This Quality Plan and Inspection and Test Plan is prepared to assure the safe operational and to provide the guidance controlling Quality, Inspection and Test activities of ready mix concrete supply, including its raw material for Betara Complex development Project, Jambi, Indonesia.
Polytek Moisture Sealing Epoxy Primer is a two-component, 100% solids, low viscosity, moisture
accepting epoxy primer. It can reduce the hydrostatic pressure mitted by the floor from 12 lbs per 1000 square feet to less
than 1 lb. Polytek Moisture Seal can even cure underwater without affecting its adhesion. When applied at 73°F / 50%
humidity, Moisture Seal is a 6–7-hour cure.
Polytek Premium Floor Coating Epoxy is a two-component, 100% solids, high-build, low viscosity, low
odor, modified cycloaliphatic, chemical resistant epoxy. This highly versatile epoxy coating comes in both clear and a variety
of pigmented colors. It can be used as a primer (when vapor emission is below 4.5lbs/1000 ft²/24hr), a base coat, or as a
topcoat.
This Quality Plan and Inspection and Test Plan is prepared to assure the safe operational and to provide the guidance controlling Quality, Inspection and Test activities of ready mix concrete supply, including its raw material for Betara Complex development Project, Jambi, Indonesia.
Polytek Moisture Sealing Epoxy Primer is a two-component, 100% solids, low viscosity, moisture
accepting epoxy primer. It can reduce the hydrostatic pressure mitted by the floor from 12 lbs per 1000 square feet to less
than 1 lb. Polytek Moisture Seal can even cure underwater without affecting its adhesion. When applied at 73°F / 50%
humidity, Moisture Seal is a 6–7-hour cure.
Polytek Premium Floor Coating Epoxy is a two-component, 100% solids, high-build, low viscosity, low
odor, modified cycloaliphatic, chemical resistant epoxy. This highly versatile epoxy coating comes in both clear and a variety
of pigmented colors. It can be used as a primer (when vapor emission is below 4.5lbs/1000 ft²/24hr), a base coat, or as a
topcoat.
Polytek’s Ultimate Top Coat is a two-component, high solids, water-based, aliphatic polyurethane. The
excellent UV resistant, mar-resistant, chemical resistant nature of this product will cause it to outperform most other types of
sealers or topcoats without the unwanted smell of solvents. Ultimate Top Coat comes in both a high-gloss and satin-gloss
finish
Polytek’s Ultimate Top Coat is a two-component, high solids, water-based, aliphatic polyurethane. The
excellent UV resistant, mar-resistant, chemical resistant nature of this product will cause it to outperform most other types of
sealers or topcoats without the unwanted smell of solvents. Ultimate Top Coat comes in both a high-gloss and satin-gloss
finish
Cementflex is a two component, polymer modified, flexible, cement based, waterproof coating for concrete and masonry.
Find out more here:
http://www.riw.co.uk/products/cement-based-systems/cementflex
We would like to present the supreme material for pitched roofs - QUEENTILE STONE COATED STEEL ROOFING.
Now the Company is expanding its sales market and searching for new partners and dealers.
Cementfill WP is a single component, polymer modified,
fibre reinforced, portland cement based plugging and sealing
compound.
Find out more here:
http://www.riw.co.uk/products/cement-based-systems/cementfill-wp
Polytek’s Floor Patch Paste is a premium quality, 2-part epoxy, patching compound. It provides epoxy
high build, maximum toughness, flexibility, excellent chemical resistance in a quick-drying paste.
Polytek’s Floor Patch Paste is a premium quality, 2-part epoxy, patching compound. It provides epoxy
high build, maximum toughness, flexibility, excellent chemical resistance in a quick-drying paste.
A fully bonded waterproof coating based on polyurethane technology
Find out more about RIW Flexiseal typical uses and benefits here:
http://www.riw.co.uk/products/liquid-applied-systems/Flexiseal
Aquaurethane Extreme - Regulation 31 Approved Polyurea by LINE-XDarren Hull
PRODUCT USE DESCRIPTION
LINE-X Aquaurethane Extreme is designed to be used to coat existing substrates that have become porous. For example, by coating the external concrete surface of underground reservoirs that are starting to leak you will be able to prevent untreated rainwater from leaking into the reservoirs. This product can also be used to line the internal walls of the reservoirs to prevent the water from leaking out into the groundwater whilst also preventing the groundwater from penetrating the sidewalls into the drinking water.
