EOT Claims
Prepared by:
Eng. Mohamed Maged, MBA, PMP
Profile:
https://www.luqmanacademy.com/profile/8
PgMO - Project Control Manager, MBA, B.Sc. of Civil engineering – Ain Shams
University, with experience in MENA region of (construction, infrastructure, and roads)
Mega projects, in professions of Contract administration, Procurement, Tender estimating,
Cost control, Planning & Claim analysis.
Certificates & Memberships: MBA, PMP, ACIArb, AIA Fellow, SCE-PE, SFC, FIDIC
Contracts Consultant & Certified Negotiation Associate
M.M. Arranged Three Annual Conferences of Planning and Project Management
(Anniversary of Facebook Page: Prof.Planner)- American University in Cairo, Aug. 2014,
2015 & Online Sep. 2017.
Other accounts:
 SlideShare: www.slideshare.net/MohamedMaged8/
 YouTube Channel: https://www.youtube.com/ArabPlanners.
 (related groups: Best Advice for Planners/ Cost/ Contract – Public groups)
2
Mohamed Maged:
‫المحتوى‬
•‫التأخير‬ ‫أسباب‬
•‫التأخير‬ ‫قياس‬ ‫طرق‬
•‫التأخير‬ ‫تحليل‬
•‫التأخير‬ ‫معالجة‬
•‫الزمنيه‬ ‫المطالبات‬ ‫حاالت‬
•‫مطالبة‬ ‫مكونات‬‫التمديد‬
4
‫تأخير‬ ‫يحدث‬ ‫متى‬‫؟‬
WHAT IS DELAY?
• DELAY is an act or event that extends the time
required to perform tasks or activities under a
Contract . It is usually reflected as additional days of
work or as delayed start of activities.
• DELAY May or may not include change(s) in the
scope of work of activity(s) or the Contract.
5
‫التأخير‬ ‫أسباب‬
•‫التأخير؟‬ ‫أسباب‬ ‫هي‬ ‫ما‬‫المقاول‬ ‫بسبب‬ ‫تكون‬ ‫أن‬ ‫إما‬ ‫التأخير‬ ‫أسباب‬contractor risk event (CRE)‫أن‬ ‫أو‬
‫المالك‬ ‫أواستشاري‬ ‫المالك‬ ‫بسبب‬ ‫أي‬ ‫عنه‬ ‫خارجه‬ ‫تكون‬employer risk event (ERE).
‫ااك‬‫ا‬‫وهن‬‫ا‬‫ا‬‫ري‬ ‫ارو‬‫ا‬‫ه‬ ‫ام‬‫ا‬‫تس‬ ‫اباب‬‫ا‬‫أس‬ ‫اا‬‫ا‬‫أحيان‬force majeure‫ا‬‫ا‬ ‫والتو‬ ‫اةراال‬ ‫ان‬‫ا‬‫ع‬ ‫ا‬‫ا‬‫خارج‬unforeseen
‫ار‬‫ا‬‫يبتب‬ ‫ا‬ ‫ا‬‫ا‬‫وه‬'neutral event'‫ا‬‫ا‬ ‫تك‬ ‫اون‬ ‫ا‬‫ا‬ ‫الو‬ ‫ان‬‫ا‬‫ع‬ ‫اا‬‫ا‬‫عالب‬ ‫ااول‬‫ا‬‫المق‬ ‫اه‬‫ا‬‫هي‬ ‫اوف‬‫ا‬‫يب‬non-compensable
and excusable.
‫وما‬ ‫المب‬ ‫جم‬ ‫تأخيريتم‬ ‫حاوث‬ ‫وعنا‬investigation‫المشارو‬ ‫ساجت‬ ‫كل‬ ‫طريق‬ ‫عن‬records (doc.
control)‫السابب‬ ‫يال‬ ‫تح‬ ‫ثام‬root cause analysis (technique)‫هاي‬ ‫المتسابب‬ ‫هاو‬ ‫المقااول‬ ‫كاان‬ ‫هانن‬ ،
‫بمبالجته‬ ‫يقوم‬ ‫التأخير‬recover‫السبب‬ ‫تكرار‬ ‫وعام‬ ‫حل‬ ‫ل‬ ‫خط‬ ‫ووض‬ ،corrective action‫عمل‬ ‫يتم‬ ‫كما‬ ،
action plan.
‫أما‬‫يمناي‬ ‫تاأثير‬ ‫ولاه‬ ‫المقااول‬ ‫إراال‬ ‫عن‬ ‫خارج‬ ‫التأخير‬ ‫كان‬ ‫إن‬time impact‫مطالبا‬ ‫بتقاايم‬ ‫يقاوم‬ ‫المقااول‬ ‫هانن‬
‫به‬ ‫يمني‬EOT Claim (Extension Of Time).
6
‫التأخير‬ ‫ألسباب‬ ‫أمثلة‬
Contractor risk event (CRE) Vs Employer risk event (ERE)
7
‫قياس‬ ‫طرق‬‫التأخير‬(5)
.1‫التحديث‬ ‫بعد‬ ‫الزمني‬ ‫البرنامج‬ ‫على‬ ‫الموجود‬ ‫الكلي‬ ‫الفائض‬Total float.
.2‫المخطط‬ ‫بنسبة‬ ‫مقارنة‬ ‫المكتسبة‬ ‫للقيمة‬ ‫طبقا‬ ‫المنفذ‬ ‫نسبة‬SPI.
.3‫تغير‬‫ذلك‬ ‫معالجة‬ ‫وكيفية‬ ‫المشروع‬ ‫في‬ ‫حرج‬ ‫مسار‬ ‫أطول‬Longest critical
path change and mitigation actions if required.
.4‫ال‬ ‫وموقف‬ ‫الرئيسية‬ ‫المشروع‬ ‫بنود‬ ‫تنفيذ‬ ‫نسب‬ ‫بين‬ ‫االتزان‬ ‫تحليل‬‫خطوط‬
‫المفتوحة‬LOB.
.5‫حركة‬‫المتوقعة‬ ‫المتبقية‬ ‫المدة‬ ‫على‬ ‫ذلك‬ ‫وأثر‬ ‫الزمن‬ ‫مع‬ ‫المشروع‬ ‫تقدم‬Trend
analysis vs ETC.
8
1-‫الكلي‬ ‫الفائض‬‫بالسالب‬(-ve TF)
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
-3, 2
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
20, 22
19, 22
12, 20
17, 19
12, 19
9, 12
8, 12
8, 12
2, 8
3, 8
5, 8
-3
-3
-3
-2 -3
-3
-2 2
0 0 0 0
Update Finish Date > Imposed Finish Date
9
2-‫المكتسبة‬ ‫القيمة‬ ‫مؤشر‬(SPI)
•‫ما‬‫هي‬EVM‫؟‬‫المكتساب‬ ‫القيما‬ ‫طرياق‬ ‫عان‬ ‫االاارل‬ ‫هي‬(earned value management)‫تبتماا‬ ‫وهاي‬
‫ي‬ ‫المث‬ ‫المقارن‬ ‫ع‬apple to apple، ‫والو‬ ‫التك‬ ‫هرق‬ ‫حال‬ ‫هي‬‫ا‬ ‫ومبااالت‬‫الو‬ ‫هي‬‫كالتالي‬:
BCWS: budget cost of work scheduled= planned value
BCWP: budget cost of work performed = earned value
Schedule performance index (SPI)= EV/PV
(SPI>1: ahead of schedule & SPI<1: behind schedule)
BAC: budget cost at completion= total budget of project
•‫ما‬‫نسب‬ ‫هي‬performance, scheduled %‫؟‬‫تببر‬ ‫النسب‬ ‫ه‬ ‫ه‬
‫ي‬ ‫ي‬ ‫كما‬ ‫المكتسب‬ ‫قيم‬ ‫ل‬ ‫طبقا‬ ‫ي‬ ‫ب‬ ‫وال‬ ‫المخطط‬ ‫عن‬:
Scheduled % = (PV) / (BAC)
Performance % = earned value (EV) / (BAC)
Planned Vs Actual
10
(TF vs SPI)
Shortage in Each:
1- Availability of resources and resource
usage in remaining works can affect the
