SlideShare a Scribd company logo
1 of 2
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management
Rev. Date: Rev. Date:
Revision: 0 Revision: 0
Page 1 of 2 HSEQ -Rev-01(Jan-2023)
No Specific Task Step Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
1 Emergency Procedure
 Emergency
Response;
 Uncontrolled emergency
responses;
5 5 25
i. Each ATC project shall create a specific Emergency Response Management Plan
following requirements and Codes of Practice contained below; Low
2
Access requirement for
Emergency Vehicles
 Police;
 Civil Defense;
 Ambulance;
(Including as per 2017
Fire Life Safety COP
Requirements)
 Access required by
emergency vehicles
during incident;
 Emergency vehicles not able to
access site in an emergency;
 Unable to attend to incident due to
blocked roads;
 Unable to reach incident with
equipment;
 Inadequate width of roads;
 Time delay in rescue, treatment of
injured and fighting fire;
5 5
25
HIGH
ii. Access for use of Civil Defence apparatus shall be designated and provided at the start of
the project and maintained until completion;
iii. All ATC project sites shall be designed to be accessible by Civil Defence apparatus by
means of roadways having an all-weather driving service of not less than 6.1m of
unobstructed width;
iv. The roads shall have the ability to withstand the live loads of fire apparatus of 80 tons of
distributed load and have a minimum 4.5m of both vertical clearance and access gate
width and max. 10% grade;
v. Fire access shall not planned to be through basements or underpasses of the building
under construction;
vi. Dead end fire access roads in excess of 45m in length shall be provided with approved U
turns (A minimum of 12m as per FLSCOP);
vii. A suitable location at the site such as meeting room or office shall be designated as an
emergency command post and provided with plans, emergency information, keys,
communications and equipment, etc.;
viii. The designated person (s) in charge of emergency procedure actions (Senior ATC site
management) shall respond to the designated location whenever fire occurs;
ix. Where access to or within a structure or an area is unduly difficult because of secured
openings or where immediate access is necessary for life-saving or firefighting purposes,
ATC shall ensure the Civil Defence personnel has access to a key box installed in an
accessible location;
x. The required width of access roadways shall not be obstructed in any manner, including
obstruction by parked vehicles, storage of material and assembly points;
xi. Signs or other appropriate notices, or both, prohibiting obstruction shall be installed and
shall be maintained, worded ‘Parking Reserved for Civil Defence Fire Lane’;
xii. The access roadway shall be extended to within 46m of all portions of the exterior walls of
the first story of any building under construction;
xiii. Where an access roadway cannot be adequately provided, an approved fire protection
system or systems shall be provided and approved by the Civil Defence;
xiv. Where a bridge is required to be used as access, it shall be constructed and maintained
using design live loading sufficient to carry the imposed loads of the fire apparatus in
accordance with Fire Service Vehicle and Personnel Accessibility;
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the work place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substituted for
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered away with
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be worn to safe guard against
hazards?
Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Overall project Emergency response specific to the size, location and complexity of
the area, including the requirements of the UAE Fire Life Safety Code of Practice
2017 Chapters 2 and 12. Use with RA 17 – Initial Site Set up;
Relevant Applicable MAS:
 00241 Fire Fighting Equipment;
 00236 Housekeeping;
Additional Training required: NOC’s Required for task:
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management
Rev. Date: Rev. Date:
Revision: 0 Revision: 0
Page 2 of 2 HSEQ -Rev-01(Jan-2023)
No Specific Task Step Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
3
Reverse Parking of
private vehicles office
areas
 Emergency site
evacuation;
 Vehicle collision;
 Vehicle and pedestrian collision;
 Ineffective site evacuation, staff at
risk due to slow exit;
 Exits blocked;
4 3
12
HIGH
i. All vehicles will reverse park in designated areas, this will be communicated at induction
and areas clearly signed;
ii. Security will monitor car parking areas for compliance;
Low
4
Project Vehicle Parking  Car Parking on
Construction Sites;
 Site access blocked;
 Emergency vehicles not able to
access site in an emergency;
 Unable to attend to incident;
 Time delay in rescue, treatment of
injured and fighting fire;
 Unauthorized parking;
4 4
16
HIGH
i. ATC will consider the exact location of vehicle parking on site set up, considering access
and egress, exit routes, restricted parking, potential drop zones etc.;
ii. All vehicles shall be parked a minimum of 20 feet (6.1m) from new buildings under
construction with the following exceptions;
iii. Vehicles that are parked temporarily for loading/unloading or other construction related
operations. However, such vehicles shall not be left unattended;
iv. Private ATC staff vehicles may be parked in parking garages of project sites if the
automatic fire sprinkler system is in service and vertical openings are protected;
5
Project Emergency Site
Exits  Emergency site
egress;
 Ineffective site evacuation, staff
at risk due to slow exit;
 Blocked exits – egress
prevention;
 Incident due to poor exit lighting;
5 5
25
HIGH
i. All projects under construction shall have at least two unobstructed exits. All exits shall
be identified in the Project Fire Plan;
ii. Where stairs and exit routes of a building are under construction, exterior temporary
steel stairs and exits shall be provided which lead directly to ground floor to the safety of
outside the building;
iii. In multi-story construction, each level above the first story shall be provided with at least
two usable exit stairs after the floor decking is installed. The stairways shall be
continuous and discharge to grade level;
iv. Stairways serving more than two floor levels shall be enclosed (with openings
adequately protected) after exterior walls/windows are in place;
v. Exit stairs shall be lighted and maintained clear of debris and construction materials at
all times except when one of the required exit stairs is under construction (i.e. installation
of gypsum board, painting, flooring etc.), but not more than two continuous floors;
vi. All exit stairs shall be provided with stair identification signs to include the floor level, stair
designation, and exit path direction as required to provide for safe egress;
vii. Night time construction work shall not be performed without adequate lighting in exits,
exit stairs and escape routes to safety outside the building;
6
Project Emergency
Communication
 Emergency
communication with
emergency services;
 Time delay in rescue, treatment
of injured and fighting fire; 4 4
16
HIGH
i. On commencing the project, ATC Senior Project Management shall assess and decide
the exact means of communication on the project, including additional site phones, two-
way radios etc. based on the location, complexity and size of the project;
ii. The agreed communication system shall be made up of strategically placed equipment
and properly defined responsibilities. The emergency response plan posted in a
conspicuous place on the project must identify the designated equipment and the people
to operate it;
iii. Emergency phone numbers and the site address/location shall be posted beside all site
phones. On assessment, the location of any emergency phones shall be clearly marked;
iv. Instructions shall be issued for the immediate notification of the Civil Defence in case of
a fire emergency;
v. A system of communication shall be established with ATC Head Office to be used in the
event of an incident, including lines and means of contact. This will be identified in the
HSE Emergency Response Plan and sign posted in prominent areas;
Low
7
Project Assembly
points
 Emergency site
egress;
 Ineffective head count – workers
left inside buildings;
4 4
16
HIGH
i. Designated exterior assembly points shall be established for all construction personnel to
relocate to upon evacuation. The assembly points shall also be identified in the Project
Fire Plan.
Low

