SlideShare a Scribd company logo
1 of 18
1Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
The Mystery of OEE
Definitions
Marek Piatkowski – April 2016
Thinkingwin, Win, WIN
2Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
Introduction - Marek Piatkowski
 Professional Background
 Toyota Motor Manufacturing Canada (TMMC) - Cambridge, Ontario from
1987-1994
 TPS/Lean Transformation Consulting - since 1994
 Professional Affiliations
 TWI Network – John Shook, Founder
 Lean Enterprise Institute (LEI) – Jim Womack
 Lean Enterprise Academy (LEA) – Daniel Jones
 CCM/CAINTRA – Monterrey, Mexico
 SME, AME, ASQ, CME
 Lean Manufacturing Solutions - Toronto, Canada
http://twi-network.com
3Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
4Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
TPM Implementation should be driven by the following phrase.
“THIS IS THE WORST CONDITION
THIS EQUIPMENT HAS EVER BEEN IN”
5Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
Operational Availability
 The time that a machine operates maintenance free as a percentage of the time
during it is switched on.
 This is equivalent to the reliability of equipment and its maintenance
 The ideal condition is to have 100% operational availability during the time the
machine is switched on to fill production orders.
Rate of Operation
 The rate of operation states the actual production levels being achieved by
equipment
 This is the percentage of total production capacity actually produced during regular
work hours as determined by demand.
 This rate of operation itself changes depending upon sales.
6Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
OEE - Improvement Measurements
 OEE - Overall equipment effectiveness measures how the plant is performing
relative to reducing the equipment losses and conditions which prevent customer
satisfaction
 The OEE improvement measurement is the product of three different
measurements:
EA - Equipment Availability
EEP - Equipment Efficiency Performance
EQP - Equipment Quality Performance
7Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
EA – Equipment Availability
 EA - is a basic TPM performance measurement.
 EA measures how often equipment is not producing units (unplanned downtime)
due to breakdown or adjustment losses. It compares the actual time the equipment
was producing units (uptime) to the time it was scheduled to produce units
(scheduled production time).
 A breakdown is defined as a condition which requires assistance of a specially
trained maintenance technician or an engineer
 Equipment adjustments are should be normally performed by operators
 Unplanned downtime does not include breaks, lunches, personal relief, team
meetings or scheduled maintenance.
EA
8Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
EA – Equipment Availability
Uptime
EA
Uptime = Scheduled Production Time - Unplanned Downtime
X 100 %EA =
Scheduled Production Time
EA percentage (%) gives the actual time the machine is
running versus what it should be running
9Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
What is a Down Time Clock?
 Down Time Clock is a simple method to measure (EA), total duration of machine
stops – regardless of the reasons or causes
 In it’s simplest form it is an analog clock connected to the “logic” of a machine or
an automated process
 At the start of the shift the clock is reset to 12:00
 When machine is operating – the clock is not running. When the machine stops –
the clock starts to run.
 This way at the end of a work period (for example a shift) you can have an accurate
read-out how many minutes the machine was not running.
 In the example on the next slide the machine was not running for almost 2 hours
and 50 minutes – 170 minutes down time per shift
 How accurate is your down time? You might surprise yourself
11Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
EEP – Equipment Efficiency Performancee
 EEP - measures the actual machine cycle time versus the theoretical or “standard”
cycle time.
 It compares the actual number of units produced versus the “standard” number of
units the machine should have produced in a given length of time (uptime)
 Uptime is the same number that was previously defined in the EA calculation.
 The standard cycle time assumes there are no minor stoppage losses or reduced
speed losses.
 Minor stoppages are defined as stoppages which can be corrected by the operator
EEP
12Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
EEP – Equipment Efficiency Performance
EEP X 100 %EEP =
Actual Run Time
Standard Cycle Time x # of Units Produced
EEP percentage shows the percent of units produced versus the
“standard” quantity that should have been produced.
The number of Units Produced also includes any defective units that were
produced during that period of time.
13Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
EQP – Equipment Quality Performance
 EQP - measures the performance of the machine from a quality standpoint.
 It compares the number of good units to the total number of units produced for a
given period of time.
 Defective units can be produced when equipment does not perform properly or
during machine start-up, before the process has stabilized.
 Parts which can be reworked are counted as defective.
EQP
14Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
EQP – Equipment Quality Performance
EQP # of Good Units
X 100 %EQP =
Total # of Units Produced
# of Good units = Total # of Units Produced - Total # of Units Defective
EQP percentage shows the quality performance of equipment
15Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
OEE – Overall Equipment Efficiency
OEE = EA x EEP x EQP
Benchmarks for these measurements are:
EA = 90% EEP = 95% EQP = 99%
OEE = 85%
OEE
16Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
Availability
Greater than 90%
Running Time
Net Operating Time
B
A
=
Overall Equipment Effectiveness =
Availability x Performance rate x Quality rate 85%+
Idling and minor stoppages per
machine (under 10 minutes)
...less than 3 times/month
Idling &minor
stoppages
3
Operation speed increased
...increase 15% or more
Speed4
Quality defects in process
(including products to be
reworked)...less than 0.1%
Quality defects
in process &
rework
5
Raw material yield
...greater than 99%
Startup6
Setup & adjustment time
...less than 10 minutes
Setup/
adjustment2
1 Breakdowns
Machine down no longer than
10 minutes
...less than once a month
Average total operating loss
30 - 50%
Performance rate
Greater than 95%
Actual Output
Target Output
D
C
=
Total yield
Throughout process > 99%
Good Output
Actual Output
F
E
=
Equipment
Downtime
losses
Speed
losses
Quality
losses
Total operating time
Running time
Good
Output
Optimal conditions in "man-machine" system
Increase continuous unmanned operation time
Equipment operation and the six big losses Improvement Targets
Not
Scheduled
Net operating time
Target Output
Actual Output
Actual Output
A
B
C
D
E
F
OEE
17Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
Changing the World. One Transformation at a time
This presentation is an intellectual property of W3 Group Canada Inc.
No parts of this document can be copied or reproduced
without written permission from:
Marek Piatkowski
W3 Group Canada Inc.
iPhone: 416-235-2631
Cell: 248-207-0416
Marek.Piatkowski@rogers.com
http://twi-network.com
Thinkingwin, Win, WIN
18Marek.Piatkowski@Rogers.com
OEE
Definitions
Thinkingwin, Win, WIN
Presentations in this
Workshop
1. Log in to:
www.slideshare.net
2. Type in my name in
search area:
Marek Piatkowski
3. Select a presentation you
want to see
4. Learn and Enjoy