rationality of the total float specially if
many paths overlapped in the remaining
duration.
2- Out of sequence can disturb the results
of EVM schedule factors specially if the
progress of critical path is different.
11
‫المكتسب‬ ‫والقيمة‬ ‫الزمني‬ ‫البرنامج‬ ‫بين‬ ‫الجمع‬‫ة‬
12
3-‫الحرج‬ ‫المسار‬ ‫منطق‬(Critical Path)
A
B
C
D
F
Dependency Determination. Logical Relationship/ mathematical analysis:
Successor Activity. that logically comes after Vs Predecessor.
Mandatory Dependency. contractually required or inherent in the nature of the work. Hard
Logic.
Discretionary Dependency. based on knowledge of best practices, Preferred Logic. Soft
Logic.
External Dependency. A relationship with non-project activities.
Applying Lag. a successor activity waiting Vs Lead (-ve lag).
13
4-‫المتكررة‬ ‫األنشطة‬ ‫بين‬ ‫االتزان‬ ‫خط‬(LOB)
‫الـ‬ ‫هو‬ ‫ما‬line of balance‫؟‬‫مجموع‬ ‫عن‬ ‫عبارل‬ ‫المشرو‬ ‫كون‬ ‫حال‬ ‫هي‬ ‫مناسب‬ ‫وتكون‬ ‫اليمني‬ ‫البرامج‬ ‫عمل‬ ‫هي‬ ‫طريق‬ ‫هي‬
‫الموارا‬ ‫ع‬ ‫مبتمال‬ ‫وتكون‬ ،‫متباال‬ ‫أماكن‬ ‫هي‬ ‫وتن‬ ‫الببف‬ ‫ا‬ ‫بببض‬ ‫المرتبط‬ ‫المتتالي‬ ‫المتكررل‬ ‫االنشط‬ ‫من‬resource
constrained‫اليمن‬ ‫م‬ ‫تراكمي‬ ‫منحنيا‬ ‫ع‬ ‫ا‬ ‫وضب‬ ‫ويمكن‬ ،diagrams on a cumulative basis‫وتشمل‬
‫مشاري‬housing, pipelines, bridges, roads, rail and tunneling works.
0.0%
20.0%
40.0%
Sep-18 Oct-18 Nov-18 Dec-18 Jan-19
Key KPI's - LOB
Excavation all
soil types
Installation
(Pipes & box
culvert)
Manholes
Asphalt
14
5-‫العمل‬ ‫في‬ ‫التقدم‬ ‫منحنى‬ ‫ميل‬(Trend)
•‫هاي‬ ‫ماا‬trend analysis‫؟‬‫ا‬ ‫المتو‬ ‫او‬ ‫الن‬ ‫وتااريه‬ ‫ا‬ ‫تك‬ ‫ل‬ ‫با‬ ‫المتو‬ ‫حساابا‬ ‫ل‬ ‫يساتخام‬forecast‫عان‬
‫ا‬ ‫ال‬‫ا‬‫مث‬ ‫اي‬‫ا‬‫رياض‬ ‫ارق‬‫ا‬‫ط‬ ‫اتخاام‬‫ا‬‫باس‬ ‫االمخطط‬‫ا‬‫ب‬ ‫اا‬‫ا‬ ‫ومقارنت‬ ، ‫اابق‬‫ا‬‫الس‬ ‫ا‬‫ا‬‫ي‬ ‫ب‬ ‫ال‬ ‫ااال‬‫ا‬‫المب‬ ‫اتمرار‬‫ا‬‫اس‬ ‫اق‬‫ا‬‫طري‬‫اتخاام‬‫ا‬‫س‬
‫اام‬‫ا‬‫التق‬ ‫اط‬‫ا‬‫متوس‬progress‫اا‬‫ا‬‫المنحني‬ ‫اتكمال‬‫ا‬‫الس‬ ‫اا‬‫ا‬‫م‬ ‫ارل‬‫ا‬‫هت‬ ‫اتل‬‫ا‬‫خ‬extend s-curve‫ا‬‫ا‬‫اي‬ ‫ن‬ ‫ا‬‫ا‬‫حت‬
‫المشرو‬.
0.0%
25.0%
50.0%
75.0%
100.0%
Sep-18 Oct-18 Nov-18 Dec-18 Jan-19
Overall Progress
Planned
Actual EV
SPI
15
1515
(earned value)
(Invoices)
(planned value)
Cost baseline
SV= -1,067$
Daily
planned
budget=
266.67
$ / day
ETC, TF= -15 Days
Trend analysis
delay= -35 days
% Complete = 26.7%
= - 4 days
‫اااااين‬‫ا‬‫ب‬ ‫ااااا‬‫ا‬‫الجم‬
‫ااااااااارا‬‫ا‬‫المؤش‬
‫المخت‬...
ETC: time schedule update
16 ‫التأخير‬ ‫تصنيف‬
Delay
Neutral Event
In-Excusable (CRE)Excusable
ERE
Non- CompensableCompensable
Concurrent
17
•‫بين‬ ‫رق‬ ‫ال‬recovery, revised programme‫؟‬
‫النو‬‫وهو‬ ‫األول‬recovery‫هيه‬ ‫ويتم‬ ، ‫به‬ ‫المتسبب‬ ‫هو‬ ‫المقاول‬ ‫تأخير‬ ‫وجوا‬ ‫حال‬ ‫هي‬ ‫ويكون‬‫ت‬‫باويف‬
‫المشرو‬ ‫اي‬ ‫ن‬ ‫لتاريه‬ ‫بالبرنامج‬ ‫والرجو‬ ‫التأخير‬‫ي‬ ‫األص‬.
‫ااا‬‫ا‬‫أم‬‫اااني‬‫ا‬‫الث‬ ‫ااو‬‫ا‬‫الن‬revised‫اارو‬‫ا‬‫المش‬ ‫ااي‬‫ا‬‫ه‬ ‫اار‬‫ا‬‫يي‬ ‫ت‬ ‫اا‬‫ا‬ ‫ع‬ ‫اااوا‬‫ا‬‫بن‬ ‫ااون‬‫ا‬‫يك‬ ‫ااث‬‫ا‬‫حي‬ ‫ااك‬‫ا‬‫ل‬ ‫ااه‬‫ا‬‫هي‬ ‫ااترط‬‫ا‬‫يش‬ ‫اات‬‫ا‬‫ه‬
variation/change‫اا‬‫ا‬‫ح‬ ‫أو‬ ‫ارو‬‫ا‬‫اله‬ ‫ار‬‫ا‬‫ي‬ ‫ت‬ ‫ابب‬‫ا‬‫بس‬ ‫ال‬‫ا‬‫ب‬ ‫ان‬‫ا‬‫م‬ ‫ا‬‫ا‬‫المقام‬ ‫ا‬‫ا‬‫ي‬ ‫التن‬ ‫ا‬‫ا‬‫طريق‬ ‫اايل‬‫ا‬‫تب‬ ‫أو‬ ،‫وث‬
Disruption،‫شابه‬ ‫وما‬ ‫جايا‬ ‫اي‬ ‫ن‬ ‫وتاريه‬ ‫يمن‬ ‫تمايا‬ ‫اعتماا‬ ‫أو‬.
Revised Programme
(types & cases):
https://www.youtube.c
om/watch?v=75iB5BEa
pIQ
‫الزمني؟‬ ‫البرنامج‬ ‫تعديل‬ ‫يتم‬ ‫كيف‬
18 ‫التأخير‬ ‫معالجة‬
There are two techniques to compress a programme:
1- Crashing: Done by selectively crashing specific activities to shorten project duration
(increase resources – refer to duration equation).
2- Fast-tracking: Done by re-sequence the logic and overlap activities can be done in the
same time.
3- Merge and do both together.
Compression approaches
‫جدا‬ ‫هام‬‫االجراءات‬ ‫متابعة‬ ‫التصحيحية‬ ‫الخطط‬ ‫في‬‫المتخذة‬‫سواءا‬‫كانت‬‫ت‬‫شمل‬
‫االدارة‬ ‫عناصر‬ ‫ادراج‬ ‫فينبغى‬ ‫مثال‬ ‫أوالموارد‬ ‫الالزمة‬ ‫التجهيزات‬ ‫عمل‬
‫بالفرق‬ ‫مقسمة‬ ‫الموارد‬ ‫وجميع‬ ‫واالشراف‬(‫ومواد‬ ‫ومعدات‬ ‫عمالة‬)‫أو‬ ،
‫ك‬ ‫التأكد‬ ‫يتم‬ ‫بحيث‬ ‫التنفيذ‬ ‫طريقة‬ ‫أو‬ ‫العمل‬ ‫بتسلسل‬ ‫خاصة‬ ‫اجراءات‬‫من‬ ‫فترة‬ ‫ل‬
‫ال‬ ‫أم‬ ‫أخرى‬ ‫إجراءات‬ ‫اتخاذ‬ ‫مطلوب‬ ‫وهل‬ ‫فاعليتها‬ ‫لقياس‬ ‫الخطة‬ ‫فاعلية‬.
19 ‫تحليل‬ ‫طرق‬‫التأخير‬
Prospective Delay Analysis:
Analysis of facts associated with delay events during
construction of a project and the estimation of their effect upon
