SlideShare a Scribd company logo
1 of 89
is the application of technique designed to establish
the time for a qualified worker to carry out a specified
job at a defined level of performance.
 Designed to establish the time for a qualified worker
to carry out a specified job.
 Provides the management with a means of
measuring the time taken in the performance of an
operation.
 Used to set standard times for carrying out the work
and standard output level.
1. To reveal the existence of ineffective time.
2. To compare the efficiency of alternative methods.
3. To balance the work of members of a team.
4. To determine the number of machines an operator
can run.
5. To set the time standards to carrying out the work.
6. To provide information to estimate tenders, selling
prices and delivery promises.
7. Helps to plan and schedule the production.
8. Helps to carry out the effective utilization of available
capacity.
9. Used as a basis for realistic and fair incentive scheme.
10. To compare the actual time and target time.
11. To control the labour cost.
12. To enable standard costs to be fixed and maintained.
13. Used as a basis for labour budgeting and budgetary
control system.
1. Select- the work to be studied.
2. Record- all the relevant data.
3. Examine- all the recorded data.
4. Measure- the time required to complete each
element.
5. Compile- the standard time for the operation.
6. Define- the series of activities and method of
operation.
1) A repetitive element is an element which occurs in
every work cycle of the job.
2) An occasional element does not occur in each work
cycle of the job, but which may occur at regular or
irregular intervals. e.g. machine setting.
3) For a constant element, the basic time remains
constant whenever it is performed. e.g. switch the
machine on.
4) A variable element is an element for which the basic
time varies in relation to some characteristics of the
product, equipment or process, e.g. dimensions,
weight, quality etc. e.g. push trolley of parts to next
shop.
5) A manual element is an element performed by a
worker.
6) A machine element is automatically performed by a
power driven machine (or process).
7) A governing element occupies a longer time than any
of the other elements which are being performed
concurrently. e.g. boil kettle of water, while setting
out teapot and cups.
8) A foreign element is observed during a study which,
after analysis, is not found to be necessary part of
the job. e.g. degreasing a part that has still to be
machined further.
 An element is an distinct part of a specified job
selected for convenience of observation,
measurement and analysis.
 A work cycle is the sequence of elements which are
required to perform a job or yield a unit of
production. The sequence may sometimes include
occasional elements.
 For each job, a detailed breakdown of the complete
job into elements is necessary.
 To ensure that productive work (or effective time) is
separated from unproductive activity (or ineffective
time).
 To ensure better and accurate rating.
 To identify and distinguish different types of
elements
 To isolate elements involving high degree of fatigue
to allocate fatigue allowances more accurately
 To facilitate checking of method.
 To enable a detailed work specification to be
prepared.
 For compilation of standard data for the recurring
elements.
 To facilitate assessment of performance rate in a
better way for each individual element.
i. Each element should be as short in duration as
possible.
ii. Each element can be timed accurately and reliably.
iii. Manual elements should be separated from machine
elements.
iv. Constant elements should be separated from
variable elements.
v. Certain elements which do not occur in each work
cycle should be separated and timed separately.
vi. Handling time should be separated from machining
time.
 New Job: The job in question is a new one, not previously
carried out (new product, component, operation or set of
activities)
 Change in method/material: A change in material or
method of working has been made and a new time
standard is required.
 Complaint from worker: A complaint has been received
from a worker or worker’s representative about the time
standard for an operation.
 Bottleneck in operations: A particular operation appears
to be a “bottleneck” holding up subsequent operations
and possibly previous operations.
 New incentive scheme: Standard times are required
before an incentive scheme is introduced.
 Low output: To carry out investigation when output
of plant is low.
 Alternative Methods: For comparing alternative
methods and find out the best one.
 Excessive cost: When the cost of particular job
appears to be excessive.
A work cycle is the sequence of elements which are
required to perform a job.
It starts at the beginning of the first element of the
operation and continues to the same point in a
repetition of operation.
The time required to complete each element vary
slightly from cycle to cycle.
This variation in time introduces a sampling error.
Commonly in industries 95% confidence level is used
and the accuracy desired is ±5%
If n=required no. of observations to predict the true
time within ±5% accuracy and 95% confidence level,
then statistically,
n=[(40√n’∑x2-(∑x)2)/ ∑x]2
where,
n’= number of preliminary readings
n= sample size(no. of observations required)
∑x= the sum of preliminary set of individual
observations
∑x2= sum of the square of individual observations of the
preliminary set of readings.
 Work measurement technique for recording the times
and rates of working for the elements of a specified job
under specified condition; for analyzing the data so as to
obtain the time necessary for an operator to carry out
the job at a defined level of performance.
The equipments required fro time study consists of:
1) Stop Watch
a. Flyback decimal minute stop watch
b. Non-flyback stop watch
2) Time Study Board
3) Time Study Forms
4) A small calculator
5) A reliable clock, with a seconds hand
6) Measuring instruments such as a tape measure,
steel rule, micrometer, spring balance etc.
 There are two methods used for timing with stop
watch.
1) Cumulative timing:
o In this method, the watch is started from the zero
position at the beginning of the study and not
stopped through out the study.
o The analyst simply records the stopwatch reading
at the end of each element.
o The elemental times are obtained at the end of the
study by taking the difference between successive
readings.
2) Flyback/Snap back timing:
o The analyst simultaneously notes the stopwatch
reading at the end of each element .
o Then brings the hands to zero position by pressing
the winding knob.
o Since the hands are snapped back to zero at the
beginning of each element, the recording readings
represent elemental times.
Steps:
1) Observed or Actual Time:
o It is the actual time taken in completing the job.
o If an operator work with 100% efficiency then
observed time will be equal to normal/basic time.
o it can be used in:
i. Method Study
ii. Plant Layout
iii. Realistic setting of starting and finishing times of
operations.
2) Normal time:
o It is the productive time required to perform a job
utilizing appropriate work method and work place
layout at normal pace.
o It is associated with a set of tasks and is determined
by the actual measurement and pace adjustment.
o Avg. Observed/Actual time X Performance Rating
100
3) Standard Time:
o It is the time required by an operator of average skill,
who uses an average amount of effort.
o When operator is working under existing working
condition using the specific method and machines
at a standard pace.
o Standard Time= Normal time + Allowances
 Rating means gauging and comparing the
performance or pace rate of a worker against a
standard performance.
 It can be calculated as:
Observed performance X 100
Normal Performance
 The time standard formed must be with in the
working capacity of majority of workers in the unit.
 It is used to set the normal time for a normal worker.
 Actual time or observed time is multiplied with this
factor to obtain the normal time.
 Expressed as a percentage of the efficiency of
