SlideShare a Scribd company logo
1 of 18
Project Contract Management
Extension of Time
© Project-O-Metric
@projectometric
www.projectometric.com
For more subscribe to:
Project Contract Management
What is Extension of Time?
• Before we understand what is ‘Extension of Time’,
we need to understand what is ‘Time’ for a project.
• Every project is a time-bound event.
• The ‘time period’ for a project is mentioned in the
contract (stipulated by the Employer), within which
the project is to be completed. It may vary up to any
extent, even years, depending on the type and
volume of the project.
• If the project is not completed within the prescribed
time period of the project, then ‘Extension of Time’
(abbreviated popularly as EOT is required to
complete the balance work.
Project Contract Management
Illustration of EOT
• Let us consider the case of a project whose time
period is 24 months as per the contract.
• The project is delayed before or / and after
commencement of work and not completed within
the timeframe of 24 months.
• The client and contractor jointly agrees a revised
timeline to complete the balance work of the project.
The client awards an Extension of Time to the
contractor.
• The revised timeline is called the ‘Extended
timeline’.
Project Contract Management
Why Projects are Delayed?
• The Timeframe of a contract is stipulated at the
bid-stage of the contract and all the bidders
(including the successful bidder) must agree to
that.
• According to the timeframe the bidder
(Contractor) prepares their plans to execute. This
plan generally considers the ideal conditions
given in the contract, with some considerations
for the odds may happen during the contract
period.
• It is not possible to envisage and assess all the
problems can arise at a later stage which
hampers the progress of work.
Project Contract Management
General reasons for delay in work
• Delay in handing over the work site to
Contractor by the Employer due to many issues
including land acquisition issues.
• Delay in obtaining statutory licenses and
Government approvals for the project.
• Delayed release of construction drawings by the
Architects and Structural Design Engineers.
• Delay in procurement of required materials by
the contractor.
• Cessation or delay in manufacturing of
important materials by the approved
manufacturers.
Contd.
Project Contract Management
General reasons for delay in work Contd.
• Delay in transportation of materials.
• Delay due to Force majeure reasons
(unprecedented natural calamities, unrest or riots,
wars, pandemic conditions etc.)
• Delayed payment release by the Employers to the
Contractors.
• Unavailability of sufficient skilled manpower.
• Poorly planned completion schedules
(not considering realistic work-methodology for
tasks and thereby under-considerations of
resources)
• Addition of scope in the contract after commencement
of Project.
Project Contract Management
Extension of Time (EOT) – Flow Chart
Project
announced with a
stipulated
timeframe
Bidders plan
to complete
within the
timeframe
Project
awarded to
lowest price
bidders
Unprecedented
delays happen
Project is not
completed within the
stipulated timeframe
Contractor estimates
time extension and
applies to the Employer
Delay accountability is
assessed and agreed by
Employer and Contractor
Project
announced with a
stipulated
timeframe
Bidders plan
to complete
within the
timeframe
Project Contract Management
Delay accountability
• ‘Delay accountability’ is deciding the party
responsible for the delay happened in a project.
• Contractors are responsible for delays pertaining to
delay in mobilizing important resources for
completing the project, poor planning etc.
• Employers are responsible for delays in handing
over work-site to Contractors, issue of deliverables
(drawings, decisions, Govt. approvals etc.) on time,
payment to the contractors on time etc.
• Neither of the parties are accountable for delays
happened due to Force majeure events, changes in
Govt. policies or international laws.
Project Contract Management
Delay accountability – Major types of Delay
Delay by Contractor • Poor Planning for execution, resulting in
• non-timely engagement of resource
• improper / unrealistic methodology
• wrong selection of resources
• under considering resources
• Irregularity in delivery of resources at site (Supply chain
failure)
• Unable to mobilize required skilled workforce
• Delay in release of drawings by Contractor or
Consultants engaged by them (in case of an EPC
project)
• Construction error and rectification
Project Contract Management
Delay accountability – Major types of Delay
Delay by Employer
• Delay in handing over of work-front to the Contractor
• Delay in obtaining approvals from the local bodies or
Government authorities for which Employer is
responsible as per contract
• Irregularity in release interim payment to the Contractor
• Delay in engaging Consultants or Architects
• Delay in release of drawings and decisions by Employer
or Consultants engaged by them
• Construction error and rectification arisen out of faulty
drawings or decisions given by the Employer
Project Contract Management
Delay accountability – Major types of Delay
• Natural calamities (Flood, Tsunami, Cyclone,
Earthquake etc.)
• War
• People unrest or revolution
• Riot
• Epidemic or Pandemic outbreak
• Change in Govt. policies
• Change in the land of law or international law
Delay by Other Factors
(Force majeure, Change
in Govt. Policies, Law of
land or international law)
Project Contract Management
Implications of Delay in a contract
Delay by Contractor
• The Contractor is not eligible for claiming any cost
compensation.
• Employer may or may not charge liquidated
damage as per the applicable contract term.
• Time extension is awarded to the contractor to
complete the balance work.
Project Contract Management
Implications of Delay in a contract
Delay by Employer
• The Contractor is not eligible for claiming any cost
compensation.
• Employer may or may not charge liquidated
damage as per the applicable contract term.
• Time extension is awarded to the contractor to
complete the balance work.
Project Contract Management
Implications of Delay in a contract
Delay by Other Factors
(Force majeure, Change
in Govt. Policies, Law of
land or international law)
• Time extension is awarded to the contractor to
complete the balance work.
• Contractor will not have right to get cost
compensation if it is not explicitly mentioned in
the contract
• Employer will not be able to charge liquidated
damage to the contractor
Project Contract Management
Impact of EOT on the cost of contract
• EOT means staying in the contract for a
longer duration.
• Overhead of the Contractor increases.
• Employer loses on revenue generation from
the project.
Project Contract Management
EOT – What need to be done by the parties?
• Establishing a delay and granting EOT by
Employer does not entitles the Contractor for
compensation of cost by default.
• To get the cost compensation from the
Employer, the Contractor must establish that the
delay is not attributable to the Contractor.
• To establish the reasons of delay, the reasons
are to be recorded by both the parties jointly
since the commencement of the contract.
• Every details of the delay must be recorded so
that the responsibility can be easily assessed
later.
Project Contract Management
Delay register – A Sample Format
Project Contract Management
Thank You