the planned completion date of a project. (Interim Extension of
Time)
Retrospective Delay Analysis:
Analysis of facts associated with delay events after completion
of the construction period of a project. (Final Extension of Time)
20 ‫التأخير؟‬ ‫لتحليل‬ ‫طريقة‬ ‫كل‬ ‫تستخدم‬ ‫متى‬
Guidance Section 4
4.13 The table below summarises the types of analysis that can be conducted depending on
the types of factual material available. An ‘X’ indicates the factual material that is required for
a particular analysis, but in some cases there are alternatives, as indicated in the table:
21 ‫الزمنيه‬ ‫المطالبات‬ ‫حاالت‬
‫الحكومية‬ ‫والمشتريات‬ ‫المنافسات‬ ‫نظام‬
‫والخمسون‬ ‫الحادية‬ ‫المادة‬:
‫التأخي‬ ‫كان‬ ‫ا‬ ‫إ‬ ‫المالي‬ ‫ويارل‬ ‫م‬ ‫ال‬ ‫المتبا‬ ‫الحكومي‬ ‫الج‬ ‫اق‬ ‫بات‬ ‫رام‬ ‫ال‬ ‫من‬ ‫او‬ ‫واةع‬ ‫البقا‬ ‫تمايا‬ ‫يتم‬‫عن‬ ‫ا‬ً‫ج‬‫نات‬ ‫ر‬
‫األسباب‬ ‫ه‬ ‫ه‬ ‫م‬ ‫التأخير‬ ‫مال‬ ‫تتناسب‬ ‫أن‬ ‫بشرط‬ ،‫ا‬ ‫المتبا‬ ‫إراال‬ ‫عن‬ ‫خارج‬ ‫لسبب‬ ‫أو‬ ، ‫طارئ‬ ‫هرو‬.
‫والخمسون‬ ‫الثانية‬ ‫المادة‬:
‫التالي‬ ‫الحاال‬ ‫هي‬ ‫البقا‬ ‫تمايا‬ ‫المستق‬ ‫الاائرل‬ ‫رئيس‬ ‫أو‬ ‫المختص‬ ‫ويير‬ ‫ل‬:
‫م‬ ‫متناسب‬ ‫المضاه‬ ‫المال‬ ‫تكون‬ ‫أن‬ ‫بشرط‬ ،‫البقا‬ ‫هي‬ ‫ورا‬ ‫ما‬ ‫ع‬ ‫إضاهي‬ ‫بأعمال‬ ‫ا‬ ‫المتبا‬ ‫ك‬ ‫ا‬ ‫إ‬ ‫أ‬-‫حجم‬
‫ا‬ ‫ب‬ ‫ي‬ ‫التك‬ ‫وتاريه‬ ‫ا‬ ‫وطبيبت‬ ‫األعمال‬.
‫ا‬ ‫متبا‬ ‫ل‬ ‫تبوا‬ ‫ال‬ ‫ألسباب‬ ‫ا‬ ‫ببض‬ ‫أو‬ ‫األعمال‬ ‫بنيقا‬ ‫الحكومي‬ ‫الج‬ ‫من‬ ‫أمر‬ ‫صار‬ ‫ا‬ ‫إ‬ ‫ب‬-.
‫المحاا‬ ‫الو‬ ‫هي‬ ‫البمل‬ ‫ةنجاي‬ ‫كاهي‬ ‫عير‬ ‫مشرو‬ ‫ل‬ ‫السنوي‬ ‫المالي‬ ‫االعتمااا‬ ‫كان‬ ‫ا‬ ‫إ‬-.
22 ‫المتزامن‬ ‫التأخير‬Concurrent
‫واالحداث‬‫المشروع‬ ‫نهاية‬ ‫تاريخ‬ ‫بعد‬
1.4.8 Where an Employer Risk Event occurs after the contract completion date, in
a situation where failure to complete by the contract completion date has been
caused by Contractor Delays, the principle set out in Section 1.4.7 above should
apply, except where the Employer Risk Event is a noncompensable Employer Risk
Event (Neutral). In such an event, no EOT (or compensation) should be due.
Where an EOT is due after the contract completion date, the Employer Risk Event
does not exonerate the Contractor for all its delays prior to the Employer Risk Event
occurring. The effect of the Employer Risk Event should be assessed as described
above and any EOT found due should simply be added to the contract
completion date.
1.4.7 Where Employer Risk Events and Contractor Risk Events occur sequentially but
have concurrent effects, here again any Contractor Delay should not reduce the
amount of EOT due to the Contractor as a result of the Employer Delay.
23 ‫التمديد‬ ‫مطالبة‬ ‫مكونات‬
‫الزمنية‬ ‫التمديدات‬ ‫حالة‬ ‫في‬‫ما‬ ‫الزمني‬ ‫للبرنامج‬ ‫يضاف‬‫يل‬‫ي‬:
1-‫تعريف‬‫هذه‬ ‫الى‬ ‫أدت‬ ‫التي‬ ‫االحداث‬‫المطالبة‬
2-‫سرد‬‫إ‬ ‫باالشارة‬ ‫والنتيجة‬ ‫األثر‬ ‫لبيان‬ ‫المطالبات‬ ‫احداث‬‫لى‬
‫االثبات‬ ‫مستندات‬‫وارفاقها‬
3-‫البنود‬ ‫مع‬ ‫السابقة‬ ‫التمديدات‬‫الم‬ ‫التعاقدية‬ ‫واالجراءات‬‫تعلقة‬
‫وأحقية‬ ‫بالموضوع‬‫المقاول‬
4-‫البرنامج‬‫ما‬ ‫شامل‬ ‫المعدل‬ ‫الزمني‬‫في‬ ‫يطلب‬‫البرا‬ ‫تقديم‬‫مج‬
‫األصلي‬ ‫الحرج‬ ‫بالمسار‬ ‫مقارنة‬ ‫مع‬ ‫الزمنية‬
5-‫خالصة‬‫الجدي‬ ‫التعاقدي‬ ‫النهاية‬ ‫وتاريخ‬ ‫الزمني‬ ‫التمديد‬‫د‬
‫المطلوب‬
6-‫المرفقات‬‫ترقيمها‬ ‫مع‬ ‫السرد‬ ‫في‬ ‫اليها‬ ‫االشارة‬ ‫تم‬ ‫التي‬
24
•‫علو‬ ‫توأخير‬ ‫مراموة‬ ‫تطبيوق‬ ‫عودم‬ ‫هوو‬ ‫الرئيسي‬ ‫الهدف‬ ‫يكون‬‫ى‬
‫واول‬‫و‬‫المق‬LAD:liquidated and ascertained
damages‫ماان‬ ‫التااأخير‬ ‫بااه‬ ‫يتساابب‬ ‫لمااا‬ ‫لك‬ ‫كاا‬ ‫وتساام‬
، ‫اك‬‫ا‬‫مال‬ ‫ل‬ ‫ارار‬‫ا‬‫أض‬‫و‬‫اتم‬‫ا‬‫ي‬‫اا‬‫ا‬ ‫تطبيق‬‫اي‬‫ا‬‫ه‬‫الم‬ ‫ايام‬‫ا‬‫الت‬ ‫اام‬‫ا‬‫ع‬ ‫اال‬‫ا‬‫ح‬‫ااول‬‫ا‬‫ق‬
‫ا‬ ‫التماياا‬ ‫أو‬ ‫ااي‬ ‫التبا‬ ‫او‬ ‫الن‬ ‫تااريه‬ ‫هي‬ ‫المشرو‬ ‫او‬ ‫بنن‬‫ليمناي‬
‫التاأخي‬ ‫حساب‬ ‫يمنيا‬ ‫مراحال‬ ‫ا‬ ‫ع‬ ‫وتطباق‬ ،‫وجاا‬ ‫إن‬ ‫المبتما‬‫ر‬
‫البقا‬ ‫ا‬ ‫ي‬ ‫ع‬ ‫ينص‬ ‫نسب‬ ‫ص‬ ‫ا‬ ‫بحا‬stipulated.
‫المطالبات‬ ‫من‬ ‫الهدف‬‫الزمنيه‬
25
‫صلة‬ ‫ذات‬ ‫ودوات‬ ‫محاضرات‬
https://www.youtube.
com/watch?v=syxza-
ivtbk&index=4&list=PL9
HqmhqTzU-
VHjidVEP7FbAkivlfIr0aK
https://www.luqman
academy.com/cours
e?course=16
https://www.luqman
academy.com/cour
se?course=1
‫ورشة‬ ‫من‬ ‫مقتطقات‬
‫المطالبات‬ ‫عمل‬
‫التأخير‬ ‫وتحليل‬
https://www.youtub
e.com/watch?v=XB
og3BRwPeU&index=
8&list=PL9HqmhqTzU-
VTvrJDskZ4fjUzHqydrf
_O
Thank You
Don’t Hesitate to contact….
M.Maged
magedkom@gmail.com
mobile : 00966-580264968

