EXPANSIVE MORTAR / CRACKING POWDER A NON-EXPLOSIVE CRACKING
AGENT
By Kalva Krishnudu, FCC(R), Manager (Training), MGVTS, Hosapete, Karnataka.
Email: mgvtshpt@gmail.com; Mobile: +91 9448656260.
INTRODUCTION:
Expansive Mortar (Crack Powder) is widely used for splitting the Granite Blocks in
Ornamental Granite Quarries in India. This is an alkaline non-explosive chemical
powder available in packed bags in the market and this can be purchased,
transported, stored and used in quarries without any permission, or license any
Government agencies, but some safety precautions need to be taken while storage
and use.
The Expansive mortar / Crack Powder is having pH is about 13 and it is non-poisonous,
tasteless, silent, which is chiefly made of aluminum acid calcium, silicates, cement,
and slow coagulant. The powder is mixed with water and poured into drilled holes and
this is powder is eco-friendly no noise, no vibrations, no fly rocks, and no toxic gases.
This mixture expands due to chemical reaction, exerts pressure on the wall of drilled
holes walls and cracks through the direction of the holes. This mixture does not need
any detonator or ignition.
The mixture of Expansive Mortar is capable of exerting pressure about 50 MPa (5000
kg/cm2
. Water and ambient temperature are the most important variables in
influencing in generation of expansive pressure.
APPLICATION EXPANSIVE MORTAR / CRACKING POWDER:
The Expansive Mortar (Crack Powder) is used in Granite, Marble, Sandstone, Quartz,
etc., for splitting or cracking the rock. This powder is also used to demolish the
reinforced concrete constructions.
CHEMICAL COMPOSITIONS OF EXPANSIVE MORTAR / CRACKING POWDER:
1. Calcium hydroxide : 60 to 100 %
2. Silica vitreous : 5 to 10 %
3. Diiron trioxide : 1 to 5 %
4. Aluminum oxide : 1 to 5 %
Page 2 of 6
TYPES OF EXPANSIVE MORTAR / CRACKING POWDER:
According to the different ambient and stone temperatures, the produce is divided
into three types. Appropriate product should be selected and used depending up on
the changes in the temperature.
TYPE TEMPERATURE RANGE
C-I TYPE 25℃ - 40℃
C-II TYPE 10℃ - 25℃
C-III TYPE 05℃ - 10℃
C-IIII TYPE 40℃ - 50℃
SALIENT FEATURES & CHARACTERS OF EXPANSIVE MORTAR / CRACKING POWDER:
1. Expansive mortar (Crack Powder) is a soundless, safe and non-explosive, soundless
agent used to develop crack, and split the Granite Blocks in to required size and
shape.
2. It is efficiently used in quarrying to split big mass of homogeneous rock in the
required shape and size. It can also be used to achieve the perfect blocks from
granite rock, or any other type of stone as final product for sale.
3. It is non-explosive, and safe cracking or demolition agent, easy to transport,
store, handle and use as alternative solution to blasting in dimensional stone
quarries without any license.
4. Large expansion force: It exerts maximum expansion force may hit 1,220 kg/cm2.
5. Short Reaction Time: Reaction time is adjustable in the range of 5 minutes to 10
hours.
6. Long shelf time: It can be stored for two years under the conditions of dryness
and constant temperature of 15 - 30°C without any breakage in its package.
7. Shelf life of this powder is 12 months when stored in sealed container in dry
conditions.
PROCESS OF USING EXPANSIVE MORTAR / CRACK POWDER:
1. The process in short: drilling-stirring-pouring-splitting,
2. First drill the holes in the Stone,
3. Second, pour some of the produce into the plastic bucket with water, the
proportion of water and powder is 1:3, and then stir it into a paste/semi-liquid,
4. Third, slowly pour it down in to the drill holes and fill it with the lid,
5. Fourth, allow eight to twelve hours time to develop the crack/split, depending on
the type of material choosed and temperature.
Page 3 of 6
TOOLS & PERSONAL PROTECTIVE EQUIPMENTS REQUIRED:
Following are the requirements to be made available before take up of Mixing and
Pouring the Expansive mortar (Crack Powder):
1. Clean and cold water for mixing,
2. Plastic bucket is for mixing,
3. Beater or wooden rod for mixing,
4. Safety goggles, shoes, Rubber gloves, Helmet and Dust-proof mask should be
used,
5. Thermometer for checking the temperature,
6. Wooden plugs for placing after filling the holes.
MIXING OF EXPANSIVE MORTAR / CRACK POWDER:
1. Make sure you select the correct temperature, specific to the weather.
2. For regular safety reasons and mixing small amounts by hand, it is recommended
to use rubber gloves.
3. In a plastic bucket, combine 1.5 Liters of water to one 5 kg bag of Expansive
mortar. Or pour water and powder at a rate of 1:3 units by weight.
4. Mix well, using a Beater or Wooden rod. If mixing with a Beater or wooden rod,
make sure powder is completely dissolved into the water.
5. Do not mix more than 2 bags (10 kg) for each lot at a time. Never use glass or
metal containers for mixing.
