SlideShare a Scribd company logo
1 of 34
1
Tunnel Mechanics
隧道力学
Lecture 3
2020-09-28(Mon.)9:50-12:15, 4304B
CHEN Shougen, Professor
Department of Underground Engineering
School of Civil Engineering,SWJTU
2
2
Chapter 2 Design of tunnels
2.1 Concept of tunnel design
Contents
Notation in tunneling
Cross sections
Alignment
Costs
Installations in tunnels
3
Longitudinal sections of heading
A tunnel cross section
Notations in tunneling
Width/Span
Height
Overbruden/Cover
Ground surface
Altitude/Elevation
Ventilation
Chainage
Rock bolt
Shotcrete
4
4
Cross sections (Profiles) Popular profiles
Circular profile
Horse shoe
Mouth (oblate) profile
Rectangle
5
5
Various profiles are conceivable
6
6
Road tunnel profile
7
7
Two tracks One track
Railway tunnel profile
8
8
 Underground water conduits are
built for water supply and water
power plants. For hydroelectric
purposes the water is conducted
from an elevated reservoir to a
low lying powerhouse.
 The conduit is generally
subdivided in a more or less
horizontal headrace tunnel and
an inclined or vertical shaft.
Underground water conduits
Turbo
pumps
9
9
Cross section area
>100
Very big
50-100
Big
10-50
Medium
3-10
Small
<3
Mini
Area( m2 )
Type
10
10
Aerodynamic pressure rise
Fig. 1.16. Piston moving within a tube
11
11
An aerodynamic pressure rise
 causes discomfort of the passengers (unless
the cars are pressure-tight), and,
 Produces noise near exit, and,
 constitutes a load acting upon the lining.
12
12
Comparison
between one-tube with two tracks and twin tubes
Cost
Enveronment
Big
Small
Aerodynamic
Easier in case of fire,
stop operation only in
one tube
Difficult in case of fire,
fully stop operation
Disaster
prevention
and rescue
Helpful from piston wind
No help from piston wind
Ventilation
Bigger section, bigger
deformation, higher risk
Difficulty
and risk
Two-tube with one track
one-tube with two tracks
Comparison
Smaller section, smaller
deformation, lower risk
Small Big
Lower Costs 20-40% more
Tunnel length <10km: one-tube with two tracks
Tunnel length >20km: Two-tube with one track
13
13
Warning:
With respect to double tracks in one tube, one should
take into account that a high speed train should not
encounter a freight (货运) train inside a tunnel, because it
could be endangered by falling items.
Flying block
14
14
Choice of tunnel alignment
1. Depends on geotechnical conditions, traffic, hydrological,
risk management, excavation method (drill & blast or
TBM).
2. To minimize the disturbance of the environment, aspects
of vibration (e.g. due to blasting), noise and ventilation
should be considered.
3. In road tunnels, straight alignments longer than 1,500m
should be avoided, as they could distract the driver.
4. Furthermore, to avoid excessive concentration on one
point, the last few meters of a tunnel should have a
gentle curve in plan view.
15
15
 A high level tunnel is much shorter and reduces
geological risk (because of the reduced cover). On the
other hand, the operation is more expensive because
of increased power consumption and increased wear of
the waggons. Velocity is reduced and traffic
interruptions or delays during winter must be factored
in.
 A base tunnel is much longer and, therefore, much
more expensive and difficult to construct. But it offers
many operational advantages.
Choice between a high level tunnel and a base tunnel
16
16
Cost of tunneling
The reasons behind the success of Madrid are:
 good and extremely lean management (enabling
decisions in 24 hours), own project management
(solution of disputes before they arise), and,
 the appropriate selection of construction methods (full
face methods forbidden, open faces no greater than 5
m2, selection of extremely powerful EPB tunnelling
machines).
17
17
Installations in tunnels:
 Installation for traffic control
 Installation for telecommunication
 Ventilation
 Fire protection
 Illumination of road tunnels
 Drainage
18
Costs in tunneling of Plabutsch western tube (road
tunnel, 9.2km long)
%
8.5
70.5
1.8
13.9
4.5
0.8
19
Installation for traffic control
 Road signs
 Traffic lights
 Traffic guide equipment (floor labelling, side reflectors)
 Traffic census. Peak of maximum allowable traffic
 Height control to catch oversized vehicles before they enter the
tunnel (measured e.g. with photo-sensors)
 Video-monitoring of those tunnels longer than 1,500 m or with a
high traffic density.
 Modern sensors provide warning of traffic slow down (e.g. due to
a fire).
