SlideShare a Scribd company logo
1 of 4
W4N1: Cost Management Overview
Cost management is a critical component of any project. It is
very rare that there is no concern over what a project will cost!
Reliable cost estimates are required for responsible fiscal
management at each stage of a project. Unreliable estimates
and resulting budgets typically cause significant problems
within an organization -- particularly for large enterprise
projects. Cost management is closely related to time
management because when projects overrun schedule there are
typically cost overruns as well.
There are varying degrees of budgetary estimates at different
stages of a project. At each stage, cost estimates must be
accurate, transparent and reliable to the degree possible at that
particular stage. Budgetary estimates (before the project is
approved) will be high level, but should be based on a high
level understanding of scope and approach. By the time that
project budgets are established just prior to execution, much
more detail is known and the estimates can be provided with
more clarity. The degree of uncertainty should be defined with
each estimate. Management needs the best information
available on which to base decisions about the project. The
degree of estimation detail and the basis of the estimates
improves over time.
Cost estimates are not static -- estimating costs is not an exact
science and actual costs must be regularly reviewed and tracked
to budgetary estimates. The estimates do, however, set
expectations and affect management decisions. A successful
project manager is expected to establish a budget for a project
and then manage the project to that budget. Any changes in the
overall cost to complete a project must be discussed with
management and key project stakeholders. If an initial
budgetary estimate made during project initiation is extremely
different from the budget planned for project execution (or
worse from what it actually takes to complete the project in the
late stages), management must rethink whether or not the
project should proceed.
W4N2: Cost Estimating
There are various methods for estimating project costs.
Sometimes historical data is available to support cost estimates,
sometimes teams define the cost estimate in a “bottom up”
manner by estimating what it will cost to perform each project
work activity and then summing up the activities for the project,
and for some specialty areas there may be industry or corporate
formulas or guidelines that can help guide estimates. Various
tools, from cost models, to project management systems, to
complex excel spreadsheets typically support the development
of cost estimates.
Based on the activity resource and duration estimates, the cost
estimates define the cost of completing the work of the project.
Cost estimates include labor, materials, services, equipment
and any other direct costs for performing project activities.
There are many factors that should be considered when
preparing cost estimates, including:
· The planned execution strategy for the project
· The overall duration of the project
· Complexity of the solution
· Phasing of when work will be performed
· The cash flow of the project (when money is required)
· Escalation that may occur over the course of the project in
such factors as labor rates, facility costs, materials, currency
fluctuation, cost of money (e.g., interest), etc.
· Where the work will be performed and any local practices
and/or productivity variables associated with the location
· How the organization accounts for overhead costs (what labor,
services, and equipment need to be included in the project cost
estimate; sometimes organizations have items like IT service
center costs, purchasing overhead, facility costs or management
costs applied to overhead and other times they need to be
included in the budget of the project).
Cost baselines represent the budget that has been approved by
management and stakeholders and represents the budgetary
estimates used to determine whether or not project costs are
occurring according to plan.
W4N3: Contingencies and Reserves
Reserves are used to prepare for unplanned events that occur
over the course of a project. They are calculated based on risks
assessed for the project. There are two types of reserves:
· Contingency Reserves are an allowance for unplanned but
potentially required changes. They are based on the items
contained in the project’s Risk Register.
· Management Reserves are budgets for unplanned changes to
project scope and cost that are not part of the project cost
baseline and not included in any earned value calculations.
Typically the project manager needs approval from management
to spend these reserves.
[endif]Most project estimates include a
contingency reserve in the estimate to account for uncertainty.
The reserve can be a percentage of estimated cost, a fixed
amount or can be developed with quantative analysis methods.
[endif]Any reserve must be clearly
identified so it can be adjusted as more information becomes
available over the course of the project. The reserve should not
be padding in individual estimates. The way in which reserves
are created and released are often driven by organizational
processes and policies. As a project manager it is important to
understand how these operate.
W4N1 Cost Management OverviewCost management is a critical comp.docx

More Related Content

Similar to W4N1 Cost Management OverviewCost management is a critical comp.docx

5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptxAberraBeri
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplinesKuppusamy P
 
Cost management
Cost managementCost management
Cost managementshkadry
 
EstimatingGuidelines.pdf
EstimatingGuidelines.pdfEstimatingGuidelines.pdf
EstimatingGuidelines.pdfIctsol
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Amr Miqdadi
 
Software Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementSoftware Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementAhsan Rahim
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software EngineeringFáber D. Giraldo
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxbjohn46
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 

Similar to W4N1 Cost Management OverviewCost management is a critical comp.docx (20)

Project Mangement
Project MangementProject Mangement
Project Mangement
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptx
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplines
 
Cost management
Cost managementCost management
Cost management
 
Ch04
Ch04Ch04
Ch04
 
EstimatingGuidelines.pdf
EstimatingGuidelines.pdfEstimatingGuidelines.pdf
EstimatingGuidelines.pdf
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
6. mba 206 project management assignment 2nd semester
6. mba 206 project management assignment 2nd semester6. mba 206 project management assignment 2nd semester
6. mba 206 project management assignment 2nd semester
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1
 
Project cost management
Project cost management Project cost management
Project cost management
 
Software Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementSoftware Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project Management
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
 
Estimation
EstimationEstimation
Estimation
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 

More from celenarouzie

Attaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docxAttaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docxcelenarouzie
 
attachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docxattachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docxcelenarouzie
 
AttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docxAttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docxcelenarouzie
 
Attachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docxAttachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docxcelenarouzie
 
Attachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docxAttachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docxcelenarouzie
 
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docxATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docxcelenarouzie
 
Attached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docxAttached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docxcelenarouzie
 
Attached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docxAttached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docxcelenarouzie
 
Attached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docxAttached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docxcelenarouzie
 
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docxB. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docxcelenarouzie
 
B)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docxB)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docxcelenarouzie
 
B)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docxB)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docxcelenarouzie
 
b) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docxb) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docxcelenarouzie
 
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docxb$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docxcelenarouzie
 
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docx
B A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docxB A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docx
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docxcelenarouzie
 
B H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docxB H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docxcelenarouzie
 
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docxb l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docxcelenarouzie
 
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docxB R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docxcelenarouzie
 
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docx
B L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docxB L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docx
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docxcelenarouzie
 
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docxAño 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docxcelenarouzie
 

More from celenarouzie (20)

Attaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docxAttaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docx
 
attachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docxattachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docx
 
AttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docxAttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docx
 
Attachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docxAttachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docx
 
Attachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docxAttachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docx
 
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docxATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
 
Attached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docxAttached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docx
 
Attached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docxAttached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docx
 
Attached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docxAttached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docx
 
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docxB. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
 
B)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docxB)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docx
 
B)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docxB)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docx
 
b) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docxb) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docx
 
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docxb$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docx
 
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docx
B A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docxB A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docx
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docx
 
B H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docxB H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docx
 
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docxb l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
 
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docxB R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
 
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docx
B L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docxB L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docx
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docx
 
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docxAño 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docx
 

Recently uploaded

POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...RKavithamani
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 

Recently uploaded (20)

TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 

W4N1 Cost Management OverviewCost management is a critical comp.docx

  • 1. W4N1: Cost Management Overview Cost management is a critical component of any project. It is very rare that there is no concern over what a project will cost! Reliable cost estimates are required for responsible fiscal management at each stage of a project. Unreliable estimates and resulting budgets typically cause significant problems within an organization -- particularly for large enterprise projects. Cost management is closely related to time management because when projects overrun schedule there are typically cost overruns as well. There are varying degrees of budgetary estimates at different stages of a project. At each stage, cost estimates must be accurate, transparent and reliable to the degree possible at that particular stage. Budgetary estimates (before the project is approved) will be high level, but should be based on a high level understanding of scope and approach. By the time that project budgets are established just prior to execution, much more detail is known and the estimates can be provided with more clarity. The degree of uncertainty should be defined with each estimate. Management needs the best information available on which to base decisions about the project. The degree of estimation detail and the basis of the estimates improves over time. Cost estimates are not static -- estimating costs is not an exact science and actual costs must be regularly reviewed and tracked to budgetary estimates. The estimates do, however, set expectations and affect management decisions. A successful project manager is expected to establish a budget for a project and then manage the project to that budget. Any changes in the overall cost to complete a project must be discussed with management and key project stakeholders. If an initial budgetary estimate made during project initiation is extremely different from the budget planned for project execution (or worse from what it actually takes to complete the project in the
  • 2. late stages), management must rethink whether or not the project should proceed. W4N2: Cost Estimating There are various methods for estimating project costs. Sometimes historical data is available to support cost estimates, sometimes teams define the cost estimate in a “bottom up” manner by estimating what it will cost to perform each project work activity and then summing up the activities for the project, and for some specialty areas there may be industry or corporate formulas or guidelines that can help guide estimates. Various tools, from cost models, to project management systems, to complex excel spreadsheets typically support the development of cost estimates. Based on the activity resource and duration estimates, the cost estimates define the cost of completing the work of the project. Cost estimates include labor, materials, services, equipment and any other direct costs for performing project activities. There are many factors that should be considered when preparing cost estimates, including: · The planned execution strategy for the project · The overall duration of the project · Complexity of the solution · Phasing of when work will be performed · The cash flow of the project (when money is required) · Escalation that may occur over the course of the project in such factors as labor rates, facility costs, materials, currency fluctuation, cost of money (e.g., interest), etc. · Where the work will be performed and any local practices and/or productivity variables associated with the location · How the organization accounts for overhead costs (what labor, services, and equipment need to be included in the project cost estimate; sometimes organizations have items like IT service center costs, purchasing overhead, facility costs or management costs applied to overhead and other times they need to be
  • 3. included in the budget of the project). Cost baselines represent the budget that has been approved by management and stakeholders and represents the budgetary estimates used to determine whether or not project costs are occurring according to plan. W4N3: Contingencies and Reserves Reserves are used to prepare for unplanned events that occur over the course of a project. They are calculated based on risks assessed for the project. There are two types of reserves: · Contingency Reserves are an allowance for unplanned but potentially required changes. They are based on the items contained in the project’s Risk Register. · Management Reserves are budgets for unplanned changes to project scope and cost that are not part of the project cost baseline and not included in any earned value calculations. Typically the project manager needs approval from management to spend these reserves. [endif]Most project estimates include a contingency reserve in the estimate to account for uncertainty. The reserve can be a percentage of estimated cost, a fixed amount or can be developed with quantative analysis methods. [endif]Any reserve must be clearly identified so it can be adjusted as more information becomes available over the course of the project. The reserve should not be padding in individual estimates. The way in which reserves are created and released are often driven by organizational processes and policies. As a project manager it is important to understand how these operate.