More Related Content

Similar to 3 Emergency Management Risk Assessment Templates.docx

7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
Dwarika Bhushan Sharma
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
Dwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 

Similar to 3 Emergency Management Risk Assessment Templates.docx (20)

7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 

More from Dwarika Bhushan Sharma

PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
Dwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
Dwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
Dwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
Dwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Recently uploaded (20)

👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 

3 Emergency Management Risk Assessment Templates.docx

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management Rev. Date: Rev. Date: Revision: 0 Revision: 0 Page 1 of 2 HSEQ -Rev-01(Jan-2023) No Specific Task Step Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR 1 Emergency Procedure  Emergency Response;  Uncontrolled emergency responses; 5 5 25 i. Each ATC project shall create a specific Emergency Response Management Plan following requirements and Codes of Practice contained below; Low 2 Access requirement for Emergency Vehicles  Police;  Civil Defense;  Ambulance; (Including as per 2017 Fire Life Safety COP Requirements)  Access required by emergency vehicles during incident;  Emergency vehicles not able to access site in an emergency;  Unable to attend to incident due to blocked roads;  Unable to reach incident with equipment;  Inadequate width of roads;  Time delay in rescue, treatment of injured and fighting fire; 5 5 25 HIGH ii. Access for use of Civil Defence apparatus shall be designated and provided at the start of the project and maintained until completion; iii. All ATC project sites shall be designed to be accessible by Civil Defence apparatus by means of roadways having an all-weather driving service of not less than 6.1m of unobstructed width; iv. The roads shall have the ability to withstand the live loads of fire apparatus of 80 tons of distributed load and have a minimum 4.5m of both vertical clearance and access gate width and max. 10% grade; v. Fire access shall not planned to be through basements or underpasses of the building under construction; vi. Dead end fire access roads in excess of 45m in length shall be provided with approved U turns (A minimum of 12m as per FLSCOP); vii. A suitable location at the site such as meeting room or office shall be designated as an emergency command post and provided with plans, emergency information, keys, communications and equipment, etc.; viii. The designated person (s) in charge of emergency procedure actions (Senior ATC site management) shall respond to the designated location whenever fire occurs; ix. Where access to or within a structure or an area is unduly difficult because of secured openings or where immediate access is necessary for life-saving or firefighting purposes, ATC shall ensure the Civil Defence personnel has access to a key box installed in an accessible location; x. The required width of access roadways shall not be obstructed in any manner, including obstruction by parked vehicles, storage of material and assembly points; xi. Signs or other appropriate notices, or both, prohibiting obstruction shall be installed and shall be maintained, worded ‘Parking Reserved for Civil Defence Fire Lane’; xii. The access roadway shall be extended to within 46m of all portions of the exterior walls of the first story of any building under construction; xiii. Where an access roadway cannot be adequately provided, an approved fire protection system or systems shall be provided and approved by the Civil Defence; xiv. Where a bridge is required to be used as access, it shall be constructed and maintained using design live loading sufficient to carry the imposed loads of the fire apparatus in accordance with Fire Service Vehicle and Personnel Accessibility; RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the work place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards? Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1 Project Name: xxx RA Ref No.: xxx RA compilation Date: Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Overall project Emergency response specific to the size, location and complexity of the area, including the requirements of the UAE Fire Life Safety Code of Practice 2017 Chapters 2 and 12. Use with RA 17 – Initial Site Set up; Relevant Applicable MAS:  00241 Fire Fighting Equipment;  00236 Housekeeping; Additional Training required: NOC’s Required for task:
