Work study
Work measurement: Job design determines the content of a job,
and method analysis determines how a job is to be performed. Work
measurement is concerned with determining the length of time it
should take to complete the job. Job times are vital inputs for
workplace planning, estimating labor costs, scheduling, budgeting
and designing incentive systems.
From the workers standpoint, time standards reflect the amount of
time it should take to do a given job working under typical
conditions.
Standard time: A standard time is the amount of time it should take a
qualified worker to complete a specified task, working under sustainable
rate, using given methods, tools and equipment, raw material inputs and
workplace arrangement. Whenever a time standard is developed for a
job, it is essential to provide a complete description of the parameters of
the job because the actual time to do the job is sensitive to all of these
factors.
The most commonly used methods of work measurement are
1. Stopwatch time study
2. Historical times
3. Predetermined data
4. Work sampling
Stopwatch time study was formally introduced by frederick winslow taylor in the
late nineteenth century.
Stopwatch time study is used to develop a time standard based on
observations of one worker taken over a number of cycles. That is then
applied to the work of all others in the organization who perform the
same tasks.
The basic steps in a time study are:
1. Define the task to be studied, and inform the worker who will be
studied.
2. Determine the number of cycles to observe.
3. Time the job and rate the worker’s performance.
4. Compute the standard time.
The analyst who studies the job should be thoroughly familiar with the
process since it is not unusual for workers to attempt to include extra
motions during the study in hope of gaining a standard that allows more
time per piece (i.e., the worker will be able to work at a slower pace and
still meet the standard.)
In most instances, an analyst will break all but very short jobs down into
basic elemental motions and obtain time for each element. Reasons are
1. Some elements are not performed in every cycle, and the breakdown enables
the analyst to get a better perspective on them.
2. The workers proficiency may not be the4 same for all elements of the job.
3. To build a file of elemental times that can be used to set times for the other
jobs.
Development of a time standard involves computation of three times:
1. The observed time (OT)
2. The normal time (NT)
3. The standard time (ST)
Observed time: The observed time is simply the average of the recorded
times. Thus
n
i∑=
x
OT
Where,
OT= Observed time
∑Xi = Sum of recorded times
n = Number of observations
If a job element does not occur
each cycle, its average time
should be determined separately
and that amount should be
included in the observed time,
OT.
Normal time: The normal time is the observed time adjusted for worker
performance. It is computed by multiplying the observed time by a
performance rating. That is
PROTNT ×=
Where,
NT = Normal time
PR = Performance Rating
OT = Observed time
If ratings are made on an element by element basis, the normal time is
obtained by
)PR(XNT jj ×∑=
Where, Xj = Average time for element j
PRj= Performance rating for element j
The reason for including performance rating
1. May be working at different rate from the normal rate.
Normal rating is 1.00. A performance rating of .9 indicates a pace
that is 90 percent of normal, whereas a rating of 1.05 indicates a
pace that is slightly faster than normal.
Standard time: The normal time does not take into account such factors
as personal delays (getting a drink of water or going to the restroom),
unavoidable delays (machine adjustments and repairs, talking to a
supervisor, waiting for materials), rest breaks. So standard time is
AFNTST ×=
Where, ST = Standard time
AF= Allowance factor
Allowances can be based on either job time or time worked (e.g., a
workday)
,1AFjob A+=
,
1
1
AFday
A−
=
II
ObservationObservation
Time, xTime, x
minutesminutes
II
ObservationObservation
Time, xTime, x
minutesminutes
11 1.121.12 66 1.181.18
22 1.151.15 77 1.141.14
33 1.161.16 88 1.141.14