More Related Content

Similar to Extensions of Time - Contract Management

Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 
Contract adminstration and planning
Contract adminstration and planningContract adminstration and planning
Contract adminstration and planningawad suliman
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in IndiaSanjay Kedia
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 

Similar to Extensions of Time - Contract Management (20)

Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
contract procedure
contract procedurecontract procedure
contract procedure
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
Contract adminstration and planning
Contract adminstration and planningContract adminstration and planning
Contract adminstration and planning
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in India
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Construction contract
Construction contract Construction contract
Construction contract
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Project management
Project managementProject management
Project management
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 

Recently uploaded

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 

Extensions of Time - Contract Management

  • 1. Project Contract Management Extension of Time © Project-O-Metric @projectometric www.projectometric.com For more subscribe to:
  • 2. Project Contract Management What is Extension of Time? • Before we understand what is ‘Extension of Time’, we need to understand what is ‘Time’ for a project. • Every project is a time-bound event. • The ‘time period’ for a project is mentioned in the contract (stipulated by the Employer), within which the project is to be completed. It may vary up to any extent, even years, depending on the type and volume of the project. • If the project is not completed within the prescribed time period of the project, then ‘Extension of Time’ (abbreviated popularly as EOT is required to complete the balance work.
  • 3. Project Contract Management Illustration of EOT • Let us consider the case of a project whose time period is 24 months as per the contract. • The project is delayed before or / and after commencement of work and not completed within the timeframe of 24 months. • The client and contractor jointly agrees a revised timeline to complete the balance work of the project. The client awards an Extension of Time to the contractor. • The revised timeline is called the ‘Extended timeline’.
  • 4. Project Contract Management Why Projects are Delayed? • The Timeframe of a contract is stipulated at the bid-stage of the contract and all the bidders (including the successful bidder) must agree to that. • According to the timeframe the bidder (Contractor) prepares their plans to execute. This plan generally considers the ideal conditions given in the contract, with some considerations for the odds may happen during the contract period. • It is not possible to envisage and assess all the problems can arise at a later stage which hampers the progress of work.
  • 5. Project Contract Management General reasons for delay in work • Delay in handing over the work site to Contractor by the Employer due to many issues including land acquisition issues. • Delay in obtaining statutory licenses and Government approvals for the project. • Delayed release of construction drawings by the Architects and Structural Design Engineers. • Delay in procurement of required materials by the contractor. • Cessation or delay in manufacturing of important materials by the approved manufacturers. Contd.
  • 6. Project Contract Management General reasons for delay in work Contd. • Delay in transportation of materials. • Delay due to Force majeure reasons (unprecedented natural calamities, unrest or riots, wars, pandemic conditions etc.) • Delayed payment release by the Employers to the Contractors. • Unavailability of sufficient skilled manpower. • Poorly planned completion schedules (not considering realistic work-methodology for tasks and thereby under-considerations of resources) • Addition of scope in the contract after commencement of Project.
