APPLICATION OF BIM DESIGN MANUALS:
A CASE STUDY
David FĂŒrstenberg1 and Ola LĂŠdre2
ABSTRACT
A problem often encountered by contractors is that the information provided is not always
equal to the information needed in the Building Information Model (BIM). Somewhere
between the BIM design manual and the final BIM information is omitted. The purpose of
this paper is to identify the source of the information loss. Therefore, the relation between
model information requirements in BIM design manuals, tender documents and the final
BIM was investigated. The research included a literature study, a document study and a
case study. In detail, three discipline models (road, construction and lighting) were
investigated from a design-bid-build project in Norway. The results showed that the
requirements were mostly complied with (sometimes with a pragmatic approach).
However, the requirements represent the client's focus on the design and the in-use phase.
Whereas the contractor's focus on the production phase is not given the same attention.
From that perspective, the results are twofold; 1) some of the required information is not
provided in an exact and reliable form, while 2) resources are spent on providing not
required information. This applied research showed that design manuals should reflect new
project delivery methods to support lean principles for all parties involved in the project.
KEYWORDS
BIM design manual, infrastructure, lean construction, waste, standardization.
INTRODUCTION
BIM is a widely used term in the architecture, engineering and construction (AEC) industry.
The acronym is used for both an action (Building Information Modelling) and a result
(Building Information Model). While both descriptions of the term are true in most
contexts, BIM is most of all a method for object-based computer modelling with attached
information. According to Williams (2015), the term "Building" is misleading, because
"BIM models are not exclusive to building projects". However, the term describes the
current situation well as BIM is still mainly applied to buildings and the infrastructure
sector is left behind (Shou et al. 2015).
1
PhD candidate, Department of Civil and Environmental Engineering (DCEE), Norwegian University of
Science and Technology (NTNU), Trondheim, Norway/BIM specialist, COWI Norway,
+47 482 35 793, david.furstenberg@ntnu.no/ dafu@cowi.com
2
Professor, DCEE, NTNU, Trondheim, Norway, ola.ladre@ntnu.no
FĂŒrstenberg, D., and LĂŠdre, O.
146
Proceedings IGLC – 27, July 2019, Dublin, Ireland
As public infrastructure is mainly owned by governments, public initiatives are
necessary to increase the usage of BIM in infrastructure projects. In Norway, public clients
such as the Norwegian Public Roads Administration (NPRA) have published BIM design
manuals. While the usage of the design manual (and BIM) is not mandatory yet, the NPRA
can force the AEC industry to use BIM for infrastructure projects. It is an important tool to
stimulate and contribute to the digitalization of this industry.
The NPRA's design manual V770 (Vegvesen 2015) was first published in 2012 and has
since then been applied to many road projects. Most recently, the NPRA started projects
requiring only a limited number of drawings. The information that is normally conveyed
in drawings must therefore be included in the BIM. A problem often encountered for the
contractor is that the information provided is not always equal to the information needed
in the BIM (Eastman et al. 2011). Somewhere between the BIM design manual and the
final BIM information requirements are omitted. The results are twofold; 1) some of the
required information is not provided, while 2) resources are spent on providing not required
information.
Womack and Jones (1996) described the five principles of lean thinking (value, the
value stream, flow, pull and perfection) based on the concepts and principles of the Toyota
Production System (TPS) developed by Ohno (1988). Other researchers investigated the
application of the TPS concept on the AEC industry and introduced lean construction
(Koskela 1992, Ballard and Howell 1994, Howell 1999). Lean construction focuses on
waste reduction; value increase and continuous improvement (Sacks et al. 2010). Hicks
(2007) mapped the seven wastes of manufacturing reported on in Womack and Jones (1996)
to information management. This is especially interesting, as recently "Better Information
Management" was introduced as an alternative explanation of the acronym BIM
(Borrmann et al. 2018, UK Roads Liaison Group 2018). This alternative understanding of
BIM stresses the importance of information in AEC projects and the value that lies within
BIM. While BIM and lean can be applied independently on AEC projects, Sacks et al.
(2010) revealed several interactions, which were demonstrated by Fosse et al. (2016)
through a case study.
The study presented in this paper identified the lean construction principles waste
reduction, value increase and improvement of the information flow. To the authors'
knowledge there is little empirical research on the relation between model information
requirements in BIM design manuals and tender documents, and between tender
documents and the final BIM. To examine this, the paper addressed the following research
questions:
 What is the difference between the model information requirements in the BIM
design manual and the tender documents?
 What is the difference between the model information requirements in the tender
documents and the BIM model?
One design-bid-build project from Norway was studied. The project covered the concept
development and detailed designing phase like outlined in Knotten et al. (2016). Other
delivery methods like design-build or integrated project delivery (IPD) were not evaluated.
Application of BIM Design Manuals: A Case Study
147
Value in Procurement
CASE STUDY DESCRIPTION AND METHOD
A qualitative research design was selected instead of a quantitative because requirements
in BIM design manuals are a novel topic. Therefore, the research reported on in this study
included a literature study, a document study and a case study. A literature study was
carried out according to the steps described by Blumberg et al. (2014): 1) build information
pool, 2) apply filters to reduce pool size, 3) rough assessment of sources to further reduce
pool size, 4) analyze literature in pool and 4) refine filters or stop search.
Thereafter a case was selected. The case was a road project (Fv47 Åkra sþr –
Veakrossen) in western Norway, consisting of 7 km highway and 3 km secondary roads.
This case was chosen because it was one of the first road projects from the NPRA not
demanding any drawings in the tender documents except legal binding ones. In fact, the
ambition was to deliver the project with no drawings at all. One of the requirements in the
tender documents was the usage of the client's BIM design manual (V770). The core
element of this manual is a mandatory BIM approach for infrastructure projects.
Concerning the usage of BIM, the client and the designers agreed early upon waste
reduction, one of the principles of lean construction as adapted by Koskela (1992). BIM
was the means for this principle. In the examined case, drawings should only be produced
when they conveyed the information more effectively than the BIM. Is must be mentioned
that the project's design phase was not finished yet when it was studied. However, the
authors regarded the models to be valid for the research intention and fresh results could
be presented to the IGLC community.
The prescriptions as outlined by Yin (2018) were followed during the case study and
documentation was used as the source of evidence. The BIM was examined, and relevant
documents were studied. The first author was part of the project team and obtained the
documents and had access to the BIM. In detail, the client's tender documents and an
additional document clarifying the mutual understanding of the level of information in the
discipline models were studied. This document was agreed on after the contract was signed
and replaced those parts of the original tender documents concerning the level of
information. Furthermore, a BIM execution plan (BEP) solely produced for the
construction discipline model was examined. A BEP describes "how the information
modelling aspects of a project will be carried out" (British Standards Institution 2013). All
of these documents were chosen because they described the requested level of information
in the models for the case study.
Thereafter, the discipline leaders for the three discipline models were interviewed. They
were chosen because they were responsible for compliance with the information
requirements. The reason for the interviews was to confirm that the authors' impression of
the available information in the BIM was correct and to find out why some requirements
were not complied with. The interviews were semi-structured and lasted between 15 and
30 minutes.
FĂŒrstenberg, D., and LĂŠdre, O.
148
Proceedings IGLC – 27, July 2019, Dublin, Ireland
THEORETICAL BACKGROUND
BIM FOR INFRASTRUCTURE
According to Williams (2015) there are a variety of different terms used to distinguish the
application of BIM to vertical and horizontal constructions, like "Civil BIM, CIM, BIM
for infrastructure, Heavy BIM, etc.". The authors' impression is that the term "BIM for
infrastructure" is mainly used, especially in Scandinavia, and they decided to use it in this
paper. The main difference between BIM for infrastructure and "vertical" BIM is its
geographical extend and its dependency on geospatial data and coordinate systems. In BIM
for infrastructure projects real-world coordinates are assigned to all objects (EUREF89
NTM in the presented case) instead of local coordinates and a reference point like in
"vertical" BIM. Something unique to BIM for infrastructure in Scandinavia, especially in
Norway, is the wide use of a BIM tool which handles information and models comparable
to a GIS tool, namely Trimble Novapoint (2019).
DIGITALIZATION
There are different definitions of the digitalization process used by practitioners and
researchers. One definition, which the authors regard precise is from i-scoop (2018). They
used the terms "digitization", "digitalization" and "full transformation".