44 1.121.12 99 1.191.19
55 1.151.15 TotalTotal 10.3510.35
9=n 03.1=PR 20.0=A
min15.1
9
35.10
===
∑
n
X
OT i
min30.113.115.1 =×=×= PROTNT
min56.120.130.1)20.01(30.1)1( =×=+×=+×= ANTST
If an abnormally short time has been recorded, it typically
would be assumed to be the result of observational error and
thus discarded. If one of the observations in example had
been 0.10, it would have been discarded. However, if an
abnormally long time has been recorded, the analyst would
want to investigate that observation to determine whether
some irregularly occurring aspect of the task (e.g., retrieving a
dropped tool or part) exists. Which should legitimately be
factored into the job.
Limitations
One limitation is the fact that only those jobs that can be observed can
be studied.
Most managerial and creative jobs, that involve mental as well as
physical aspects can not be studied.
It is costly for irregular and infrequently occurring jobs.
Standard elemental times
Standard elemental times are derived from a firm’s own historical time study data.
Over the years, a time study department can accumulate a file of elemental times
that are common to many jobs.
The procedure for using standard elemental times consists of the following steps:
1. Analyze the job to identify the standard elements.
2. Check the file for elements that have historical times, and record them. Use
time study to obtain others, if necessary.
3. Modify the file times if necessary.
4. Sum the elemental times of obtain the normal time, and factor in allowances to
obtain the standard time.
Predetermined time standards
Predetermined time standards involve the use of published data on standard
elemental times.
A commonly used system is methods time measurement (MTM). Which was
developed in the late 1940s by the method engineering council.
The MTM tables are based on extensive research of basic elemental motions and
times.
To use the approach, the analyst must divide the job into its basic elements (reach,
move, turn, disengage), measure the distances involved (if applicable).
Rate the difficulty of the element, and then refer to the appropriate table of data to
obtain the time for that element.
The Standard time for the job is obtained by adding the times for all of the basic
elements.
Times of the basic elements are measured in time measurement units(TMU).
1 TMU = 0.0006 minute.
Work Sampling
Work sampling is a technique for estimating the proportion of time that a worker or
machine spends on various activities and the idle time.
Unlike work study, work sampling does not require timing an activity nor does it
even involve continuous observation of the activity. Instead, an observer makes
brief observations of a worker or a machine at random intervals and simply notes
the nature of the activity. For example, a machine may be busy or idle; a secretary
may be typing, filing, talking on the telephone, and so on.
The resulting data are counts of the number of times each category of activity or
non-activity was observed.
Although work sampling is occasionally used to set time standards, its two
primary uses are in
1. Ratio delay studies
2. Analysis of non-repetitive jobs
Ratio delay studies: concern the percentage of a worker’s time that involves
unavoidable delays or the proportion of time a machine is idle
Non repetitive jobs: typically involve a broader range of skills than repetitive
jobs, and workers in these jobs are often paid on the basis of the highest skill
involved. Therefore it is important to determine the proportion of time spent on the
high skill level.
Importance
Work sampling estimates an approximations of the actual proportion of time
devoted to a given activity. The goal of work sampling is to obtain an estimate
that provides a specified confidence not differing from the true value by more
than a specified error.
Example: a hospital administrator might request an estimate of X-ray idle time
that will provide a 95 percent confidence of being within 4 percent of the actual
percentage.
Hence work sampling is designed to produce a value, p, which
estimates the true proportion, P, within some allowable error, e:
epP ±=
Work study Training Manual