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management Rev. Date: Rev. Date: Revision: 0 Revision: 0 Page 2 of 2 HSEQ -Rev-01(Jan-2023) No Specific Task Step Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR 3 Reverse Parking of private vehicles office areas  Emergency site evacuation;  Vehicle collision;  Vehicle and pedestrian collision;  Ineffective site evacuation, staff at risk due to slow exit;  Exits blocked; 4 3 12 HIGH i. All vehicles will reverse park in designated areas, this will be communicated at induction and areas clearly signed; ii. Security will monitor car parking areas for compliance; Low 4 Project Vehicle Parking  Car Parking on Construction Sites;  Site access blocked;  Emergency vehicles not able to access site in an emergency;  Unable to attend to incident;  Time delay in rescue, treatment of injured and fighting fire;  Unauthorized parking; 4 4 16 HIGH i. ATC will consider the exact location of vehicle parking on site set up, considering access and egress, exit routes, restricted parking, potential drop zones etc.; ii. All vehicles shall be parked a minimum of 20 feet (6.1m) from new buildings under construction with the following exceptions; iii. Vehicles that are parked temporarily for loading/unloading or other construction related operations. However, such vehicles shall not be left unattended; iv. Private ATC staff vehicles may be parked in parking garages of project sites if the automatic fire sprinkler system is in service and vertical openings are protected; 5 Project Emergency Site Exits  Emergency site egress;  Ineffective site evacuation, staff at risk due to slow exit;  Blocked exits – egress prevention;  Incident due to poor exit lighting; 5 5 25 HIGH i. All projects under construction shall have at least two unobstructed exits. All exits shall be identified in the Project Fire Plan; ii. Where stairs and exit routes of a building are under construction, exterior temporary steel stairs and exits shall be provided which lead directly to ground floor to the safety of outside the building; iii. In multi-story construction, each level above the first story shall be provided with at least two usable exit stairs after the floor decking is installed. The stairways shall be continuous and discharge to grade level; iv. Stairways serving more than two floor levels shall be enclosed (with openings adequately protected) after exterior walls/windows are in place; v. Exit stairs shall be lighted and maintained clear of debris and construction materials at all times except when one of the required exit stairs is under construction (i.e. installation of gypsum board, painting, flooring etc.), but not more than two continuous floors; vi. All exit stairs shall be provided with stair identification signs to include the floor level, stair designation, and exit path direction as required to provide for safe egress; vii. Night time construction work shall not be performed without adequate lighting in exits, exit stairs and escape routes to safety outside the building; 6 Project Emergency Communication  Emergency communication with emergency services;  Time delay in rescue, treatment of injured and fighting fire; 4 4 16 HIGH i. On commencing the project, ATC Senior Project Management shall assess and decide the exact means of communication on the project, including additional site phones, two- way radios etc. based on the location, complexity and size of the project; ii. The agreed communication system shall be made up of strategically placed equipment and properly defined responsibilities. The emergency response plan posted in a conspicuous place on the project must identify the designated equipment and the people to operate it; iii. Emergency phone numbers and the site address/location shall be posted beside all site phones. On assessment, the location of any emergency phones shall be clearly marked; iv. Instructions shall be issued for the immediate notification of the Civil Defence in case of a fire emergency; v. A system of communication shall be established with ATC Head Office to be used in the event of an incident, including lines and means of contact. This will be identified in the HSE Emergency Response Plan and sign posted in prominent areas; Low 7 Project Assembly points  Emergency site egress;  Ineffective head count – workers left inside buildings; 4 4 16 HIGH i. Designated exterior assembly points shall be established for all construction personnel to relocate to upon evacuation. The assembly points shall also be identified in the Project Fire Plan. Low