhaveaneffecton
ourproduct.Or
T
reeDiagramwill helpusinbetter
understandingofthesituationandourfuture
decisions.
8.2.2 Perform Quality Assurance: T&Ts
8.2.2.1 Quality Management and Control Tools
• Besideother available tools,in quality assuranceweusall thetools that areusedin
PlanQuality Management andControl Quality Processes
Network Diagram: Network Diagram shows
how activates are connected to each other. It
helps us understand when are we going to
apply our quality procedures
Matrix Diagram: The matrix diagram shows
relationship between factors, causes, and
objectives.
8.2.2 Perform Quality Assurance: T&Ts
8.2.2.2 Quality Audits
• Qualityauditsareindependentreviewsofthequalityprocessesandproceduresof
anorganization.
• Quality audits candonerandomly or onscheduledbasesandcanbecarried
externally or internally
.
• Quality audits canconfirm implementation of approvedchanges, correctiveactions,
preventive action, ordefect repairs.
8.2.2.3 Process Analysis
• In ProcessAnalysis weimplemented theplan outlined as“ProcessImprovement
Plan” which wasanoutput to PlanQualityManagement process
• Hereweuseroot-causeanalysis which will helpusidentify problems in our
processesandtakepreventiveactions.
8.2.3.1 Change Requests
• Changerequests related to corrective,preventive, anddefectrepairare made.
8.2.3.2 Project Management Plan updates
• Quality ManagementPlan,ScopeManagement Plan, ScheduleManagementPlan,andCost
Management Planareupdated.
• Audit Reports,TrainingPlans, andProcessDocumentationareupdated.
8.2.3.3 Project DocumentUpdate
• Organizationquality standards andquality management systemsareupdated
8.2.3.4 OPA Updates
8.2.3 Perform Quality Assurance: Outputs
8.3 Control Quality: ITTOs
1.Project Management
Plan
2. Quality Metrics
3. Quality Checklists
4.W
orkPerformance
Data
5.Approved Change
Requests
6. Deliverables
7. Project Documents
8. OP
A
1.SevenBasic
QualityT
ools
2.Statistical
Sampling
3. Inspection
4.Approved change
requestsreview
1.Quality Control
Measurements
2. V
alidatedchanges
3. V
erifieddeliverables
4. W
orkPerf Info
5. Change Requests
6. Project Docupdates
7.Project MangtmPlan
updates
8. OP
Aupdates
Input Tools & Techniques Output
In Control Quality we monitor and record results from executing the quality
activities. We do this mainly for two reason:
1. To identify the cause for poor quality and request change, and 2 Validate the
deliverables to be accepted by stakeholders.
8.3 Control Quality
More Quality Concepts
Prevention Vs
Inspection
Prevention is about
keeping errors out of
process, and
Inspection is about
keeping errors out of
hands of the
customer
Tolerance Vs Control
Limits
Tolerance is a
specified range of
acceptable results,
and Control Limits is
about specifying
boundaries for a
stable process
Attribute Sampling
Vs Variable Sampling
The result of an
attribute either
conforms or does not
conforms, and the
result of variable is
on continue scale
with a degree
conformity
8.3.1.1 Project Management Plan
• QualityManagementPlanofthe Project Management Planis used
8.3.1.2 Quality Metrics
• It describes project or productsattributesandhowthey will bemeasured.
• Someexamplesare: FunctionPoints, MeanTimeBetweenFailure (MTBF), andMeanTimeto
Repair(MTTR)
Function Points: In IT, Function Points are used a unit of measurement to count the
number of function an information system providing to a business. The same as we use
hours to measure time.
MTBF: it shows the reliability of product. It specifies the time between two failures that a
product can have. For example an hard disk will have a failure after 300,000 hours.
MTTR: is the average amount of time a device or product will need to be repaired for a
given failure.
8.3.1 Control Quality: Inputs
8.3.1.3 Quality Checklists
• Alist that will help usverifythat ourwork will fulfill the requirements of the product.
8.3.1.4 Work Performance Data
• ThedatagatherfromactualwhichcanincludeplannedVsactualscheduleperformance, cost
performance andtechnicalperformance
• Thechangesrequestedmayincludedefectrepairs whichneedsto qualitycontrolled and
verified
8.1.3.5 ApprovedChangeRequests
8.3 Control Quality: Inputs
8.3.1.6 Deliverables
• Deliverables are validatedin Control Qualityprocess.
8.3.1.7 Project Documents
• Agreements, qualityauditdocuments,trainingplansandtheir assessment,process
documentation
• Organization’s qualitypolicies,defect reporting procedure,andcommunicationpolicy
8.3.1.8 OP
A
8.3 Control Quality: Inputs
8.3.2.1 The Seven Basic Quality Tools
• Thesewereexplainedin 8.1.2.3
8.3.2.2 Statistical Sampling
• Asdefined in the QualityManagementPlan,samplesareselected andtested
8.3.2.3 Inspection
• Inspectionrefers to the examinationof the product in order to determinewhetherit according
to the documentedstandards.
• Inspectioncanberelated to asingleactivity,part of product,or thewholeproduct.
• Inspectionarealsocalled,review,peerreviews,audits, orwalkthroughs.
• Inspectionsarealsousedtovalidatedefect repairs.
8.3.2.4ApprovedChangeRequestReviews
• All theapproved changerequests are reviewedtoverify they areimplementedasapproved.
8.3.2 Control Quality: T&Ts
8.3.3.1 Control Quality Measurements
• Control QualityMeasurements are the resultsof Control Qualityprocess
• Theseare inputto Perform QualityAssuranceprocess
8.3.3.2 Validated Changes
• Whenaproductis changedorrepaired afterapprovedchangesareimplemented,the change
or repair isvalidatedinControl Quality process.
• Thisis doneusingReviewApprovedChangeRequeststechnique
• Thechangeorrepaired doneis eithervalidatedorrejected
8.3.3.3 V
erifiedDeliverables
• Ofthe goalsof Control Qualityis to verify the correctness of deliverables
• Thusdeliverablesare eitherverifiedorrejectedfor repairor change
• Theverified deliverablesbecomesinputto ValidateScopeprocesswherethey are formally
acceptedor rejected.
8.3.3 Control Quality: Outputs
8.3.3.4. Work Performance Information
• WPIis performance related data that is output to manymonitoringandcontrolling
processes
• In this processWPIwill showprojects achievement of therequirements, information
aboutrejectionsandreasonsfortherejections, alsoreworkrequiredandneedfor
changeinquality processes
8.3.3.5 Change Requests
• Changerequests in the formof rework, repair, changeto management planetcare made.
• QualityManagement Plan, and
• ProcessImprovement Plansmight beupdated
8.3.3.6 Project Management PlanUpdates
8.3.3 Control Quality: Outputs
8.3.3.7 Project Document Updates
• Agreements, quality audit documents, training plans and their assessment,
process documentation
• Completed Checklists: When checklists are used, the documented
checklist becomes part of project document and OPA
• Lesson Learned Doc: The causes of variances, the reasoning behind the
corrective action selected, and other types of lessons learned stored as
OPA
8.3.3.8 OPA updates
8.3.3 Control Quality: Outputs