representative worker .
 It shows how efficient an operator is in comparison
to his fellow operators.
 Also known as ‘levelling factor’.
Various rating techniques are as follows:
1) Speed rating
2) Westing-house system of rating
3) Synthetic rating
4) Objective rating
5) Psychological Evaluation of Performance rating
 It consists of judging the speed of the operator’s
movements in relation to a normal pace.
 It can be applied to different elements of job.
 Mathematically,
Normal time= Observed time X Worker’s speed
Speed Expected
 A four factor system developed at Westing house by
C.E. Bedaux.
 Four factors are:
i. Skill
ii. Effort
iii. Conditions
iv. Consistency
 The numerical values for each of these factors are
available in tabular form.
 The operator is watched while working and given a
value from these tables.
 This system was proposed by Morrow.
 This method of rating has two main advantages over
other methods. These are:
i. it does not rely on the judgment of time study
person and
ii. it gives consistent results.
 The time study is made as usual.
 Some manually controlled elements of the work
cycle are selected.
 Using a PMT system (Pre-determined motion time
system), the times for these selected elements are
determined.
 The times of these elements as determined are
compared with the actual observed times and the
performance factor is estimated for each of the
selected elements.
 Performance or Rating Factor, R = P / A
Where,
P = Predetermined motion time of the element, and
A = Average actual observed time of the element.
 The overall rating factor is the mean of rating factors
determined for the selected elements. This is applied
uniformly to all the manually controlled elements of
the work cycle.
 This was developed by M.E. Mundel.
 Tempo of doing a job, job difficulty are taken into
account.
 First of all pace rating is done and then allowance is
added to it to take care of job difficulty.
 The following six factors constitute job difficulty:
i. Amount of body used
ii. Foot pedals
iii. Bimanualness
iv. Handling requirements
v. Weight
vi. Eye-hand coordination
 When an operator has worked for a specified period,
he is allowed to sit on a chair and relax.
 Side by side heart rate is measured and compared
with earlier record till the rate become stabilize.
 This comparison for different jobs and workers
would help the time study observer to find out
performance rating.
 The normal time for an operation does not contain
any allowances for the worker.
 It is impossible to work throughout the day even
though the most practicable, effective method has
been developed.
 Even under the best working method situation, the
job will still demand the expenditure of human effort
and some allowance must therefore be made for
recovery from fatigue and for relaxation.
 Allowances must also be made to enable the worker
to attend to his personal needs.
 The allowances depend upon:
i. Factors related to individual worker.
ii. Factors related to the nature of the work itself.
iii. Factors related to environment
 Thus allowance is the additional time allowed to
perform the work over and above the basic time.
1. Relaxation allowances:
a) Personal need allowances
b) Fatigue allowances
i. Basic fatigue allowances ii.Variable fatigue allowances
2. Contingency allowances
3. Special allowances
4. Interference allowances
5. Process allowances
 Relaxation allowance is an addition to the basic time
intended to provide the worker with the opportunity to
recover from the physiological and psychological effects
of carrying out specified work under specified conditions
and to allow attention to personal needs.
 The amount of allowance will depend on the nature of
the job.
 There are 2 type of relaxation allowance:
a) Personal needs allowances: This allowance provides
for the necessity to leave the workplace to attend to
personal needs such as washing, going to the lavatory or
fetching a drink . Common figures are from 5 to 7 percent
of basic time.
b) Fatigue allowances: It provides a worker an
opportunity to recover from physiological and
psychological effects of fatigue caused by carrying
out a specific task under specified conditions.
i. Basic Fatigue allowances: it is provided to the
worker who performs a job seated, who is engaged
on light work in good working conditions, and who
is called upon to make normal use of members of
the body. Usually, it taken as 4% of the basic time.
The personal need allowances and the basic fatigue
allowances are called as fixed allowances.
ii. Variable fatigue allowances: it is provided to an
operator who is engaged on medium and heavy
work, who work in a posture other than sitting.
Some of the factors to be taken into account are:
 Abnormal position
 Accident hazard of the job
 Weight lifting or use of force
 Illumination of the work site.
 Ventilation
 Temperature
 Noise
 Strain
A contingency allowance is a small allowance of time
which may be included in a standard time to meet
legitimate and expected items of work or delays, the
precise measurement of which is uneconomical
because of their infrequent or irregular occurrence like:
Tool breakage.
Obtaining necessary gauges, special tools from stores.
Filling coolant.
Consultation with foreman.
It is an allowance of time included into the work
content of the job to compensate the operator for the
unavoidable loss of production due to simultaneous
stoppage of two or more machines being operated by
him.
This allowance is applicable for machine or process
controlled jobs.
Interference allowance varies in proportion to number
of machines assigned to the operator.
The interference of the machine increases the work
content.
 it is provided for the activities which are not normally
a part of operation cycle, but essential for satisfactory
performance of the work.
It may be permanent or temporary.
These includes:
Start up allowance
A shut down allowance
A cleaning allowance
Tool allowance
Change over allowance
Implementation allowance
Policy allowances are not the genuine part of the time
study and should be used with utmost care and only in
clearly defined circumstances.
The usual reason for making the policy allowance is to
line up standard times with requirements of wage
agreement between employers and trade unions.
The policy allowance is an increment, other than
bonus increment, applied to a standard time (or to some
constituent part of it, e.g., work content) to provide a
satisfactory level of earnings for a specified level of
performance under exceptional circumstances. Policy
allowances are sometimes made as imperfect
functioning of a division or part of a plant.
 It is a work measurement technique in which a large
number of instantaneous observations are made at
random intervals over a specified period of time of a
group of workers, machines and processes.
 is defined as a method of finding the percentage
occurrence of a certain activity by statistical
sampling and random observations.
 A technique for estimating the proportion of time
that a worker or machine spends on various activities
and the idle time.
 Work sampling is a commonly used industrial
engineering technique designed to measure how
resources such as people, machines, facilities, or
equipment are used.
 The work sampling objective is to assess selected
aspects of an organization's operations. To find the
frequency of occurrence of every work element.
 Work sampling determines the percentage of
occurrence of certain activity by statistical sampling
and random observation.
 Work Sampling, (also referred to as random
sampling or activity sampling) is a work
measurement technique where observations about
work are collected at discrete time intervals, either
periodic or random.
 Work sampling is broadly defined as the application
of statistical sampling techniques to the study of
work activities.
The work sampling procedure can be divided into the
following three phases:
a) Preparation for work sampling:
i. Decide the main objective of the study.
ii. obtain the approval of the supervisor of the
department in which work sampling is to be
performed.
iii. Based upon the objectives, establish the quantitative