More Related Content

What's hot

SMED - Quick Change Over
SMED - Quick Change OverSMED - Quick Change Over
SMED - Quick Change OverOskar Olofsson
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessW3 Group Canada Inc.
 
Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016W3 Group Canada Inc.
 
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu HozenAim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu Hozenavijit biswas
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleAndrew Schwartz
 
Principles of Kanban - November 2016
Principles of Kanban - November 2016Principles of Kanban - November 2016
Principles of Kanban - November 2016W3 Group Canada Inc.
 
TPM for lean manufacturing | lean tools
 TPM  for lean manufacturing |  lean tools	 TPM  for lean manufacturing |  lean tools
TPM for lean manufacturing | lean tools 博行 門眞
 

What's hot (20)

TPM Activity
TPM ActivityTPM Activity
TPM Activity
 
010 bmw tpm management training
010 bmw tpm management training010 bmw tpm management training
010 bmw tpm management training
 
SMED - Quick Change Over
SMED - Quick Change OverSMED - Quick Change Over
SMED - Quick Change Over
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
 
Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016
 
OFFICE TPM PPT
OFFICE TPM PPTOFFICE TPM PPT
OFFICE TPM PPT
 
Tpm preview
Tpm previewTpm preview
Tpm preview
 
Tpm principles and concepts
Tpm principles and conceptsTpm principles and concepts
Tpm principles and concepts
 
Dwm overview
Dwm overviewDwm overview
Dwm overview
 
Lean manufacturing ppt
Lean manufacturing pptLean manufacturing ppt
Lean manufacturing ppt
 
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu HozenAim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
 
Abnomality and jishu hozen
Abnomality and jishu hozenAbnomality and jishu hozen
Abnomality and jishu hozen
 
Autonomous maintenance preview
Autonomous maintenance previewAutonomous maintenance preview
Autonomous maintenance preview
 
