SlideShare a Scribd company logo
1 of 19
Risk Adjusted Project Schedules
Intaver Institute Inc.
400, 7015 Macleod Trail S.W, Calgary, AB, Canada
Tel: +1(403)692-2252
www.intaver.com
Objectives
• Goal to create realistic or “credible” project plans
• Identify and manage critical risks
• Monte Carlo risk analysis
• Calculate model and risk appropriate schedule margin and
contingency reserve
Risk adjusted project plans allow projects to
withstand impact of foreseen and unforeseen
circumstances
www.intaver.com Intaver Institute Inc.
Sources of Risk
www.intaver.com Intaver Institute Inc.
Discrete Risks
•Risk events that can directly impact project objectives Technical, Schedule,
Cost.
•Characterized by probability of occurrence and impacts and period of exposure
(sunrise and sunset)
•Are “reducible” – they can be managed or eliminated give sufficient effort
Uncertainties
•Natural variance caused by randomness in all processes
•Characterized using statistical distributions that capture most likely and
boundary estimates (Low and High)
•Are “irreducible” – they cannot be reduced
Building Risk Adjusted Plans
www.intaver.com Intaver Institute Inc.
1 Create WBS. WBS is primarily developed using Scope of Work.
2 Create Integrated Management Plan. IMP provides high level
structure for program deliverables, technical measures of success
as well as cost and schedule estimates
3 Analyze and manage risks. Identify, assess, and manage reducible
risks for every WBS item in the plan.
Manage Discrete Risks
www.intaver.com Intaver Institute Inc.
1. Identify Risks
o What events could impact key objectives
1. What are the impacts?
o Assess the impact of a risk event occurring on technical, cost
and schedule measures.
1. What can you do about it?
o What is your risk strategy: Avoid, Transfer, Mitigate, or Accept
o If mitigate, create mitigation plan with activities that will reduce
probability and impact.
o Residual risk (cost, schedule) added to contingency reserve
Assign Risks to WBS
www.intaver.com Intaver Institute Inc.
Drag selected risk and drop it on the
task; define risk probabilities and
impacts
Assess Risks
www.intaver.com Intaver Institute Inc.
Risks are initially assessed using Risk Matrix or Risk
Register Prioritization
Risk Planning
www.intaver.com Intaver Institute Inc.
• Mitigation activities for each risk are
modeled to waterfall chart
• Mitigation activities are added to the
schedule with associated dates, costs
and durations
• Successful completion of mitigation
activities in schedule are tracked and
updated in risk register.
Contingency and Management Reserves
www.intaver.com Intaver Institute Inc.
• Contingency and Margin cover “known unknowns”
o Residual risk from known risks (manageable)
o Natural variance in project performance (unmanageable)
o Does not cover scope changes
• Management Reserves cover unknown unknowns
o Risks not previously identified, etc.
Managing Irreducible Risk
www.intaver.com Intaver Institute Inc.
• Modeling irreducible risk is used to develop Schedule
margins for the Program
• Uncertainties are modeled using 3 pt. estimates (L, ML, H)
• Use all available information including SME opinion,
previous analogous projects
• Uncertainty should be added to all tasks in relation to their
known and forecasted level of uncertainty.
Monte Carlo is Essential
www.intaver.com Intaver Institute Inc.
Monte Carlo Simulations
Contingency and Management Reserves
www.intaver.com Intaver Institute Inc.
$Cost
Time
Contingency
Margin
MR
P80
P80
x
x
Unmanaged Risks and Contingency
www.intaver.com Intaver Institute Inc.
• Impact of unmanaged and
residual risks added to
contingency
• Contingency is difference
between baseline and level
of confidence P-?
• Calculated with Monte Carlo
simulation
Residual risk
www.intaver.com Intaver Institute Inc.
$
Pre-Mitigation
Original
Estimates
With Risk
CR
$
Post-Mitigation
Margin
Pre-Mitigation Post-Mitigation
Residual risk is accounted for in contingency and margin
Schedule Margin
www.intaver.com Intaver Institute Inc.
• Deterministic Plan = 330 days
• With uncertainties and residual
risk P80 = 353 days
• Schedule Margin = P80 – DP =
33 days
Schedule Margin
www.intaver.com Intaver Institute Inc.
Margin is added directly to the schedule to
provide buffers for key deliverables.
Cost Contingency
www.intaver.com Intaver Institute Inc.
Forecasts for cost and schedule now account for
risks and uncertainties and are integrated into plan
Max
P50
Low
When is this appropriate?
www.intaver.com Intaver Institute Inc.
• Always perform risk management as appropriate for the
size and importance of your project.
• Scale with Project
– Small, Routine: Qualitative
– Large, Complex: Quantitative (Monte Carlo)
• Set thresholds
– US Federal
– $20M Perform EV and RM evidenced by reports
– $50 Certified EV and RM systems
Summary
www.intaver.com Intaver Institute Inc.
Program managers can increase confidence of
successfully delivering programs on time and budget
by:
•Managing and controlling risks (reducible)
•Accounting for uncertainties and residual risk
integrating sufficient schedule margin and
management reserves
•This creates a project plan that is….
Risk adjusted plans and protects key program objectivesRisk adjusted plans and protects key program objectives