measure of activity.
iv. Selection and training of personnel.
v. Making a detailed plan for taking observations.
b) Performing work sampling:
i. Classify the different categories of activities to be
studied.
ii. Design the observation forms.
iii. Determine the number of days or shifts required for
study.
iv. Develop properly randomised times of observations.
Before actual observations are taken, the following steps are
important from the initial planning:
 Define and decide the areas to be studied and the time
limits.
 Decide the number of observations per day or per
period.
Decide number of locations to be observed.
Distance between two operators.
v. Observing activity and recording data.
vi. Summarising the data.
c) Evaluating and presenting of work sampling:
i. Evaluating the validity and reliability of the data.
ii. Presenting and analysing data.
iii. Planning for future studies.
 Control charts are used to evaluate the reliability of data.
The formula for determining the number of
observations required is given by:
P.S. = k σ = k [√P(1-P)/n]
Where,
K= a factor, value of which depends on the desired
confidence level.
P= percentage occurrence of the activity.
S= error in fraction.
n= no. of observations required for the desired
confidence level and margin of error.
 For ratio delay studies.
 To indicate the nature of the distribution of work
activities within a gang operation.
 To estimate the percentage of utilization of groups of
similar machines or equipment.
 To determine the productive and non- productive
utilization of clerical operations.
 To measure performance.
 To aid in job evaluation.
 To indicate how materials handling equipments are being
used.
 For appraisal of organisational efficiency.
 It is a less expensive procedure.
 Observers with minimal specialized training can
conduct the sampling.
 It is an effective means of collecting facts that would
not normally be collected by other means.
 Several operators or machines may be observed
simultaneously by a single observer.
 No mechanical device needed.
 It measures the utilization of people and equipment
directly.
 A work sampling study may be interrupted at any
time without affecting the results.
 It is not economical for studying a single operator or
machine, or for studying operators or machines
located over wide areas.
 It cannot provide a much detailed information .
 The operator may change his or her work pattern
upon sight of the observer.
 It is of little value in helping to improve work
methods.
 A lot of groundwork is required.
 A work sampling study made of a group obviously
presents average results, and there is no information
as to the magnitude of the individual differences.
 Work measurement technique whereby times
established for basic human motions (classified
according to nature of motion and the conditions
under which it is made) used to build up the time for
a job at a defined level of performance.
 Also known as Micro data which is based upon much
smaller division of motions i.e., therbligs.
 Very useful in Method Analysis.
 Helps modifying and improving work methods
before starting the work on the job.
 Sets time standards for different jobs.
 Assists in constructing time formulae.
 Aids in the prebalancing of the manufacturing lines.
 Provides a basis for wage plans and labour cost
estimation.
 Facilitates training of the workers and supervisor.
 Eliminates inaccuracies associated with stop watch
time study.
 Much effective then stop watch time study in case
of short cycle highly repetitive operations.
 Time standard for a job can be arrived at without
going to the place of work.
 No rating factor is employed like in stop watch
study.
 More reliable and accurate as compared to stop
watch time study data.
 Less time and cost associated.
 Helps in tool and product design.
1. Method Time Measurement (M.T.M.)
2. Work Factor (W.F.)
3. Dimensional Motion Times (D.M.T.)
4. Basic Motion Time (B.M.T.)
5. Motion Time Analysis (M.T.A.)
 is a procedure which analyses any manual operation
into the basic motions required to perform it and
assigns to each motion a predetermined time value
by the nature of motion.
 Developed from motion picture studies on
industrial operations. (1 time unit= 0.0006 minute)
 Tool of method analysis that provides the answer in
terms of time.
 No use of stop watch.
 Developing effective methods and planning in advance
of beginning production.
 Improving existing methods.
 Establish time standards.
 Cost estimating.
 Training supervisors to become method conscious.
 Operator training.
 Determining incentives, wages rates etc.
 Research in operating methods, training and
performance rating.
 Helps in product design.
 Assist in selecting effective equipments.
 Movement of body can be broken up into number of
fundamental motions as follows:
 Basic manual movements (8)
 Pedal and trunk movements (9)
 Ocular movements (2)
 Data of these motions is considered in the
establishment of any motion pattern.
 Predetermined time values are given to each motion.
 All such times are added up to obtain the normal
time for the job.
 Standard time is calculated by adding suitable
allowances.
 Eight basic manual movements are:
1. Reach-R
2. Move-M
3. Apply Pressure-AP
4. Turn-T
5. Grasp-G
6. Position-P
7. Release-RL
8. Disengage-D
 Nine pedal and trunk movements are:
1. Side step
2. Turn body
3. Walk
4. Bend
5. Stoop
6. Kneel on one leg
7. Kneel on both legs
8. Foot motions
9. Sit
 Two eye movements.
 Movement of hands to a destination with predefined
objective.
 Time for reach depends upon:
i. The distance moved.
ii. Nature of destination.
iii. Type of reach.
 Classes of Reach depending on the surrounding of
object:
A. Motion of habit and is the fastest case of reach.
B. Motion to a known location of object.
C. Motion to an object jumbled with other objects,
involves search and select.
D. Reach to a single object and accurate grasp is
required. Required both sight and concentration.
E. Motion is performed to get hand into position for
the body balance for the next motion or out of way.
 Combination of predetermined manual motion times
and mental process time.
 Arranged to obtain an appropriate time for every manual
motion.
 Based upon performance of skilled and experienced
worker.
 1 time unit= 0.0001 minute
 Very simple and easy procedure.
 Quick work measurement.
 More accurate than M.T.M.
 Eliminates the use of stop watch.
 Avoids inconsistencies arising from judgement of
effort rating.
 Very precise preparation of job descriptions.
 Mental process time is taken into consideration.
 Gives a smaller time as compared to M.T.M.
1. Detailed Work Factor.
2. Simplified Work Factor.
3. Abbreviated Work Factor.
4. Ready Work Factor.
 Includes some basic motions whose time in turn is
modified by the elements of difficulty.
 Time increases with increase in number of
difficulties.
 Number of work factors is proportional to time taken
for a motion.
 Considers the following elements of work:
a. Assemble- Putting objects together.
b. Disassemble- Separating different parts of a body.
c. Grasp- Taking hold of something.
d. Mental Process- Involves sort, inspect, recollect etc.
e. Preposition- Locating an article in predetermined
position.
f. Release- Releasing or letting go an object.
g. Transport- Moving an article or hand from one
place to another.
h. Use- Manipulating or causing a tool to do its work.
 Four major variables:
i. Body member which performs the motion:
a. Arm-A b. Leg-L c. Trunk-T
d. Finger-Hand (F-H) e. Foot- Ft
f. Forearm Swivel- FS
ii. Distance
iii. Weight or Resistance
iv. Manual Control
a. Steering or Directional Control (S)
b. Change of Direction Work Factor (U).
c. Precaution or Care (P).
d. Manner of Terminating the Motion(D-Definite stop).
 Steps involved in finding the operation time:
a. Analyse the job in detail into individual motions.
b. Determine the number of work factors associated
with each motion.
c. Find the time for each motion from the table
provided.
d. Add the times for each motion.
e. Add the appropriate allowances to arrive at standard
time.
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx

More Related Content

What's hot

Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive MaintenanceMahendra K SHUKLA
 
Work Study
Work StudyWork Study
Work Studyvishakeb
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods StudyJoseph Konnully
 
Unit 3 Micro and Memo motion study.pdf
Unit 3 Micro and Memo motion study.pdfUnit 3 Micro and Memo motion study.pdf
Unit 3 Micro and Memo motion study.pdfSugumarSarDurai
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Vishal Shinde
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivityahmad bassiouny
 
Chronocycle graph
Chronocycle graphChronocycle graph
Chronocycle graphBinoy Benny
 
Work study work measurement
Work study   work measurementWork study   work measurement
Work study work measurementJoseph Konnully
 
method study- micromotion vs memo motion
method study- micromotion vs memo motionmethod study- micromotion vs memo motion
method study- micromotion vs memo motionpranav teli
 
Work study and method study
Work study and method studyWork study and method study
Work study and method studyNitin Gulgulia
 
Micro-Macro Motion Study
Micro-Macro Motion StudyMicro-Macro Motion Study
Micro-Macro Motion StudyManthan Kanani
 

What's hot (20)

Line balancing
Line balancingLine balancing
Line balancing
 
Method study
Method studyMethod study
Method study
 
Method study
Method studyMethod study
Method study
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
Work Study
Work StudyWork Study
Work Study
 
Motion & time study
Motion & time studyMotion & time study
Motion & time study
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods Study
 
Unit 3 Micro and Memo motion study.pdf
Unit 3 Micro and Memo motion study.pdfUnit 3 Micro and Memo motion study.pdf
Unit 3 Micro and Memo motion study.pdf
 
137 work study
137 work study137 work study
137 work study
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
 
Time study
Time studyTime study
Time study
 
Chronocycle graph
Chronocycle graphChronocycle graph
Chronocycle graph
 
Work study work measurement
Work study   work measurementWork study   work measurement
Work study work measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
method study- micromotion vs memo motion
method study- micromotion vs memo motionmethod study- micromotion vs memo motion
method study- micromotion vs memo motion
 