More Related Content

Similar to projectqualitymanagement-140816235544-phpapp02.pptx

Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Managementmzedan
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Quality management slides
Quality management slidesQuality management slides
Quality management slidesSaba Afaq
 
2.08 quality management 1
2.08 quality management 12.08 quality management 1
2.08 quality management 1reddvise
 
Product quality management
Product quality managementProduct quality management
Product quality managementSunil Meena
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PROJECT QUALITY KNOLEDGE AREA.ppt
PROJECT QUALITY KNOLEDGE    AREA.pptPROJECT QUALITY KNOLEDGE    AREA.ppt
PROJECT QUALITY KNOLEDGE AREA.pptRandolphRodrigues2
 
Quality management templates
Quality management templatesQuality management templates
Quality management templatesselinasimpson371
 
Episode 24 : Project Quality Management
Episode 24 :  Project Quality ManagementEpisode 24 :  Project Quality Management
Episode 24 : Project Quality ManagementSAJJAD KHUDHUR ABBAS
 
Quality management review template
Quality management review templateQuality management review template
Quality management review templateselinasimpson2801
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpointDjamadaMuhamedKAGUSU
 
Quality assurance
Quality assuranceQuality assurance
Quality assuranceRajThakuri
 
8.project qualitymanagement
8.project qualitymanagement8.project qualitymanagement
8.project qualitymanagementNiranjana K.R.
 
Quality management strategy template
Quality management strategy templateQuality management strategy template
Quality management strategy templateselinasimpson2701
 
Tools and Ways of Improving Quality.pptx
Tools and Ways of Improving Quality.pptxTools and Ways of Improving Quality.pptx
Tools and Ways of Improving Quality.pptxAbiolaOgunsanwo
 
L07 quality management
L07 quality managementL07 quality management
L07 quality managementAsa Chan
 

Similar to projectqualitymanagement-140816235544-phpapp02.pptx (20)

Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Chapter 08 - Updated
Chapter 08 - UpdatedChapter 08 - Updated
Chapter 08 - Updated
 
Quality management slides
Quality management slidesQuality management slides
Quality management slides
 
2.08 quality management 1
2.08 quality management 12.08 quality management 1
2.08 quality management 1
 