20
Accidents in tunnels
The frequency of accidents in road tunnels is reduced by
ca 50% compared with open roads. The reasons are:
 Speed limits in tunnels are, in general, accepted by
the users.
 Snow, ice, wind, rain and fog are rarely encountered
in tunnels.
One should, however, take into account the
consequences of accidents in tunnels which are
much more severe than on open roads.
21
Installations for telecommunication
Equipment for emergency calls: These have to be
provided in tunnels of more than 500 m length with a
spacing of 150 m. Portals and U-turn niches should
also be equipped with emergency call facilities.
Telephone boxes should be provided with glass doors
that can be opened toward the tunnel.
Service telephones: These telephones have to be
provided in tunnels of more than 1000m in length at
every service station and also in every control room.
They are dispensable if radio communication facilities
are provided.
Radio communication: In those tunnels longer than
1000m or with a high traffic density, radio
communication should be provided for fire brigade,
police and road administration as well as for traffic
announcements via radio. Radio re-broadcasting
22
Ventilation
Two different systems of ventilation:
Ventilation during construction (i.e. during the heading
of the tunnel) ;
Service ventilation (i.e. during the operation of the tunnel).
Expenditures on the latter amount occupies up to 30% of
the total construction costs.
23
Ventilation during construction
Supply with oxygen: The O2-content of air should not
fall below 20 vol.%. Below 18 vol.%2 breathing is not
possible and protection masks should be used. The
lack of oxygen is due to:
 Combustion motors
 Breathing
 Oxidation of wood, coal etc.
 Ground water dissolves more O2 than N2
Cleaning-up of air: The following pollutants have to be
removed
 Dust from rock excavation and shotcreting
 Combustion motors
 Blasting fumes
 Gas egression from rock
 Radon decay products.
24
Allowable concentrations apply (MAC)
25
Ventilation alternatives:
 Supply: supply with fresh air
 Extraction: extraction of polluted air (to be preferred
for shotcrete applications).
26
Ventilation during operation (Service ventilation)
Four types of ventilation techniques:
1-Natural longitudinal ventilation: This ventilation is
accomplished by the pressure difference between the
portals and also by the piston action of the vehicles.
2-Fans: These produce a longitudinal ventilation. The
blowing direction is reversible. Large ventilators
achieve a higher thrust related to installation costs.
27
3-Semi-transverse ventilation: Fresh air is supplied from
special pathways perpendicular to the tunnel’s longitudinal
axis, whereas the polluted air escapes from the portals
(supply system). This is appropriate for tunnels with 2 to
4km length and medium traffic load.
Alternatively, the used air is extracted through special
ducts, while fresh air enters through the portals.
28
4-Transverse ventilation: Fresh air is introduced and
polluted air (which moves upwards) is extracted
perpendicular to the tunnel axis.
29
Fresh air supply
polluted air
extraction
30
Choice of ventilation method
31
Fire protection
 Because of the confined space, fires in tunnels can be
disastrous.17,18 In 1995 a fire in the metro of Baku
caused 289 casualties.
 Other disastrous fires in metros occurred 1903 in Paris
(84 casualties) and 1987 in London (Kings cross station,
the fire cost 31 lifes).
 Between 1978 and 1999, 97 casualties resulted from
accidents in tunnels.
 In 1999 12 people died in the Tauern-tunnel and the
Montblanc-tunnel disaster claimed 41 lives.
Reasons of the Montblanc disaster :
 Obsolete (old) ventilation system
 Inefficient warning systems
 Insufficient communication between the French and the
Italian sides
 When the fire broke out only one fireman was on duty.
32
Illumination of road tunnels
Road tunnels must be sufficiently illuminated. The
luminance is gradually reduced from the portal towards
the interior of the tunnel.
33
Drainage
The interaction of a tunnel with the groundwater via its
drainage is a very important issue The following waters
should be collected and diverted:
 Groundwater (for ecological reasons the withdrawal of
groundwater should be as low as possible)
 Day water (precipitation or melting ice entering from
the portals)
 Service water (e.g. from washing).
34
Longitudinal drains are installed in the sides of
the tunnel.