TPM: Autonomous Maintenance
TPM: Autonomous MaintenanceTPM: Autonomous Maintenance
TPM: Autonomous Maintenance
 
TPM: Quality Maintenance (Hinshitsu Hozen) Poster
TPM: Quality Maintenance (Hinshitsu Hozen) PosterTPM: Quality Maintenance (Hinshitsu Hozen) Poster
TPM: Quality Maintenance (Hinshitsu Hozen) Poster
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
One point lessons (OPLs)
One point lessons (OPLs)One point lessons (OPLs)
One point lessons (OPLs)
 
TPM: Focused Improvement (Kobetsu Kaizen) Poster
TPM: Focused Improvement (Kobetsu Kaizen) PosterTPM: Focused Improvement (Kobetsu Kaizen) Poster
TPM: Focused Improvement (Kobetsu Kaizen) Poster
 
Principles of Kanban - November 2016
Principles of Kanban - November 2016Principles of Kanban - November 2016
Principles of Kanban - November 2016
 
TPM for lean manufacturing | lean tools
 TPM  for lean manufacturing |  lean tools	 TPM  for lean manufacturing |  lean tools
TPM for lean manufacturing | lean tools
 

Viewers also liked

The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)Claire Healey
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Brian Thomas
 
OEE Financial Benefits From Component Improvement
OEE Financial Benefits From Component ImprovementOEE Financial Benefits From Component Improvement
OEE Financial Benefits From Component ImprovementLean Teams USA
 
TPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing Operations
TPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing OperationsTPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing Operations
TPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing OperationsMarcelo Costa
 
Information centers and meeting areas
Information centers and meeting areas   Information centers and meeting areas
Information centers and meeting areas W3 Group Canada Inc.
 
Elimination of 7 Types of Waste (Muda) - Learning to See - December 2016
Elimination of 7 Types of  Waste (Muda) - Learning to See - December 2016Elimination of 7 Types of  Waste (Muda) - Learning to See - December 2016
Elimination of 7 Types of Waste (Muda) - Learning to See - December 2016W3 Group Canada Inc.
 
Chattanooga sme oee down time presentation
Chattanooga sme oee down time presentationChattanooga sme oee down time presentation
Chattanooga sme oee down time presentationJames Mansfield
 
Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012Adrian Pask
 
OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?Jesús Cañada
 
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICAS
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICASIDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICAS
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICASJesús Cañada
 
Designing a Manufacturing Supermarket - November 2016
Designing a Manufacturing Supermarket - November 2016Designing a Manufacturing Supermarket - November 2016
Designing a Manufacturing Supermarket - November 2016W3 Group Canada Inc.
 
Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Anang Tristianto
 

Viewers also liked (20)

OEE
OEEOEE
OEE
 
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
 
Oee guide
Oee guideOee guide
Oee guide
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
 
OEE Financial Benefits From Component Improvement
OEE Financial Benefits From Component ImprovementOEE Financial Benefits From Component Improvement
OEE Financial Benefits From Component Improvement
 
TPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing Operations
TPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing OperationsTPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing Operations
TPM BPN F2F3_Sandoz BR_Increasing OEE throughout Manufacturing Operations
 
Information centers and meeting areas
Information centers and meeting areas   Information centers and meeting areas
Information centers and meeting areas
 
Pure Hoshin Kanri
Pure Hoshin Kanri  Pure Hoshin Kanri
Pure Hoshin Kanri
 
Elimination of 7 Types of Waste (Muda) - Learning to See - December 2016
Elimination of 7 Types of  Waste (Muda) - Learning to See - December 2016Elimination of 7 Types of  Waste (Muda) - Learning to See - December 2016
Elimination of 7 Types of Waste (Muda) - Learning to See - December 2016
 
Chattanooga sme oee down time presentation
Chattanooga sme oee down time presentationChattanooga sme oee down time presentation
Chattanooga sme oee down time presentation
 
Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012
 
Preso: The OEE Story
Preso: The OEE StoryPreso: The OEE Story
Preso: The OEE Story
 
OEE IMPLEMENTATION part 1
OEE IMPLEMENTATION part 1OEE IMPLEMENTATION part 1
OEE IMPLEMENTATION part 1
 
OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?OEE Target - ¿What is the basis for your current OEE goal?
OEE Target - ¿What is the basis for your current OEE goal?
 