 "digitization": "transformation from analog to digital (
) with the goal to digitize
and automate processes or workflows".
 "digitalization": "use of digital technologies and of data (
) to create revenue,
improve business, replace/transform business processes and create an environment
for digital business, whereby digital information is at the core." In other words,
using the digitized data to create an improved product.
 "digital transformation": builds upon digitization and digitalization and
"encompasses all aspects of business, regardless of whether it concerns a digital
business or not, 
 ultimately leading to a new economy."
DESIGN MANUAL V770
The design manual V770 was first published in 2012 and revised in 2015. The NPRA
invited designers, contractors, surveyors and software developers to contribute. The
purpose of the manual is to reduce the number of errors in the production phase by using
BIM in the design phase. It defines delivery requirements for models of the existing and
designed situation. These delivery requirements describe both the model data and the
model content. However, it does not explicitly prescribe that all information must be
included as property data on the object level in the models. Drawings and external
documents are mentioned as an alternative. This was mainly due to the fact that
infrastructure projects with only a limited number of drawings were not common at the
time the V770 was published. The manual classifies models of the existing situation into
four types and models of the designed situation into 19 discipline models. Besides the
delivery requirements there are also process requirements, like multi-discipline
Application of BIM Design Manuals: A Case Study
149
Value in Procurement
collaboration, clash detection and the extraction of stakeout data from the discipline models.
Finally, it requires as-built models to be delivered to the national maintenance base.
For the purpose of this paper three of the 19 discipline models were selected and
investigated. In particular, the required information of the discipline models road,
construction and lighting was examined. Table 1, column 2 shows the model information
requirements for the three models investigated.
DESIGN PROCESS
The Norwegian approach called Next Step was used for the classification of project phases,
reported on in Knotten et al. (2016). In design-bid-build projects for the NPRA designers
usually are involved in step 3 (concept development) and step 4 (detailed designing). The
deliverables are different types of plans. In the concept development phase designers
deliver legally binding (municipal) zoning plans. If these zoning plans describe the project
with enough detail no further permit is needed prior to construction. However,
constructions (bridges and culverts) always have to be approved by the Directorate of
Public Roads. In the detailed designing phase, designers deliver a construction plan. The
construction plan is based on the zoning plan and is the foundation for the contractors in
the production phase.
FINDINGS
This paper investigated the relation between requirements in BIM design manuals and
tender documents, and between tender documents and the final BIM by answering the
following questions.
 What is the difference between the model information requirements in the BIM
design manual and the tender documents?
 What is the difference between the model information requirements in the tender
documents and the BIM model?
DIFFERENCE BETWEEN BIM DESIGN MANUAL AND TENDER DOCUMENTS
A comparison of the BIM design manual and the tender documents (see table 1, column 2
and 3) revealed that there were no deviations for the road and the lighting discipline model.
However, major deviations could be found for the construction model. Only two
requirements from the design manual were reflected in the tender documents, but four extra
requirements were added. One of these additional requirements were "all other information
that is normally conveyed in drawings".
The reason for the deviations for the construction model are a changed approval mode
by the Directorate of Public Roads. This was especially true for the "all other information"
requirement. At all times, constructions needed to be approved by the Directorate. A
special set of drawings had to be produced. However, when the tender was sent, the
Directorate opened for model-based approval requiring only a minimal number of drawings.
The basic principle of the model-based approval was that models should have at least the
same level of detail as drawings used to have. This new approval mode was neither
reflected in the design manual V770 nor in the tender documents. Instead, the Directorate
FĂŒrstenberg, D., and LĂŠdre, O.
150
Proceedings IGLC – 27, July 2019, Dublin, Ireland
required a detailed BIM Execution Plan (BEP) specific for the construction discipline
model. The BEP contained one chapter describing information requirements which were
much more detailed than the requirements in the V770 or the tender documents. This makes
the construction discipline model somewhat special since it is based on requirements that
were not part of the tender documents.
DIFFERENCE BETWEEN TENDER DOCUMENTS AND BIM
Varying deviations were observed between the tender documents and the final BIM for the
three discipline models (see table 1, column 3 and 4). While there were no deviations for
the construction model and only minor deviations for the lighting model, there were major
deviations for the road discipline model.
There was only one requirement complied with in the road model (design criteria).
Some of the requirements that were not met (slope, camber and super elevation) were due
to technical limitations in the BIM software. The designers had access to these data in the
design process, but they could not be implemented as property data on the object level.
This information is typically included in drawings. However, having the lean principle of
waste reduction in mind, the client and the designers agreed to not produce drawings.
Instead, they chose to convey the information to the client directly through the BIM
software in meetings.
Information about visibility (line of sight) was not included either. This could be
technically implemented in the BIM software, but – thinking of waste reduction – the
designers decided not to. They had access to this information in the design process and it
was visually conveyed in the zoning plan. However, it was not regarded as important
information for the following phases.
Information about masses was not available in the BIM either. The designers had access
to these data and delivered it in Excel sheets. Even though one could argue that this
information would add value for the client, the requirement was not complied with since
the V770 does not explicitly state that all information must be conveyed as property data
on the object level. At this point it must be noted that the road discipline model was slightly
less mature than the other two discipline models. This was due to a delay in the legal
process which made extra design loops necessary for this specific discipline. However, the
interview results indicate that the above-mentioned facts are still valid.
The only missing information in the lighting discipline model were the mounting details.
These details are supplied in an external document.
Application of BIM Design Manuals: A Case Study
151
Value in Procurement
Table 1: Model information requirements and their compliance in the BIM
Discipline
model
Model information
requirements set in the
BIM design manual V770
Model information
requirements set in the
tender documents
Compliance in
the BIM
Road
Design criteria Design criteria Yes
Visibility Visibility No
(in zoning plan)
Mass haul balance Mass haul balance No
(in Excel sheets)
Mass overview Mass overview No
(in Excel sheets)
Slope Slope No
Camber Camber No
Super elevation Super elevation No
Construction
Road information - No (in drawing)
Cross-reference to bridge
design manual
- No (in drawing)
Cross-reference to detailed
drawings and other models
Cross-reference to detailed
drawings and other models
Yes
Quality of materials Quality of materials Yes
Type and weight of
pavement
- No (in drawing)
Water level - No (in drawing)
Ship impact load Not applicable Not applicable
Rivers' direction of flow - No (in drawing)
Clearance height - No (in drawing)
Distance from road center
line to nearest construction
part
- No
- Object code Yes
- Object type Yes
- Toponym Yes
- "All other information that is
normally conveyed in
drawings"
Yes (geometry
details,
tolerances)
[Specific BIM Execution
plan (88 specific attributes)]
Yes
FĂŒrstenberg, D., and LĂŠdre, O.
152
Proceedings IGLC – 27, July 2019, Dublin, Ireland
Discipline
model
Model information
requirements set in the
BIM design manual V770
Model information
requirements set in the
tender documents
Compliance in
the BIM
Lighting
Light poles
Pole number Pole number Yes
Pole height Pole height Yes
Type of pole Type of pole Yes
Type of lighting Type of lighting Yes
Type of foundation Type of foundation Yes
Distance from shoulder Distance from shoulder Yes
Station number Station number Yes
Hight of bulb Hight of bulb Yes
Color Color Yes
Effect Effect Yes
Lighting class Lighting class Yes
Course number Course number Yes
Mounting details Mounting details No (external
documentation)
Pull manhole
Number Number Yes
Type Type Yes
Dimension Dimension Yes
Other technical installation
Number Number Yes
Toponym Toponym Yes
DISCUSSION
In the presented case BIM supported the following lean principles; waste reduction,
improvement of the information flow and value increase. Several types of waste were
reduced by improving the information flow. Overproduction, waiting (Womack and Jones
1996), mass electronic communication and legacy databases (Hicks 2007) were diminished
by direct access to information through the BIM instead of drawings. BIM created value
for both the client, the designers and the contractor. BIM enabled the designers to remove
some non-value adding activities by automating time consuming manual tasks. Value was
also created downstream for the customer by preparing the information for the contractor.
Instead of paying extra for the creation of data for machine control the contractor could
extract the necessary information directly from the BIM.