6. When mixing, if the cracking agent begins to steam in container, add some water
to dilute and process properly.
POURING / FILLING OF EXPANSIVE MORTAR / CRACK POWDER:
1. Make sure the holes are clean and no dust or water and residues left in the holes,
or use high-pressure air hose to clean out, before pouring the Expansive mortar
slurry.
2. Expansive mortar slurry should be poured into holes within 5-10 minutes after
mixing. Do not fill to the top only fill the holes about 15 mm (½” to 1”) from the
top.
3. Mix well and pour into holes while agitating the hole to make sure no air gaps are
in the hole. Keep your face away from the holes filled by mortar. Stay away from
filled holes at least 3 hours after filling to avoid blow-out shot. Keep people away
from job site after filling.
Page 4 of 6
GENERAL PRECAUTIONARY MEASURES WHILE SUE OF EXPANSIVE MORTAR / CRACK
POWDER:
1. Make sure that everyone working with expansive mortar understands the
possibility of blown out, and aware of safe handling of the material.
2. Expansive mortar is a highly alkaline, skin and eye contacts with the mixture must
be rinsed off with large amounts of cold water immediately without rubbing.
Consult a doctor quickly for further care.
3. Wear safety goggles and rubber gloves during expansive mortar handling, mixing
and filling. Dust-proof mask is recommended in poorly ventilated areas.
4. Warm or bubbling mortar is forbidden to fill into holes, once the filled holes start
to smoke or steam, that is the sign they may be about to blow out. Clear the area
of people immediately.
Figure: Mixing and Pouring of Expansive mortar (Crack Powder)
]
Page 5 of 6
PRECAUTIONS IN QUARRYING:
1. Unscientific selection of the faces without taking into consideration of the
geological disturbances like cracks, joint planes, mattas, etc., will affect the
performance.
2. Wrong application of expansive mortar may leads to explosion in quarrying while
dressing the blocks with less burden of rock or presence of cracks/joints.
3. For releasing the granite blocks from sheet rock (in-situ), it is essential to develop
free faces at lease on two sides besides bottom and on the top portion also to
avoid blown out.
4. The diameter of drilling has a great effect on the performance, a range of drill
hole diameter of 28-40 mm is better.
5. Pitch-row shall be 30-50 cm for reinforced concrete, 10-15 cm for marble, and 10-
30 cm for granite based on the hardness and size of the rock.
SAFE OPERATING PROCEDUR FOR USE OF EXPANSIVE MORTAR IN QUARRIES:
1. Mines Manager shall authorize in writing the personnel permitted to draw and use
the Expansive Mortar (crack powder).
2. Expansive Mortar (Crack Powder) shall be used under the direct supervision of
Blaster or Mate or Competent person authorized by Mines Manager.
3. Before using the Cracking Powder clean up the drilled holes for dust & drill
cuttings by using compressed air.
4. Always wear all Personal Protective Equipments such as Safety goggles, Shoes,
Rubber Gloves, Helmet and Dust-proof mask, while using cracking powder.
5. Mix the stipulated quantity of the powder & water, Expansive Mortar (Crack
Powder) shall be thoroughly mixed with clean water of 30% of overall weight of
powder i.e., at the ratio of 1:3 water to powder by weight (1.5 Liters of water to
one 5 kg. bag of Expansive mortar).
6. Always use clean & cold water only for mixing cracking powder.
7. Always use the cracking powder prescribed for that particular rock temperature
8. Use only plastic buckets & wooden sticks for mixing the powder & water. Metal
buckets are strictly prohibited for mixing.
9. Finish the pouring work of mixture into the drilled holes within the prescribed
time of 5-10 minutes and leave the area immediately after pouring the mixture.
10. The workers need to take synchronized operation, especially in hard stone. The
quantity of holes each worker responsible to fill has to be moderate. Taking
synchronized steps when mixing, stirring and filling will lead to maximum
expansive stress with all holes expand at the same time.
Page 6 of 6
11. Do not enter the area for 3 hours where cracking powder sludge has been poured
in drilled holes since blown out of powder may take place (it takes 8-12 hours for
chemical reaction based on the temperature). Do not see directly from top of the
charged holes.
12. For the holes formed with higher temperature, the correct operation is to charge
it after its cooling down, preferably after 5 pm.
13. First aid treatment has to be taken if unexpected blown out of powder takes
place while mixing & pouring and workers should undergo relevant training for
using cracking powder.
14. Return the unused pockets of Crack Powder to stores immediately after
completing the job.
15. Daily report of consumption and other details should be recorded in a bound
paged register.
Productivity can’t be achieved without Safety
Safety can’t be achieved without Training...