More Related Content

What's hot

Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
M Maged Hegazy, LLM, MBA, CCP, P3O
 
50 qts مقابلة عمل planning
50 qts مقابلة عمل planning50 qts مقابلة عمل planning
50 qts مقابلة عمل planning
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
McLachlan Lister Pty Limited
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
Khaled M. Al Kolfat MS.Eng,MoP,P3O,PMOC,PMP,M.ASCE
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
M Maged Hegazy, LLM, MBA, CCP, P3O
 
ادارة الوقت والتكلفة
ادارة الوقت والتكلفةادارة الوقت والتكلفة
ادارة الوقت والتكلفة
mona-sh
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Procurement negotiation tips and phases
Procurement negotiation tips and phasesProcurement negotiation tips and phases
Procurement negotiation tips and phases
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
M Maged Hegazy, LLM, MBA, CCP, P3O
 
مكتب إدارة المشاريع. الفرص والتحديات
مكتب إدارة المشاريع. الفرص والتحدياتمكتب إدارة المشاريع. الفرص والتحديات
مكتب إدارة المشاريع. الفرص والتحديات
Mohamed ElSaadany, PMP, CCP, PMI-RMP, SCE-PE
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
M Maged Hegazy, LLM, MBA, CCP, P3O
 
ملخص مقدمة عن إدارة التكلفة - إدارة المشروعات
ملخص مقدمة عن إدارة التكلفة - إدارة المشروعاتملخص مقدمة عن إدارة التكلفة - إدارة المشروعات
ملخص مقدمة عن إدارة التكلفة - إدارة المشروعات
Karim Gaber
 
(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)
(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)
(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)
Hussain Sbetan
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
PMA Consultants
 
Delay analysis final
Delay analysis finalDelay analysis final
Delay analysis final
Mahmoud Awwad, PMP, MCIOB
 
Contracts classification
Contracts classificationContracts classification
Contracts classification
M Maged Hegazy, LLM, MBA, CCP, P3O
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأولخمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
M Maged Hegazy, LLM, MBA, CCP, P3O
 

What's hot (20)

Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
 
50 qts مقابلة عمل planning
50 qts مقابلة عمل planning50 qts مقابلة عمل planning
50 qts مقابلة عمل planning
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
ادارة الوقت والتكلفة
ادارة الوقت والتكلفةادارة الوقت والتكلفة
ادارة الوقت والتكلفة
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Procurement negotiation tips and phases
Procurement negotiation tips and phasesProcurement negotiation tips and phases
Procurement negotiation tips and phases
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
مكتب إدارة المشاريع. الفرص والتحديات
مكتب إدارة المشاريع. الفرص والتحدياتمكتب إدارة المشاريع. الفرص والتحديات
مكتب إدارة المشاريع. الفرص والتحديات
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
 
ملخص مقدمة عن إدارة التكلفة - إدارة المشروعات
ملخص مقدمة عن إدارة التكلفة - إدارة المشروعاتملخص مقدمة عن إدارة التكلفة - إدارة المشروعات
ملخص مقدمة عن إدارة التكلفة - إدارة المشروعات
 
(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)
(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)
(العقود الهندسية (فيديك - Engineering Contracts (FIDIC)
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Delay analysis final
Delay analysis finalDelay analysis final
Delay analysis final
 
Contracts classification
Contracts classificationContracts classification
Contracts classification
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأولخمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
 

Similar to Delay - EOT claims

أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
Dr. Mahmoud Al-Naimi
 
Project planning
Project planningProject planning
Project planning
Hamid AJ
 
Pm arabic ch6 إدارة التكلفة وإعداد موازنة المشروع
Pm arabic ch6 إدارة التكلفة وإعداد موازنة المشروعPm arabic ch6 إدارة التكلفة وإعداد موازنة المشروع
Pm arabic ch6 إدارة التكلفة وإعداد موازنة المشروع
khalid Dahleez
 
بحث معماري عن : مراحل تنفيذ مبنى إداري
بحث معماري عن : مراحل تنفيذ مبنى إداريبحث معماري عن : مراحل تنفيذ مبنى إداري
بحث معماري عن : مراحل تنفيذ مبنى إداري
Muhammad Sami , BCs , PRMG , CLAC
 
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
Dr. Mahmoud Al-Naimi
 
406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf
406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf
406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf
AmrRizk13
 
Pm arabic ch8 صياغة التقارير وغلق المشروع
Pm arabic ch8 صياغة التقارير وغلق المشروعPm arabic ch8 صياغة التقارير وغلق المشروع
Pm arabic ch8 صياغة التقارير وغلق المشروع
khalid Dahleez
 
الإقتصاد و الهندسة.
الإقتصاد و الهندسة.الإقتصاد و الهندسة.
الإقتصاد و الهندسة.
algassi2
 
Presentation1 (2).pdf
Presentation1 (2).pdfPresentation1 (2).pdf
Presentation1 (2).pdf
dhurghamalmosaoy
 
دراسات الجدوى الاقتصادية
دراسات الجدوى الاقتصاديةدراسات الجدوى الاقتصادية
دراسات الجدوى الاقتصادية
Dr Walaa Yoseph
 
التدفق النقدي لمشروع البناء
التدفق النقدي لمشروع البناء التدفق النقدي لمشروع البناء
التدفق النقدي لمشروع البناء
Muhammad Aljalali
 
Ms project
Ms projectMs project
Ms projectu083125
 
حسابات المسار الحرج Critical Path Calculations
حسابات المسار الحرج Critical Path Calculationsحسابات المسار الحرج Critical Path Calculations
حسابات المسار الحرج Critical Path Calculations
Ibrahim Ahmed Badi
 
2013 بحث أقتصاديات المشروع
2013 بحث أقتصاديات المشروع2013 بحث أقتصاديات المشروع
2013 بحث أقتصاديات المشروعHeba ElKomy
 