Application of BIM Design Manuals: A Case Study
153
Value in Procurement
The lean principle of waste reduction had a strong stand in the presented case. It was
reflected in a pragmatic approach towards the compliance with the model information
requirements. The client and the designers agreed that only necessary information was
provided in the models. Drawings and documents were preferred when they were more
effective to produce. This resulted in deviations from the requirements for the road
discipline model. For this specific model, the geometry is most important in the production
phase. Moreover, there are no specific parts that need to be changed in the in-use phase
which would make detailed information about assets necessary (like for the discipline
model lighting and construction).
The results showed that the requirements set in the BIM design manual were reflected
in the tender documents to a varying extend. While both the road and the lighting model
fully complied, the construction model had major deviations. However, a closer look
revealed that these deviations were due to a changed approval mode after the tender
documents were sent. In this respect, the construction model was not generally
representative for this comparison.
Disputes between clients and designers often root in diverging interpretations of the
content of the deliverables. Contracts and tender documents with clear requirements are
necessary to establish a common understanding between them. In the presented case both
parties agreed on a document clarifying the requirements from the design manual and the
tender documents for all discipline models. Thus, they created reliability which is one of
the principles in lean construction (Howell 1999).
Legal requirements seem to have the biggest impact on the BIM application in AEC
projects. On the one hand, this could lead up to obstacles like continued demand of
drawings (zoning plans and overview drawings in the presented case). On the other hand,
it could also raise the level of information. The discipline model construction had the
highest level of information because a specific BEP was required by the Directorate of
Public Roads for the approval process.
Requirements set in the tender documents were only partially reflected in the final BIM,
varying between the three discipline models investigated. The discipline model lighting
and construction complied with most requirements while the discipline model road had
major deviations. These deviations are partly based on limitations in the BIM software used
and partly based on pragmatic decisions by the designers thinking of waste reduction.
All requirements from the tender documents were fulfilled in the construction discipline
model. While this model only had four requirements in the tender documents it is actually
the model with the highest level of information. The BEP has approximately 80 different
properties on the object level though providing "all other information that normally
conveyed in drawings". The higher level of information is due to the fact that the
construction discipline model is the only one that needs to be approved by the Directorate
of Public Roads. At the same time this model is the only discipline model that has
additional, obligatory drawings. Even though the Directorate has opened for model-based
approval, one overview drawing per construction is still mandatory and detail drawings
might be requested. Some of the required information (cross-references, type and weight
of pavement, river's direction of flow and clearance details) is therefore only included in
drawings. This puts the construction model in a special position.
FĂŒrstenberg, D., and LĂŠdre, O.
154
Proceedings IGLC – 27, July 2019, Dublin, Ireland
CONCLUSION
In this paper, the relation between requirements in BIM design manuals and tender
documents on the one hand and between tender documents and the final BIM on the other
hand was investigated. The results showed that the requirements were mostly complied
with (sometimes with a pragmatic approach). However, both the BIM design manual and
the tender documents were made by the client and thus represent the client's perspective.
It seems like the focus of the NPRA is on the design and the in-use phase. Especially the
detailed requirements for the lighting and construction discipline model indicate this.
Whereas the contractor's focus on the production phase is not given the same attention in
the requirements. From that perspective, the results are twofold; 1) some of the required
information is not provided in an exact and reliable form (mass balances are only conveyed
as Excel sheets, not directly in the BIM), while 2) resources are spent on providing not
required information (lighting details for the in-use phase).
Contractors need exact and reliable information about the planned assets, especially on
cost drivers like masses or constructions. Providing the necessary information in one single
source lays the foundation for a digital transformation of the AEC industry. Single source
in this respect means either all information is available directly in the BIM, like for the
construction discipline model, or by using a linked data approach where the same data is
used in different ways. If the NPRA wants the AEC industry to be digitally transformed
and not just digitalized, the manuals have to reflect this. In short, the contractors'
perspective must be given more attention. Having in mind the trend towards design-build
projects, not just in Norway (Eriksson et al. 2017; Ma et al. 2018), where the contractor is
responsible for both the design and the production, this finding is even more relevant.
The design manual V770 was an important step to force the AEC industry into using
BIM for infrastructure. However, since it's first publication in 2012 BIM software has
evolved and new project delivery methods have been applied to projects in Norway. The
manual should reflect these new delivery methods and have more focus on the contractor
and their need for information.
It was the intention of the authors to present results of an ongoing industry PhD project
to the IGLC community to get feedback. It is not yet clear whether the mismatch of the
information requested and provided is a systematic problem or was unique to this case. The
presented case was the first of a series of case studies covering different delivery methods
(design-bid-build, design-build and integrated project delivery (IPD). Future work should
focus on the contractor's perspective and investigate the following; 1) relevance of
information for the contractor, 2) evaluation of experiences with delivered information and
2) comparison of the available information in different delivery methods.
Application of BIM Design Manuals: A Case Study
155
Value in Procurement
REFERENCES
Ballard, G., and Howell, G. (1994) "Implementing Lean Construction: Stabilizing Work
Flow." Proc., 2nd Annual Meeting of the International Group for Lean Construction,
Santiago de Chile, 1-10.
Blumberg, B., Cooper, D. R., and Schindler, P. S. (2014). Business research methods,
McGraw-Hill Higher Education, London.
Borrmann, A., König, M., and Koch, C. (2018). Building Information Modeling, Springer.
British Standards Institution (2013). "PAS1192-2:2013." Specification for information
management for the capital/delivery phase of construction projects using building
information modelling.
Eastman, C. M., Teicholz, P., and Sacks, R. (2011). BIM handbook: a guide to building
information modeling for owners, managers, designers, engineers, and contractors,
John Wiley & Sons, Hoboken.
Eriksson, P. E., LingegÄrd, S., Borg, L., and Nyström, J. (2017). "Procurement of railway
infrastructure projects–a european benchmarking study." Civil Engineering Journal,
3(4), 199-213.
Fosse, R., Spitler, L., and Alves, T. (2016) "Deploying BIM in a Heavy Civil Project."
Proc., 24th Annual Conference of the International Group for Lean Construction,
Boston, USA, 43-52.
Hicks, B. J. (2007). "Lean information management: Understanding and eliminating
waste." International Journal of Information Management, 27(4), 233-249.
Howell, G. A. (1999) "What Is Lean Construction - 1999." Proc., 7th Annual Conference
of the International Group for Lean Construction, Berkeley, USA, 1-10.
i-scoop (2018). "Digitization, digitalization and digital transformation: the differences."
<https://www.i-scoop.eu/digitization-digitalization-digital-transformation-
disruption/>. (2019-01-10).
Knotten, V., Hosseini, A., and Klakegg, O. J. (2016) "“Next Step”: A New Systematic
Approach to Plan and Execute AEC Projects." Proc., CIB World Building Congress
2016, Tampere, 484-495.
Koskela, L. (1992). "Application of the new production philosophy to the construction
industry." Technical Report No. 72, Center for Integrated Facilities Engineering, Dept.
of Civil Engineering, Stanford University, CA.
Ma, L., Le, Y., Hongyang, L., Jin, R., Piroozfar, P., and Liu, M. (2018). "Regional
Comparisons of Contemporary Construction Industry Sustainable Concepts in the
Chinese Context." Sustainability, 10.
Ohno, T. (1988). Toyota production system : beyond large-scale production, Productivity
Press, New York.
Sacks, R., Koskela, L., Dave, B. A., and Owen, R. (2010). "Interaction of Lean and
Building Information Modeling in Construction." J. Constr. Eng. M. ASCE, 136(9),
968-980.
Shou, W., Wang, J., Wang, X., and Chong, H. (2015). "A Comparative Review of Building
Information Modelling Implementation in Building and Infrastructure Industries." Arch.
Comput. Methods Eng., 22(2), 291-308.
Trimble (2019). "Novapoint." <https://www.novapoint.com/>. (2019-04-09).
FĂŒrstenberg, D., and LĂŠdre, O.
156
Proceedings IGLC – 27, July 2019, Dublin, Ireland
UK Roads Liaison Group (2018). "BIM guidance for infrastructure bodies." Department
for Transport, 156.
Vegvesen (2015). Modellgrunnlag, Krav til grunnlagsdata og modeller (HĂ„ndbok V770),
Vegdirektoratet, Oslo.
Williams, P. (2015). Managing Measurement Risk in Building and Civil Engineering, John
Wiley & Sons, Incorporated, Hoboken.
Womack, J. P., and Jones, D. T. (1996). Lean thinking : banish waste and create wealth in
your corporation, Free Press, New York.
Yin, R. K. (2018). Case study research: design and methods, Sage, Thousand Oaks,
California.

