SlideShare a Scribd company logo
1 of 9
- a proposal for advance project control -
• The intent of this paper is to introduce an alternative method in steps, to forecast how far the risk
reserve fund can be reduced or “drawdown” and at the same time, still ensure that adequate
money remains for the duration of the project.
• In order to effectively maintain adequate reserve fund, Manager, Cost Controller, Project Planner
and Project Manager must develop a plan together which defines the detailed parameter
necessary before make judgments.
• The plan, termed a Risk Reserve drawdown model, depicts what percentage of risk reserve fund
should be released in relation to the planned commitment of project resources.
• Term “Risk Reserve” are used because the plan only takes into account all known uncertain events
except show stoppers and game changers. With that as the case, the reflection of general
uncertainties, design allowance, cost escalation and fluctuations are excluded.
Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with
any company nor any project that has completed/currently going on.
We are using cumulative planned value of throughout the project execution to generate s-curve. The
breakdown of the project stages are depicted are overlaid.
Engineering
Procurement – Major Equipment
Procurement – Bulk Materials
Construction/Installation
Completion
Step 1:
• We are using Primavera Risk Analysis: Quantitative tab function to get the spread duration of
activities which risk is assigned to.
Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or
currently going on.
Step 2:
• Using 3 points estimate of cost impact and @Risk functions, the desired confidence level (taking at
P90) for each risk is calculated using Monte Carlo simulation.
• This figure is divided to a period of activities and spread equally in accordance to which the period of
activities is effective.
• Run a cumulative balance risk exposure in percentage format and on monthly basis. Plot the date at
the same chart (see next slide)
Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or
currently going on.
P90/Months
Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or
currently going on.
Risk Reserve fund as a percent (%) of total planned value
Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or
currently going on.
Engineering
Procurement – Major Equipment
Procurement – Bulk Materials
Construction/Installation
Completion
High reserve when project at Engineering stage.
Low reserve when project approaches completion .
• Management of risk reserve funds is a vital part of the project control effort. It is the responsibility
of project management to ensure that these funds are controlled and kept in sufficiently in
accordance with their intended purpose as documented in the project estimate.
• By analyzing the dependent of variance activities, and by utilizing a planned drawdown model and
commitment curve, this plan will provide project management with timely information and ensure
that adequate risk reserve funds are maintained throughout project lifecycle.
Risk reserve management model

More Related Content

What's hot

Cash flow report using ms project
Cash flow report  using ms projectCash flow report  using ms project
Cash flow report using ms projectKundan Sanap
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Mihai Buta
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction IndustryIntaver Insititute
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM Mati Polak
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Anakinzs
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisIntaver Insititute
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
RiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas IndustryRiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas IndustryIntaver Insititute
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementMike Tulkoff
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisProject Controls Expo
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
10 tips to create accurate project estimates
10 tips to create accurate project estimates10 tips to create accurate project estimates
10 tips to create accurate project estimatesVeronika Tondon
 
Complementing Approaches in ERP Effort Estimation Practice: an Industrial Study
Complementing Approaches in ERP Effort Estimation Practice: an Industrial StudyComplementing Approaches in ERP Effort Estimation Practice: an Industrial Study
Complementing Approaches in ERP Effort Estimation Practice: an Industrial Studygregoryg
 

What's hot (17)

Cash flow report using ms project
Cash flow report  using ms projectCash flow report  using ms project
Cash flow report using ms project
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
RiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas IndustryRiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas Industry
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
10 tips to create accurate project estimates
10 tips to create accurate project estimates10 tips to create accurate project estimates
10 tips to create accurate project estimates
 
Complementing Approaches in ERP Effort Estimation Practice: an Industrial Study
Complementing Approaches in ERP Effort Estimation Practice: an Industrial StudyComplementing Approaches in ERP Effort Estimation Practice: an Industrial Study
Complementing Approaches in ERP Effort Estimation Practice: an Industrial Study
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 