Assembly Line Production Introduction
Assembly Line Production   IntroductionAssembly Line Production   Introduction
Assembly Line Production Introduction
 
Work study and method study
Work study and method studyWork study and method study
Work study and method study
 
Micro-Macro Motion Study
Micro-Macro Motion StudyMicro-Macro Motion Study
Micro-Macro Motion Study
 

Similar to PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx

Similar to PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx (20)

Management tools
Management toolsManagement tools
Management tools
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx
 
7. work study and method measurement
7. work study and method measurement7. work study and method measurement
7. work study and method measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
work-measurement-ppt.pptx
work-measurement-ppt.pptxwork-measurement-ppt.pptx
work-measurement-ppt.pptx
 
Work Measurement
Work MeasurementWork Measurement
Work Measurement
 
Unit 3 iem part 2
Unit 3  iem part  2Unit 3  iem part  2
Unit 3 iem part 2
 
presentation group 5.pptx
presentation group 5.pptxpresentation group 5.pptx
presentation group 5.pptx
 
Unit 2 work measurement.pdf
Unit 2 work measurement.pdfUnit 2 work measurement.pdf
Unit 2 work measurement.pdf
 
Industrial egineering
Industrial egineeringIndustrial egineering
Industrial egineering
 
Unit 3 problems
Unit 3 problemsUnit 3 problems
Unit 3 problems
 
Work Measurment
Work Measurment Work Measurment
Work Measurment
 
Work study
Work studyWork study
Work study
 
Good work measurement
Good work measurementGood work measurement
Good work measurement
 
Analysis of sewing section efficiency by using time study technique in Appare...
Analysis of sewing section efficiency by using time study technique in Appare...Analysis of sewing section efficiency by using time study technique in Appare...
Analysis of sewing section efficiency by using time study technique in Appare...
 
APPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNETAPPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNET
 
Motion and time study
Motion and time studyMotion and time study
Motion and time study
 