More Related Content

What's hot

Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Intaver Insititute
 
RiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas IndustryRiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas IndustryIntaver Insititute
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisIntaver Insititute
 
Risk reserve management model
Risk reserve management modelRisk reserve management model
Risk reserve management modelAmirul Ismail
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisp6academy
 
Introduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptIntroduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptp6academy
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisProject Controls Expo
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...p6academy
 
Job Duties in Current Position
Job Duties in Current PositionJob Duties in Current Position
Job Duties in Current PositionAmanda Hartsfield
 
Process implementation for project risk management
Process implementation for project risk managementProcess implementation for project risk management
Process implementation for project risk managementvishvasyadav45
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...GIS in the Rockies
 
AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01John Blodgett
 
Budgeting and cost estimation
Budgeting and cost estimationBudgeting and cost estimation
Budgeting and cost estimationLibra chudry
 
Risk management and assessment
Risk management and assessmentRisk management and assessment
Risk management and assessmentabassociates
 

What's hot (20)

Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
RiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas IndustryRiskyProject for Oil and Gas Industry
RiskyProject for Oil and Gas Industry
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
 
Risk reserve management model
Risk reserve management modelRisk reserve management model
Risk reserve management model
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
Introduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptIntroduction to primavera risk analysis ppt
Introduction to primavera risk analysis ppt
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 
Job Duties in Current Position
Job Duties in Current PositionJob Duties in Current Position
Job Duties in Current Position
 
Process implementation for project risk management
Process implementation for project risk managementProcess implementation for project risk management
Process implementation for project risk management
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
 
AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01
 
Budgeting and cost estimation
Budgeting and cost estimationBudgeting and cost estimation
Budgeting and cost estimation
 
Risk management and assessment
Risk management and assessmentRisk management and assessment
Risk management and assessment
 

Similar to Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules

Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Glen Alleman
 
Aon Global Rapid Response
Aon Global Rapid ResponseAon Global Rapid Response
Aon Global Rapid ResponseGraeme Cross
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.pptKareemRasmy1
 
Aon Global Rapid Response
Aon Global Rapid ResponseAon Global Rapid Response
Aon Global Rapid ResponseGraeme Cross
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptYasirShaikh34
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing riskHammad Hashmi
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsIntaver Insititute
 
Risk management overview
Risk management overviewRisk management overview
Risk management overviewHossam Maghrabi
 
Operational Risk : Take a look at the raw canvas
Operational Risk : Take a look at the raw canvasOperational Risk : Take a look at the raw canvas
Operational Risk : Take a look at the raw canvasTreat Risk
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Association for Project Management
 
112 risk- metrics for risk reduction
112 risk- metrics for risk reduction112 risk- metrics for risk reduction
112 risk- metrics for risk reductionDr Fereidoun Dejahang
 

Similar to Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules (20)

Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)
 
Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015
 
Aon Global Rapid Response
Aon Global Rapid ResponseAon Global Rapid Response
Aon Global Rapid Response
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.ppt
 
Aon Global Rapid Response
Aon Global Rapid ResponseAon Global Rapid Response
Aon Global Rapid Response
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.ppt
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing risk
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
APM Edinburgh risk management january 2017 final
APM Edinburgh risk management january 2017 finalAPM Edinburgh risk management january 2017 final
APM Edinburgh risk management january 2017 final
 