More Related Content

What's hot

Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)sou_suk_sou
 
Blasting concepts (1)
Blasting concepts (1)Blasting concepts (1)
Blasting concepts (1)Safdar Ali
 
F1 1103-pipe roof singapore sun -all ,38 pg
F1 1103-pipe  roof  singapore sun -all ,38 pgF1 1103-pipe  roof  singapore sun -all ,38 pg
F1 1103-pipe roof singapore sun -all ,38 pgKimHua Cheng
 
Dam construction
Dam constructionDam construction
Dam constructionalizay41
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingHamed Zarei
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentationAlex Demidov
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...Rajesh Prasad
 
Hydraulic drill jumbos an overview
Hydraulic drill jumbos  an overviewHydraulic drill jumbos  an overview
Hydraulic drill jumbos an overviewPINAKI ROY
 
Explosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting OperationsExplosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting Operationspartha sharma
 
Slope Failure Mechanism
 Slope Failure Mechanism Slope Failure Mechanism
Slope Failure MechanismGAGAN GUPTA
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignUmer Farooq
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel designhaziq42
 
Heavy earth moving machinary
Heavy earth moving machinaryHeavy earth moving machinary
Heavy earth moving machinarySafdar Ali
 

What's hot (20)

Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
 
Blasting concepts (1)
Blasting concepts (1)Blasting concepts (1)
Blasting concepts (1)
 
F1 1103-pipe roof singapore sun -all ,38 pg
F1 1103-pipe  roof  singapore sun -all ,38 pgF1 1103-pipe  roof  singapore sun -all ,38 pg
F1 1103-pipe roof singapore sun -all ,38 pg
 
Dam construction
Dam constructionDam construction
Dam construction
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in Tunneling
 
NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)
 
DMC piling
DMC pilingDMC piling
DMC piling
 
Tunnels, types & importance
Tunnels, types &  importanceTunnels, types &  importance
Tunnels, types & importance
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentation
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
 
Rock blasting for mining
Rock blasting  for miningRock blasting  for mining
Rock blasting for mining
 