More Related Content

What's hot (20)

Time study part 2
Time study part 2Time study part 2
Time study part 2
 
QCO presentation
QCO presentationQCO presentation
QCO presentation
 
1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics
 
Work study method and time study-final - copy
Work study method and time study-final - copyWork study method and time study-final - copy
Work study method and time study-final - copy
 
7. work study and method measurement
7. work study and method measurement7. work study and method measurement
7. work study and method measurement
 
Analysis of sewing section efficiency by using time study technique in Appare...
Analysis of sewing section efficiency by using time study technique in Appare...Analysis of sewing section efficiency by using time study technique in Appare...
Analysis of sewing section efficiency by using time study technique in Appare...
 
Method Study
Method StudyMethod Study
Method Study
 
Method study
Method studyMethod study
Method study
 
Industrial engineering
Industrial engineeringIndustrial engineering
Industrial engineering
 
Time study
Time studyTime study
Time study
 
GSD Manual For Students
GSD Manual For StudentsGSD Manual For Students
GSD Manual For Students
 
Line balancing example
Line balancing exampleLine balancing example
Line balancing example
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
Work methods
Work methodsWork methods
Work methods
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work study
Work studyWork study
Work study
 
UNIT 2 - WORK STUDY
UNIT 2 -  WORK STUDYUNIT 2 -  WORK STUDY
UNIT 2 - WORK STUDY
 
Method study
Method studyMethod study
Method study
 
9 Ways to Increase Sewing Operator Efficiency.pdf
9 Ways to Increase Sewing Operator Efficiency.pdf9 Ways to Increase Sewing Operator Efficiency.pdf
9 Ways to Increase Sewing Operator Efficiency.pdf
 
Work Measurment
Work Measurment Work Measurment
Work Measurment
 

Viewers also liked

Coping with GSD: What's the Secret
Coping with GSD: What's the SecretCoping with GSD: What's the Secret
Coping with GSD: What's the Secretgsdlife
 
Standardization & digitalization of sewing operations
Standardization & digitalization of sewing operationsStandardization & digitalization of sewing operations
Standardization & digitalization of sewing operationsArpan Mahato
 
Industrial engineering presentation
Industrial engineering presentation Industrial engineering presentation
Industrial engineering presentation Işıl Tabağ
 
6 things you should know about industrial engineering
6 things you should know about industrial engineering6 things you should know about industrial engineering
6 things you should know about industrial engineeringIE Saeed Shurrab
 
A throughput bulletin for Texport Syndicate, post vsm
A throughput bulletin for Texport Syndicate, post vsmA throughput bulletin for Texport Syndicate, post vsm
A throughput bulletin for Texport Syndicate, post vsmSourav Kumar
 
Presentation on washing and garments
Presentation on washing and garmentsPresentation on washing and garments
Presentation on washing and garmentsNuruzzaman Shah
 
Garments washing imran personal
Garments washing imran personalGarments washing imran personal
Garments washing imran personalImran Hasan
 
Industrial Engineering At A glance.
Industrial Engineering At A glance.Industrial Engineering At A glance.
Industrial Engineering At A glance.Greejesh Prakash
 
Knitted fabric types
Knitted fabric typesKnitted fabric types
Knitted fabric typessuniltalekar1
 
Fashion forecasting process
Fashion forecasting processFashion forecasting process
Fashion forecasting processsuniltalekar1
 
Forecasting presentation
Forecasting presentationForecasting presentation
Forecasting presentationAlka Yadav
 
Fashion trend and fashion forecasting
Fashion trend and fashion forecastingFashion trend and fashion forecasting
Fashion trend and fashion forecastingDarshika gupta
 
cycle time, normal time and standard allowance
cycle time, normal time and standard allowancecycle time, normal time and standard allowance
cycle time, normal time and standard allowancePratibha Khemchandani
 

Viewers also liked (20)

Coping with GSD: What's the Secret
Coping with GSD: What's the SecretCoping with GSD: What's the Secret
Coping with GSD: What's the Secret
 
Standardization & digitalization of sewing operations
Standardization & digitalization of sewing operationsStandardization & digitalization of sewing operations
Standardization & digitalization of sewing operations
 
GSD Certificate
GSD CertificateGSD Certificate
GSD Certificate
 
Time study ratings&&allowances
Time  study ratings&&allowancesTime  study ratings&&allowances
Time study ratings&&allowances
 
Industrial engineering presentation
Industrial engineering presentation Industrial engineering presentation
Industrial engineering presentation
 
6 things you should know about industrial engineering
6 things you should know about industrial engineering6 things you should know about industrial engineering
6 things you should know about industrial engineering
 
