SlideShare a Scribd company logo
1 of 4
Download to read offline
DEPARTMENT OF CONSTRUCTION MANAGEMENT
PROJECT COVER SHEET
STUDENT NAME: DC
STUDENT NUMBER: C 123
COURSE/ YEAR DT117/4
SUBJECT: Advanced Construction
Technology
PROJECT TITLE: Table Formwork (tutorial 2)
LECTURER:
FOR OFFICE USE ONLY:
DATE DUE: 24th
February 2016
DATE RECEIVED:
RECEIVED BY:
REPEAT PROJECT?
MARKS:
Table Formwork
In the following study researcher will focus on ‘DOKA table formwork’ which a preassembled
formwork is creating a complete bay of suspended floor slab. This system offers mobility and quick
installations within repetitive structures. Researcher found that it is
highly suitable for flat slabs and beam layouts. Table form is assembled
by linking series of falsework sections including primary beams and
props that are connected to form a complete table. Trusses are linked
by cross-bracings. Table formwork can be fitted with wheels or trolley
components allowing for movement on solid ground. The definition
given to formwork is: ‘Formwork is the use of support structures and
modules to create structures out of concrete which is poured into the
modules. Formwork can be made using modules out of steel, wood,
aluminium, or prefabricated forms.’ The supporting structure of
formwork is known as false work. (Nemati, 2005)
DOKA Formwork design and considerations
DOKA Formwork is built to ensure that the concrete is formed on the
required shape, size and position, as well as providing the specified
surface finish on the concrete which will impact the material to be used as formwork. It should be
possible to strike formwork easily and safely and without causing any damage to the concrete.
Formwork has to be designed strong enough to take the pressure or weight of the fresh concrete during
placing and compaction at bearing locations, as well as any other loads it might have to face. Weak
forms will result in distortion, excessive deflections, leaks or other failure. It is important to consider
all the safety concerns relating to access, working areas, platforms, toe boards and guardrails have to
be provided separately. (Rupasinghe, 2007)
The system requires space around the construction to fly the table after every use therefore sufficient
carnage is required for lifting the table unit with appropriate lifting plans. Movement of tables must be
controlled using appropriate castors and trolleys. Planning is required to ensure sufficient space for
assembling the units. Pre-assembly is important on city centre sites with restricted construction space.
Design loads on forms
Table forms must be designed and constructed to safely support the vertically applied dead and live
loads. The formwork will have to be designed to hold:
-Form Dead Loads – the actual weight of the forms, plus the weight of wet concrete.
-Form Live Loads – the weight of workers, equipment and material storage.
-Lateral Loads - Wet concrete is like water it exerts lateral pressure which increases with the depth of
the form. (More for the vertical formwork) (Ravishankar, 2015)
During Erection
Loads on formwork during erection can arise from: the weight of material, equipment, which may be
stacked on it prior to pour and the effects of wind which may
apply forces on the formwork and its supports. Care should
therefore be taken to avoid excessive load concentrations and
to ensure that bracing is installed as early as possible.
During concrete pour
Dead weight on the forms is placed. Also the
weight of workers and equipment on the platform
should be considered. At this stage, also, lateral stability should be considered. Dumping concrete on
one span of the form member may cause uplift of the form in other spans. Forms must be designed to
hold together under such conditions. (Formwork T. s., 2013)
After pouring
On multi-storey projects, it is usual for work to proceed on upper floors whilst the concrete structure
below is still gaining strength. Consideration should therefore be given to the additional loads being
imposed on the formwork.
Materials
Materials used on the formwork will determine the speed and quality of finish. (Nemati, 2005)
Material Uses
Timber Timber is the most common of the materials used for form, because it has the
advantage of being easily cut and assembled on site. Also known as traditional
formwork. Timber is graded by strength into classes. It is important to use the correct
class of timber.
Aluminium Range of proprietary beams and smaller joints made from aluminium may be used in
formwork. Aluminium is strong and light, and often you need fewer supports and ties.
Plywood Both traditional and proprietary forms use plywood for panels. The plywood should
be farmed in the largest-size panel that can be handled on site. This is the most
common formwork system in DOCA formwork
Steel Steel is made in both proprietary and purpose-made forms. Proprietary systems
usually consist of panels with steel frames, clad with either a plywood or steel facing.
A range of adjustable props, soldiers, light walling and variety of ties and accessories
is available for securing the formwork in place.
Preparation for concrete pour
Check that all the formwork is free of residue or any material that may damage the finish and spray the
formwork with release agent to make dismantling of formwork easy without damaging the finish. Check
that all repairs have been completed. Check that formwork joints have been sealed. Make sure the line,
level and plumb are correct, props and supports are in the correct locations. All safety checks such as
bracing systems, wedges are nailed, clamps are tight all bolts, jacks, are in place. Once the pour starts
the work of vibrating can cause displacement of the forms. (Formwork)
Safety
Standard health and safety features include:
-Guard rails and edge protection
-The false work units can be assembled at ground level,
minimizing work at height
-Decking with non-slip surface to be used to improve safety
-Interconnected truss members create strong and stable
working platform.
-The repetitive nature of work ensures that the site operatives
can quickly become familiar with health and safety aspects
of their job. (Ravishankar, 2015)
Striking
Concrete can be struck once the concrete has gained enough strength to be self-supporting, and to carry
any other loads that may be put on it. (Nemati, 2005)
Advantages of Table formwork
Main advantages of table formwork allows for fast construction for large floor layouts. It comes in fully
assembled units that can be lifted quickly into place. It offers high quality surface finish that can be
achieved with quality control used. It reduces workforce requirements on site. For project management
it is easier to plan construction activities due to the repetitive nature of the work. The formwork system
is reusable with little waste generated compared to traditional formwork. The assembled units are
intended for use throughout the duration of a project without dismantling. And Increased speed and
time efficiency on site. (Ravishankar, 2015)
Summary
Innovations have focused on on-site efficiency of production, Health
and safety, and environmental issues, moving towards increasing
efficiency. Traditional formwork for concrete construction consisted
of bespoke results requiring skilled workers. These types of
formwork often had pour safety features and gives slow rates of
construction on-site and great levels of waste. Modern formwork
systems which are modular are designed for speed and efficiency
therefor The quality of surface finish will depend on the quality of
formwork used. The most populat formwork systems in industry are
offered by propriatery systems such as ‘DOKA and PERI’ which
specialise in formwork.