Scraper
ScraperScraper
Scraper
 
Hydraulic drill jumbos an overview
Hydraulic drill jumbos  an overviewHydraulic drill jumbos  an overview
Hydraulic drill jumbos an overview
 
Section 400
Section 400Section 400
Section 400
 
Explosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting OperationsExplosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting Operations
 
Slope Failure Mechanism
 Slope Failure Mechanism Slope Failure Mechanism
Slope Failure Mechanism
 
Cast in situ Pile
Cast in situ PileCast in situ Pile
Cast in situ Pile
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel design
 
Heavy earth moving machinary
Heavy earth moving machinaryHeavy earth moving machinary
Heavy earth moving machinary
 

Similar to EXPANSIVE MORTAR (CRACK POWDER).pdf

Max Portfolio 2.compressed
Max Portfolio 2.compressedMax Portfolio 2.compressed
Max Portfolio 2.compressedMaxine Jacobs
 
Complete denture processing & errors
Complete denture processing & errorsComplete denture processing & errors
Complete denture processing & errorsAli Alarasy
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairingBharatha Rathnayke
 
Signature bridge pdf
Signature bridge pdfSignature bridge pdf
Signature bridge pdfBhismo Dev
 
Impression material and technique
Impression material and  techniqueImpression material and  technique
Impression material and techniquemanishsundesha2
 
Chemical Varnish Datasheet Template
Chemical Varnish Datasheet TemplateChemical Varnish Datasheet Template
Chemical Varnish Datasheet TemplateTDSmaker
 
Non metallic floor hardener - arda india
Non metallic floor hardener - arda indiaNon metallic floor hardener - arda india
Non metallic floor hardener - arda indiaJames Brown
 
Mortar mixes for_masonry
Mortar mixes for_masonryMortar mixes for_masonry
Mortar mixes for_masonryVecee Khattak
 
Plastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialPlastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialConstrofacilitator
 
US Grout Ultrafine Cementitious Grout Type SD— Data Sheet
US Grout Ultrafine Cementitious Grout Type SD— Data SheetUS Grout Ultrafine Cementitious Grout Type SD— Data Sheet
US Grout Ultrafine Cementitious Grout Type SD— Data SheetHess Pumice Products
 
Mortar plaster pointing
Mortar plaster pointingMortar plaster pointing
Mortar plaster pointingDivya Vishnoi
 
Cement Australia render it™ multisurface grey
Cement Australia render it™ multisurface greyCement Australia render it™ multisurface grey
Cement Australia render it™ multisurface greycementaustralia
 
US Grout Ultrafine Cementitious Grout Type VX— Data Sheet
US Grout Ultrafine Cementitious Grout Type VX— Data SheetUS Grout Ultrafine Cementitious Grout Type VX— Data Sheet
US Grout Ultrafine Cementitious Grout Type VX— Data SheetHess Pumice Products
 

Similar to EXPANSIVE MORTAR (CRACK POWDER).pdf (20)

Max Portfolio 2.compressed
Max Portfolio 2.compressedMax Portfolio 2.compressed
Max Portfolio 2.compressed
 
Sealing & Cleaning Marble Limestone Tile or Travertine Stone Flooring
Sealing & Cleaning Marble Limestone Tile or Travertine Stone FlooringSealing & Cleaning Marble Limestone Tile or Travertine Stone Flooring
Sealing & Cleaning Marble Limestone Tile or Travertine Stone Flooring
 
Tron inject
Tron  injectTron  inject
Tron inject
 
Complete denture processing & errors
Complete denture processing & errorsComplete denture processing & errors
Complete denture processing & errors
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairing
 
Signature bridge pdf
Signature bridge pdfSignature bridge pdf
Signature bridge pdf
 
Báo giá vữa khô trộn sẵn M17,2
Báo giá vữa khô trộn sẵn M17,2 Báo giá vữa khô trộn sẵn M17,2
Báo giá vữa khô trộn sẵn M17,2
 