More Related Content

Similar to Application Of BIM Design Manuals A Case Study

Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM UTHM
 
ApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdf
ApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdfApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdf
ApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdftanerbahadir
 
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed
 
MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...
MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...
MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...Kieran Stapleton
 
BIM Presentation
BIM PresentationBIM Presentation
BIM PresentationOmer Syed
 
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdfWaliEdwardian1
 
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docxExecutive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docxelbanglis
 
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docxExecutive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docxrhetttrevannion
 
Extended Summary_Sofia Sideri_Final
Extended Summary_Sofia Sideri_FinalExtended Summary_Sofia Sideri_Final
Extended Summary_Sofia Sideri_FinalSofia Sideri
 
Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...Alexander Decker
 
What you have1) Draft word file2) Feedbacks and comments3) .docx
What you have1) Draft word file2) Feedbacks and comments3) .docxWhat you have1) Draft word file2) Feedbacks and comments3) .docx
What you have1) Draft word file2) Feedbacks and comments3) .docxeubanksnefen
 
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveAdvantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveMichael Cook
 
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveAdvantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveMichael Cook
 
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET Journal
 
BIM research report
BIM research reportBIM research report
BIM research reportChen Zhong
 
Building information modelling report
Building information modelling reportBuilding information modelling report
Building information modelling reportKiran Birdi
 
2011 27.content.04564
2011 27.content.045642011 27.content.04564
2011 27.content.04564Meghna Juli
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...IRJET Journal
 

Similar to Application Of BIM Design Manuals A Case Study (20)

Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM
 
ApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdf
ApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdfApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdf
ApplicationAreasandDataRequirementsforBIM-EnabledFacilitiesManagement (1).pdf
 
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
 
MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...
MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...
MSc-SociomaterialityandBIM_ExchanginginformationwithintheUKdesignprocess-Abst...
 
BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
 
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docxExecutive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
 
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docxExecutive SummaryBuilding Information Modelling (BIM) is a modelli.docx
Executive SummaryBuilding Information Modelling (BIM) is a modelli.docx
 
BIM Report 3
BIM Report 3BIM Report 3
BIM Report 3
 
Extended Summary_Sofia Sideri_Final
Extended Summary_Sofia Sideri_FinalExtended Summary_Sofia Sideri_Final
Extended Summary_Sofia Sideri_Final
 
Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...
 
What you have1) Draft word file2) Feedbacks and comments3) .docx
What you have1) Draft word file2) Feedbacks and comments3) .docxWhat you have1) Draft word file2) Feedbacks and comments3) .docx
What you have1) Draft word file2) Feedbacks and comments3) .docx
 
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveAdvantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
 
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveAdvantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
 
F1302033340
F1302033340F1302033340
F1302033340
 
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
 
BIM research report
BIM research reportBIM research report
BIM research report
 
Building information modelling report
Building information modelling reportBuilding information modelling report
Building information modelling report
 
2011 27.content.04564
2011 27.content.045642011 27.content.04564
2011 27.content.04564
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
 

More from Finni Rice

Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...
Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...
Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...Finni Rice
 
Essay On Assessment For Learning. PDF Reflective Essay on Assessment
Essay On Assessment For Learning. PDF Reflective Essay on AssessmentEssay On Assessment For Learning. PDF Reflective Essay on Assessment
Essay On Assessment For Learning. PDF Reflective Essay on AssessmentFinni Rice
 
Essay Outline Online. Outline example essay. Argumentative Essay Outline Wit...
Essay Outline Online.  Outline example essay. Argumentative Essay Outline Wit...Essay Outline Online.  Outline example essay. Argumentative Essay Outline Wit...
Essay Outline Online. Outline example essay. Argumentative Essay Outline Wit...Finni Rice
 
Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds Maslows hierarchy o...
Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds  Maslows hierarchy o...Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds  Maslows hierarchy o...
Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds Maslows hierarchy o...Finni Rice
 
Homeschooling Essay. Pros And Cons Of Homeschooling
Homeschooling Essay. Pros And Cons Of HomeschoolingHomeschooling Essay. Pros And Cons Of Homeschooling
Homeschooling Essay. Pros And Cons Of HomeschoolingFinni Rice
 
Pay For Someone To Write A Pape. Online assignment writing service.
Pay For Someone To Write A Pape. Online assignment writing service.Pay For Someone To Write A Pape. Online assignment writing service.
Pay For Someone To Write A Pape. Online assignment writing service.Finni Rice
 
2023-24 University Of Maryland Supplemental Es
2023-24 University Of Maryland Supplemental Es2023-24 University Of Maryland Supplemental Es
2023-24 University Of Maryland Supplemental EsFinni Rice
 
Recommendation Letter Meaning In Marathi Wallp
Recommendation Letter Meaning In Marathi WallpRecommendation Letter Meaning In Marathi Wallp
Recommendation Letter Meaning In Marathi WallpFinni Rice
 
Cheap Term Paper Help Cheap Term Papers Info,
Cheap Term Paper Help Cheap Term Papers Info,Cheap Term Paper Help Cheap Term Papers Info,
Cheap Term Paper Help Cheap Term Papers Info,Finni Rice
 
Pin By Augustus Bessah On English Teacher Essay Wri
Pin By Augustus Bessah On English Teacher Essay WriPin By Augustus Bessah On English Teacher Essay Wri
Pin By Augustus Bessah On English Teacher Essay WriFinni Rice
 
How To Write An Argumentative Essay - Ch
How To Write An Argumentative Essay - ChHow To Write An Argumentative Essay - Ch
How To Write An Argumentative Essay - ChFinni Rice
 
Lined Handwriting Paper Printable. Online assignment writing service.
Lined Handwriting Paper Printable. Online assignment writing service.Lined Handwriting Paper Printable. Online assignment writing service.
Lined Handwriting Paper Printable. Online assignment writing service.Finni Rice
 
Check Out Our Personal Stateme. Online assignment writing service.
Check Out Our Personal Stateme. Online assignment writing service.Check Out Our Personal Stateme. Online assignment writing service.
Check Out Our Personal Stateme. Online assignment writing service.Finni Rice
 