Product quality management
Product quality managementProduct quality management
Product quality management
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PROJECT QUALITY KNOLEDGE AREA.ppt
PROJECT QUALITY KNOLEDGE    AREA.pptPROJECT QUALITY KNOLEDGE    AREA.ppt
PROJECT QUALITY KNOLEDGE AREA.ppt
 
Quality management forms
Quality management formsQuality management forms
Quality management forms
 
Quality management templates
Quality management templatesQuality management templates
Quality management templates
 
8.2 Manage Quality
8.2 Manage Quality8.2 Manage Quality
8.2 Manage Quality
 
Episode 24 : Project Quality Management
Episode 24 :  Project Quality ManagementEpisode 24 :  Project Quality Management
Episode 24 : Project Quality Management
 
Quality management review template
Quality management review templateQuality management review template
Quality management review template
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpoint
 
Quality assurance
Quality assuranceQuality assurance
Quality assurance
 
8.project qualitymanagement
8.project qualitymanagement8.project qualitymanagement
8.project qualitymanagement
 
Quality management strategy template
Quality management strategy templateQuality management strategy template
Quality management strategy template
 
Tools and Ways of Improving Quality.pptx
Tools and Ways of Improving Quality.pptxTools and Ways of Improving Quality.pptx
Tools and Ways of Improving Quality.pptx
 
L07 quality management
L07 quality managementL07 quality management
L07 quality management
 
Total quality control
Total quality controlTotal quality control
Total quality control
 

More from HamzaKhawar4

Lec 20 - Design of Stair case- Longitudinally supported.pptx
Lec 20 - Design of Stair case- Longitudinally supported.pptxLec 20 - Design of Stair case- Longitudinally supported.pptx
Lec 20 - Design of Stair case- Longitudinally supported.pptxHamzaKhawar4
 
Lec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPT
Lec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPTLec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPT
Lec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPTHamzaKhawar4
 
Lec 7 - Design of Wall footing-Introduction.PPT
Lec 7 - Design of Wall footing-Introduction.PPTLec 7 - Design of Wall footing-Introduction.PPT
Lec 7 - Design of Wall footing-Introduction.PPTHamzaKhawar4
 
Lec 11 - Load transfer to the footing.pptx
Lec 11 - Load transfer to the footing.pptxLec 11 - Load transfer to the footing.pptx
Lec 11 - Load transfer to the footing.pptxHamzaKhawar4
 
Lec 21 - Prestressed Concrete-Introduction.pptx
Lec 21 - Prestressed Concrete-Introduction.pptxLec 21 - Prestressed Concrete-Introduction.pptx
Lec 21 - Prestressed Concrete-Introduction.pptxHamzaKhawar4
 
Lec 25 - Earthquake Anlaysis Procedure.pptx
Lec 25 - Earthquake Anlaysis Procedure.pptxLec 25 - Earthquake Anlaysis Procedure.pptx
Lec 25 - Earthquake Anlaysis Procedure.pptxHamzaKhawar4
 
Lec 12 - Design of Rectangular footing.PPT
Lec 12 - Design of Rectangular footing.PPTLec 12 - Design of Rectangular footing.PPT
Lec 12 - Design of Rectangular footing.PPTHamzaKhawar4
 
Lecture 01- Elastic Response Spectra.pptx
Lecture 01- Elastic Response Spectra.pptxLecture 01- Elastic Response Spectra.pptx
Lecture 01- Elastic Response Spectra.pptxHamzaKhawar4
 
Project Management Planning and Scheduling
Project Management Planning and SchedulingProject Management Planning and Scheduling
Project Management Planning and SchedulingHamzaKhawar4
 

More from HamzaKhawar4 (9)

Lec 20 - Design of Stair case- Longitudinally supported.pptx
Lec 20 - Design of Stair case- Longitudinally supported.pptxLec 20 - Design of Stair case- Longitudinally supported.pptx
Lec 20 - Design of Stair case- Longitudinally supported.pptx
 
Lec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPT
Lec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPTLec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPT
Lec 18 - Cantilever Retaining Walls-Design and Detailing Continued.PPT
 
Lec 7 - Design of Wall footing-Introduction.PPT
Lec 7 - Design of Wall footing-Introduction.PPTLec 7 - Design of Wall footing-Introduction.PPT
Lec 7 - Design of Wall footing-Introduction.PPT
 
Lec 11 - Load transfer to the footing.pptx
Lec 11 - Load transfer to the footing.pptxLec 11 - Load transfer to the footing.pptx
Lec 11 - Load transfer to the footing.pptx
 
Lec 21 - Prestressed Concrete-Introduction.pptx
Lec 21 - Prestressed Concrete-Introduction.pptxLec 21 - Prestressed Concrete-Introduction.pptx
Lec 21 - Prestressed Concrete-Introduction.pptx
 