Aquaurethane Extreme is Regulation 31 Approved.
Find out more by visiting https://line-x.co.uk/heavy-industrial/aquaurethane-extreme/
Car Park Flooring - Maris Polymers - Maripur 7100Orfeas Aggelou
Car park coating is very important. Car Parking otherwise called car park is a challenging surfacing job. Car park coating in car parks must provide a highly durable, abrasion resistant, hard-elastic, anti skid and esthetic surface, capable of withstanding long term vehicular traffic.
The MARIPUR® SYSTEM is the technologically advanced, premium liquid polyurethane car park coating system that offers easy application, high durability, quick curing times and most importantly guaranteed long lasting results. Read more about parking flooring.
Similar to Method statement honycomb repairing (20)
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
Vaccine management system project report documentation..pdfKamal Acharya
The Division of Vaccine and Immunization is facing increasing difficulty monitoring vaccines and other commodities distribution once they have been distributed from the national stores. With the introduction of new vaccines, more challenges have been anticipated with this additions posing serious threat to the already over strained vaccine supply chain system in Kenya.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Courier management system project report.pdfKamal Acharya
It is now-a-days very important for the people to send or receive articles like imported furniture, electronic items, gifts, business goods and the like. People depend vastly on different transport systems which mostly use the manual way of receiving and delivering the articles. There is no way to track the articles till they are received and there is no way to let the customer know what happened in transit, once he booked some articles. In such a situation, we need a system which completely computerizes the cargo activities including time to time tracking of the articles sent. This need is fulfilled by Courier Management System software which is online software for the cargo management people that enables them to receive the goods from a source and send them to a required destination and track their status from time to time.
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSEDuvanRamosGarzon1
AIRCRAFT GENERAL
The Single Aisle is the most advanced family aircraft in service today, with fly-by-wire flight controls.
The A318, A319, A320 and A321 are twin-engine subsonic medium range aircraft.
The family offers a choice of engines
Planning Of Procurement o different goods and services
Method statement honycomb repairing
1. EMPLOYER
NWSDB CENTRAL PROVINCE
SRI LANKA
NATIONAL WATER SUPPLY AND
DRAINAGE BOARD
MAIN CONTRACTOR
OTV
VEOLIA WATER TECHNOLOGIES
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
A Bharatha
REV /DATE/ PREPARED CHECKED APPROVED DESCRIPTION
Format :
A4
This document is the intellectual property of
the relevant issuer. It shall not be
reproduced, used or disclosed other than
with the document issuer’s acceptance.
For Employer Approval :
□ Approved □ Comment □ Rejected
Date:
Name:
Signature:
Page 1 of 23
Sub-Contractor
Document Reference :
2. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 2 of 10
Date: 16/12/2018
Rev: 1
TABLE OF CONTENTS
Section Description
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. REFERENCES
5. RESPONSIBILITIES
6. MATERIALS
6.1 Microcrete
6.2 Non-Shrink Cementitious Grout
6.3 Epoxy bonding agent
6.4 Silicon Sealant
7. MOBILIZATION OF WORKFORCE & EQUIPMENT
7.1 Construction Plant & Equipment
7.2 Manpower
8. WORKING METHODS / PROCEDURES
8.1 Surface Preparation
8.2 Identify the type ofhoneycombs
8.3 Formwork for the deep honeycombs
8.4 Mixing ofbinding agent
8.5 Mixing ofgrout
8.6 Placing of grout
8.7 Curing
9. INSPECTION, TESTING & QUALITY CONTROL
10. SAFETY & SECURITY
9.1 General Provisions
9.2 Safety Action Plan
11. ATTACHMENTS
3. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 3 of 10
Date: 16/12/2018
Rev: 1
1. PURPOSE
The purpose of this Method Statement is to create awareness of common tasks involved in repairing of
honeycombs and ensure the execution is in full compliance with Project Specifications & Standards,
Drawings and other related international Standards & Specifications including HSE requirements. This
Method Statement shall be communicated and be understood by all personnel associated with the task
before commencing the activity.
2. SCOPE
In general sub-contractor shall receive client approval for manufacturer of material, and shop drawings
prior to start repairing. Approved materials shall be verified upon received at site. honeycombs repairing
procedure shall be in accordance with this Method Statement.