Recently uploaded

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx

  • 1. is the application of technique designed to establish the time for a qualified worker to carry out a specified job at a defined level of performance.
  • 2.  Designed to establish the time for a qualified worker to carry out a specified job.  Provides the management with a means of measuring the time taken in the performance of an operation.  Used to set standard times for carrying out the work and standard output level.
  • 3. 1. To reveal the existence of ineffective time. 2. To compare the efficiency of alternative methods. 3. To balance the work of members of a team. 4. To determine the number of machines an operator can run. 5. To set the time standards to carrying out the work. 6. To provide information to estimate tenders, selling prices and delivery promises. 7. Helps to plan and schedule the production. 8. Helps to carry out the effective utilization of available capacity.
  • 4. 9. Used as a basis for realistic and fair incentive scheme. 10. To compare the actual time and target time. 11. To control the labour cost. 12. To enable standard costs to be fixed and maintained. 13. Used as a basis for labour budgeting and budgetary control system.
  • 5.
  • 6. 1. Select- the work to be studied. 2. Record- all the relevant data. 3. Examine- all the recorded data. 4. Measure- the time required to complete each element. 5. Compile- the standard time for the operation. 6. Define- the series of activities and method of operation.
  • 7. 1) A repetitive element is an element which occurs in every work cycle of the job. 2) An occasional element does not occur in each work cycle of the job, but which may occur at regular or irregular intervals. e.g. machine setting. 3) For a constant element, the basic time remains constant whenever it is performed. e.g. switch the machine on. 4) A variable element is an element for which the basic time varies in relation to some characteristics of the product, equipment or process, e.g. dimensions, weight, quality etc. e.g. push trolley of parts to next shop.
  • 8. 5) A manual element is an element performed by a worker. 6) A machine element is automatically performed by a power driven machine (or process). 7) A governing element occupies a longer time than any of the other elements which are being performed concurrently. e.g. boil kettle of water, while setting out teapot and cups. 8) A foreign element is observed during a study which, after analysis, is not found to be necessary part of the job. e.g. degreasing a part that has still to be machined further.
  • 9.  An element is an distinct part of a specified job selected for convenience of observation, measurement and analysis.  A work cycle is the sequence of elements which are required to perform a job or yield a unit of production. The sequence may sometimes include occasional elements.  For each job, a detailed breakdown of the complete job into elements is necessary.
  • 10.  To ensure that productive work (or effective time) is separated from unproductive activity (or ineffective time).  To ensure better and accurate rating.  To identify and distinguish different types of elements  To isolate elements involving high degree of fatigue to allocate fatigue allowances more accurately  To facilitate checking of method.
  • 11.  To enable a detailed work specification to be prepared.  For compilation of standard data for the recurring elements.  To facilitate assessment of performance rate in a better way for each individual element.
  • 12. i. Each element should be as short in duration as possible. ii. Each element can be timed accurately and reliably. iii. Manual elements should be separated from machine elements. iv. Constant elements should be separated from variable elements. v. Certain elements which do not occur in each work cycle should be separated and timed separately. vi. Handling time should be separated from machining time.
  • 13.  New Job: The job in question is a new one, not previously carried out (new product, component, operation or set of activities)  Change in method/material: A change in material or method of working has been made and a new time standard is required.  Complaint from worker: A complaint has been received from a worker or worker’s representative about the time standard for an operation.  Bottleneck in operations: A particular operation appears to be a “bottleneck” holding up subsequent operations and possibly previous operations.  New incentive scheme: Standard times are required before an incentive scheme is introduced.
  • 14.  Low output: To carry out investigation when output of plant is low.  Alternative Methods: For comparing alternative methods and find out the best one.  Excessive cost: When the cost of particular job appears to be excessive.
  • 15. A work cycle is the sequence of elements which are required to perform a job. It starts at the beginning of the first element of the operation and continues to the same point in a repetition of operation. The time required to complete each element vary slightly from cycle to cycle. This variation in time introduces a sampling error. Commonly in industries 95% confidence level is used and the accuracy desired is ±5%
  • 16. If n=required no. of observations to predict the true time within ±5% accuracy and 95% confidence level, then statistically, n=[(40√n’∑x2-(∑x)2)/ ∑x]2 where, n’= number of preliminary readings n= sample size(no. of observations required) ∑x= the sum of preliminary set of individual observations ∑x2= sum of the square of individual observations of the preliminary set of readings.
  • 17.  Work measurement technique for recording the times and rates of working for the elements of a specified job under specified condition; for analyzing the data so as to obtain the time necessary for an operator to carry out the job at a defined level of performance. The equipments required fro time study consists of: 1) Stop Watch a. Flyback decimal minute stop watch b. Non-flyback stop watch 2) Time Study Board 3) Time Study Forms
  • 18. 4) A small calculator 5) A reliable clock, with a seconds hand 6) Measuring instruments such as a tape measure, steel rule, micrometer, spring balance etc.
  • 19.  There are two methods used for timing with stop watch. 1) Cumulative timing: o In this method, the watch is started from the zero position at the beginning of the study and not stopped through out the study. o The analyst simply records the stopwatch reading at the end of each element. o The elemental times are obtained at the end of the study by taking the difference between successive readings.
  • 20. 2) Flyback/Snap back timing: o The analyst simultaneously notes the stopwatch reading at the end of each element . o Then brings the hands to zero position by pressing the winding knob. o Since the hands are snapped back to zero at the beginning of each element, the recording readings represent elemental times.
  • 21.
  • 23.
  • 24. 1) Observed or Actual Time: o It is the actual time taken in completing the job. o If an operator work with 100% efficiency then observed time will be equal to normal/basic time. o it can be used in: i. Method Study ii. Plant Layout iii. Realistic setting of starting and finishing times of operations.
  • 25. 2) Normal time: o It is the productive time required to perform a job utilizing appropriate work method and work place layout at normal pace. o It is associated with a set of tasks and is determined by the actual measurement and pace adjustment. o Avg. Observed/Actual time X Performance Rating 100
  • 26. 3) Standard Time: o It is the time required by an operator of average skill, who uses an average amount of effort. o When operator is working under existing working condition using the specific method and machines at a standard pace. o Standard Time= Normal time + Allowances
  • 27.  Rating means gauging and comparing the performance or pace rate of a worker against a standard performance.  It can be calculated as: Observed performance X 100 Normal Performance  The time standard formed must be with in the working capacity of majority of workers in the unit.
  • 28.  It is used to set the normal time for a normal worker.  Actual time or observed time is multiplied with this factor to obtain the normal time.  Expressed as a percentage of the efficiency of representative worker .  It shows how efficient an operator is in comparison to his fellow operators.  Also known as ‘levelling factor’.