Journey begins
Journey beginsJourney begins
Journey begins
 
VSM
VSMVSM
VSM
 
A throughput bulletin for Texport Syndicate, post vsm
A throughput bulletin for Texport Syndicate, post vsmA throughput bulletin for Texport Syndicate, post vsm
A throughput bulletin for Texport Syndicate, post vsm
 
Presentation on washing and garments
Presentation on washing and garmentsPresentation on washing and garments
Presentation on washing and garments
 
Garments washing imran personal
Garments washing imran personalGarments washing imran personal
Garments washing imran personal
 
Paradigm shift
Paradigm shiftParadigm shift
Paradigm shift
 
Industrial Engineering At A glance.
Industrial Engineering At A glance.Industrial Engineering At A glance.
Industrial Engineering At A glance.
 
Knitted fabric types
Knitted fabric typesKnitted fabric types
Knitted fabric types
 
Spinning calculations
Spinning calculationsSpinning calculations
Spinning calculations
 
Garments washing plant
Garments  washing  plantGarments  washing  plant
Garments washing plant
 
Fashion forecasting process
Fashion forecasting processFashion forecasting process
Fashion forecasting process
 
Forecasting presentation
Forecasting presentationForecasting presentation
Forecasting presentation
 
Fashion trend and fashion forecasting
Fashion trend and fashion forecastingFashion trend and fashion forecasting
Fashion trend and fashion forecasting
 
cycle time, normal time and standard allowance
cycle time, normal time and standard allowancecycle time, normal time and standard allowance
cycle time, normal time and standard allowance
 

Similar to Work study Training Manual

Similar to Work study Training Manual (20)

Good work measurement
Good work measurementGood work measurement
Good work measurement
 
4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx
 
Measurment techniques
Measurment techniquesMeasurment techniques
Measurment techniques
 
Work measurement
Work measurementWork measurement
Work measurement
 
presentation group 5.pptx
presentation group 5.pptxpresentation group 5.pptx
presentation group 5.pptx
 
Unit 3 problems
Unit 3 problemsUnit 3 problems
Unit 3 problems
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work study work measurement
Work study   work measurementWork study   work measurement
Work study work measurement
 
Industrial egineering
Industrial egineeringIndustrial egineering
Industrial egineering
 
Time and motion study
Time and motion study Time and motion study
Time and motion study
 
Om4 bbm(l) 25.03.11
Om4 bbm(l) 25.03.11Om4 bbm(l) 25.03.11
Om4 bbm(l) 25.03.11
 
Work measurement
Work measurementWork measurement
Work measurement
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work measurement ppt @ bec doms
Work measurement ppt @ bec domsWork measurement ppt @ bec doms
Work measurement ppt @ bec doms
 
Ch11
Ch11Ch11
Ch11
 
Work study method-and_time_study-final
Work study method-and_time_study-finalWork study method-and_time_study-final
Work study method-and_time_study-final
 
Chapter-7 Job Design and Work Measurement Final.pptx
Chapter-7 Job Design and Work Measurement Final.pptxChapter-7 Job Design and Work Measurement Final.pptx
Chapter-7 Job Design and Work Measurement Final.pptx
 
Cu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut universityCu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut university
 

More from মোঃ ফুরকান উদ্দিন জুয়েল

More from মোঃ ফুরকান উদ্দিন জুয়েল (16)

Teamwork
TeamworkTeamwork
Teamwork
 
Attitude
AttitudeAttitude
Attitude
 
7 wastages
7 wastages7 wastages
7 wastages
 
Why why analysis
Why why analysisWhy why analysis
Why why analysis
 
Line balancing & EOQ
Line balancing & EOQLine balancing & EOQ
Line balancing & EOQ
 
Kaizen
KaizenKaizen
Kaizen
 
Bangladesh labor law'2006
Bangladesh labor law'2006Bangladesh labor law'2006
Bangladesh labor law'2006
 