Lec 25 - Earthquake Anlaysis Procedure.pptx
Lec 25 - Earthquake Anlaysis Procedure.pptxLec 25 - Earthquake Anlaysis Procedure.pptx
Lec 25 - Earthquake Anlaysis Procedure.pptx
 
Lec 12 - Design of Rectangular footing.PPT
Lec 12 - Design of Rectangular footing.PPTLec 12 - Design of Rectangular footing.PPT
Lec 12 - Design of Rectangular footing.PPT
 
Lecture 01- Elastic Response Spectra.pptx
Lecture 01- Elastic Response Spectra.pptxLecture 01- Elastic Response Spectra.pptx
Lecture 01- Elastic Response Spectra.pptx
 
Project Management Planning and Scheduling
Project Management Planning and SchedulingProject Management Planning and Scheduling
Project Management Planning and Scheduling
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 

projectqualitymanagement-140816235544-phpapp02.pptx

  • 1. Ch.8 Project Quality Management Pages 226 - 254 of PMBOK Guide 5th Edition
  • 2. Ch.8 Project Quality Management Quality Management includes creating and following policies and procedures to ensure that a project meet the defined needs (from the customer’s perspective). Quality definitions and concepts Prevention is the better than control. Do it right the first time. Zero Defects is the goal of quality. Philip Crosby Quality is defined as the degree to which the project fulfills requirements. Or quality means fitness for use. Joseph Juran Quality relates to continues improvement of people and procedures. Kaizan Quality relates to processes and procedures not people. Or quality is the management’s problem. Management needs to provide the procedures and resources for the employees to produce quality product. Edwards Deming Quality Management is applying the processes that will ensure the project will meet the needs for which it was undertaken Quality Vs Grade Vs Gold Plating? Quality is the degree to which a set of inherent characteristics fulfill requirements” (ISO 9000) Quality definitions and concepts Quality Management is applying the processes that will ensure the project will meet the needs for which it was undertaken Quality is defined as the degree to which the project fulfills requirements. Or quality means fitness for use. Joseph Juran Quality is the degree to which a set of inherent characteristics fulfill requirements” (ISO 9000) Quality relates to processes and procedures not people. Or quality is the management’s problem. Management needs to provide the procedures and resources for the employees to produce quality product. Edwards Deming Prevention is the better than control. Do it right the first time. Zero Defects is the goal of quality. Philip Crosby Quality relates to continues improvement of people and procedures. Kaizan Quality Vs Grade Vs Gold Plating?
  • 3. Ch.8 Processes of Quality Management 8.1 Plan Quality Management • The process of identifying project’s quality requirements and how the these requirements will be met. 8.2 Perform Quality Assurance • Here we apply the quality requirements and audit results from quality control process to ensure proper procedures are applied. • In this process we measure and record quality requirements to ensure quality is achieved and recommend changes if needed. 8.3 Control Quality
  • 4. 8.1 Plan Quality Management: ITTOs 1.Project Management Plan 2. Stakeholder register 3. RiskRegister 4.Requirements documentation 6. EEF/OP A 1. Costbenefit analysis 2. Costof Quality (CoQ) 3. Benchmarking 4. Designof experiments 5. Statistical sampling 6.Additional quality planning tools 7. Meetings 8. Sevenbasicquality techniques 1.Quality management plan 2. Quality metrics 3. Quality checklists 4.Process improvement plan 5.Project document updates The process of identifying quality requirement and/or standards for the project and product and documenting how the project will demonstrate compliance. What is quality for this project ? How will we ensure it? Input Tools & Techniques Output
  • 5. 8.1 Plan Quality Management: Data Flow Diagram
  • 6. 8.1.1.1 Project Management Plan • Scope Baseline: The Scope Statement of Scope Baseline gives us important information related to project quality. The scope statements contains project deliverables and acceptance criteria for these deliverable. • The acceptance criteria can greatly affect the project quality requirements hence cost of quality or cost of project as a whole. • Other elements of the PMP used for planning the quality are the Schedule Baseline and Cost Baseline which tells us when the work is needed to be done and when the money is going to be spent. • It tells us about the stakeholder that are concerned with quality aspect of the project 8.1.1.2 Stakeholder Register 8.1 Plan Quality Management: Inputs