  • 29. Various rating techniques are as follows: 1) Speed rating 2) Westing-house system of rating 3) Synthetic rating 4) Objective rating 5) Psychological Evaluation of Performance rating
  • 30.  It consists of judging the speed of the operator’s movements in relation to a normal pace.  It can be applied to different elements of job.  Mathematically, Normal time= Observed time X Worker’s speed Speed Expected
  • 31.  A four factor system developed at Westing house by C.E. Bedaux.  Four factors are: i. Skill ii. Effort iii. Conditions iv. Consistency  The numerical values for each of these factors are available in tabular form.  The operator is watched while working and given a value from these tables.
  • 32.
  • 33.
  • 34.  This system was proposed by Morrow.  This method of rating has two main advantages over other methods. These are: i. it does not rely on the judgment of time study person and ii. it gives consistent results.  The time study is made as usual.  Some manually controlled elements of the work cycle are selected.  Using a PMT system (Pre-determined motion time system), the times for these selected elements are determined.
  • 35.  The times of these elements as determined are compared with the actual observed times and the performance factor is estimated for each of the selected elements.  Performance or Rating Factor, R = P / A Where, P = Predetermined motion time of the element, and A = Average actual observed time of the element.  The overall rating factor is the mean of rating factors determined for the selected elements. This is applied uniformly to all the manually controlled elements of the work cycle.
  • 36.
  • 37.  This was developed by M.E. Mundel.  Tempo of doing a job, job difficulty are taken into account.  First of all pace rating is done and then allowance is added to it to take care of job difficulty.  The following six factors constitute job difficulty: i. Amount of body used ii. Foot pedals iii. Bimanualness iv. Handling requirements v. Weight vi. Eye-hand coordination
  • 38.
  • 39.  When an operator has worked for a specified period, he is allowed to sit on a chair and relax.  Side by side heart rate is measured and compared with earlier record till the rate become stabilize.  This comparison for different jobs and workers would help the time study observer to find out performance rating.
  • 40.  The normal time for an operation does not contain any allowances for the worker.  It is impossible to work throughout the day even though the most practicable, effective method has been developed.  Even under the best working method situation, the job will still demand the expenditure of human effort and some allowance must therefore be made for recovery from fatigue and for relaxation.  Allowances must also be made to enable the worker to attend to his personal needs.
  • 41.  The allowances depend upon: i. Factors related to individual worker. ii. Factors related to the nature of the work itself. iii. Factors related to environment  Thus allowance is the additional time allowed to perform the work over and above the basic time.
  • 42. 1. Relaxation allowances: a) Personal need allowances b) Fatigue allowances i. Basic fatigue allowances ii.Variable fatigue allowances 2. Contingency allowances 3. Special allowances 4. Interference allowances 5. Process allowances
  • 43.  Relaxation allowance is an addition to the basic time intended to provide the worker with the opportunity to recover from the physiological and psychological effects of carrying out specified work under specified conditions and to allow attention to personal needs.  The amount of allowance will depend on the nature of the job.  There are 2 type of relaxation allowance: a) Personal needs allowances: This allowance provides for the necessity to leave the workplace to attend to personal needs such as washing, going to the lavatory or fetching a drink . Common figures are from 5 to 7 percent of basic time.
  • 44. b) Fatigue allowances: It provides a worker an opportunity to recover from physiological and psychological effects of fatigue caused by carrying out a specific task under specified conditions. i. Basic Fatigue allowances: it is provided to the worker who performs a job seated, who is engaged on light work in good working conditions, and who is called upon to make normal use of members of the body. Usually, it taken as 4% of the basic time. The personal need allowances and the basic fatigue allowances are called as fixed allowances.
  • 45. ii. Variable fatigue allowances: it is provided to an operator who is engaged on medium and heavy work, who work in a posture other than sitting. Some of the factors to be taken into account are:  Abnormal position  Accident hazard of the job  Weight lifting or use of force  Illumination of the work site.  Ventilation  Temperature  Noise  Strain
  • 46. A contingency allowance is a small allowance of time which may be included in a standard time to meet legitimate and expected items of work or delays, the precise measurement of which is uneconomical because of their infrequent or irregular occurrence like: Tool breakage. Obtaining necessary gauges, special tools from stores. Filling coolant. Consultation with foreman.
  • 47. It is an allowance of time included into the work content of the job to compensate the operator for the unavoidable loss of production due to simultaneous stoppage of two or more machines being operated by him. This allowance is applicable for machine or process controlled jobs. Interference allowance varies in proportion to number of machines assigned to the operator. The interference of the machine increases the work content.
  • 48.  it is provided for the activities which are not normally a part of operation cycle, but essential for satisfactory performance of the work. It may be permanent or temporary. These includes: Start up allowance A shut down allowance A cleaning allowance Tool allowance Change over allowance Implementation allowance
  • 49. Policy allowances are not the genuine part of the time study and should be used with utmost care and only in clearly defined circumstances. The usual reason for making the policy allowance is to line up standard times with requirements of wage agreement between employers and trade unions. The policy allowance is an increment, other than bonus increment, applied to a standard time (or to some constituent part of it, e.g., work content) to provide a satisfactory level of earnings for a specified level of performance under exceptional circumstances. Policy allowances are sometimes made as imperfect functioning of a division or part of a plant.
  • 50.  It is a work measurement technique in which a large number of instantaneous observations are made at random intervals over a specified period of time of a group of workers, machines and processes.  is defined as a method of finding the percentage occurrence of a certain activity by statistical sampling and random observations.
  • 51.
  • 52.
  • 53.  A technique for estimating the proportion of time that a worker or machine spends on various activities and the idle time.  Work sampling is a commonly used industrial engineering technique designed to measure how resources such as people, machines, facilities, or equipment are used.  The work sampling objective is to assess selected aspects of an organization's operations. To find the frequency of occurrence of every work element.
  • 54.  Work sampling determines the percentage of occurrence of certain activity by statistical sampling and random observation.  Work Sampling, (also referred to as random sampling or activity sampling) is a work measurement technique where observations about work are collected at discrete time intervals, either periodic or random.  Work sampling is broadly defined as the application of statistical sampling techniques to the study of work activities.
  • 55. The work sampling procedure can be divided into the following three phases: a) Preparation for work sampling: i. Decide the main objective of the study. ii. obtain the approval of the supervisor of the department in which work sampling is to be performed. iii. Based upon the objectives, establish the quantitative measure of activity. iv. Selection and training of personnel. v. Making a detailed plan for taking observations.