  • 7. Project Contract Management Extension of Time (EOT) – Flow Chart Project announced with a stipulated timeframe Bidders plan to complete within the timeframe Project awarded to lowest price bidders Unprecedented delays happen Project is not completed within the stipulated timeframe Contractor estimates time extension and applies to the Employer Delay accountability is assessed and agreed by Employer and Contractor Project announced with a stipulated timeframe Bidders plan to complete within the timeframe
  • 8. Project Contract Management Delay accountability • ‘Delay accountability’ is deciding the party responsible for the delay happened in a project. • Contractors are responsible for delays pertaining to delay in mobilizing important resources for completing the project, poor planning etc. • Employers are responsible for delays in handing over work-site to Contractors, issue of deliverables (drawings, decisions, Govt. approvals etc.) on time, payment to the contractors on time etc. • Neither of the parties are accountable for delays happened due to Force majeure events, changes in Govt. policies or international laws.
  • 9. Project Contract Management Delay accountability – Major types of Delay Delay by Contractor • Poor Planning for execution, resulting in • non-timely engagement of resource • improper / unrealistic methodology • wrong selection of resources • under considering resources • Irregularity in delivery of resources at site (Supply chain failure) • Unable to mobilize required skilled workforce • Delay in release of drawings by Contractor or Consultants engaged by them (in case of an EPC project) • Construction error and rectification
  • 10. Project Contract Management Delay accountability – Major types of Delay Delay by Employer • Delay in handing over of work-front to the Contractor • Delay in obtaining approvals from the local bodies or Government authorities for which Employer is responsible as per contract • Irregularity in release interim payment to the Contractor • Delay in engaging Consultants or Architects • Delay in release of drawings and decisions by Employer or Consultants engaged by them • Construction error and rectification arisen out of faulty drawings or decisions given by the Employer
  • 11. Project Contract Management Delay accountability – Major types of Delay • Natural calamities (Flood, Tsunami, Cyclone, Earthquake etc.) • War • People unrest or revolution • Riot • Epidemic or Pandemic outbreak • Change in Govt. policies • Change in the land of law or international law Delay by Other Factors (Force majeure, Change in Govt. Policies, Law of land or international law)
  • 12. Project Contract Management Implications of Delay in a contract Delay by Contractor • The Contractor is not eligible for claiming any cost compensation. • Employer may or may not charge liquidated damage as per the applicable contract term. • Time extension is awarded to the contractor to complete the balance work.
  • 13. Project Contract Management Implications of Delay in a contract Delay by Employer • The Contractor is not eligible for claiming any cost compensation. • Employer may or may not charge liquidated damage as per the applicable contract term. • Time extension is awarded to the contractor to complete the balance work.
  • 14. Project Contract Management Implications of Delay in a contract Delay by Other Factors (Force majeure, Change in Govt. Policies, Law of land or international law) • Time extension is awarded to the contractor to complete the balance work. • Contractor will not have right to get cost compensation if it is not explicitly mentioned in the contract • Employer will not be able to charge liquidated damage to the contractor
  • 15. Project Contract Management Impact of EOT on the cost of contract • EOT means staying in the contract for a longer duration. • Overhead of the Contractor increases. • Employer loses on revenue generation from the project.
  • 16. Project Contract Management EOT – What need to be done by the parties? • Establishing a delay and granting EOT by Employer does not entitles the Contractor for compensation of cost by default. • To get the cost compensation from the Employer, the Contractor must establish that the delay is not attributable to the Contractor. • To establish the reasons of delay, the reasons are to be recorded by both the parties jointly since the commencement of the contract. • Every details of the delay must be recorded so that the responsibility can be easily assessed later.
  • 17. Project Contract Management Delay register – A Sample Format