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICAS
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICASIDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICAS
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICAS
 
Daily Management Walk About
Daily Management Walk About  Daily Management Walk About
Daily Management Walk About
 
Definition of kp is november 2016
Definition of kp is   november 2016Definition of kp is   november 2016
Definition of kp is november 2016
 
Introduction to Standardized Work
Introduction to Standardized WorkIntroduction to Standardized Work
Introduction to Standardized Work
 
Designing a Manufacturing Supermarket - November 2016
Designing a Manufacturing Supermarket - November 2016Designing a Manufacturing Supermarket - November 2016
Designing a Manufacturing Supermarket - November 2016
 
Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Oee (overall equipment effectifness)
Oee (overall equipment effectifness)
 

Similar to The mystery of OEE

The+complete+guide+to+simple+oee
The+complete+guide+to+simple+oeeThe+complete+guide+to+simple+oee
The+complete+guide+to+simple+oeeGalland Tolentino
 
Total productivity maintenance
Total productivity maintenanceTotal productivity maintenance
Total productivity maintenanceFELIX JONATHAN
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryInfoStream Solutions
 
The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityCorey Vodvarka
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityJason Corder
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityParsec_Automation_Corp
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overviewWebseology
 
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionD3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionMannyjg5
 
A038301010
A038301010A038301010
A038301010theijes
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...IRJET Journal
 
Maintenance metrics in oee
Maintenance metrics in oeeMaintenance metrics in oee
Maintenance metrics in oeejohnsqms
 
Overall Equipment Effectiveness (OEE).pptx
Overall Equipment Effectiveness (OEE).pptxOverall Equipment Effectiveness (OEE).pptx
Overall Equipment Effectiveness (OEE).pptxNoman khan
 

Similar to The mystery of OEE (20)

Ofs whitepaper
Ofs whitepaperOfs whitepaper
Ofs whitepaper
 
The+complete+guide+to+simple+oee
The+complete+guide+to+simple+oeeThe+complete+guide+to+simple+oee
The+complete+guide+to+simple+oee
 
How To Track OEE
How To Track OEEHow To Track OEE
How To Track OEE
 
Total productivity maintenance
Total productivity maintenanceTotal productivity maintenance
Total productivity maintenance
 
OEE
OEEOEE
OEE
 
lean & agile
lean & agilelean & agile
lean & agile
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
 
The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing Productivity
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing Productivity
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing Productivity
 
OEE article
OEE articleOEE article
OEE article
 
Oee
OeeOee
Oee
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overview
 
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionD3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
 
A038301010
A038301010A038301010
A038301010
 
OEE.pptx
OEE.pptxOEE.pptx
OEE.pptx
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
 
Maintenance metrics in oee
Maintenance metrics in oeeMaintenance metrics in oee
Maintenance metrics in oee
 
Overall Equipment Effectiveness (OEE).pptx
Overall Equipment Effectiveness (OEE).pptxOverall Equipment Effectiveness (OEE).pptx
Overall Equipment Effectiveness (OEE).pptx
 
[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)
 

More from W3 Group Canada Inc.

Lean Manager Certification Program - January 2018
Lean Manager Certification Program - January 2018Lean Manager Certification Program - January 2018
Lean Manager Certification Program - January 2018W3 Group Canada Inc.
 
My Journey and Passion for Lean - July 2017
My Journey and Passion for Lean - July 2017My Journey and Passion for Lean - July 2017
My Journey and Passion for Lean - July 2017W3 Group Canada Inc.
 
What is TPS - Toyota Production System
What is TPS - Toyota Production SystemWhat is TPS - Toyota Production System
What is TPS - Toyota Production SystemW3 Group Canada Inc.
 
Workshops and presentations by Marek Piatkowski
Workshops and presentations by Marek Piatkowski Workshops and presentations by Marek Piatkowski
Workshops and presentations by Marek Piatkowski W3 Group Canada Inc.
 
Elimination of 7 types of Waste (MUDA)
Elimination of 7 types of Waste (MUDA)Elimination of 7 types of Waste (MUDA)
Elimination of 7 types of Waste (MUDA)W3 Group Canada Inc.
 