Academic Writing Companies. TOP. Online assignment writing service.
Academic Writing Companies. TOP. Online assignment writing service.Academic Writing Companies. TOP. Online assignment writing service.
Academic Writing Companies. TOP. Online assignment writing service.Finni Rice
 
The Journey, Creative Writing - GCSE English - Marked B
The Journey, Creative Writing - GCSE English - Marked BThe Journey, Creative Writing - GCSE English - Marked B
The Journey, Creative Writing - GCSE English - Marked BFinni Rice
 
Writing Workshop Anchor Charts - Distance Learnin
Writing Workshop Anchor Charts - Distance LearninWriting Workshop Anchor Charts - Distance Learnin
Writing Workshop Anchor Charts - Distance LearninFinni Rice
 
Back To School Writing Pages - My Teaching Libra
Back To School Writing Pages - My Teaching LibraBack To School Writing Pages - My Teaching Libra
Back To School Writing Pages - My Teaching LibraFinni Rice
 
Problem Of Global Warming Argument. Online assignment writing service.
Problem Of Global Warming Argument. Online assignment writing service.Problem Of Global Warming Argument. Online assignment writing service.
Problem Of Global Warming Argument. Online assignment writing service.Finni Rice
 
Plain Premium Writing Paper Packs Envelopes
Plain Premium Writing Paper Packs EnvelopesPlain Premium Writing Paper Packs Envelopes
Plain Premium Writing Paper Packs EnvelopesFinni Rice
 
Essay Plan Essay Plan, Study Notes, College Esse
Essay Plan Essay Plan, Study Notes, College EsseEssay Plan Essay Plan, Study Notes, College Esse
Essay Plan Essay Plan, Study Notes, College EsseFinni Rice
 

More from Finni Rice (20)

Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...
Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...
Against Gun Control Essay. Persuasive essay on anti gun control - mfacourses8...
 
Essay On Assessment For Learning. PDF Reflective Essay on Assessment
Essay On Assessment For Learning. PDF Reflective Essay on AssessmentEssay On Assessment For Learning. PDF Reflective Essay on Assessment
Essay On Assessment For Learning. PDF Reflective Essay on Assessment
 
Essay Outline Online. Outline example essay. Argumentative Essay Outline Wit...
Essay Outline Online.  Outline example essay. Argumentative Essay Outline Wit...Essay Outline Online.  Outline example essay. Argumentative Essay Outline Wit...
Essay Outline Online. Outline example essay. Argumentative Essay Outline Wit...
 
Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds Maslows hierarchy o...
Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds  Maslows hierarchy o...Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds  Maslows hierarchy o...
Maslow Hierarchy Of Needs Essay. MaslowsHierarchyOfNeeds Maslows hierarchy o...
 
Homeschooling Essay. Pros And Cons Of Homeschooling
Homeschooling Essay. Pros And Cons Of HomeschoolingHomeschooling Essay. Pros And Cons Of Homeschooling
Homeschooling Essay. Pros And Cons Of Homeschooling
 
Pay For Someone To Write A Pape. Online assignment writing service.
Pay For Someone To Write A Pape. Online assignment writing service.Pay For Someone To Write A Pape. Online assignment writing service.
Pay For Someone To Write A Pape. Online assignment writing service.
 
2023-24 University Of Maryland Supplemental Es
2023-24 University Of Maryland Supplemental Es2023-24 University Of Maryland Supplemental Es
2023-24 University Of Maryland Supplemental Es
 
Recommendation Letter Meaning In Marathi Wallp
Recommendation Letter Meaning In Marathi WallpRecommendation Letter Meaning In Marathi Wallp
Recommendation Letter Meaning In Marathi Wallp
 
Cheap Term Paper Help Cheap Term Papers Info,
Cheap Term Paper Help Cheap Term Papers Info,Cheap Term Paper Help Cheap Term Papers Info,
Cheap Term Paper Help Cheap Term Papers Info,
 
Pin By Augustus Bessah On English Teacher Essay Wri
Pin By Augustus Bessah On English Teacher Essay WriPin By Augustus Bessah On English Teacher Essay Wri
Pin By Augustus Bessah On English Teacher Essay Wri
 
How To Write An Argumentative Essay - Ch
How To Write An Argumentative Essay - ChHow To Write An Argumentative Essay - Ch
How To Write An Argumentative Essay - Ch
 
Lined Handwriting Paper Printable. Online assignment writing service.
Lined Handwriting Paper Printable. Online assignment writing service.Lined Handwriting Paper Printable. Online assignment writing service.
Lined Handwriting Paper Printable. Online assignment writing service.
 
Check Out Our Personal Stateme. Online assignment writing service.
Check Out Our Personal Stateme. Online assignment writing service.Check Out Our Personal Stateme. Online assignment writing service.
Check Out Our Personal Stateme. Online assignment writing service.
 
Academic Writing Companies. TOP. Online assignment writing service.
Academic Writing Companies. TOP. Online assignment writing service.Academic Writing Companies. TOP. Online assignment writing service.
Academic Writing Companies. TOP. Online assignment writing service.
 
The Journey, Creative Writing - GCSE English - Marked B
The Journey, Creative Writing - GCSE English - Marked BThe Journey, Creative Writing - GCSE English - Marked B
The Journey, Creative Writing - GCSE English - Marked B
 
Writing Workshop Anchor Charts - Distance Learnin
Writing Workshop Anchor Charts - Distance LearninWriting Workshop Anchor Charts - Distance Learnin
Writing Workshop Anchor Charts - Distance Learnin
 
Back To School Writing Pages - My Teaching Libra
Back To School Writing Pages - My Teaching LibraBack To School Writing Pages - My Teaching Libra
Back To School Writing Pages - My Teaching Libra
 
Problem Of Global Warming Argument. Online assignment writing service.
Problem Of Global Warming Argument. Online assignment writing service.Problem Of Global Warming Argument. Online assignment writing service.
Problem Of Global Warming Argument. Online assignment writing service.
 
Plain Premium Writing Paper Packs Envelopes
Plain Premium Writing Paper Packs EnvelopesPlain Premium Writing Paper Packs Envelopes
Plain Premium Writing Paper Packs Envelopes
 
Essay Plan Essay Plan, Study Notes, College Esse
Essay Plan Essay Plan, Study Notes, College EsseEssay Plan Essay Plan, Study Notes, College Esse
Essay Plan Essay Plan, Study Notes, College Esse
 

Recently uploaded

9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...Pooja Nehwal
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Dr. Mazin Mohamed alkathiri
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 

Recently uploaded (20)