More Related Content

What's hot

MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
Soil exploration methods and soil investigation report
Soil exploration  methods and soil investigation reportSoil exploration  methods and soil investigation report
Soil exploration methods and soil investigation reportAnjana R Menon
 
Soil arching in granular soil
Soil arching in granular soilSoil arching in granular soil
Soil arching in granular soilJithu G Francis
 
Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...A Makwana
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Hill road construction
Hill road constructionHill road construction
Hill road constructionGeet KH
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rockkamariya keyur
 
construction equipment and agreegate production equipment
construction equipment and agreegate production equipmentconstruction equipment and agreegate production equipment
construction equipment and agreegate production equipmentkonagallasrivardhan
 
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfREPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfMuhammadMuazzam16
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point systemAnshuman Tyagi
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2RAMPRASAD KUMAWAT
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt1971995
 

What's hot (20)

MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
 
Soil exploration methods and soil investigation report
Soil exploration  methods and soil investigation reportSoil exploration  methods and soil investigation report
Soil exploration methods and soil investigation report
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Soil arching in granular soil
Soil arching in granular soilSoil arching in granular soil
Soil arching in granular soil
 
Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Hill road construction
Hill road constructionHill road construction
Hill road construction
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
construction equipment and agreegate production equipment
construction equipment and agreegate production equipmentconstruction equipment and agreegate production equipment
construction equipment and agreegate production equipment
 
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfREPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Setting out work
Setting out workSetting out work
Setting out work
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point system
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 

Similar to Tunnel Mechanics Lecture on Design, Construction & Safety

TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014Hitesh Khanna
 
Tunnelling method in transportation .pptx
Tunnelling method in transportation .pptxTunnelling method in transportation .pptx
Tunnelling method in transportation .pptxLokeshKumarMeena20
 
Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsgifanta
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelAbhishek Kansara
 
Road Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD ModelingRoad Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD ModelingWSP
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnelsarravindsai
 
Auxiliary ventilation
Auxiliary ventilationAuxiliary ventilation
Auxiliary ventilationSafdar Ali
 
Seikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail TunnelSeikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail TunnelJuhi Aggarwal
 
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.pptunit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.pptPranaysandeepjadhav
 
ENG1002 Design project - Client Brief Version 2.0 1 © .docx
ENG1002 Design project - Client Brief Version 2.0 1 © .docxENG1002 Design project - Client Brief Version 2.0 1 © .docx
ENG1002 Design project - Client Brief Version 2.0 1 © .docxYASHU40
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologykumarrajagp
 
3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c 3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c Junaida Wally
 
Gyromat in tunnelling practice
Gyromat in tunnelling practiceGyromat in tunnelling practice
Gyromat in tunnelling practiceNorbert Benecke
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Abner Silva
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal MinesAdil Mathew
 
Dynamic behaviour of tall chimneys
Dynamic behaviour of tall chimneysDynamic behaviour of tall chimneys
Dynamic behaviour of tall chimneyseSAT Journals
 

Similar to Tunnel Mechanics Lecture on Design, Construction & Safety (20)

TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
 
Tunnelling.pdf
Tunnelling.pdfTunnelling.pdf
Tunnelling.pdf
 
On the road
On the roadOn the road
On the road
 
Tunnelling method in transportation .pptx
Tunnelling method in transportation .pptxTunnelling method in transportation .pptx
Tunnelling method in transportation .pptx
 
Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problems
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnel
 
Road Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD ModelingRoad Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD Modeling
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
 
Tunneling
Tunneling Tunneling
Tunneling
 
Auxiliary ventilation
Auxiliary ventilationAuxiliary ventilation
Auxiliary ventilation
 
Seikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail TunnelSeikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail Tunnel
 
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.pptunit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
 
Tunnels firefighting
Tunnels firefightingTunnels firefighting
Tunnels firefighting
 
ENG1002 Design project - Client Brief Version 2.0 1 © .docx
ENG1002 Design project - Client Brief Version 2.0 1 © .docxENG1002 Design project - Client Brief Version 2.0 1 © .docx
ENG1002 Design project - Client Brief Version 2.0 1 © .docx
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c 3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c
 
Gyromat in tunnelling practice
Gyromat in tunnelling practiceGyromat in tunnelling practice
Gyromat in tunnelling practice
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal Mines
 
Dynamic behaviour of tall chimneys
Dynamic behaviour of tall chimneysDynamic behaviour of tall chimneys
Dynamic behaviour of tall chimneys
 