How to implement lean - Executive overview
How to implement lean - Executive overviewHow to implement lean - Executive overview
How to implement lean - Executive overviewW3 Group Canada Inc.
 
Introduction to Shop Floor management - Janaury 2017
Introduction to Shop Floor management - Janaury 2017Introduction to Shop Floor management - Janaury 2017
Introduction to Shop Floor management - Janaury 2017W3 Group Canada Inc.
 
Introduction to Takt time - January 2017
Introduction to Takt time - January 2017Introduction to Takt time - January 2017
Introduction to Takt time - January 2017W3 Group Canada Inc.
 
What is lean transformation - January 2017
What is lean transformation - January 2017What is lean transformation - January 2017
What is lean transformation - January 2017W3 Group Canada Inc.
 
History of Toyota Production System (TPS)
History of Toyota Production System (TPS)History of Toyota Production System (TPS)
History of Toyota Production System (TPS)W3 Group Canada Inc.
 
Operational KPIs - Definitions November 2016
Operational KPIs - Definitions November 2016Operational KPIs - Definitions November 2016
Operational KPIs - Definitions November 2016W3 Group Canada Inc.
 
Business Unit KPIs - Definitions November 2016
Business Unit KPIs - Definitions November 2016Business Unit KPIs - Definitions November 2016
Business Unit KPIs - Definitions November 2016W3 Group Canada Inc.
 
Production scheduling boards - November 2016
Production scheduling boards - November 2016Production scheduling boards - November 2016
Production scheduling boards - November 2016W3 Group Canada Inc.
 
Lean Matrials Management - Introduction to milk run - November 2016
Lean Matrials Management - Introduction to milk run - November 2016Lean Matrials Management - Introduction to milk run - November 2016
Lean Matrials Management - Introduction to milk run - November 2016W3 Group Canada Inc.
 
Design of Lean Mini Markets - November 2016
Design of Lean Mini Markets - November 2016Design of Lean Mini Markets - November 2016
Design of Lean Mini Markets - November 2016W3 Group Canada Inc.
 
Introduction to Pull system - November 2016
Introduction to Pull system - November 2016Introduction to Pull system - November 2016
Introduction to Pull system - November 2016W3 Group Canada Inc.
 
Lean Supermarket - Visual Management - November 2016
Lean Supermarket - Visual Management - November 2016Lean Supermarket - Visual Management - November 2016
Lean Supermarket - Visual Management - November 2016W3 Group Canada Inc.
 
Lean Supermarekt principles - November 2016
Lean Supermarekt principles - November 2016Lean Supermarekt principles - November 2016
Lean Supermarekt principles - November 2016W3 Group Canada Inc.
 

More from W3 Group Canada Inc. (20)

Lean Manager Certification Program - January 2018
Lean Manager Certification Program - January 2018Lean Manager Certification Program - January 2018
Lean Manager Certification Program - January 2018
 
My Journey and Passion for Lean - July 2017
My Journey and Passion for Lean - July 2017My Journey and Passion for Lean - July 2017
My Journey and Passion for Lean - July 2017
 
What is TPS - Toyota Production System
What is TPS - Toyota Production SystemWhat is TPS - Toyota Production System
What is TPS - Toyota Production System
 
Workshops and presentations by Marek Piatkowski
Workshops and presentations by Marek Piatkowski Workshops and presentations by Marek Piatkowski
Workshops and presentations by Marek Piatkowski
 
5 s workplace organization
5 s workplace organization 5 s workplace organization
5 s workplace organization
 
Elimination of 7 types of Waste (MUDA)
Elimination of 7 types of Waste (MUDA)Elimination of 7 types of Waste (MUDA)
Elimination of 7 types of Waste (MUDA)
 
How to implement lean - Executive overview
How to implement lean - Executive overviewHow to implement lean - Executive overview
How to implement lean - Executive overview
 
The DNA of Toyota - January 2017
The DNA of Toyota - January 2017The DNA of Toyota - January 2017
The DNA of Toyota - January 2017
 
Introduction to Shop Floor management - Janaury 2017
Introduction to Shop Floor management - Janaury 2017Introduction to Shop Floor management - Janaury 2017
Introduction to Shop Floor management - Janaury 2017
 