  • 7. • It contains information about the risks that may affect the quality of the project 8.1.1.3 Risk Register 8.1.1.4 Requirements Documentation • The requirements documentation includes stakeholder requirements about the project, product, and quality of the product. • Requirements documentation will help us better plan Control Quality Process • Government Regulations, Industry Standards, Policies and Procedures, Historical Information etc 8.1.1.5 EEF/OPA 8.1 Plan Quality Management: Inputs
  • 8. 8.1.2.1 Cost Benefit Analysis • Themainreasonbehindmaintaining qualityisto havelessrework, lowercosts, higher productivity , andhighercostumer satisfaction • In CostBenefitAnalysis wecompare benefitsversusthe costof meeting qualityrequirements 8.1.2.1 Cost of Quality • Lookingatwhatthe costof conformanceandnonconformanceto qualityandcreatingan appropriate balance Should be less than 8.1.2 Plan Quality Management: T&Ts <
  • 9. 8.1.2.3 Seven basic quality tools • The 7QC tools as they are called, are used in within the context of Plan-Do- Check-Act (PDCA) cycle to solve quality related problems 8.1.2 Plan Quality Management: T&Ts Theproblem(theEffect) isplacedat theheadof fishandthepossiblesourceof theproblem(the Cause)issought after inthefour factors (Machine, Man, Methods, andMaterials). Thewholeprocessisconduct inbrainstorming sessions.Thestepsinvolvedareasfollow: 1. Identifytheproblem. 2. W orkout themajor factors involved. 3. Identifypossiblecauses. 4. Analyzeyour diagram Y oucanalsoaddfactors suchasEnvironment, andMaterialsor anyotherfactor deemed related. Major causesarefurther investigated.Attheendthewhole diagramis analyzedandpossiblecauseorcausesareidentified. 1. Cause-and-effect Diagram: Cause-and-effect diagram or fishbone diagram or Ishikawa diagram is used to find possible causes of a problem or failure
  • 10. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts Flowchart showslogicalrelationship betweendifferent process. Flowchart helpsusinbetter understandingtheprocess Flowchart isalsoagood communicationwhichshowswhat reallyhappensinprocessorwhat shouldhappen. Flowchartsalsoshowsdecision pointsinaprocess Flowchart will helpusinbetter understandingthecostsrelatedto qualityrequirements 2. Flowcharts: Also called process maps, because flowcharts display sequence of steps. The flowchart transforms one or more input to one or more outputs.
  • 11. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts 2. Flowcharts: Also called process maps, because flowcharts display sequence of steps. The flowchart transforms one or more input to one or more outputs.
  • 12. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts 2. Flowcharts: Also called process maps, because flowcharts display sequence of steps. The flowchart transforms one or more input to one or more outputs.
  • 13. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts Checksheets tellsusabout a problemandits frequencyof occurrence. Diagrams. Dataobtained through Checksheetsare oftenusedfor generating Pareto Diagrams. 3. Checksheet: Checksheets or tally sheet are used to collect used to collect useful data about a problem or its attributes when performing inspections. Cheeksheets can also be used checklist.
  • 14. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts ParetoDiagram isaspecial type of vertical bar chart that shows frequencyof the sourcesof a problemand cumulative percentageof all vital sources Thebarsshow eachsourceand thelineshows commutative total 4. Pareto Diagrams: Pareto thought 80 percent of the quality related problems are effects of 20 percent of the causes.
  • 15. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts Inthisexamplethe distributionof datais basedonabell curve. Thenamecomesfrom it shapewhichlikea bell. Inthisexamplethe highest frequencyof themeasurementwas between20and22. The occurrence/frequency for thismeasurement iscloseto28times. 5. Histograms: Histograms are special types of bar charts that show central tendency, dispersion, and shape of statistical distribution.
  • 16. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts If weget 7resultsonthe eithersideof themean, we concludethat theprocessis out of control, see4.Alsoif a measurement isout of control limitsweconcludethat the processisout of control, see 3. Control Chartsarealsoused todetermineif amanagement processisincontrol by measuringfactors like scheduleor cost variances, or thefrequencyof changesinto scopeetc. 1.Upper control limit 2. Lower control limit 3. Out of control 5.Specification limit: is point determines by customer, not calculated based on control chart 4. Rule of seven: Out of control if 7 measurements are above or below the mean 6. Normal and expected variation Usually 3 or 6 sigma 6. Control Charts: Control Charts are used to know whether a process is stable or has the desired performance. Control Charts are used for repetitive process e.g manufacturing