9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 

Application Of BIM Design Manuals A Case Study

  • 1. FĂŒrstenberg, D., and LĂŠdre, O. (2019). “Application of BIM Design Manuals: A Case Study.” In: Proc. 27th Annual Conference of the International. Group for Lean Construction (IGLC), Pasquire C. and Hamzeh F.R. (ed.), Dublin, Ireland, pp. 145-156. DOI: https://doi.org/10.24928/2019/0147. Available at: <www.iglc.net>. 145 APPLICATION OF BIM DESIGN MANUALS: A CASE STUDY David FĂŒrstenberg1 and Ola LĂŠdre2 ABSTRACT A problem often encountered by contractors is that the information provided is not always equal to the information needed in the Building Information Model (BIM). Somewhere between the BIM design manual and the final BIM information is omitted. The purpose of this paper is to identify the source of the information loss. Therefore, the relation between model information requirements in BIM design manuals, tender documents and the final BIM was investigated. The research included a literature study, a document study and a case study. In detail, three discipline models (road, construction and lighting) were investigated from a design-bid-build project in Norway. The results showed that the requirements were mostly complied with (sometimes with a pragmatic approach). However, the requirements represent the client's focus on the design and the in-use phase. Whereas the contractor's focus on the production phase is not given the same attention. From that perspective, the results are twofold; 1) some of the required information is not provided in an exact and reliable form, while 2) resources are spent on providing not required information. This applied research showed that design manuals should reflect new project delivery methods to support lean principles for all parties involved in the project. KEYWORDS BIM design manual, infrastructure, lean construction, waste, standardization. INTRODUCTION BIM is a widely used term in the architecture, engineering and construction (AEC) industry. The acronym is used for both an action (Building Information Modelling) and a result (Building Information Model). While both descriptions of the term are true in most contexts, BIM is most of all a method for object-based computer modelling with attached information. According to Williams (2015), the term "Building" is misleading, because "BIM models are not exclusive to building projects". However, the term describes the current situation well as BIM is still mainly applied to buildings and the infrastructure sector is left behind (Shou et al. 2015). 1 PhD candidate, Department of Civil and Environmental Engineering (DCEE), Norwegian University of Science and Technology (NTNU), Trondheim, Norway/BIM specialist, COWI Norway, +47 482 35 793, david.furstenberg@ntnu.no/ dafu@cowi.com 2 Professor, DCEE, NTNU, Trondheim, Norway, ola.ladre@ntnu.no
  • 2. FĂŒrstenberg, D., and LĂŠdre, O. 146 Proceedings IGLC – 27, July 2019, Dublin, Ireland As public infrastructure is mainly owned by governments, public initiatives are necessary to increase the usage of BIM in infrastructure projects. In Norway, public clients such as the Norwegian Public Roads Administration (NPRA) have published BIM design manuals. While the usage of the design manual (and BIM) is not mandatory yet, the NPRA can force the AEC industry to use BIM for infrastructure projects. It is an important tool to stimulate and contribute to the digitalization of this industry. The NPRA's design manual V770 (Vegvesen 2015) was first published in 2012 and has since then been applied to many road projects. Most recently, the NPRA started projects requiring only a limited number of drawings. The information that is normally conveyed in drawings must therefore be included in the BIM. A problem often encountered for the contractor is that the information provided is not always equal to the information needed in the BIM (Eastman et al. 2011). Somewhere between the BIM design manual and the final BIM information requirements are omitted. The results are twofold; 1) some of the required information is not provided, while 2) resources are spent on providing not required information. Womack and Jones (1996) described the five principles of lean thinking (value, the value stream, flow, pull and perfection) based on the concepts and principles of the Toyota Production System (TPS) developed by Ohno (1988). Other researchers investigated the application of the TPS concept on the AEC industry and introduced lean construction (Koskela 1992, Ballard and Howell 1994, Howell 1999). Lean construction focuses on waste reduction; value increase and continuous improvement (Sacks et al. 2010). Hicks (2007) mapped the seven wastes of manufacturing reported on in Womack and Jones (1996) to information management. This is especially interesting, as recently "Better Information Management" was introduced as an alternative explanation of the acronym BIM (Borrmann et al. 2018, UK Roads Liaison Group 2018). This alternative understanding of BIM stresses the importance of information in AEC projects and the value that lies within BIM. While BIM and lean can be applied independently on AEC projects, Sacks et al. (2010) revealed several interactions, which were demonstrated by Fosse et al. (2016) through a case study. The study presented in this paper identified the lean construction principles waste reduction, value increase and improvement of the information flow. To the authors' knowledge there is little empirical research on the relation between model information requirements in BIM design manuals and tender documents, and between tender documents and the final BIM. To examine this, the paper addressed the following research questions:  What is the difference between the model information requirements in the BIM design manual and the tender documents?  What is the difference between the model information requirements in the tender documents and the BIM model? One design-bid-build project from Norway was studied. The project covered the concept development and detailed designing phase like outlined in Knotten et al. (2016). Other delivery methods like design-build or integrated project delivery (IPD) were not evaluated.
  • 3. Application of BIM Design Manuals: A Case Study 147 Value in Procurement CASE STUDY DESCRIPTION AND METHOD A qualitative research design was selected instead of a quantitative because requirements in BIM design manuals are a novel topic. Therefore, the research reported on in this study included a literature study, a document study and a case study. A literature study was carried out according to the steps described by Blumberg et al. (2014): 1) build information pool, 2) apply filters to reduce pool size, 3) rough assessment of sources to further reduce pool size, 4) analyze literature in pool and 4) refine filters or stop search. Thereafter a case was selected. The case was a road project (Fv47 Åkra sĂžr – Veakrossen) in western Norway, consisting of 7 km highway and 3 km secondary roads. This case was chosen because it was one of the first road projects from the NPRA not demanding any drawings in the tender documents except legal binding ones. In fact, the ambition was to deliver the project with no drawings at all. One of the requirements in the tender documents was the usage of the client's BIM design manual (V770). The core element of this manual is a mandatory BIM approach for infrastructure projects. Concerning the usage of BIM, the client and the designers agreed early upon waste reduction, one of the principles of lean construction as adapted by Koskela (1992). BIM was the means for this principle. In the examined case, drawings should only be produced when they conveyed the information more effectively than the BIM. Is must be mentioned that the project's design phase was not finished yet when it was studied. However, the authors regarded the models to be valid for the research intention and fresh results could be presented to the IGLC community. The prescriptions as outlined by Yin (2018) were followed during the case study and documentation was used as the source of evidence. The BIM was examined, and relevant documents were studied. The first author was part of the project team and obtained the documents and had access to the BIM. In detail, the client's tender documents and an additional document clarifying the mutual understanding of the level of information in the discipline models were studied. This document was agreed on after the contract was signed and replaced those parts of the original tender documents concerning the level of information. Furthermore, a BIM execution plan (BEP) solely produced for the construction discipline model was examined. A BEP describes "how the information modelling aspects of a project will be carried out" (British Standards Institution 2013). All of these documents were chosen because they described the requested level of information in the models for the case study. Thereafter, the discipline leaders for the three discipline models were interviewed. They were chosen because they were responsible for compliance with the information requirements. The reason for the interviews was to confirm that the authors' impression of the available information in the BIM was correct and to find out why some requirements were not complied with. The interviews were semi-structured and lasted between 15 and 30 minutes.
  • 4. FĂŒrstenberg, D., and LĂŠdre, O. 148 Proceedings IGLC – 27, July 2019, Dublin, Ireland THEORETICAL BACKGROUND BIM FOR INFRASTRUCTURE According to Williams (2015) there are a variety of different terms used to distinguish the application of BIM to vertical and horizontal constructions, like "Civil BIM, CIM, BIM for infrastructure, Heavy BIM, etc.". The authors' impression is that the term "BIM for infrastructure" is mainly used, especially in Scandinavia, and they decided to use it in this paper. The main difference between BIM for infrastructure and "vertical" BIM is its geographical extend and its dependency on geospatial data and coordinate systems. In BIM for infrastructure projects real-world coordinates are assigned to all objects (EUREF89 NTM in the presented case) instead of local coordinates and a reference point like in "vertical" BIM. Something unique to BIM for infrastructure in Scandinavia, especially in Norway, is the wide use of a BIM tool which handles information and models comparable to a GIS tool, namely Trimble Novapoint (2019). DIGITALIZATION There are different definitions of the digitalization process used by practitioners and researchers. One definition, which the authors regard precise is from i-scoop (2018). They used the terms "digitization", "digitalization" and "full transformation".  "digitization": "transformation from analog to digital (