Recently uploaded

Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryWilliamVickery6
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改yuu sss
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdfvaibhavkanaujia
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Servicejennyeacort
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,Aginakm1
 
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degreeyuu sss
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfSumit Lathwal
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一Fi L
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一diploma 1
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girlsssuser7cb4ff
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxmapanig881
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCRdollysharma2066
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxnewslab143
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一z xss
 

Recently uploaded (20)

Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William Vickery
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdf
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
 
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdf
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girls
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptx
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
 

Tunnel Mechanics Lecture on Design, Construction & Safety

  • 1. 1 Tunnel Mechanics 隧道力学 Lecture 3 2020-09-28(Mon.)9:50-12:15, 4304B CHEN Shougen, Professor Department of Underground Engineering School of Civil Engineering,SWJTU
  • 2. 2 2 Chapter 2 Design of tunnels 2.1 Concept of tunnel design Contents Notation in tunneling Cross sections Alignment Costs Installations in tunnels
  • 3. 3 Longitudinal sections of heading A tunnel cross section Notations in tunneling Width/Span Height Overbruden/Cover Ground surface Altitude/Elevation Ventilation Chainage Rock bolt Shotcrete
  • 4. 4 4 Cross sections (Profiles) Popular profiles Circular profile Horse shoe Mouth (oblate) profile Rectangle
  • 7. 7 7 Two tracks One track Railway tunnel profile
  • 8. 8 8  Underground water conduits are built for water supply and water power plants. For hydroelectric purposes the water is conducted from an elevated reservoir to a low lying powerhouse.  The conduit is generally subdivided in a more or less horizontal headrace tunnel and an inclined or vertical shaft. Underground water conduits Turbo pumps
  • 9. 9 9 Cross section area >100 Very big 50-100 Big 10-50 Medium 3-10 Small <3 Mini Area( m2 ) Type
  • 10. 10 10 Aerodynamic pressure rise Fig. 1.16. Piston moving within a tube
  • 11. 11 11 An aerodynamic pressure rise  causes discomfort of the passengers (unless the cars are pressure-tight), and,  Produces noise near exit, and,  constitutes a load acting upon the lining.
  • 12. 12 12 Comparison between one-tube with two tracks and twin tubes Cost Enveronment Big Small Aerodynamic Easier in case of fire, stop operation only in one tube Difficult in case of fire, fully stop operation Disaster prevention and rescue Helpful from piston wind No help from piston wind Ventilation Bigger section, bigger deformation, higher risk Difficulty and risk Two-tube with one track one-tube with two tracks Comparison Smaller section, smaller deformation, lower risk Small Big Lower Costs 20-40% more Tunnel length <10km: one-tube with two tracks Tunnel length >20km: Two-tube with one track
  • 13. 13 13 Warning: With respect to double tracks in one tube, one should take into account that a high speed train should not encounter a freight (货运) train inside a tunnel, because it could be endangered by falling items. Flying block
  • 14. 14 14 Choice of tunnel alignment 1. Depends on geotechnical conditions, traffic, hydrological, risk management, excavation method (drill & blast or TBM). 2. To minimize the disturbance of the environment, aspects of vibration (e.g. due to blasting), noise and ventilation should be considered. 3. In road tunnels, straight alignments longer than 1,500m should be avoided, as they could distract the driver. 4. Furthermore, to avoid excessive concentration on one point, the last few meters of a tunnel should have a gentle curve in plan view.
  • 15. 15 15  A high level tunnel is much shorter and reduces geological risk (because of the reduced cover). On the other hand, the operation is more expensive because of increased power consumption and increased wear of the waggons. Velocity is reduced and traffic interruptions or delays during winter must be factored in.  A base tunnel is much longer and, therefore, much more expensive and difficult to construct. But it offers many operational advantages. Choice between a high level tunnel and a base tunnel
  • 16. 16 16 Cost of tunneling The reasons behind the success of Madrid are:  good and extremely lean management (enabling decisions in 24 hours), own project management (solution of disputes before they arise), and,  the appropriate selection of construction methods (full face methods forbidden, open faces no greater than 5 m2, selection of extremely powerful EPB tunnelling machines).