  • 17. 8.1.2.3 Seven basic quality tools • The7QCtoolsasthey are called,are usedin within the context of Plan-Do-Check-Act(PDCA) cycletosolvequalityrelated problems 8.1.2 Plan Quality Management: T&Ts Onceweknowthat thereisa correlationbetweenthetwo variablesthenwecan estimatehowchangesto independentvariablecan result inachangeinthe dependent variable. Grapha, b, c, anddshow different correlationthat may exist betweentwovariables. For exampleingraphbtheY axismayshownumberof iterationandXaxismay shownumber of bugsfound inthesoftware. 7. Scatter Diagram: Scatter Diagram is used to check for correlation between two variables
  • 18. 8.1.2.4 Benchmarking • Comparingthe project in handwith similarprojectscompletedin the past in order to identify best practices, andgenerate newideas. 8.1.2.5 Design of Experiment • DOEis usedto identify factorsthat caninfluencedifferent variablesofthe productorprocess • DOEis usedin PlanQualityManagementto determinethe numberandtype of tests needed toachievetherequiredquality 8.1 Plan Quality Management: T&Ts InDOEwecanchangemultiplevariablesat a time.Indoingsowefindoptimalconditionfor product or process. Imaginetheexampleontheleft isabout producingbrickunderdifferent conditionsorwith aninputofdifferentproportions ofthe materials Onceweknowthatvariousfactorscaninfluence ourproductin various ways, wewill develop testsor qualitychecklist for them.
  • 19. 8.1.2.6 Statistical Sampling • Statistical Samplingrefers to choosingfewitemsasasamplefrom alarger groupof items. • Herewedonot dothe actualsamplingbutdecideonhowwewill dohowsamplinginthe comingqualityprocesses • Thiswill helpusin correctlydetermining thecostof quality. 8.1.2.7 Other Quality Tools • Brainstorming: Usedfor generatingideas • ForceFieldAnalysis: Diagramsof forces for andagainstchange • Nominal GroupTechnique: Inthis technique wevotefor ideasto befurther discussedbya larger groupof people • Quality ControlandManagementTools:Thistoolswill beexplainedin the next process. Thesetoolsareusedto link andsequencethe toolsof the project. 8.1.2.8 Meetings • Qualityrelated meetingsareattendedbytheprojectsponsor,project management,selected projectteammember,selectedstakeholders,teammembersthatareresponsibleforqualityof theproject. 8.1 Plan Quality Management: T&Ts
  • 20. 8.1 Plan Quality Management: T&Ts Below is an example of force-field diagram In the force-field you basically identify the force that will support or oppose a planned work which usually is something related to change. In the force-field you basically identify the force the will support or oppose the change. This will help you better understand the situation and plan you quality accordingly.
  • 21. 8.1.3.1 Quality Management Plan • Qualitymanagementplansexplainshoworganizationsqualitypolicieswill beimplemented. • Dependingonthe project,theplancanbeverydetailedorsimple. 8.1.3.2 Process Improvement Plan • ProcessImprovement Planispart of the PMP • Thisplandetailsthe steps that will help asin improvingvarious processin ourproject. • Theplanis developedin the PlanQualityManagement Processandimplementedin the QA andQCprocesses 8.1 Plan Quality Management: Outputs Areas included in the Process Improvement Plan are as follow: 1. Process Boundaries: The propose of the process, the start and end date, the inputs and outputs of the process 2. Process Configuration: Graphical depiction of the process 3. Process Metric: Used for measuring process efficiency 4. Targets for Improved Performance: Targets for improvement
  • 22. 8.1.3.3 Quality Metrics • It describes the project orproductattributesandhowthe qualitycontrol processwill measure it. • Examplesof qualitymetrics are finishingthe project withinthe budgetandtime, the frequency of defects, failure rate, etc. • Themetrics andthe tolerancelevelfor variation is set in PlanQuality • Theattributesaremeasuredincontrol quality 8.1.3.4 Quality Checklists • Basedonthe productrequirementsachecklistis developed • Thechecklistwill list the steps to befollowed to achievethe desired qualityfor the product • Thechecklistshouldalsocontain the productrequirements 8.1.3.5 Document Update • RiskRegister, RequirementTraceability Matrix, andWBSdictionary are updated 8.1 Plan Quality Management: Outputs
  • 23. 8.2 Perform Quality Assurance: ITTOs 1. Quality Management Plan 2.ProcessImprovement Plan Quality metrics 3.Quality control measurement 4. Project Documents 1.Quality Management and Control T ools 2. Quality audits 3. Processanalysis 1.Change Requests 2.Project management planupdates 3.Project document updates 4. OP Aupdates Input Tools & Techniques Output In Quality Assurance we ensure the proper quality related procedures are followed. We do this by auditing the quality requirements and results received from Quality Control Process
  • 24. 8.2 Perform Quality Assurance: Data Flow Diagram