  • 56. b) Performing work sampling: i. Classify the different categories of activities to be studied. ii. Design the observation forms. iii. Determine the number of days or shifts required for study. iv. Develop properly randomised times of observations. Before actual observations are taken, the following steps are important from the initial planning:  Define and decide the areas to be studied and the time limits.  Decide the number of observations per day or per period.
  • 57. Decide number of locations to be observed. Distance between two operators. v. Observing activity and recording data. vi. Summarising the data. c) Evaluating and presenting of work sampling: i. Evaluating the validity and reliability of the data. ii. Presenting and analysing data. iii. Planning for future studies.  Control charts are used to evaluate the reliability of data.
  • 58. The formula for determining the number of observations required is given by: P.S. = k σ = k [√P(1-P)/n] Where, K= a factor, value of which depends on the desired confidence level. P= percentage occurrence of the activity. S= error in fraction. n= no. of observations required for the desired confidence level and margin of error.
  • 59.
  • 60.
  • 61.
  • 62.  For ratio delay studies.  To indicate the nature of the distribution of work activities within a gang operation.  To estimate the percentage of utilization of groups of similar machines or equipment.  To determine the productive and non- productive utilization of clerical operations.  To measure performance.  To aid in job evaluation.  To indicate how materials handling equipments are being used.  For appraisal of organisational efficiency.
  • 63.  It is a less expensive procedure.  Observers with minimal specialized training can conduct the sampling.  It is an effective means of collecting facts that would not normally be collected by other means.  Several operators or machines may be observed simultaneously by a single observer.  No mechanical device needed.  It measures the utilization of people and equipment directly.  A work sampling study may be interrupted at any time without affecting the results.
  • 64.  It is not economical for studying a single operator or machine, or for studying operators or machines located over wide areas.  It cannot provide a much detailed information .  The operator may change his or her work pattern upon sight of the observer.  It is of little value in helping to improve work methods.  A lot of groundwork is required.  A work sampling study made of a group obviously presents average results, and there is no information as to the magnitude of the individual differences.
  • 65.
  • 66.  Work measurement technique whereby times established for basic human motions (classified according to nature of motion and the conditions under which it is made) used to build up the time for a job at a defined level of performance.  Also known as Micro data which is based upon much smaller division of motions i.e., therbligs.
  • 67.  Very useful in Method Analysis.  Helps modifying and improving work methods before starting the work on the job.  Sets time standards for different jobs.  Assists in constructing time formulae.  Aids in the prebalancing of the manufacturing lines.  Provides a basis for wage plans and labour cost estimation.  Facilitates training of the workers and supervisor.
  • 68.  Eliminates inaccuracies associated with stop watch time study.  Much effective then stop watch time study in case of short cycle highly repetitive operations.  Time standard for a job can be arrived at without going to the place of work.  No rating factor is employed like in stop watch study.  More reliable and accurate as compared to stop watch time study data.  Less time and cost associated.  Helps in tool and product design.
  • 69. 1. Method Time Measurement (M.T.M.) 2. Work Factor (W.F.) 3. Dimensional Motion Times (D.M.T.) 4. Basic Motion Time (B.M.T.) 5. Motion Time Analysis (M.T.A.)
  • 70.  is a procedure which analyses any manual operation into the basic motions required to perform it and assigns to each motion a predetermined time value by the nature of motion.  Developed from motion picture studies on industrial operations. (1 time unit= 0.0006 minute)  Tool of method analysis that provides the answer in terms of time.  No use of stop watch.
  • 71.  Developing effective methods and planning in advance of beginning production.  Improving existing methods.  Establish time standards.  Cost estimating.  Training supervisors to become method conscious.  Operator training.  Determining incentives, wages rates etc.  Research in operating methods, training and performance rating.  Helps in product design.  Assist in selecting effective equipments.
  • 72.  Movement of body can be broken up into number of fundamental motions as follows:  Basic manual movements (8)  Pedal and trunk movements (9)  Ocular movements (2)  Data of these motions is considered in the establishment of any motion pattern.  Predetermined time values are given to each motion.  All such times are added up to obtain the normal time for the job.  Standard time is calculated by adding suitable allowances.
  • 73.  Eight basic manual movements are: 1. Reach-R 2. Move-M 3. Apply Pressure-AP 4. Turn-T 5. Grasp-G 6. Position-P 7. Release-RL 8. Disengage-D
  • 74.  Nine pedal and trunk movements are: 1. Side step 2. Turn body 3. Walk 4. Bend 5. Stoop 6. Kneel on one leg 7. Kneel on both legs 8. Foot motions 9. Sit  Two eye movements.
  • 75.  Movement of hands to a destination with predefined objective.  Time for reach depends upon: i. The distance moved. ii. Nature of destination. iii. Type of reach.
  • 76.  Classes of Reach depending on the surrounding of object: A. Motion of habit and is the fastest case of reach. B. Motion to a known location of object. C. Motion to an object jumbled with other objects, involves search and select. D. Reach to a single object and accurate grasp is required. Required both sight and concentration. E. Motion is performed to get hand into position for the body balance for the next motion or out of way.
  • 77.
  • 78.
  • 79.
  • 80.
  • 81.
  • 82.  Combination of predetermined manual motion times and mental process time.  Arranged to obtain an appropriate time for every manual motion.  Based upon performance of skilled and experienced worker.  1 time unit= 0.0001 minute
  • 83.  Very simple and easy procedure.  Quick work measurement.  More accurate than M.T.M.  Eliminates the use of stop watch.  Avoids inconsistencies arising from judgement of effort rating.  Very precise preparation of job descriptions.  Mental process time is taken into consideration.  Gives a smaller time as compared to M.T.M.
  • 84. 1. Detailed Work Factor. 2. Simplified Work Factor. 3. Abbreviated Work Factor. 4. Ready Work Factor.
  • 85.  Includes some basic motions whose time in turn is modified by the elements of difficulty.  Time increases with increase in number of difficulties.  Number of work factors is proportional to time taken for a motion.  Considers the following elements of work: a. Assemble- Putting objects together. b. Disassemble- Separating different parts of a body. c. Grasp- Taking hold of something. d. Mental Process- Involves sort, inspect, recollect etc.
  • 86. e. Preposition- Locating an article in predetermined position. f. Release- Releasing or letting go an object. g. Transport- Moving an article or hand from one place to another. h. Use- Manipulating or causing a tool to do its work.  Four major variables: i. Body member which performs the motion: a. Arm-A b. Leg-L c. Trunk-T d. Finger-Hand (F-H) e. Foot- Ft f. Forearm Swivel- FS
  • 87. ii. Distance iii. Weight or Resistance iv. Manual Control a. Steering or Directional Control (S) b. Change of Direction Work Factor (U). c. Precaution or Care (P). d. Manner of Terminating the Motion(D-Definite stop).  Steps involved in finding the operation time: a. Analyse the job in detail into individual motions. b. Determine the number of work factors associated with each motion.
  • 88. c. Find the time for each motion from the table provided. d. Add the times for each motion. e. Add the appropriate allowances to arrive at standard time.