Operational Risk : Take a look at the raw canvas
Operational Risk : Take a look at the raw canvasOperational Risk : Take a look at the raw canvas
Operational Risk : Take a look at the raw canvas
 
Risk management
Risk managementRisk management
Risk management
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
 
112 risk- metrics for risk reduction
112 risk- metrics for risk reduction112 risk- metrics for risk reduction
112 risk- metrics for risk reduction
 

More from Intaver Insititute

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2Intaver Insititute
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear ProjectsIntaver Insititute
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk AnalysisIntaver Insititute
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryIntaver Insititute
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project ManagementIntaver Insititute
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive managementIntaver Insititute
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project ManagementIntaver Insititute
 
Risky projectpresentation rus
Risky projectpresentation rusRisky projectpresentation rus
Risky projectpresentation rusIntaver Insititute
 
Risky project Cloud presentation rus
Risky project Cloud presentation rusRisky project Cloud presentation rus
Risky project Cloud presentation rusIntaver Insititute
 
Risky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementRisky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementIntaver Insititute
 
Risky Project Lite vs. Professional
Risky Project Lite vs. ProfessionalRisky Project Lite vs. Professional
Risky Project Lite vs. ProfessionalIntaver Insititute
 
Enterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProjectEnterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProjectIntaver Insititute
 
Risky projectcloudpresentation
Risky projectcloudpresentationRisky projectcloudpresentation
Risky projectcloudpresentationIntaver Insititute
 
Adaptive Project Management
Adaptive Project ManagementAdaptive Project Management
Adaptive Project ManagementIntaver Insititute
 
Decision Framing in Project Decision-Making
Decision Framing in Project Decision-MakingDecision Framing in Project Decision-Making
Decision Framing in Project Decision-MakingIntaver Insititute
 

More from Intaver Insititute (19)

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2
 
Project Cost Analysis
Project Cost AnalysisProject Cost Analysis
Project Cost Analysis
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
RiskyProject 7
RiskyProject 7RiskyProject 7
RiskyProject 7
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
 
RiskyProject Enterprise
RiskyProject EnterpriseRiskyProject Enterprise
RiskyProject Enterprise
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace Industry
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project Management
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project Management
 
Risky projectpresentation rus
Risky projectpresentation rusRisky projectpresentation rus
Risky projectpresentation rus
 
Risky project Cloud presentation rus
Risky project Cloud presentation rusRisky project Cloud presentation rus
Risky project Cloud presentation rus
 
Risky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementRisky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagement
 
Risky Project Lite vs. Professional
Risky Project Lite vs. ProfessionalRisky Project Lite vs. Professional
Risky Project Lite vs. Professional
 
Enterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProjectEnterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProject
 
Risky projectcloudpresentation
Risky projectcloudpresentationRisky projectcloudpresentation
Risky projectcloudpresentation
 
Adaptive Project Management
Adaptive Project ManagementAdaptive Project Management
Adaptive Project Management
 
Decision Framing in Project Decision-Making
Decision Framing in Project Decision-MakingDecision Framing in Project Decision-Making
Decision Framing in Project Decision-Making
 

Recently uploaded

Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 

Recently uploaded (20)

Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 

Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules

  • 1. Risk Adjusted Project Schedules Intaver Institute Inc. 400, 7015 Macleod Trail S.W, Calgary, AB, Canada Tel: +1(403)692-2252 www.intaver.com
  • 2. Objectives • Goal to create realistic or “credible” project plans • Identify and manage critical risks • Monte Carlo risk analysis • Calculate model and risk appropriate schedule margin and contingency reserve Risk adjusted project plans allow projects to withstand impact of foreseen and unforeseen circumstances www.intaver.com Intaver Institute Inc.
  • 3. Sources of Risk www.intaver.com Intaver Institute Inc. Discrete Risks •Risk events that can directly impact project objectives Technical, Schedule, Cost. •Characterized by probability of occurrence and impacts and period of exposure (sunrise and sunset) •Are “reducible” – they can be managed or eliminated give sufficient effort Uncertainties •Natural variance caused by randomness in all processes •Characterized using statistical distributions that capture most likely and boundary estimates (Low and High) •Are “irreducible” – they cannot be reduced
  • 4. Building Risk Adjusted Plans www.intaver.com Intaver Institute Inc. 1 Create WBS. WBS is primarily developed using Scope of Work. 2 Create Integrated Management Plan. IMP provides high level structure for program deliverables, technical measures of success as well as cost and schedule estimates 3 Analyze and manage risks. Identify, assess, and manage reducible risks for every WBS item in the plan.
  • 5. Manage Discrete Risks www.intaver.com Intaver Institute Inc. 1. Identify Risks o What events could impact key objectives 1. What are the impacts? o Assess the impact of a risk event occurring on technical, cost and schedule measures. 1. What can you do about it? o What is your risk strategy: Avoid, Transfer, Mitigate, or Accept o If mitigate, create mitigation plan with activities that will reduce probability and impact. o Residual risk (cost, schedule) added to contingency reserve
  • 6. Assign Risks to WBS www.intaver.com Intaver Institute Inc. Drag selected risk and drop it on the task; define risk probabilities and impacts
  • 7. Assess Risks www.intaver.com Intaver Institute Inc. Risks are initially assessed using Risk Matrix or Risk Register Prioritization
  • 8. Risk Planning www.intaver.com Intaver Institute Inc. • Mitigation activities for each risk are modeled to waterfall chart • Mitigation activities are added to the schedule with associated dates, costs and durations • Successful completion of mitigation activities in schedule are tracked and updated in risk register.
  • 9. Contingency and Management Reserves www.intaver.com Intaver Institute Inc. • Contingency and Margin cover “known unknowns” o Residual risk from known risks (manageable) o Natural variance in project performance (unmanageable) o Does not cover scope changes • Management Reserves cover unknown unknowns o Risks not previously identified, etc.
  • 10. Managing Irreducible Risk www.intaver.com Intaver Institute Inc. • Modeling irreducible risk is used to develop Schedule margins for the Program • Uncertainties are modeled using 3 pt. estimates (L, ML, H) • Use all available information including SME opinion, previous analogous projects • Uncertainty should be added to all tasks in relation to their known and forecasted level of uncertainty.
  • 11. Monte Carlo is Essential www.intaver.com Intaver Institute Inc. Monte Carlo Simulations
  • 12. Contingency and Management Reserves www.intaver.com Intaver Institute Inc. $Cost Time Contingency Margin MR P80 P80 x x
  • 13. Unmanaged Risks and Contingency www.intaver.com Intaver Institute Inc. • Impact of unmanaged and residual risks added to contingency • Contingency is difference between baseline and level of confidence P-? • Calculated with Monte Carlo simulation
  • 14. Residual risk www.intaver.com Intaver Institute Inc. $ Pre-Mitigation Original Estimates With Risk CR $ Post-Mitigation Margin Pre-Mitigation Post-Mitigation Residual risk is accounted for in contingency and margin
  • 15. Schedule Margin www.intaver.com Intaver Institute Inc. • Deterministic Plan = 330 days • With uncertainties and residual risk P80 = 353 days • Schedule Margin = P80 – DP = 33 days
  • 16. Schedule Margin www.intaver.com Intaver Institute Inc. Margin is added directly to the schedule to provide buffers for key deliverables.
  • 17. Cost Contingency www.intaver.com Intaver Institute Inc. Forecasts for cost and schedule now account for risks and uncertainties and are integrated into plan Max P50 Low
  • 18. When is this appropriate? www.intaver.com Intaver Institute Inc. • Always perform risk management as appropriate for the size and importance of your project. • Scale with Project – Small, Routine: Qualitative – Large, Complex: Quantitative (Monte Carlo) • Set thresholds – US Federal – $20M Perform EV and RM evidenced by reports – $50 Certified EV and RM systems
  • 19. Summary www.intaver.com Intaver Institute Inc. Program managers can increase confidence of successfully delivering programs on time and budget by: •Managing and controlling risks (reducible) •Accounting for uncertainties and residual risk integrating sufficient schedule margin and management reserves •This creates a project plan that is…. Risk adjusted plans and protects key program objectivesRisk adjusted plans and protects key program objectives