شبكات الأعمال.pptx
شبكات الأعمال.pptxشبكات الأعمال.pptx
شبكات الأعمال.pptx
adeliaazuva
 
إدارة الوقت والتكلفة
إدارة الوقت  والتكلفةإدارة الوقت  والتكلفة
إدارة الوقت والتكلفة
mona-sh
 
Technical_Report-Building_Structural_Assessment_&_Rehabilitation.pdf
Technical_Report-Building_Structural_Assessment_&_Rehabilitation.pdfTechnical_Report-Building_Structural_Assessment_&_Rehabilitation.pdf
Technical_Report-Building_Structural_Assessment_&_Rehabilitation.pdf
Adnan Lazem
 
Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...
Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...
Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...
Juma Yousef J. Saleh جمعة يوسف جمعة صالح
 
Earned valueالقطفة الاولى
Earned valueالقطفة الاولى  Earned valueالقطفة الاولى
Earned valueالقطفة الاولى
Omar Selim
 

Similar to Delay - EOT claims (20)

أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
Project planning
Project planningProject planning
Project planning
 
Pm arabic ch6 إدارة التكلفة وإعداد موازنة المشروع
Pm arabic ch6 إدارة التكلفة وإعداد موازنة المشروعPm arabic ch6 إدارة التكلفة وإعداد موازنة المشروع
Pm arabic ch6 إدارة التكلفة وإعداد موازنة المشروع
 
بحث معماري عن : مراحل تنفيذ مبنى إداري
بحث معماري عن : مراحل تنفيذ مبنى إداريبحث معماري عن : مراحل تنفيذ مبنى إداري
بحث معماري عن : مراحل تنفيذ مبنى إداري
 
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf
406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf
406315160-المسار-الحرج-للمشروعات-ادارة-المشاريع.pdf
 
Pm arabic ch8 صياغة التقارير وغلق المشروع
Pm arabic ch8 صياغة التقارير وغلق المشروعPm arabic ch8 صياغة التقارير وغلق المشروع
Pm arabic ch8 صياغة التقارير وغلق المشروع
 
الإقتصاد و الهندسة.
الإقتصاد و الهندسة.الإقتصاد و الهندسة.
الإقتصاد و الهندسة.
 
Presentation1 (2).pdf
Presentation1 (2).pdfPresentation1 (2).pdf
Presentation1 (2).pdf
 
دراسات الجدوى الاقتصادية
دراسات الجدوى الاقتصاديةدراسات الجدوى الاقتصادية
دراسات الجدوى الاقتصادية
 
التدفق النقدي لمشروع البناء
التدفق النقدي لمشروع البناء التدفق النقدي لمشروع البناء
التدفق النقدي لمشروع البناء
 
Ms project
Ms projectMs project
Ms project
 
86532486 مفاهيم-ادارة-المشاريع
86532486 مفاهيم-ادارة-المشاريع86532486 مفاهيم-ادارة-المشاريع
86532486 مفاهيم-ادارة-المشاريع
 
حسابات المسار الحرج Critical Path Calculations
حسابات المسار الحرج Critical Path Calculationsحسابات المسار الحرج Critical Path Calculations
حسابات المسار الحرج Critical Path Calculations
 
2013 بحث أقتصاديات المشروع
2013 بحث أقتصاديات المشروع2013 بحث أقتصاديات المشروع
2013 بحث أقتصاديات المشروع
 
شبكات الأعمال.pptx
شبكات الأعمال.pptxشبكات الأعمال.pptx
شبكات الأعمال.pptx
 
إدارة الوقت والتكلفة
إدارة الوقت  والتكلفةإدارة الوقت  والتكلفة
إدارة الوقت والتكلفة
 
Technical_Report-Building_Structural_Assessment_&_Rehabilitation.pdf
Technical_Report-Building_Structural_Assessment_&_Rehabilitation.pdfTechnical_Report-Building_Structural_Assessment_&_Rehabilitation.pdf
Technical_Report-Building_Structural_Assessment_&_Rehabilitation.pdf
 
Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...
Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...
Roadmap and Guidelines to decide and issue the Green Regulations in Kuwait St...
 
Earned valueالقطفة الاولى
Earned valueالقطفة الاولى  Earned valueالقطفة الاولى
Earned valueالقطفة الاولى
 

More from M Maged Hegazy, LLM, MBA, CCP, P3O

Variation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and ConsequencesVariation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and Consequences
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Performance Measurement and Weightage Systems
Performance Measurement and Weightage SystemsPerformance Measurement and Weightage Systems
Performance Measurement and Weightage Systems
M Maged Hegazy, LLM, MBA, CCP, P3O
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Missing and modern necessary skills
Missing and modern necessary skillsMissing and modern necessary skills
Missing and modern necessary skills
M Maged Hegazy, LLM, MBA, CCP, P3O
 
5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group
M Maged Hegazy, LLM, MBA, CCP, P3O
 
26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
M Maged Hegazy, LLM, MBA, CCP, P3O
 
3 years acheivements
3 years acheivements3 years acheivements
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Pmp procurement rev
Pmp procurement revPmp procurement rev

More from M Maged Hegazy, LLM, MBA, CCP, P3O (13)

Variation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and ConsequencesVariation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and Consequences
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Performance Measurement and Weightage Systems
Performance Measurement and Weightage SystemsPerformance Measurement and Weightage Systems
Performance Measurement and Weightage Systems
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
 
Missing and modern necessary skills
Missing and modern necessary skillsMissing and modern necessary skills
Missing and modern necessary skills
 
5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group
 
26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management
 
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
 
3 years acheivements
3 years acheivements3 years acheivements
3 years acheivements
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Pmp procurement rev
Pmp procurement revPmp procurement rev
Pmp procurement rev
 