  • 17. 17 17 Installations in tunnels:  Installation for traffic control  Installation for telecommunication  Ventilation  Fire protection  Illumination of road tunnels  Drainage
  • 18. 18 Costs in tunneling of Plabutsch western tube (road tunnel, 9.2km long) % 8.5 70.5 1.8 13.9 4.5 0.8
  • 19. 19 Installation for traffic control  Road signs  Traffic lights  Traffic guide equipment (floor labelling, side reflectors)  Traffic census. Peak of maximum allowable traffic  Height control to catch oversized vehicles before they enter the tunnel (measured e.g. with photo-sensors)  Video-monitoring of those tunnels longer than 1,500 m or with a high traffic density.  Modern sensors provide warning of traffic slow down (e.g. due to a fire).
  • 20. 20 Accidents in tunnels The frequency of accidents in road tunnels is reduced by ca 50% compared with open roads. The reasons are:  Speed limits in tunnels are, in general, accepted by the users.  Snow, ice, wind, rain and fog are rarely encountered in tunnels. One should, however, take into account the consequences of accidents in tunnels which are much more severe than on open roads.
  • 21. 21 Installations for telecommunication Equipment for emergency calls: These have to be provided in tunnels of more than 500 m length with a spacing of 150 m. Portals and U-turn niches should also be equipped with emergency call facilities. Telephone boxes should be provided with glass doors that can be opened toward the tunnel. Service telephones: These telephones have to be provided in tunnels of more than 1000m in length at every service station and also in every control room. They are dispensable if radio communication facilities are provided. Radio communication: In those tunnels longer than 1000m or with a high traffic density, radio communication should be provided for fire brigade, police and road administration as well as for traffic announcements via radio. Radio re-broadcasting
  • 22. 22 Ventilation Two different systems of ventilation: Ventilation during construction (i.e. during the heading of the tunnel) ; Service ventilation (i.e. during the operation of the tunnel). Expenditures on the latter amount occupies up to 30% of the total construction costs.
  • 23. 23 Ventilation during construction Supply with oxygen: The O2-content of air should not fall below 20 vol.%. Below 18 vol.%2 breathing is not possible and protection masks should be used. The lack of oxygen is due to:  Combustion motors  Breathing  Oxidation of wood, coal etc.  Ground water dissolves more O2 than N2 Cleaning-up of air: The following pollutants have to be removed  Dust from rock excavation and shotcreting  Combustion motors  Blasting fumes  Gas egression from rock  Radon decay products.
  • 25. 25 Ventilation alternatives:  Supply: supply with fresh air  Extraction: extraction of polluted air (to be preferred for shotcrete applications).
  • 26. 26 Ventilation during operation (Service ventilation) Four types of ventilation techniques: 1-Natural longitudinal ventilation: This ventilation is accomplished by the pressure difference between the portals and also by the piston action of the vehicles. 2-Fans: These produce a longitudinal ventilation. The blowing direction is reversible. Large ventilators achieve a higher thrust related to installation costs.
  • 27. 27 3-Semi-transverse ventilation: Fresh air is supplied from special pathways perpendicular to the tunnel’s longitudinal axis, whereas the polluted air escapes from the portals (supply system). This is appropriate for tunnels with 2 to 4km length and medium traffic load. Alternatively, the used air is extracted through special ducts, while fresh air enters through the portals.
  • 28. 28 4-Transverse ventilation: Fresh air is introduced and polluted air (which moves upwards) is extracted perpendicular to the tunnel axis.
  • 31. 31 Fire protection  Because of the confined space, fires in tunnels can be disastrous.17,18 In 1995 a fire in the metro of Baku caused 289 casualties.  Other disastrous fires in metros occurred 1903 in Paris (84 casualties) and 1987 in London (Kings cross station, the fire cost 31 lifes).  Between 1978 and 1999, 97 casualties resulted from accidents in tunnels.  In 1999 12 people died in the Tauern-tunnel and the Montblanc-tunnel disaster claimed 41 lives. Reasons of the Montblanc disaster :  Obsolete (old) ventilation system  Inefficient warning systems  Insufficient communication between the French and the Italian sides  When the fire broke out only one fireman was on duty.
  • 32. 32 Illumination of road tunnels Road tunnels must be sufficiently illuminated. The luminance is gradually reduced from the portal towards the interior of the tunnel.
  • 33. 33 Drainage The interaction of a tunnel with the groundwater via its drainage is a very important issue The following waters should be collected and diverted:  Groundwater (for ecological reasons the withdrawal of groundwater should be as low as possible)  Day water (precipitation or melting ice entering from the portals)  Service water (e.g. from washing).
  • 34. 34 Longitudinal drains are installed in the sides of the tunnel.