New gazzettee 10
New gazzettee   10New gazzettee   10
New gazzettee 10
 
SMV & Benefits
SMV & BenefitsSMV & Benefits
SMV & Benefits
 
Basic concepts on lean manufacturing
Basic concepts on lean manufacturingBasic concepts on lean manufacturing
Basic concepts on lean manufacturing
 
Motion Economy
Motion EconomyMotion Economy
Motion Economy
 
Kanban
KanbanKanban
Kanban
 
Industrial engineer
Industrial engineerIndustrial engineer
Industrial engineer
 
Different types of Production Layout
Different types of Production LayoutDifferent types of Production Layout
Different types of Production Layout
 
pre- determined time standard of work measurement
pre- determined time standard of work measurement pre- determined time standard of work measurement
pre- determined time standard of work measurement
 
Industrial Engineering Tools of Motion economy principles for developing manu...
Industrial Engineering Tools of Motion economy principles for developing manu...Industrial Engineering Tools of Motion economy principles for developing manu...
Industrial Engineering Tools of Motion economy principles for developing manu...
 

Recently uploaded

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Work study Training Manual

  • 1. Work study Work measurement: Job design determines the content of a job, and method analysis determines how a job is to be performed. Work measurement is concerned with determining the length of time it should take to complete the job. Job times are vital inputs for workplace planning, estimating labor costs, scheduling, budgeting and designing incentive systems. From the workers standpoint, time standards reflect the amount of time it should take to do a given job working under typical conditions.
  • 2. Standard time: A standard time is the amount of time it should take a qualified worker to complete a specified task, working under sustainable rate, using given methods, tools and equipment, raw material inputs and workplace arrangement. Whenever a time standard is developed for a job, it is essential to provide a complete description of the parameters of the job because the actual time to do the job is sensitive to all of these factors. The most commonly used methods of work measurement are 1. Stopwatch time study 2. Historical times 3. Predetermined data 4. Work sampling
  • 3. Stopwatch time study was formally introduced by frederick winslow taylor in the late nineteenth century. Stopwatch time study is used to develop a time standard based on observations of one worker taken over a number of cycles. That is then applied to the work of all others in the organization who perform the same tasks. The basic steps in a time study are: 1. Define the task to be studied, and inform the worker who will be studied. 2. Determine the number of cycles to observe. 3. Time the job and rate the worker’s performance. 4. Compute the standard time.
  • 4. The analyst who studies the job should be thoroughly familiar with the process since it is not unusual for workers to attempt to include extra motions during the study in hope of gaining a standard that allows more time per piece (i.e., the worker will be able to work at a slower pace and still meet the standard.) In most instances, an analyst will break all but very short jobs down into basic elemental motions and obtain time for each element. Reasons are 1. Some elements are not performed in every cycle, and the breakdown enables the analyst to get a better perspective on them. 2. The workers proficiency may not be the4 same for all elements of the job. 3. To build a file of elemental times that can be used to set times for the other jobs.
  • 5. Development of a time standard involves computation of three times: 1. The observed time (OT) 2. The normal time (NT) 3. The standard time (ST) Observed time: The observed time is simply the average of the recorded times. Thus n i∑= x OT Where, OT= Observed time ∑Xi = Sum of recorded times n = Number of observations If a job element does not occur each cycle, its average time should be determined separately and that amount should be included in the observed time, OT.
  • 6. Normal time: The normal time is the observed time adjusted for worker performance. It is computed by multiplying the observed time by a performance rating. That is PROTNT ×= Where, NT = Normal time PR = Performance Rating OT = Observed time If ratings are made on an element by element basis, the normal time is obtained by )PR(XNT jj ×∑= Where, Xj = Average time for element j PRj= Performance rating for element j
  • 7. The reason for including performance rating 1. May be working at different rate from the normal rate. Normal rating is 1.00. A performance rating of .9 indicates a pace that is 90 percent of normal, whereas a rating of 1.05 indicates a pace that is slightly faster than normal.