) with the goal to digitize and automate processes or workflows".  "digitalization": "use of digital technologies and of data (
) to create revenue, improve business, replace/transform business processes and create an environment for digital business, whereby digital information is at the core." In other words, using the digitized data to create an improved product.  "digital transformation": builds upon digitization and digitalization and "encompasses all aspects of business, regardless of whether it concerns a digital business or not, 
 ultimately leading to a new economy." DESIGN MANUAL V770 The design manual V770 was first published in 2012 and revised in 2015. The NPRA invited designers, contractors, surveyors and software developers to contribute. The purpose of the manual is to reduce the number of errors in the production phase by using BIM in the design phase. It defines delivery requirements for models of the existing and designed situation. These delivery requirements describe both the model data and the model content. However, it does not explicitly prescribe that all information must be included as property data on the object level in the models. Drawings and external documents are mentioned as an alternative. This was mainly due to the fact that infrastructure projects with only a limited number of drawings were not common at the time the V770 was published. The manual classifies models of the existing situation into four types and models of the designed situation into 19 discipline models. Besides the delivery requirements there are also process requirements, like multi-discipline
  • 5. Application of BIM Design Manuals: A Case Study 149 Value in Procurement collaboration, clash detection and the extraction of stakeout data from the discipline models. Finally, it requires as-built models to be delivered to the national maintenance base. For the purpose of this paper three of the 19 discipline models were selected and investigated. In particular, the required information of the discipline models road, construction and lighting was examined. Table 1, column 2 shows the model information requirements for the three models investigated. DESIGN PROCESS The Norwegian approach called Next Step was used for the classification of project phases, reported on in Knotten et al. (2016). In design-bid-build projects for the NPRA designers usually are involved in step 3 (concept development) and step 4 (detailed designing). The deliverables are different types of plans. In the concept development phase designers deliver legally binding (municipal) zoning plans. If these zoning plans describe the project with enough detail no further permit is needed prior to construction. However, constructions (bridges and culverts) always have to be approved by the Directorate of Public Roads. In the detailed designing phase, designers deliver a construction plan. The construction plan is based on the zoning plan and is the foundation for the contractors in the production phase. FINDINGS This paper investigated the relation between requirements in BIM design manuals and tender documents, and between tender documents and the final BIM by answering the following questions.  What is the difference between the model information requirements in the BIM design manual and the tender documents?  What is the difference between the model information requirements in the tender documents and the BIM model? DIFFERENCE BETWEEN BIM DESIGN MANUAL AND TENDER DOCUMENTS A comparison of the BIM design manual and the tender documents (see table 1, column 2 and 3) revealed that there were no deviations for the road and the lighting discipline model. However, major deviations could be found for the construction model. Only two requirements from the design manual were reflected in the tender documents, but four extra requirements were added. One of these additional requirements were "all other information that is normally conveyed in drawings". The reason for the deviations for the construction model are a changed approval mode by the Directorate of Public Roads. This was especially true for the "all other information" requirement. At all times, constructions needed to be approved by the Directorate. A special set of drawings had to be produced. However, when the tender was sent, the Directorate opened for model-based approval requiring only a minimal number of drawings. The basic principle of the model-based approval was that models should have at least the same level of detail as drawings used to have. This new approval mode was neither reflected in the design manual V770 nor in the tender documents. Instead, the Directorate
  • 6. FĂŒrstenberg, D., and LĂŠdre, O. 150 Proceedings IGLC – 27, July 2019, Dublin, Ireland required a detailed BIM Execution Plan (BEP) specific for the construction discipline model. The BEP contained one chapter describing information requirements which were much more detailed than the requirements in the V770 or the tender documents. This makes the construction discipline model somewhat special since it is based on requirements that were not part of the tender documents. DIFFERENCE BETWEEN TENDER DOCUMENTS AND BIM Varying deviations were observed between the tender documents and the final BIM for the three discipline models (see table 1, column 3 and 4). While there were no deviations for the construction model and only minor deviations for the lighting model, there were major deviations for the road discipline model. There was only one requirement complied with in the road model (design criteria). Some of the requirements that were not met (slope, camber and super elevation) were due to technical limitations in the BIM software. The designers had access to these data in the design process, but they could not be implemented as property data on the object level. This information is typically included in drawings. However, having the lean principle of waste reduction in mind, the client and the designers agreed to not produce drawings. Instead, they chose to convey the information to the client directly through the BIM software in meetings. Information about visibility (line of sight) was not included either. This could be technically implemented in the BIM software, but – thinking of waste reduction – the designers decided not to. They had access to this information in the design process and it was visually conveyed in the zoning plan. However, it was not regarded as important information for the following phases. Information about masses was not available in the BIM either. The designers had access to these data and delivered it in Excel sheets. Even though one could argue that this information would add value for the client, the requirement was not complied with since the V770 does not explicitly state that all information must be conveyed as property data on the object level. At this point it must be noted that the road discipline model was slightly less mature than the other two discipline models. This was due to a delay in the legal process which made extra design loops necessary for this specific discipline. However, the interview results indicate that the above-mentioned facts are still valid. The only missing information in the lighting discipline model were the mounting details. These details are supplied in an external document.
  • 7. Application of BIM Design Manuals: A Case Study 151 Value in Procurement Table 1: Model information requirements and their compliance in the BIM Discipline model Model information requirements set in the BIM design manual V770 Model information requirements set in the tender documents Compliance in the BIM Road Design criteria Design criteria Yes Visibility Visibility No (in zoning plan) Mass haul balance Mass haul balance No (in Excel sheets) Mass overview Mass overview No (in Excel sheets) Slope Slope No Camber Camber No Super elevation Super elevation No Construction Road information - No (in drawing) Cross-reference to bridge design manual - No (in drawing) Cross-reference to detailed drawings and other models Cross-reference to detailed drawings and other models Yes Quality of materials Quality of materials Yes Type and weight of pavement - No (in drawing) Water level - No (in drawing) Ship impact load Not applicable Not applicable Rivers' direction of flow - No (in drawing) Clearance height - No (in drawing) Distance from road center line to nearest construction part - No - Object code Yes - Object type Yes - Toponym Yes - "All other information that is normally conveyed in drawings" Yes (geometry details, tolerances) [Specific BIM Execution plan (88 specific attributes)] Yes
  • 8. FĂŒrstenberg, D., and LĂŠdre, O. 152 Proceedings IGLC – 27, July 2019, Dublin, Ireland Discipline model Model information requirements set in the BIM design manual V770 Model information requirements set in the tender documents Compliance in the BIM Lighting Light poles Pole number Pole number Yes Pole height Pole height Yes Type of pole Type of pole Yes Type of lighting Type of lighting Yes Type of foundation Type of foundation Yes Distance from shoulder Distance from shoulder Yes Station number Station number Yes Hight of bulb Hight of bulb Yes Color Color Yes Effect Effect Yes Lighting class Lighting class Yes Course number Course number Yes Mounting details Mounting details No (external documentation) Pull manhole Number Number Yes Type Type Yes Dimension Dimension Yes Other technical installation Number Number Yes Toponym Toponym Yes DISCUSSION In the presented case BIM supported the following lean principles; waste reduction, improvement of the information flow and value increase. Several types of waste were reduced by improving the information flow. Overproduction, waiting (Womack and Jones 1996), mass electronic communication and legacy databases (Hicks 2007) were diminished by direct access to information through the BIM instead of drawings. BIM created value for both the client, the designers and the contractor. BIM enabled the designers to remove some non-value adding activities by automating time consuming manual tasks. Value was also created downstream for the customer by preparing the information for the contractor. Instead of paying extra for the creation of data for machine control the contractor could extract the necessary information directly from the BIM.