Similar to Risk reserve management model

PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesRicardo Leite
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM Divante
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
software-project-management-unit-2.ppt
software-project-management-unit-2.pptsoftware-project-management-unit-2.ppt
software-project-management-unit-2.pptMaanbahadurkhadka
 
software-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfsoftware-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfVinoth Kumar
 
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxTemplates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxmattinsonjanel
 
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docxFIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docxmydrynan
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkitsIT-Toolkits.org
 
W4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxW4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxcelenarouzie
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.commkhilauria
 
Project Management
Project ManagementProject Management
Project ManagementPrarthan P
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptxAberraBeri
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.pptUjalaBatool7
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 
UNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docx
UNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docxUNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docx
UNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docxouldparis
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1ghulam MUSTAFA
 

Similar to Risk reserve management model (20)

PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
software-project-management-unit-2.ppt
software-project-management-unit-2.pptsoftware-project-management-unit-2.ppt
software-project-management-unit-2.ppt
 
software-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfsoftware-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdf
 
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxTemplates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
 
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docxFIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
 
W4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxW4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docx
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.com
 
Project Management
Project ManagementProject Management
Project Management
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptx
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
Unit 2.pptx
Unit 2.pptxUnit 2.pptx
Unit 2.pptx
 
Value chain analysis 4
Value chain analysis 4Value chain analysis 4
Value chain analysis 4
 
UNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docx
UNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docxUNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docx
UNIT 14 GROUP ASSIGNMENTPart 11. Describe how a project manager ca.docx
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 

Recently uploaded

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...ssuserdfc773
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information SystemsAnge Felix NSANZIYERA
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxhublikarsn
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257subhasishdas79
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 

Recently uploaded (20)

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 

Risk reserve management model

  • 1. - a proposal for advance project control -
  • 2. • The intent of this paper is to introduce an alternative method in steps, to forecast how far the risk reserve fund can be reduced or “drawdown” and at the same time, still ensure that adequate money remains for the duration of the project. • In order to effectively maintain adequate reserve fund, Manager, Cost Controller, Project Planner and Project Manager must develop a plan together which defines the detailed parameter necessary before make judgments. • The plan, termed a Risk Reserve drawdown model, depicts what percentage of risk reserve fund should be released in relation to the planned commitment of project resources. • Term “Risk Reserve” are used because the plan only takes into account all known uncertain events except show stoppers and game changers. With that as the case, the reflection of general uncertainties, design allowance, cost escalation and fluctuations are excluded. Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed/currently going on.
  • 3. We are using cumulative planned value of throughout the project execution to generate s-curve. The breakdown of the project stages are depicted are overlaid. Engineering Procurement – Major Equipment Procurement – Bulk Materials Construction/Installation Completion
  • 4. Step 1: • We are using Primavera Risk Analysis: Quantitative tab function to get the spread duration of activities which risk is assigned to. Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or currently going on.
  • 5. Step 2: • Using 3 points estimate of cost impact and @Risk functions, the desired confidence level (taking at P90) for each risk is calculated using Monte Carlo simulation. • This figure is divided to a period of activities and spread equally in accordance to which the period of activities is effective. • Run a cumulative balance risk exposure in percentage format and on monthly basis. Plot the date at the same chart (see next slide) Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or currently going on. P90/Months
  • 6. Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or currently going on. Risk Reserve fund as a percent (%) of total planned value
  • 7. Disclaimer: The data used to support presentation here is taken from a dummy project, purposely created to support the presentation. It has no relation with any company nor any project that has completed or currently going on. Engineering Procurement – Major Equipment Procurement – Bulk Materials Construction/Installation Completion High reserve when project at Engineering stage. Low reserve when project approaches completion .
  • 8. • Management of risk reserve funds is a vital part of the project control effort. It is the responsibility of project management to ensure that these funds are controlled and kept in sufficiently in accordance with their intended purpose as documented in the project estimate. • By analyzing the dependent of variance activities, and by utilizing a planned drawdown model and commitment curve, this plan will provide project management with timely information and ensure that adequate risk reserve funds are maintained throughout project lifecycle.