Introduction to Takt time - January 2017
Introduction to Takt time - January 2017Introduction to Takt time - January 2017
Introduction to Takt time - January 2017
 
What is lean transformation - January 2017
What is lean transformation - January 2017What is lean transformation - January 2017
What is lean transformation - January 2017
 
History of Toyota Production System (TPS)
History of Toyota Production System (TPS)History of Toyota Production System (TPS)
History of Toyota Production System (TPS)
 
Operational KPIs - Definitions November 2016
Operational KPIs - Definitions November 2016Operational KPIs - Definitions November 2016
Operational KPIs - Definitions November 2016
 
Business Unit KPIs - Definitions November 2016
Business Unit KPIs - Definitions November 2016Business Unit KPIs - Definitions November 2016
Business Unit KPIs - Definitions November 2016
 
Production scheduling boards - November 2016
Production scheduling boards - November 2016Production scheduling boards - November 2016
Production scheduling boards - November 2016
 
Lean Matrials Management - Introduction to milk run - November 2016
Lean Matrials Management - Introduction to milk run - November 2016Lean Matrials Management - Introduction to milk run - November 2016
Lean Matrials Management - Introduction to milk run - November 2016
 
Design of Lean Mini Markets - November 2016
Design of Lean Mini Markets - November 2016Design of Lean Mini Markets - November 2016
Design of Lean Mini Markets - November 2016
 
Introduction to Pull system - November 2016
Introduction to Pull system - November 2016Introduction to Pull system - November 2016
Introduction to Pull system - November 2016
 
Lean Supermarket - Visual Management - November 2016
Lean Supermarket - Visual Management - November 2016Lean Supermarket - Visual Management - November 2016
Lean Supermarket - Visual Management - November 2016
 
Lean Supermarekt principles - November 2016
Lean Supermarekt principles - November 2016Lean Supermarekt principles - November 2016
Lean Supermarekt principles - November 2016
 

Recently uploaded

Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 

Recently uploaded (17)

Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 

The mystery of OEE

  • 1. 1Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN The Mystery of OEE Definitions Marek Piatkowski – April 2016 Thinkingwin, Win, WIN
  • 2. 2Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN Introduction - Marek Piatkowski  Professional Background  Toyota Motor Manufacturing Canada (TMMC) - Cambridge, Ontario from 1987-1994  TPS/Lean Transformation Consulting - since 1994  Professional Affiliations  TWI Network – John Shook, Founder  Lean Enterprise Institute (LEI) – Jim Womack  Lean Enterprise Academy (LEA) – Daniel Jones  CCM/CAINTRA – Monterrey, Mexico  SME, AME, ASQ, CME  Lean Manufacturing Solutions - Toronto, Canada http://twi-network.com
  • 4. 4Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN TPM Implementation should be driven by the following phrase. “THIS IS THE WORST CONDITION THIS EQUIPMENT HAS EVER BEEN IN”
  • 5. 5Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN Operational Availability  The time that a machine operates maintenance free as a percentage of the time during it is switched on.  This is equivalent to the reliability of equipment and its maintenance  The ideal condition is to have 100% operational availability during the time the machine is switched on to fill production orders. Rate of Operation  The rate of operation states the actual production levels being achieved by equipment  This is the percentage of total production capacity actually produced during regular work hours as determined by demand.  This rate of operation itself changes depending upon sales.
  • 6. 6Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN OEE - Improvement Measurements  OEE - Overall equipment effectiveness measures how the plant is performing relative to reducing the equipment losses and conditions which prevent customer satisfaction  The OEE improvement measurement is the product of three different measurements: EA - Equipment Availability EEP - Equipment Efficiency Performance EQP - Equipment Quality Performance
  • 7. 7Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN EA – Equipment Availability  EA - is a basic TPM performance measurement.  EA measures how often equipment is not producing units (unplanned downtime) due to breakdown or adjustment losses. It compares the actual time the equipment was producing units (uptime) to the time it was scheduled to produce units (scheduled production time).  A breakdown is defined as a condition which requires assistance of a specially trained maintenance technician or an engineer  Equipment adjustments are should be normally performed by operators  Unplanned downtime does not include breaks, lunches, personal relief, team meetings or scheduled maintenance. EA
  • 8. 8Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN EA – Equipment Availability Uptime EA Uptime = Scheduled Production Time - Unplanned Downtime X 100 %EA = Scheduled Production Time EA percentage (%) gives the actual time the machine is running versus what it should be running
  • 9. 9Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN What is a Down Time Clock?  Down Time Clock is a simple method to measure (EA), total duration of machine stops – regardless of the reasons or causes  In it’s simplest form it is an analog clock connected to the “logic” of a machine or an automated process  At the start of the shift the clock is reset to 12:00  When machine is operating – the clock is not running. When the machine stops – the clock starts to run.  This way at the end of a work period (for example a shift) you can have an accurate read-out how many minutes the machine was not running.  In the example on the next slide the machine was not running for almost 2 hours and 50 minutes – 170 minutes down time per shift  How accurate is your down time? You might surprise yourself
  • 10.
  • 11. 11Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN EEP – Equipment Efficiency Performancee  EEP - measures the actual machine cycle time versus the theoretical or “standard” cycle time.  It compares the actual number of units produced versus the “standard” number of units the machine should have produced in a given length of time (uptime)  Uptime is the same number that was previously defined in the EA calculation.  The standard cycle time assumes there are no minor stoppage losses or reduced speed losses.  Minor stoppages are defined as stoppages which can be corrected by the operator EEP
  • 12. 12Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN EEP – Equipment Efficiency Performance EEP X 100 %EEP = Actual Run Time Standard Cycle Time x # of Units Produced EEP percentage shows the percent of units produced versus the “standard” quantity that should have been produced. The number of Units Produced also includes any defective units that were produced during that period of time.
  • 13. 13Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN EQP – Equipment Quality Performance  EQP - measures the performance of the machine from a quality standpoint.  It compares the number of good units to the total number of units produced for a given period of time.  Defective units can be produced when equipment does not perform properly or during machine start-up, before the process has stabilized.  Parts which can be reworked are counted as defective. EQP
  • 14. 14Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN EQP – Equipment Quality Performance EQP # of Good Units X 100 %EQP = Total # of Units Produced # of Good units = Total # of Units Produced - Total # of Units Defective EQP percentage shows the quality performance of equipment
  • 15. 15Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN OEE – Overall Equipment Efficiency OEE = EA x EEP x EQP Benchmarks for these measurements are: EA = 90% EEP = 95% EQP = 99% OEE = 85% OEE
  • 16. 16Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN Availability Greater than 90% Running Time Net Operating Time B A = Overall Equipment Effectiveness = Availability x Performance rate x Quality rate 85%+ Idling and minor stoppages per machine (under 10 minutes) ...less than 3 times/month Idling &minor stoppages 3 Operation speed increased ...increase 15% or more Speed4 Quality defects in process (including products to be reworked)...less than 0.1% Quality defects in process & rework 5 Raw material yield ...greater than 99% Startup6 Setup & adjustment time ...less than 10 minutes Setup/ adjustment2 1 Breakdowns Machine down no longer than 10 minutes ...less than once a month Average total operating loss 30 - 50% Performance rate Greater than 95% Actual Output Target Output D C = Total yield Throughout process > 99% Good Output Actual Output F E = Equipment Downtime losses Speed losses Quality losses Total operating time Running time Good Output Optimal conditions in "man-machine" system Increase continuous unmanned operation time Equipment operation and the six big losses Improvement Targets Not Scheduled Net operating time Target Output Actual Output Actual Output A B C D E F OEE
  • 17. 17Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN Changing the World. One Transformation at a time This presentation is an intellectual property of W3 Group Canada Inc. No parts of this document can be copied or reproduced without written permission from: Marek Piatkowski W3 Group Canada Inc. iPhone: 416-235-2631 Cell: 248-207-0416 Marek.Piatkowski@rogers.com http://twi-network.com Thinkingwin, Win, WIN
  • 18. 18Marek.Piatkowski@Rogers.com OEE Definitions Thinkingwin, Win, WIN Presentations in this Workshop 1. Log in to: www.slideshare.net 2. Type in my name in search area: Marek Piatkowski 3. Select a presentation you want to see 4. Learn and Enjoy