Tron crete
Tron  creteTron  crete
Tron crete
 
Impression material and technique
Impression material and  techniqueImpression material and  technique
Impression material and technique
 
Chemical Varnish Datasheet Template
Chemical Varnish Datasheet TemplateChemical Varnish Datasheet Template
Chemical Varnish Datasheet Template
 
Non metallic floor hardener - arda india
Non metallic floor hardener - arda indiaNon metallic floor hardener - arda india
Non metallic floor hardener - arda india
 
Tron cryst
Tron  crystTron  cryst
Tron cryst
 
Kota stone
Kota stoneKota stone
Kota stone
 
Mortar mixes for_masonry
Mortar mixes for_masonryMortar mixes for_masonry
Mortar mixes for_masonry
 
Plastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialPlastering mortar insulation and bonding material
Plastering mortar insulation and bonding material
 
Use of FOAM in underground works
Use of FOAM in underground works Use of FOAM in underground works
Use of FOAM in underground works
 
US Grout Ultrafine Cementitious Grout Type SD— Data Sheet
US Grout Ultrafine Cementitious Grout Type SD— Data SheetUS Grout Ultrafine Cementitious Grout Type SD— Data Sheet
US Grout Ultrafine Cementitious Grout Type SD— Data Sheet
 
Mortar plaster pointing
Mortar plaster pointingMortar plaster pointing
Mortar plaster pointing
 
Cement Australia render it™ multisurface grey
Cement Australia render it™ multisurface greyCement Australia render it™ multisurface grey
Cement Australia render it™ multisurface grey
 
US Grout Ultrafine Cementitious Grout Type VX— Data Sheet
US Grout Ultrafine Cementitious Grout Type VX— Data SheetUS Grout Ultrafine Cementitious Grout Type VX— Data Sheet
US Grout Ultrafine Cementitious Grout Type VX— Data Sheet
 

Recently uploaded

Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information SystemsAnge Felix NSANZIYERA
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...ssuserdfc773
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesRashidFaridChishti
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257subhasishdas79
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesChandrakantDivate1
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 

Recently uploaded (20)

Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 

EXPANSIVE MORTAR (CRACK POWDER).pdf

  • 1. Page 1 of 6 EXPANSIVE MORTAR / CRACKING POWDER A NON-EXPLOSIVE CRACKING AGENT By Kalva Krishnudu, FCC(R), Manager (Training), MGVTS, Hosapete, Karnataka. Email: mgvtshpt@gmail.com; Mobile: +91 9448656260. INTRODUCTION: Expansive Mortar (Crack Powder) is widely used for splitting the Granite Blocks in Ornamental Granite Quarries in India. This is an alkaline non-explosive chemical powder available in packed bags in the market and this can be purchased, transported, stored and used in quarries without any permission, or license any Government agencies, but some safety precautions need to be taken while storage and use. The Expansive mortar / Crack Powder is having pH is about 13 and it is non-poisonous, tasteless, silent, which is chiefly made of aluminum acid calcium, silicates, cement, and slow coagulant. The powder is mixed with water and poured into drilled holes and this is powder is eco-friendly no noise, no vibrations, no fly rocks, and no toxic gases. This mixture expands due to chemical reaction, exerts pressure on the wall of drilled holes walls and cracks through the direction of the holes. This mixture does not need any detonator or ignition. The mixture of Expansive Mortar is capable of exerting pressure about 50 MPa (5000 kg/cm2 . Water and ambient temperature are the most important variables in influencing in generation of expansive pressure. APPLICATION EXPANSIVE MORTAR / CRACKING POWDER: The Expansive Mortar (Crack Powder) is used in Granite, Marble, Sandstone, Quartz, etc., for splitting or cracking the rock. This powder is also used to demolish the reinforced concrete constructions. CHEMICAL COMPOSITIONS OF EXPANSIVE MORTAR / CRACKING POWDER: 1. Calcium hydroxide : 60 to 100 % 2. Silica vitreous : 5 to 10 % 3. Diiron trioxide : 1 to 5 % 4. Aluminum oxide : 1 to 5 %
  • 2. Page 2 of 6 TYPES OF EXPANSIVE MORTAR / CRACKING POWDER: According to the different ambient and stone temperatures, the produce is divided into three types. Appropriate product should be selected and used depending up on the changes in the temperature. TYPE TEMPERATURE RANGE C-I TYPE 25℃ - 40℃ C-II TYPE 10℃ - 25℃ C-III TYPE 05℃ - 10℃ C-IIII TYPE 40℃ - 50℃ SALIENT FEATURES & CHARACTERS OF EXPANSIVE MORTAR / CRACKING POWDER: 1. Expansive mortar (Crack Powder) is a soundless, safe and non-explosive, soundless agent used to develop crack, and split the Granite Blocks in to required size and shape. 2. It is efficiently used in quarrying to split big mass of homogeneous rock in the required shape and size. It can also be used to achieve the perfect blocks from granite rock, or any other type of stone as final product for sale. 3. It is non-explosive, and safe cracking or demolition agent, easy to transport, store, handle and use as alternative solution to blasting in dimensional stone quarries without any license. 4. Large expansion force: It exerts maximum expansion force may hit 1,220 kg/cm2. 5. Short Reaction Time: Reaction time is adjustable in the range of 5 minutes to 10 hours. 6. Long shelf time: It can be stored for two years under the conditions of dryness and constant temperature of 15 - 30°C without any breakage in its package. 7. Shelf life of this powder is 12 months when stored in sealed container in dry conditions. PROCESS OF USING EXPANSIVE MORTAR / CRACK POWDER: 1. The process in short: drilling-stirring-pouring-splitting, 2. First drill the holes in the Stone, 3. Second, pour some of the produce into the plastic bucket with water, the proportion of water and powder is 1:3, and then stir it into a paste/semi-liquid, 4. Third, slowly pour it down in to the drill holes and fill it with the lid, 5. Fourth, allow eight to twelve hours time to develop the crack/split, depending on the type of material choosed and temperature.
  • 3. Page 3 of 6 TOOLS & PERSONAL PROTECTIVE EQUIPMENTS REQUIRED: Following are the requirements to be made available before take up of Mixing and Pouring the Expansive mortar (Crack Powder): 1. Clean and cold water for mixing, 2. Plastic bucket is for mixing, 3. Beater or wooden rod for mixing, 4. Safety goggles, shoes, Rubber gloves, Helmet and Dust-proof mask should be used, 5. Thermometer for checking the temperature, 6. Wooden plugs for placing after filling the holes. MIXING OF EXPANSIVE MORTAR / CRACK POWDER: 1. Make sure you select the correct temperature, specific to the weather. 2. For regular safety reasons and mixing small amounts by hand, it is recommended to use rubber gloves. 3. In a plastic bucket, combine 1.5 Liters of water to one 5 kg bag of Expansive mortar. Or pour water and powder at a rate of 1:3 units by weight. 4. Mix well, using a Beater or Wooden rod. If mixing with a Beater or wooden rod, make sure powder is completely dissolved into the water. 5. Do not mix more than 2 bags (10 kg) for each lot at a time. Never use glass or metal containers for mixing. 