  • 25. 8.2.1 Perform Quality Assurance: Inputs 8.2.1.1 Quality Management Plan • It contains planfor quality assuranceandprocessimprovement 8.2.1.2 Process Improvement Plan • Thiswill tell usaboutthe project’s processimprovement plan which needsto be alignedwith quality assuranceprocess. 8.2.1.3 Quality Metrics • Thiswill tells what weneedto measureandwhat arethe allowable variation for our measurements. 8.2.1.4 Quality Control Measurements • Thesearethemeasurements takenintheControl Quality Process • Themeasurements areusedfedbackto QualityAssuranceinorder toevaluate the effectiveness of quality assuranceprocedures/processes
  • 26. 8.2.2 Perform Quality Assurance: T&Ts 8.2.2.1 Quality Management and Control Tools • Besideother available tools,in quality assuranceweusall thetools that areusedin PlanQuality Management andControl Quality Processes Affinity Diagram……? • Classifying large number of ideas into groups
  • 27. 8.2.2 Perform Quality Assurance: T&Ts 8.2.2.1 Quality Management and Control Tools • Besideother available tools,in quality assuranceweusall thetools that areusedin PlanQuality Management andControl Quality Processes Process Decision Program Chart (PDPC) PDPC systematically identifies what might go wrong in a plan under development. 1. Y oudivided in andsubdividea complexplaninto more simple steps 3 . Y ouidentify possibleproblems that will hinder implementing theplan. 4 . Y ouidentify possibleproblems that will hinder implementing theplan. 5 . Y ouput Oinfront of thesolutions that are practical andyouput Xinfront of the solutions that arenot practical Attheendyoueitherchangeyourplanwherethereisnopractical solutionor prepareyourself accordingly
  • 28. 8.2.2 Perform Quality Assurance: T&Ts 8.2.2.1 Quality Management and Control Tools • Besideother available tools,in quality assuranceweusall thetools that areusedin PlanQuality Management andControl Quality Processes Interrelationship Digraph It is usedfor problemidentification andproblem solving in complex systems Interrelationship Digraph isusually usedafter Case-and-effect diagram, ideamindmapping, affinitydiagram. Hereweconstruct howdifferent problems are relatedto eachother. After constructingtheDigraph westart interpreting it. Interpretationcanbeas: 1. Anitemwith largenumberofoutputse.g“Poor SchedulingPractice”canbecauseofmanyeffect 2. Anitemwith largenumberofinputse. g“Poor SchedulingofTrucker”canbesourceof Quality metrics.
  • 29. 8.2.2 Perform Quality Assurance: T&Ts 8.2.2.1 Quality Management and Control Tools • Besideother available tools,in quality assuranceweusall thetools that areusedin PlanQuality Management andControl Quality Processes Tree Diagram It is usedto showhowthe generalplan is related to specific parts e. gin WBS.Alsoit is usedto seethe results of different decision that wemight bemakingin ourproject. ThroughT reeDiagramwelearnhowdifferent decisioncanaffect ourproject.Howdoinga processindifferent waycanhaveaneffecton ourproduct.Or T reeDiagramwill helpusinbetter understandingofthesituationandourfuture decisions.
  • 30. 8.2.2 Perform Quality Assurance: T&Ts 8.2.2.1 Quality Management and Control Tools • Besideother available tools,in quality assuranceweusall thetools that areusedin PlanQuality Management andControl Quality Processes Network Diagram: Network Diagram shows how activates are connected to each other. It helps us understand when are we going to apply our quality procedures Matrix Diagram: The matrix diagram shows relationship between factors, causes, and objectives.
  • 31. 8.2.2 Perform Quality Assurance: T&Ts 8.2.2.2 Quality Audits • Qualityauditsareindependentreviewsofthequalityprocessesandproceduresof anorganization. • Quality audits candonerandomly or onscheduledbasesandcanbecarried externally or internally . • Quality audits canconfirm implementation of approvedchanges, correctiveactions, preventive action, ordefect repairs. 8.2.2.3 Process Analysis • In ProcessAnalysis weimplemented theplan outlined as“ProcessImprovement Plan” which wasanoutput to PlanQualityManagement process • Hereweuseroot-causeanalysis which will helpusidentify problems in our processesandtakepreventiveactions.
  • 32. 8.2.3.1 Change Requests • Changerequests related to corrective,preventive, anddefectrepairare made. 8.2.3.2 Project Management Plan updates • Quality ManagementPlan,ScopeManagement Plan, ScheduleManagementPlan,andCost Management Planareupdated. • Audit Reports,TrainingPlans, andProcessDocumentationareupdated. 8.2.3.3 Project DocumentUpdate • Organizationquality standards andquality management systemsareupdated 8.2.3.4 OPA Updates 8.2.3 Perform Quality Assurance: Outputs