  • 9. Application of BIM Design Manuals: A Case Study 153 Value in Procurement The lean principle of waste reduction had a strong stand in the presented case. It was reflected in a pragmatic approach towards the compliance with the model information requirements. The client and the designers agreed that only necessary information was provided in the models. Drawings and documents were preferred when they were more effective to produce. This resulted in deviations from the requirements for the road discipline model. For this specific model, the geometry is most important in the production phase. Moreover, there are no specific parts that need to be changed in the in-use phase which would make detailed information about assets necessary (like for the discipline model lighting and construction). The results showed that the requirements set in the BIM design manual were reflected in the tender documents to a varying extend. While both the road and the lighting model fully complied, the construction model had major deviations. However, a closer look revealed that these deviations were due to a changed approval mode after the tender documents were sent. In this respect, the construction model was not generally representative for this comparison. Disputes between clients and designers often root in diverging interpretations of the content of the deliverables. Contracts and tender documents with clear requirements are necessary to establish a common understanding between them. In the presented case both parties agreed on a document clarifying the requirements from the design manual and the tender documents for all discipline models. Thus, they created reliability which is one of the principles in lean construction (Howell 1999). Legal requirements seem to have the biggest impact on the BIM application in AEC projects. On the one hand, this could lead up to obstacles like continued demand of drawings (zoning plans and overview drawings in the presented case). On the other hand, it could also raise the level of information. The discipline model construction had the highest level of information because a specific BEP was required by the Directorate of Public Roads for the approval process. Requirements set in the tender documents were only partially reflected in the final BIM, varying between the three discipline models investigated. The discipline model lighting and construction complied with most requirements while the discipline model road had major deviations. These deviations are partly based on limitations in the BIM software used and partly based on pragmatic decisions by the designers thinking of waste reduction. All requirements from the tender documents were fulfilled in the construction discipline model. While this model only had four requirements in the tender documents it is actually the model with the highest level of information. The BEP has approximately 80 different properties on the object level though providing "all other information that normally conveyed in drawings". The higher level of information is due to the fact that the construction discipline model is the only one that needs to be approved by the Directorate of Public Roads. At the same time this model is the only discipline model that has additional, obligatory drawings. Even though the Directorate has opened for model-based approval, one overview drawing per construction is still mandatory and detail drawings might be requested. Some of the required information (cross-references, type and weight of pavement, river's direction of flow and clearance details) is therefore only included in drawings. This puts the construction model in a special position.
  • 10. FĂŒrstenberg, D., and LĂŠdre, O. 154 Proceedings IGLC – 27, July 2019, Dublin, Ireland CONCLUSION In this paper, the relation between requirements in BIM design manuals and tender documents on the one hand and between tender documents and the final BIM on the other hand was investigated. The results showed that the requirements were mostly complied with (sometimes with a pragmatic approach). However, both the BIM design manual and the tender documents were made by the client and thus represent the client's perspective. It seems like the focus of the NPRA is on the design and the in-use phase. Especially the detailed requirements for the lighting and construction discipline model indicate this. Whereas the contractor's focus on the production phase is not given the same attention in the requirements. From that perspective, the results are twofold; 1) some of the required information is not provided in an exact and reliable form (mass balances are only conveyed as Excel sheets, not directly in the BIM), while 2) resources are spent on providing not required information (lighting details for the in-use phase). Contractors need exact and reliable information about the planned assets, especially on cost drivers like masses or constructions. Providing the necessary information in one single source lays the foundation for a digital transformation of the AEC industry. Single source in this respect means either all information is available directly in the BIM, like for the construction discipline model, or by using a linked data approach where the same data is used in different ways. If the NPRA wants the AEC industry to be digitally transformed and not just digitalized, the manuals have to reflect this. In short, the contractors' perspective must be given more attention. Having in mind the trend towards design-build projects, not just in Norway (Eriksson et al. 2017; Ma et al. 2018), where the contractor is responsible for both the design and the production, this finding is even more relevant. The design manual V770 was an important step to force the AEC industry into using BIM for infrastructure. However, since it's first publication in 2012 BIM software has evolved and new project delivery methods have been applied to projects in Norway. The manual should reflect these new delivery methods and have more focus on the contractor and their need for information. It was the intention of the authors to present results of an ongoing industry PhD project to the IGLC community to get feedback. It is not yet clear whether the mismatch of the information requested and provided is a systematic problem or was unique to this case. The presented case was the first of a series of case studies covering different delivery methods (design-bid-build, design-build and integrated project delivery (IPD). Future work should focus on the contractor's perspective and investigate the following; 1) relevance of information for the contractor, 2) evaluation of experiences with delivered information and 2) comparison of the available information in different delivery methods.
  • 11. Application of BIM Design Manuals: A Case Study 155 Value in Procurement REFERENCES Ballard, G., and Howell, G. (1994) "Implementing Lean Construction: Stabilizing Work Flow." Proc., 2nd Annual Meeting of the International Group for Lean Construction, Santiago de Chile, 1-10. Blumberg, B., Cooper, D. R., and Schindler, P. S. (2014). Business research methods, McGraw-Hill Higher Education, London. Borrmann, A., König, M., and Koch, C. (2018). Building Information Modeling, Springer. British Standards Institution (2013). "PAS1192-2:2013." Specification for information management for the capital/delivery phase of construction projects using building information modelling. Eastman, C. M., Teicholz, P., and Sacks, R. (2011). BIM handbook: a guide to building information modeling for owners, managers, designers, engineers, and contractors, John Wiley & Sons, Hoboken. Eriksson, P. E., LingegĂ„rd, S., Borg, L., and Nyström, J. (2017). "Procurement of railway infrastructure projects–a european benchmarking study." Civil Engineering Journal, 3(4), 199-213. Fosse, R., Spitler, L., and Alves, T. (2016) "Deploying BIM in a Heavy Civil Project." Proc., 24th Annual Conference of the International Group for Lean Construction, Boston, USA, 43-52. Hicks, B. J. (2007). "Lean information management: Understanding and eliminating waste." International Journal of Information Management, 27(4), 233-249. Howell, G. A. (1999) "What Is Lean Construction - 1999." Proc., 7th Annual Conference of the International Group for Lean Construction, Berkeley, USA, 1-10. i-scoop (2018). "Digitization, digitalization and digital transformation: the differences." <https://www.i-scoop.eu/digitization-digitalization-digital-transformation- disruption/>. (2019-01-10). Knotten, V., Hosseini, A., and Klakegg, O. J. (2016) "“Next Step”: A New Systematic Approach to Plan and Execute AEC Projects." Proc., CIB World Building Congress 2016, Tampere, 484-495. Koskela, L. (1992). "Application of the new production philosophy to the construction industry." Technical Report No. 72, Center for Integrated Facilities Engineering, Dept. of Civil Engineering, Stanford University, CA. Ma, L., Le, Y., Hongyang, L., Jin, R., Piroozfar, P., and Liu, M. (2018). "Regional Comparisons of Contemporary Construction Industry Sustainable Concepts in the Chinese Context." Sustainability, 10. Ohno, T. (1988). Toyota production system : beyond large-scale production, Productivity Press, New York. Sacks, R., Koskela, L., Dave, B. A., and Owen, R. (2010). "Interaction of Lean and Building Information Modeling in Construction." J. Constr. Eng. M. ASCE, 136(9), 968-980. Shou, W., Wang, J., Wang, X., and Chong, H. (2015). "A Comparative Review of Building Information Modelling Implementation in Building and Infrastructure Industries." Arch. Comput. Methods Eng., 22(2), 291-308. Trimble (2019). "Novapoint." <https://www.novapoint.com/>. (2019-04-09).
  • 12. FĂŒrstenberg, D., and LĂŠdre, O. 156 Proceedings IGLC – 27, July 2019, Dublin, Ireland UK Roads Liaison Group (2018). "BIM guidance for infrastructure bodies." Department for Transport, 156. Vegvesen (2015). Modellgrunnlag, Krav til grunnlagsdata og modeller (HĂ„ndbok V770), Vegdirektoratet, Oslo. Williams, P. (2015). Managing Measurement Risk in Building and Civil Engineering, John Wiley & Sons, Incorporated, Hoboken. Womack, J. P., and Jones, D. T. (1996). Lean thinking : banish waste and create wealth in your corporation, Free Press, New York. Yin, R. K. (2018). Case study research: design and methods, Sage, Thousand Oaks, California.