Delay - EOT claims

  • 1. ‫الزمني‬ ‫التمديد‬ ‫مطالبات‬ EOT Claims Prepared by: Eng. Mohamed Maged, MBA, PMP Profile: https://www.luqmanacademy.com/profile/8
  • 2. PgMO - Project Control Manager, MBA, B.Sc. of Civil engineering – Ain Shams University, with experience in MENA region of (construction, infrastructure, and roads) Mega projects, in professions of Contract administration, Procurement, Tender estimating, Cost control, Planning & Claim analysis. Certificates & Memberships: MBA, PMP, ACIArb, AIA Fellow, SCE-PE, SFC, FIDIC Contracts Consultant & Certified Negotiation Associate M.M. Arranged Three Annual Conferences of Planning and Project Management (Anniversary of Facebook Page: Prof.Planner)- American University in Cairo, Aug. 2014, 2015 & Online Sep. 2017. Other accounts:  SlideShare: www.slideshare.net/MohamedMaged8/  YouTube Channel: https://www.youtube.com/ArabPlanners.  (related groups: Best Advice for Planners/ Cost/ Contract – Public groups) 2 Mohamed Maged:
  • 3. ‫المحتوى‬ •‫التأخير‬ ‫أسباب‬ •‫التأخير‬ ‫قياس‬ ‫طرق‬ •‫التأخير‬ ‫تحليل‬ •‫التأخير‬ ‫معالجة‬ •‫الزمنيه‬ ‫المطالبات‬ ‫حاالت‬ •‫مطالبة‬ ‫مكونات‬‫التمديد‬
  • 4. 4 ‫تأخير‬ ‫يحدث‬ ‫متى‬‫؟‬ WHAT IS DELAY? • DELAY is an act or event that extends the time required to perform tasks or activities under a Contract . It is usually reflected as additional days of work or as delayed start of activities. • DELAY May or may not include change(s) in the scope of work of activity(s) or the Contract.
  • 5. 5 ‫التأخير‬ ‫أسباب‬ •‫التأخير؟‬ ‫أسباب‬ ‫هي‬ ‫ما‬‫المقاول‬ ‫بسبب‬ ‫تكون‬ ‫أن‬ ‫إما‬ ‫التأخير‬ ‫أسباب‬contractor risk event (CRE)‫أن‬ ‫أو‬ ‫المالك‬ ‫أواستشاري‬ ‫المالك‬ ‫بسبب‬ ‫أي‬ ‫عنه‬ ‫خارجه‬ ‫تكون‬employer risk event (ERE). ‫ااك‬‫ا‬‫وهن‬‫ا‬‫ا‬‫ري‬ ‫ارو‬‫ا‬‫ه‬ ‫ام‬‫ا‬‫تس‬ ‫اباب‬‫ا‬‫أس‬ ‫اا‬‫ا‬‫أحيان‬force majeure‫ا‬‫ا‬ ‫والتو‬ ‫اةراال‬ ‫ان‬‫ا‬‫ع‬ ‫ا‬‫ا‬‫خارج‬unforeseen ‫ار‬‫ا‬‫يبتب‬ ‫ا‬ ‫ا‬‫ا‬‫وه‬'neutral event'‫ا‬‫ا‬ ‫تك‬ ‫اون‬ ‫ا‬‫ا‬ ‫الو‬ ‫ان‬‫ا‬‫ع‬ ‫اا‬‫ا‬‫عالب‬ ‫ااول‬‫ا‬‫المق‬ ‫اه‬‫ا‬‫هي‬ ‫اوف‬‫ا‬‫يب‬non-compensable and excusable. ‫وما‬ ‫المب‬ ‫جم‬ ‫تأخيريتم‬ ‫حاوث‬ ‫وعنا‬investigation‫المشارو‬ ‫ساجت‬ ‫كل‬ ‫طريق‬ ‫عن‬records (doc. control)‫السابب‬ ‫يال‬ ‫تح‬ ‫ثام‬root cause analysis (technique)‫هاي‬ ‫المتسابب‬ ‫هاو‬ ‫المقااول‬ ‫كاان‬ ‫هانن‬ ، ‫بمبالجته‬ ‫يقوم‬ ‫التأخير‬recover‫السبب‬ ‫تكرار‬ ‫وعام‬ ‫حل‬ ‫ل‬ ‫خط‬ ‫ووض‬ ،corrective action‫عمل‬ ‫يتم‬ ‫كما‬ ، action plan. ‫أما‬‫يمناي‬ ‫تاأثير‬ ‫ولاه‬ ‫المقااول‬ ‫إراال‬ ‫عن‬ ‫خارج‬ ‫التأخير‬ ‫كان‬ ‫إن‬time impact‫مطالبا‬ ‫بتقاايم‬ ‫يقاوم‬ ‫المقااول‬ ‫هانن‬ ‫به‬ ‫يمني‬EOT Claim (Extension Of Time).
  • 6. 6 ‫التأخير‬ ‫ألسباب‬ ‫أمثلة‬ Contractor risk event (CRE) Vs Employer risk event (ERE)
  • 7. 7 ‫قياس‬ ‫طرق‬‫التأخير‬(5) .1‫التحديث‬ ‫بعد‬ ‫الزمني‬ ‫البرنامج‬ ‫على‬ ‫الموجود‬ ‫الكلي‬ ‫الفائض‬Total float. .2‫المخطط‬ ‫بنسبة‬ ‫مقارنة‬ ‫المكتسبة‬ ‫للقيمة‬ ‫طبقا‬ ‫المنفذ‬ ‫نسبة‬SPI. .3‫تغير‬‫ذلك‬ ‫معالجة‬ ‫وكيفية‬ ‫المشروع‬ ‫في‬ ‫حرج‬ ‫مسار‬ ‫أطول‬Longest critical path change and mitigation actions if required. .4‫ال‬ ‫وموقف‬ ‫الرئيسية‬ ‫المشروع‬ ‫بنود‬ ‫تنفيذ‬ ‫نسب‬ ‫بين‬ ‫االتزان‬ ‫تحليل‬‫خطوط‬ ‫المفتوحة‬LOB. .5‫حركة‬‫المتوقعة‬ ‫المتبقية‬ ‫المدة‬ ‫على‬ ‫ذلك‬ ‫وأثر‬ ‫الزمن‬ ‫مع‬ ‫المشروع‬ ‫تقدم‬Trend analysis vs ETC.
  • 8. 8 1-‫الكلي‬ ‫الفائض‬‫بالسالب‬(-ve TF) A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 -3, 2 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 20, 22 19, 22 12, 20 17, 19 12, 19 9, 12 8, 12 8, 12 2, 8 3, 8 5, 8 -3 -3 -3 -2 -3 -3 -2 2 0 0 0 0 Update Finish Date > Imposed Finish Date
  • 9. 9 2-‫المكتسبة‬ ‫القيمة‬ ‫مؤشر‬(SPI) •‫ما‬‫هي‬EVM‫؟‬‫المكتساب‬ ‫القيما‬ ‫طرياق‬ ‫عان‬ ‫االاارل‬ ‫هي‬(earned value management)‫تبتماا‬ ‫وهاي‬ ‫ي‬ ‫المث‬ ‫المقارن‬ ‫ع‬apple to apple، ‫والو‬ ‫التك‬ ‫هرق‬ ‫حال‬ ‫هي‬‫ا‬ ‫ومبااالت‬‫الو‬ ‫هي‬‫كالتالي‬: BCWS: budget cost of work scheduled= planned value BCWP: budget cost of work performed = earned value Schedule performance index (SPI)= EV/PV (SPI>1: ahead of schedule & SPI<1: behind schedule) BAC: budget cost at completion= total budget of project •‫ما‬‫نسب‬ ‫هي‬performance, scheduled %‫؟‬‫تببر‬ ‫النسب‬ ‫ه‬ ‫ه‬ ‫ي‬ ‫ي‬ ‫كما‬ ‫المكتسب‬ ‫قيم‬ ‫ل‬ ‫طبقا‬ ‫ي‬ ‫ب‬ ‫وال‬ ‫المخطط‬ ‫عن‬: Scheduled % = (PV) / (BAC) Performance % = earned value (EV) / (BAC) Planned Vs Actual