6. When mixing, if the cracking agent begins to steam in container, add some water to dilute and process properly. POURING / FILLING OF EXPANSIVE MORTAR / CRACK POWDER: 1. Make sure the holes are clean and no dust or water and residues left in the holes, or use high-pressure air hose to clean out, before pouring the Expansive mortar slurry. 2. Expansive mortar slurry should be poured into holes within 5-10 minutes after mixing. Do not fill to the top only fill the holes about 15 mm (½” to 1”) from the top. 3. Mix well and pour into holes while agitating the hole to make sure no air gaps are in the hole. Keep your face away from the holes filled by mortar. Stay away from filled holes at least 3 hours after filling to avoid blow-out shot. Keep people away from job site after filling.
  • 4. Page 4 of 6 GENERAL PRECAUTIONARY MEASURES WHILE SUE OF EXPANSIVE MORTAR / CRACK POWDER: 1. Make sure that everyone working with expansive mortar understands the possibility of blown out, and aware of safe handling of the material. 2. Expansive mortar is a highly alkaline, skin and eye contacts with the mixture must be rinsed off with large amounts of cold water immediately without rubbing. Consult a doctor quickly for further care. 3. Wear safety goggles and rubber gloves during expansive mortar handling, mixing and filling. Dust-proof mask is recommended in poorly ventilated areas. 4. Warm or bubbling mortar is forbidden to fill into holes, once the filled holes start to smoke or steam, that is the sign they may be about to blow out. Clear the area of people immediately. Figure: Mixing and Pouring of Expansive mortar (Crack Powder) ]
  • 5. Page 5 of 6 PRECAUTIONS IN QUARRYING: 1. Unscientific selection of the faces without taking into consideration of the geological disturbances like cracks, joint planes, mattas, etc., will affect the performance. 2. Wrong application of expansive mortar may leads to explosion in quarrying while dressing the blocks with less burden of rock or presence of cracks/joints. 3. For releasing the granite blocks from sheet rock (in-situ), it is essential to develop free faces at lease on two sides besides bottom and on the top portion also to avoid blown out. 4. The diameter of drilling has a great effect on the performance, a range of drill hole diameter of 28-40 mm is better. 5. Pitch-row shall be 30-50 cm for reinforced concrete, 10-15 cm for marble, and 10- 30 cm for granite based on the hardness and size of the rock. SAFE OPERATING PROCEDUR FOR USE OF EXPANSIVE MORTAR IN QUARRIES: 1. Mines Manager shall authorize in writing the personnel permitted to draw and use the Expansive Mortar (crack powder). 2. Expansive Mortar (Crack Powder) shall be used under the direct supervision of Blaster or Mate or Competent person authorized by Mines Manager. 3. Before using the Cracking Powder clean up the drilled holes for dust & drill cuttings by using compressed air. 4. Always wear all Personal Protective Equipments such as Safety goggles, Shoes, Rubber Gloves, Helmet and Dust-proof mask, while using cracking powder. 5. Mix the stipulated quantity of the powder & water, Expansive Mortar (Crack Powder) shall be thoroughly mixed with clean water of 30% of overall weight of powder i.e., at the ratio of 1:3 water to powder by weight (1.5 Liters of water to one 5 kg. bag of Expansive mortar). 6. Always use clean & cold water only for mixing cracking powder. 7. Always use the cracking powder prescribed for that particular rock temperature 8. Use only plastic buckets & wooden sticks for mixing the powder & water. Metal buckets are strictly prohibited for mixing. 9. Finish the pouring work of mixture into the drilled holes within the prescribed time of 5-10 minutes and leave the area immediately after pouring the mixture. 10. The workers need to take synchronized operation, especially in hard stone. The quantity of holes each worker responsible to fill has to be moderate. Taking synchronized steps when mixing, stirring and filling will lead to maximum expansive stress with all holes expand at the same time.
  • 6. Page 6 of 6 11. Do not enter the area for 3 hours where cracking powder sludge has been poured in drilled holes since blown out of powder may take place (it takes 8-12 hours for chemical reaction based on the temperature). Do not see directly from top of the charged holes. 12. For the holes formed with higher temperature, the correct operation is to charge it after its cooling down, preferably after 5 pm. 13. First aid treatment has to be taken if unexpected blown out of powder takes place while mixing & pouring and workers should undergo relevant training for using cracking powder. 14. Return the unused pockets of Crack Powder to stores immediately after completing the job. 15. Daily report of consumption and other details should be recorded in a bound paged register. Productivity can’t be achieved without Safety Safety can’t be achieved without Training...