  • 33. 8.3 Control Quality: ITTOs 1.Project Management Plan 2. Quality Metrics 3. Quality Checklists 4.W orkPerformance Data 5.Approved Change Requests 6. Deliverables 7. Project Documents 8. OP A 1.SevenBasic QualityT ools 2.Statistical Sampling 3. Inspection 4.Approved change requestsreview 1.Quality Control Measurements 2. V alidatedchanges 3. V erifieddeliverables 4. W orkPerf Info 5. Change Requests 6. Project Docupdates 7.Project MangtmPlan updates 8. OP Aupdates Input Tools & Techniques Output In Control Quality we monitor and record results from executing the quality activities. We do this mainly for two reason: 1. To identify the cause for poor quality and request change, and 2 Validate the deliverables to be accepted by stakeholders.
  • 34. 8.3 Control Quality More Quality Concepts Prevention Vs Inspection Prevention is about keeping errors out of process, and Inspection is about keeping errors out of hands of the customer Tolerance Vs Control Limits Tolerance is a specified range of acceptable results, and Control Limits is about specifying boundaries for a stable process Attribute Sampling Vs Variable Sampling The result of an attribute either conforms or does not conforms, and the result of variable is on continue scale with a degree conformity
  • 35. 8.3.1.1 Project Management Plan • QualityManagementPlanofthe Project Management Planis used 8.3.1.2 Quality Metrics • It describes project or productsattributesandhowthey will bemeasured. • Someexamplesare: FunctionPoints, MeanTimeBetweenFailure (MTBF), andMeanTimeto Repair(MTTR) Function Points: In IT, Function Points are used a unit of measurement to count the number of function an information system providing to a business. The same as we use hours to measure time. MTBF: it shows the reliability of product. It specifies the time between two failures that a product can have. For example an hard disk will have a failure after 300,000 hours. MTTR: is the average amount of time a device or product will need to be repaired for a given failure. 8.3.1 Control Quality: Inputs
  • 36. 8.3.1.3 Quality Checklists • Alist that will help usverifythat ourwork will fulfill the requirements of the product. 8.3.1.4 Work Performance Data • ThedatagatherfromactualwhichcanincludeplannedVsactualscheduleperformance, cost performance andtechnicalperformance • Thechangesrequestedmayincludedefectrepairs whichneedsto qualitycontrolled and verified 8.1.3.5 ApprovedChangeRequests 8.3 Control Quality: Inputs
  • 37. 8.3.1.6 Deliverables • Deliverables are validatedin Control Qualityprocess. 8.3.1.7 Project Documents • Agreements, qualityauditdocuments,trainingplansandtheir assessment,process documentation • Organization’s qualitypolicies,defect reporting procedure,andcommunicationpolicy 8.3.1.8 OP A 8.3 Control Quality: Inputs
  • 38. 8.3.2.1 The Seven Basic Quality Tools • Thesewereexplainedin 8.1.2.3 8.3.2.2 Statistical Sampling • Asdefined in the QualityManagementPlan,samplesareselected andtested 8.3.2.3 Inspection • Inspectionrefers to the examinationof the product in order to determinewhetherit according to the documentedstandards. • Inspectioncanberelated to asingleactivity,part of product,or thewholeproduct. • Inspectionarealsocalled,review,peerreviews,audits, orwalkthroughs. • Inspectionsarealsousedtovalidatedefect repairs. 8.3.2.4ApprovedChangeRequestReviews • All theapproved changerequests are reviewedtoverify they areimplementedasapproved. 8.3.2 Control Quality: T&Ts
  • 39. 8.3.3.1 Control Quality Measurements • Control QualityMeasurements are the resultsof Control Qualityprocess • Theseare inputto Perform QualityAssuranceprocess 8.3.3.2 Validated Changes • Whenaproductis changedorrepaired afterapprovedchangesareimplemented,the change or repair isvalidatedinControl Quality process. • Thisis doneusingReviewApprovedChangeRequeststechnique • Thechangeorrepaired doneis eithervalidatedorrejected 8.3.3.3 V erifiedDeliverables • Ofthe goalsof Control Qualityis to verify the correctness of deliverables • Thusdeliverablesare eitherverifiedorrejectedfor repairor change • Theverified deliverablesbecomesinputto ValidateScopeprocesswherethey are formally acceptedor rejected. 8.3.3 Control Quality: Outputs
  • 40. 8.3.3.4. Work Performance Information • WPIis performance related data that is output to manymonitoringandcontrolling processes • In this processWPIwill showprojects achievement of therequirements, information aboutrejectionsandreasonsfortherejections, alsoreworkrequiredandneedfor changeinquality processes 8.3.3.5 Change Requests • Changerequests in the formof rework, repair, changeto management planetcare made. • QualityManagement Plan, and • ProcessImprovement Plansmight beupdated 8.3.3.6 Project Management PlanUpdates 8.3.3 Control Quality: Outputs
  • 41. 8.3.3.7 Project Document Updates • Agreements, quality audit documents, training plans and their assessment, process documentation • Completed Checklists: When checklists are used, the documented checklist becomes part of project document and OPA • Lesson Learned Doc: The causes of variances, the reasoning behind the corrective action selected, and other types of lessons learned stored as OPA 8.3.3.8 OPA updates 8.3.3 Control Quality: Outputs