  • 10. 10 (TF vs SPI) Shortage in Each: 1- Availability of resources and resource usage in remaining works can affect the rationality of the total float specially if many paths overlapped in the remaining duration. 2- Out of sequence can disturb the results of EVM schedule factors specially if the progress of critical path is different.
  • 11. 11 ‫المكتسب‬ ‫والقيمة‬ ‫الزمني‬ ‫البرنامج‬ ‫بين‬ ‫الجمع‬‫ة‬
  • 12. 12 3-‫الحرج‬ ‫المسار‬ ‫منطق‬(Critical Path) A B C D F Dependency Determination. Logical Relationship/ mathematical analysis: Successor Activity. that logically comes after Vs Predecessor. Mandatory Dependency. contractually required or inherent in the nature of the work. Hard Logic. Discretionary Dependency. based on knowledge of best practices, Preferred Logic. Soft Logic. External Dependency. A relationship with non-project activities. Applying Lag. a successor activity waiting Vs Lead (-ve lag).
  • 13. 13 4-‫المتكررة‬ ‫األنشطة‬ ‫بين‬ ‫االتزان‬ ‫خط‬(LOB) ‫الـ‬ ‫هو‬ ‫ما‬line of balance‫؟‬‫مجموع‬ ‫عن‬ ‫عبارل‬ ‫المشرو‬ ‫كون‬ ‫حال‬ ‫هي‬ ‫مناسب‬ ‫وتكون‬ ‫اليمني‬ ‫البرامج‬ ‫عمل‬ ‫هي‬ ‫طريق‬ ‫هي‬ ‫الموارا‬ ‫ع‬ ‫مبتمال‬ ‫وتكون‬ ،‫متباال‬ ‫أماكن‬ ‫هي‬ ‫وتن‬ ‫الببف‬ ‫ا‬ ‫بببض‬ ‫المرتبط‬ ‫المتتالي‬ ‫المتكررل‬ ‫االنشط‬ ‫من‬resource constrained‫اليمن‬ ‫م‬ ‫تراكمي‬ ‫منحنيا‬ ‫ع‬ ‫ا‬ ‫وضب‬ ‫ويمكن‬ ،diagrams on a cumulative basis‫وتشمل‬ ‫مشاري‬housing, pipelines, bridges, roads, rail and tunneling works. 0.0% 20.0% 40.0% Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Key KPI's - LOB Excavation all soil types Installation (Pipes & box culvert) Manholes Asphalt
  • 14. 14 5-‫العمل‬ ‫في‬ ‫التقدم‬ ‫منحنى‬ ‫ميل‬(Trend) •‫هاي‬ ‫ماا‬trend analysis‫؟‬‫ا‬ ‫المتو‬ ‫او‬ ‫الن‬ ‫وتااريه‬ ‫ا‬ ‫تك‬ ‫ل‬ ‫با‬ ‫المتو‬ ‫حساابا‬ ‫ل‬ ‫يساتخام‬forecast‫عان‬ ‫ا‬ ‫ال‬‫ا‬‫مث‬ ‫اي‬‫ا‬‫رياض‬ ‫ارق‬‫ا‬‫ط‬ ‫اتخاام‬‫ا‬‫باس‬ ‫االمخطط‬‫ا‬‫ب‬ ‫اا‬‫ا‬ ‫ومقارنت‬ ، ‫اابق‬‫ا‬‫الس‬ ‫ا‬‫ا‬‫ي‬ ‫ب‬ ‫ال‬ ‫ااال‬‫ا‬‫المب‬ ‫اتمرار‬‫ا‬‫اس‬ ‫اق‬‫ا‬‫طري‬‫اتخاام‬‫ا‬‫س‬ ‫اام‬‫ا‬‫التق‬ ‫اط‬‫ا‬‫متوس‬progress‫اا‬‫ا‬‫المنحني‬ ‫اتكمال‬‫ا‬‫الس‬ ‫اا‬‫ا‬‫م‬ ‫ارل‬‫ا‬‫هت‬ ‫اتل‬‫ا‬‫خ‬extend s-curve‫ا‬‫ا‬‫اي‬ ‫ن‬ ‫ا‬‫ا‬‫حت‬ ‫المشرو‬. 0.0% 25.0% 50.0% 75.0% 100.0% Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Overall Progress Planned Actual EV SPI
  • 15. 15 1515 (earned value) (Invoices) (planned value) Cost baseline SV= -1,067$ Daily planned budget= 266.67 $ / day ETC, TF= -15 Days Trend analysis delay= -35 days % Complete = 26.7% = - 4 days ‫اااااين‬‫ا‬‫ب‬ ‫ااااا‬‫ا‬‫الجم‬ ‫ااااااااارا‬‫ا‬‫المؤش‬ ‫المخت‬... ETC: time schedule update
  • 16. 16 ‫التأخير‬ ‫تصنيف‬ Delay Neutral Event In-Excusable (CRE)Excusable ERE Non- CompensableCompensable Concurrent
  • 17. 17 •‫بين‬ ‫رق‬ ‫ال‬recovery, revised programme‫؟‬ ‫النو‬‫وهو‬ ‫األول‬recovery‫هيه‬ ‫ويتم‬ ، ‫به‬ ‫المتسبب‬ ‫هو‬ ‫المقاول‬ ‫تأخير‬ ‫وجوا‬ ‫حال‬ ‫هي‬ ‫ويكون‬‫ت‬‫باويف‬ ‫المشرو‬ ‫اي‬ ‫ن‬ ‫لتاريه‬ ‫بالبرنامج‬ ‫والرجو‬ ‫التأخير‬‫ي‬ ‫األص‬. ‫ااا‬‫ا‬‫أم‬‫اااني‬‫ا‬‫الث‬ ‫ااو‬‫ا‬‫الن‬revised‫اارو‬‫ا‬‫المش‬ ‫ااي‬‫ا‬‫ه‬ ‫اار‬‫ا‬‫يي‬ ‫ت‬ ‫اا‬‫ا‬ ‫ع‬ ‫اااوا‬‫ا‬‫بن‬ ‫ااون‬‫ا‬‫يك‬ ‫ااث‬‫ا‬‫حي‬ ‫ااك‬‫ا‬‫ل‬ ‫ااه‬‫ا‬‫هي‬ ‫ااترط‬‫ا‬‫يش‬ ‫اات‬‫ا‬‫ه‬ variation/change‫اا‬‫ا‬‫ح‬ ‫أو‬ ‫ارو‬‫ا‬‫اله‬ ‫ار‬‫ا‬‫ي‬ ‫ت‬ ‫ابب‬‫ا‬‫بس‬ ‫ال‬‫ا‬‫ب‬ ‫ان‬‫ا‬‫م‬ ‫ا‬‫ا‬‫المقام‬ ‫ا‬‫ا‬‫ي‬ ‫التن‬ ‫ا‬‫ا‬‫طريق‬ ‫اايل‬‫ا‬‫تب‬ ‫أو‬ ،‫وث‬ Disruption،‫شابه‬ ‫وما‬ ‫جايا‬ ‫اي‬ ‫ن‬ ‫وتاريه‬ ‫يمن‬ ‫تمايا‬ ‫اعتماا‬ ‫أو‬. Revised Programme (types & cases): https://www.youtube.c om/watch?v=75iB5BEa pIQ ‫الزمني؟‬ ‫البرنامج‬ ‫تعديل‬ ‫يتم‬ ‫كيف‬
  • 18. 18 ‫التأخير‬ ‫معالجة‬ There are two techniques to compress a programme: 1- Crashing: Done by selectively crashing specific activities to shorten project duration (increase resources – refer to duration equation). 2- Fast-tracking: Done by re-sequence the logic and overlap activities can be done in the same time. 3- Merge and do both together. Compression approaches ‫جدا‬ ‫هام‬‫االجراءات‬ ‫متابعة‬ ‫التصحيحية‬ ‫الخطط‬ ‫في‬‫المتخذة‬‫سواءا‬‫كانت‬‫ت‬‫شمل‬ ‫االدارة‬ ‫عناصر‬ ‫ادراج‬ ‫فينبغى‬ ‫مثال‬ ‫أوالموارد‬ ‫الالزمة‬ ‫التجهيزات‬ ‫عمل‬ ‫بالفرق‬ ‫مقسمة‬ ‫الموارد‬ ‫وجميع‬ ‫واالشراف‬(‫ومواد‬ ‫ومعدات‬ ‫عمالة‬)‫أو‬ ، ‫ك‬ ‫التأكد‬ ‫يتم‬ ‫بحيث‬ ‫التنفيذ‬ ‫طريقة‬ ‫أو‬ ‫العمل‬ ‫بتسلسل‬ ‫خاصة‬ ‫اجراءات‬‫من‬ ‫فترة‬ ‫ل‬ ‫ال‬ ‫أم‬ ‫أخرى‬ ‫إجراءات‬ ‫اتخاذ‬ ‫مطلوب‬ ‫وهل‬ ‫فاعليتها‬ ‫لقياس‬ ‫الخطة‬ ‫فاعلية‬.