There are two types to be repair
1. Shallow honeycombs (d < 50 mm, rebar not exposed)
2. Deep honeycombs ( d ≥ 50 mm, rebar exposed)
1. d <50 mm 2. d ≥ 50 mm
4. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 4 of 10
Date: 16/12/2018
Rev: 1
3. DEFINITIONS
NWSDB : National Water Supply and Drainage Board
CONTRACTOR : OTV Veolia
SUB-CONTRACTOR : China Eleventh Chemical Construction Co. Ltd.( ELECO)
PROJECT : Greater Malate Water Supply Scheme
CMS : Construction Method Statement
QA / QC : Quality Assurance & Quality Control
HSE : Health Safety & Environment
PPE : Personnel Protective Equipment
RA : Risk Assessment
4. REFERENCES
- Specification for civil engineering works – NWSDB/SBD/Plant & Design – Build: Specification
- Material Technical Data sheet of non-shrink grout / Mapefill GP
- Material Technical Data sheet of X – Roc Epoxy Bond
- Material Technical Data sheet of X – Roc MicroCrete
- ITP & Check lists for grout works
5. RESPONSIBILITIES
- Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
Site Manager
Construction manager
QA/QC Engineer
Site Engineer
HSE officer
SK
5. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 5 of 10
Date: 16/12/2018
Rev: 1
6. MATERIALS
All Material listed below shall be approved and inspected by NWSDB prior to use at site.
6.1 MICROCRETE
-X-Roc MicroCrete is a single component, shrinkage compensated, fluid micro concrete
manufactured from selected cements, aggregates and additives. It can be used at a wide range
of workability’s. When used as a fluid micro concrete it is self-compacting. It has exceptional
resistance to carbonation, chloride ingress, sulphate attack and freeze thaw attack.
-Physical Properties
Compressive strength Mpa(psi) 70(101150) [28 days]
Initial set < 1 hour at 25°C
Final set < 24 hours at 25°C
Initial expansion < 4% within 24 hours
Expansion(3-28 days) < 0.4%
6.2 NON-SHRINK CEMENTITIOUS GROUT
-Mapefill GP is a pre-blended powdered grout based on high strength cement, 1mm diameter graded
aggregates and special additives with an expansive agent
-Physical Properties
Compressive strength Mpa > 8
Initial set 7 hrs.
Final set 8 hrs.
Volume expansion (ASTM
C827)
1%
Color Grey
6.3 EPOXY BONDING AGENT (PRIMER)
- X-Roc EpoxyBond is an epoxy bonding agent used to bond fresh concrete to hardened
concrete or steel. It can also be used to protect reinforcing steel from corrosion, and as an
anti-chloride barrier and primer for concrete repair.
6. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 6 of 10
Date: 16/12/2018
Rev: 1
-Physical Properties
Compressive strength Mpa 60
Application temperature 5 - 35°C
Pot life
6 hrs. - 20°C
3 hrs. - 30°C
Maximum overlay time
24 hrs. - 20°C
12 hrs. - 30°C
6.4 SILICON SEALANT
7. MOBILIZATION OF WORKFORCE AND EQUIPMENT
7.1 CONSTRUCTION PLANT & EQUIPMENT
Air Compressor
Grinder
Chipping hammer
Chisel
Carpentry / Masonry Tools
Wire brush
7.2 MAN POWER
Site / QC Engineer
Foremen
Carpenters
Masons
Helpers
7. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 7 of 10
Date: 16/12/2018
Rev: 1
8. WORKING METHODS / PROCEDURES
8.1 Surface Preparation
Visible separation shall be identified and marked. The defect shall be grooved “V” shape by
routing to a minimum depth of 10 mm and if found loose concrete, continued up to sound
concrete. Prepared surfaces must be clean, sound, and free from dust and shutter release
oils after chipping. Concrete surfaces must be thoroughly pre-wetted but excess surface water
(free water) must be removed prior to placing the grout. Always ensure that the shutters are
watertight and sealed to prevent suction of water from the product.
8.2 Identify the type of honeycomb
- After the preparation of surface, if the depth of concrete hole below 50mm. (Figure: 01)
It was shallow honeycomb. For this type grouting
X – Roc Epoxy Bonding agent
Mapefill GP non shrink grout
these two materials were used. Mixed grout can directly apply to the cleaned surface
using spatula or mason trowel.
- If the depth above the 50mm and exposed rebar, (Figure: 02) it was deep honeycomb.
For these type of grouting.
X – Roc Epoxy Bonding agent
X – Roc Microcrete
These two materials were used. Other than that this type of grouting may need formwork
with the chute.
8. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 8 of 10
Date: 16/12/2018
Rev: 1
8.3 Formwork for the deep honeycomb holes
- The wall shall equipped with chute to
facilitate proper pouring of grout as shown
in the figure
- Make sure the water tightness of the
formwork before the pouring of grout, any
spaces gaps or holes shall be sealed with
silicon sealant.
8.4 Mixing of binding agent
The hardener ‘Part B’ into the base ‘Part A’ and mix using a slow speed drill (350rpm) with an Mixer
Paddle for 3 minutes, or until both components have fully dispersed and are uniform in colour. Be
sure to rotate the mixer throughout the drum. Mix only full packs.
8.5 Mixing of grout
1. Mapefill GP grout
Pour 80% of the required mixing water into a suitable rust free container and slowly add a 25 kg
bag of MAPEFILL GP. Add the remaining water to achieve the desired mortar consistency (water
ratios are 4 litres for ‘pumpable’ consistency; 4.5 for ‘pourable’ consistency). Mix for 1-2 minutes
with a low speed mechanical mixer, then check that the mixture is well blended by removing any
powder left on the sides of the mixer. Re-mix for another 2-3 minutes. Larger quantities can be
mixed in a grout mixer.
The mix obtained remains workable for about 1 hour at +20°C. Application: Pour the MAPEFILL
GP mix from one side only into the prepared cavity or shutter in a continual flow in order to prevent
the entrapment of air bubbles.
Consumption: 13.5 litres per 25 kg bag.
2. X-Roc MicroCrete grout
Add X-Roc MicroCrete to water and mix for at least five minutes using an X-Calibur approved forced
action mechanical mixer.
9. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 9 of 10
Date: 16/12/2018
Rev: 1
8.6 Placing of grout
1. For the shallow honeycomb
- After cleaned the grouting area, apply single coat of epoxy bonding agent by brush, ensure
uniform coating is achieved and no ponding occurs
- Pour Mapefill GP from one side only in a continual flow encouraging the discharge of
air bubbles using spatula or mason trowel.
2. For the deep honeycombs
- After cleaned the grouting area, apply single coat of epoxy bonding agent by brush, ensure
uniform coating is achieved and no ponding occurs
- Mixed grout should be poured into the cavity at one point only to avoid entrapping air with the
use of chute for pointing grout
- The formwork should include drainage outlets for pre-soaking and, if beneath a soffit,
provision for air release
- Immediately after mixing, pump or pour the X-Roc MicroCrete into the formwork. No
vibration is required when X-Roc MicroCrete is used in a fluid condition
-
8.7 Curing
Grout surfaces should be protected from wind or high temperature, which can cause rapid
drying. Cover the surface with damp sacks (hessian). Do not allow the sacks to dry out.
Curing to be continued for minimum 3 days. Leave formwork in place until the compressive
strength has reached 20 MPa. WB or water soak/ polythene wrap. Curing to be continued
for minimum 3 days.
10. GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR HONEYCOMBS REPAIRING
Page: 10 of 10
Date: 16/12/2018
Rev: 1
9. INSPECTION, TESTING & QUALITY CONTROL (QA/ QC)
- Inspection shall be accordance with approved ITP & Checklist
- Temperature shall be maintained at manufacture recommended limits, ice or chilled water shall
be need as necessary
- Sample of grout shall be taken, size 100mm x 100mm molds to verify the compressive strength
of grout
- An RFI shall be raised 24 hrs. in advance prior to executing the activity
10. SAFETY& SECURITY
10.1 General Provisions
Protection and safety shall be in accordance with Project Safety Manual and ELECO Safety Manual
approved by OTV / NWSDB. ELECO shall provide temporary fence, barricades, lights and any other
preventive measure according to the approved Safety Manual for personnel safety during
construction. Directions given in manufacture’s MSDS shall strictly followed.
10.2 Safety Action Plan
Where applicable, Permit to Work will be obtained prior to starting the works.
Workforce and supervisors shall be aware of common risks that could be encountered during the
activities associated with masonry works.
Necessary warnings, suitable barricades, proper access, shall be established.
PPE for workers are mandatory.
Site Engineer and General Foreman shall arrange all necessarysafety requirements at site and they
will ensure workplace is safe.
Safety Inspector shall ensure that all safety measures are implemented at workplace and
workers/staff are aware of safety risks.
11. ATTACHMENT
Annex 1: Risk Assessment