  • 8. Standard time: The normal time does not take into account such factors as personal delays (getting a drink of water or going to the restroom), unavoidable delays (machine adjustments and repairs, talking to a supervisor, waiting for materials), rest breaks. So standard time is AFNTST ×= Where, ST = Standard time AF= Allowance factor Allowances can be based on either job time or time worked (e.g., a workday) ,1AFjob A+= , 1 1 AFday A− =
  • 9. II ObservationObservation Time, xTime, x minutesminutes II ObservationObservation Time, xTime, x minutesminutes 11 1.121.12 66 1.181.18 22 1.151.15 77 1.141.14 33 1.161.16 88 1.141.14 44 1.121.12 99 1.191.19 55 1.151.15 TotalTotal 10.3510.35 9=n 03.1=PR 20.0=A min15.1 9 35.10 === ∑ n X OT i min30.113.115.1 =×=×= PROTNT min56.120.130.1)20.01(30.1)1( =×=+×=+×= ANTST
  • 10. If an abnormally short time has been recorded, it typically would be assumed to be the result of observational error and thus discarded. If one of the observations in example had been 0.10, it would have been discarded. However, if an abnormally long time has been recorded, the analyst would want to investigate that observation to determine whether some irregularly occurring aspect of the task (e.g., retrieving a dropped tool or part) exists. Which should legitimately be factored into the job.
  • 11. Limitations One limitation is the fact that only those jobs that can be observed can be studied. Most managerial and creative jobs, that involve mental as well as physical aspects can not be studied. It is costly for irregular and infrequently occurring jobs.
  • 12. Standard elemental times Standard elemental times are derived from a firm’s own historical time study data. Over the years, a time study department can accumulate a file of elemental times that are common to many jobs. The procedure for using standard elemental times consists of the following steps: 1. Analyze the job to identify the standard elements. 2. Check the file for elements that have historical times, and record them. Use time study to obtain others, if necessary. 3. Modify the file times if necessary. 4. Sum the elemental times of obtain the normal time, and factor in allowances to obtain the standard time.
  • 13. Predetermined time standards Predetermined time standards involve the use of published data on standard elemental times. A commonly used system is methods time measurement (MTM). Which was developed in the late 1940s by the method engineering council. The MTM tables are based on extensive research of basic elemental motions and times. To use the approach, the analyst must divide the job into its basic elements (reach, move, turn, disengage), measure the distances involved (if applicable). Rate the difficulty of the element, and then refer to the appropriate table of data to obtain the time for that element. The Standard time for the job is obtained by adding the times for all of the basic elements. Times of the basic elements are measured in time measurement units(TMU). 1 TMU = 0.0006 minute.
  • 14. Work Sampling Work sampling is a technique for estimating the proportion of time that a worker or machine spends on various activities and the idle time. Unlike work study, work sampling does not require timing an activity nor does it even involve continuous observation of the activity. Instead, an observer makes brief observations of a worker or a machine at random intervals and simply notes the nature of the activity. For example, a machine may be busy or idle; a secretary may be typing, filing, talking on the telephone, and so on. The resulting data are counts of the number of times each category of activity or non-activity was observed. Although work sampling is occasionally used to set time standards, its two primary uses are in 1. Ratio delay studies 2. Analysis of non-repetitive jobs
  • 15. Ratio delay studies: concern the percentage of a worker’s time that involves unavoidable delays or the proportion of time a machine is idle Non repetitive jobs: typically involve a broader range of skills than repetitive jobs, and workers in these jobs are often paid on the basis of the highest skill involved. Therefore it is important to determine the proportion of time spent on the high skill level. Importance Work sampling estimates an approximations of the actual proportion of time devoted to a given activity. The goal of work sampling is to obtain an estimate that provides a specified confidence not differing from the true value by more than a specified error. Example: a hospital administrator might request an estimate of X-ray idle time that will provide a 95 percent confidence of being within 4 percent of the actual percentage. Hence work sampling is designed to produce a value, p, which estimates the true proportion, P, within some allowable error, e: epP ±=