  • 19. 19 ‫تحليل‬ ‫طرق‬‫التأخير‬ Prospective Delay Analysis: Analysis of facts associated with delay events during construction of a project and the estimation of their effect upon the planned completion date of a project. (Interim Extension of Time) Retrospective Delay Analysis: Analysis of facts associated with delay events after completion of the construction period of a project. (Final Extension of Time)
  • 20. 20 ‫التأخير؟‬ ‫لتحليل‬ ‫طريقة‬ ‫كل‬ ‫تستخدم‬ ‫متى‬ Guidance Section 4 4.13 The table below summarises the types of analysis that can be conducted depending on the types of factual material available. An ‘X’ indicates the factual material that is required for a particular analysis, but in some cases there are alternatives, as indicated in the table:
  • 21. 21 ‫الزمنيه‬ ‫المطالبات‬ ‫حاالت‬ ‫الحكومية‬ ‫والمشتريات‬ ‫المنافسات‬ ‫نظام‬ ‫والخمسون‬ ‫الحادية‬ ‫المادة‬: ‫التأخي‬ ‫كان‬ ‫ا‬ ‫إ‬ ‫المالي‬ ‫ويارل‬ ‫م‬ ‫ال‬ ‫المتبا‬ ‫الحكومي‬ ‫الج‬ ‫اق‬ ‫بات‬ ‫رام‬ ‫ال‬ ‫من‬ ‫او‬ ‫واةع‬ ‫البقا‬ ‫تمايا‬ ‫يتم‬‫عن‬ ‫ا‬ً‫ج‬‫نات‬ ‫ر‬ ‫األسباب‬ ‫ه‬ ‫ه‬ ‫م‬ ‫التأخير‬ ‫مال‬ ‫تتناسب‬ ‫أن‬ ‫بشرط‬ ،‫ا‬ ‫المتبا‬ ‫إراال‬ ‫عن‬ ‫خارج‬ ‫لسبب‬ ‫أو‬ ، ‫طارئ‬ ‫هرو‬. ‫والخمسون‬ ‫الثانية‬ ‫المادة‬: ‫التالي‬ ‫الحاال‬ ‫هي‬ ‫البقا‬ ‫تمايا‬ ‫المستق‬ ‫الاائرل‬ ‫رئيس‬ ‫أو‬ ‫المختص‬ ‫ويير‬ ‫ل‬: ‫م‬ ‫متناسب‬ ‫المضاه‬ ‫المال‬ ‫تكون‬ ‫أن‬ ‫بشرط‬ ،‫البقا‬ ‫هي‬ ‫ورا‬ ‫ما‬ ‫ع‬ ‫إضاهي‬ ‫بأعمال‬ ‫ا‬ ‫المتبا‬ ‫ك‬ ‫ا‬ ‫إ‬ ‫أ‬-‫حجم‬ ‫ا‬ ‫ب‬ ‫ي‬ ‫التك‬ ‫وتاريه‬ ‫ا‬ ‫وطبيبت‬ ‫األعمال‬. ‫ا‬ ‫متبا‬ ‫ل‬ ‫تبوا‬ ‫ال‬ ‫ألسباب‬ ‫ا‬ ‫ببض‬ ‫أو‬ ‫األعمال‬ ‫بنيقا‬ ‫الحكومي‬ ‫الج‬ ‫من‬ ‫أمر‬ ‫صار‬ ‫ا‬ ‫إ‬ ‫ب‬-. ‫المحاا‬ ‫الو‬ ‫هي‬ ‫البمل‬ ‫ةنجاي‬ ‫كاهي‬ ‫عير‬ ‫مشرو‬ ‫ل‬ ‫السنوي‬ ‫المالي‬ ‫االعتمااا‬ ‫كان‬ ‫ا‬ ‫إ‬-.
  • 22. 22 ‫المتزامن‬ ‫التأخير‬Concurrent ‫واالحداث‬‫المشروع‬ ‫نهاية‬ ‫تاريخ‬ ‫بعد‬ 1.4.8 Where an Employer Risk Event occurs after the contract completion date, in a situation where failure to complete by the contract completion date has been caused by Contractor Delays, the principle set out in Section 1.4.7 above should apply, except where the Employer Risk Event is a noncompensable Employer Risk Event (Neutral). In such an event, no EOT (or compensation) should be due. Where an EOT is due after the contract completion date, the Employer Risk Event does not exonerate the Contractor for all its delays prior to the Employer Risk Event occurring. The effect of the Employer Risk Event should be assessed as described above and any EOT found due should simply be added to the contract completion date. 1.4.7 Where Employer Risk Events and Contractor Risk Events occur sequentially but have concurrent effects, here again any Contractor Delay should not reduce the amount of EOT due to the Contractor as a result of the Employer Delay.
  • 23. 23 ‫التمديد‬ ‫مطالبة‬ ‫مكونات‬ ‫الزمنية‬ ‫التمديدات‬ ‫حالة‬ ‫في‬‫ما‬ ‫الزمني‬ ‫للبرنامج‬ ‫يضاف‬‫يل‬‫ي‬: 1-‫تعريف‬‫هذه‬ ‫الى‬ ‫أدت‬ ‫التي‬ ‫االحداث‬‫المطالبة‬ 2-‫سرد‬‫إ‬ ‫باالشارة‬ ‫والنتيجة‬ ‫األثر‬ ‫لبيان‬ ‫المطالبات‬ ‫احداث‬‫لى‬ ‫االثبات‬ ‫مستندات‬‫وارفاقها‬ 3-‫البنود‬ ‫مع‬ ‫السابقة‬ ‫التمديدات‬‫الم‬ ‫التعاقدية‬ ‫واالجراءات‬‫تعلقة‬ ‫وأحقية‬ ‫بالموضوع‬‫المقاول‬ 4-‫البرنامج‬‫ما‬ ‫شامل‬ ‫المعدل‬ ‫الزمني‬‫في‬ ‫يطلب‬‫البرا‬ ‫تقديم‬‫مج‬ ‫األصلي‬ ‫الحرج‬ ‫بالمسار‬ ‫مقارنة‬ ‫مع‬ ‫الزمنية‬ 5-‫خالصة‬‫الجدي‬ ‫التعاقدي‬ ‫النهاية‬ ‫وتاريخ‬ ‫الزمني‬ ‫التمديد‬‫د‬ ‫المطلوب‬ 6-‫المرفقات‬‫ترقيمها‬ ‫مع‬ ‫السرد‬ ‫في‬ ‫اليها‬ ‫االشارة‬ ‫تم‬ ‫التي‬
  • 24. 24 •‫علو‬ ‫توأخير‬ ‫مراموة‬ ‫تطبيوق‬ ‫عودم‬ ‫هوو‬ ‫الرئيسي‬ ‫الهدف‬ ‫يكون‬‫ى‬ ‫واول‬‫و‬‫المق‬LAD:liquidated and ascertained damages‫ماان‬ ‫التااأخير‬ ‫بااه‬ ‫يتساابب‬ ‫لمااا‬ ‫لك‬ ‫كاا‬ ‫وتساام‬ ، ‫اك‬‫ا‬‫مال‬ ‫ل‬ ‫ارار‬‫ا‬‫أض‬‫و‬‫اتم‬‫ا‬‫ي‬‫اا‬‫ا‬ ‫تطبيق‬‫اي‬‫ا‬‫ه‬‫الم‬ ‫ايام‬‫ا‬‫الت‬ ‫اام‬‫ا‬‫ع‬ ‫اال‬‫ا‬‫ح‬‫ااول‬‫ا‬‫ق‬ ‫ا‬ ‫التماياا‬ ‫أو‬ ‫ااي‬ ‫التبا‬ ‫او‬ ‫الن‬ ‫تااريه‬ ‫هي‬ ‫المشرو‬ ‫او‬ ‫بنن‬‫ليمناي‬ ‫التاأخي‬ ‫حساب‬ ‫يمنيا‬ ‫مراحال‬ ‫ا‬ ‫ع‬ ‫وتطباق‬ ،‫وجاا‬ ‫إن‬ ‫المبتما‬‫ر‬ ‫البقا‬ ‫ا‬ ‫ي‬ ‫ع‬ ‫ينص‬ ‫نسب‬ ‫ص‬ ‫ا‬ ‫بحا‬stipulated. ‫المطالبات‬ ‫من‬ ‫الهدف‬‫الزمنيه‬
  • 25. 25 ‫صلة‬ ‫ذات‬ ‫ودوات‬ ‫محاضرات‬ https://www.youtube. com/watch?v=syxza- ivtbk&index=4&list=PL9 HqmhqTzU- VHjidVEP7FbAkivlfIr0aK https://www.luqman academy.com/cours e?course=16 https://www.luqman academy.com/cour se?course=1 ‫ورشة‬ ‫من‬ ‫مقتطقات‬ ‫المطالبات‬ ‫عمل‬ ‫التأخير‬ ‫وتحليل‬ https://www.youtub e.com/watch?v=XB og3BRwPeU&index= 8&list=PL9HqmhqTzU- VTvrJDskZ4fjUzHqydrf _O
  • 26. Thank You Don’t Hesitate to contact…. M.Maged magedkom@gmail.com mobile : 00966-580264968