More Related Content

What's hot

Multi storey structural steel structures
Multi storey structural steel structuresMulti storey structural steel structures
Multi storey structural steel structures
Thomas Britto
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
Sagar Shah
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
FAIZAL MUHAMMED
 

What's hot (20)

TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
Multi storey structural steel structures
Multi storey structural steel structuresMulti storey structural steel structures
Multi storey structural steel structures
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
High rise construction
High rise constructionHigh rise construction
High rise construction
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
modular coordination
modular coordinationmodular coordination
modular coordination
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
 
Rigid frame systems
Rigid frame systemsRigid frame systems
Rigid frame systems
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Cable systems - form active structure system
Cable systems - form active structure systemCable systems - form active structure system
Cable systems - form active structure system
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building construction
 
Report on rigid frame structures
Report  on rigid frame structuresReport  on rigid frame structures
Report on rigid frame structures
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 

Viewers also liked

Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
Abhishek Shah
 
Optimisation of earth quake response of tall building by using different fram...
Optimisation of earth quake response of tall building by using different fram...Optimisation of earth quake response of tall building by using different fram...
Optimisation of earth quake response of tall building by using different fram...
eSAT Journals
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
마 이환
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
Hamdija Velagic
 

Viewers also liked (19)

Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Formwork
FormworkFormwork
Formwork
 
Optimisation of earth quake response of tall building by using different fram...
Optimisation of earth quake response of tall building by using different fram...Optimisation of earth quake response of tall building by using different fram...
Optimisation of earth quake response of tall building by using different fram...
 
Easy wall vario
Easy wall varioEasy wall vario
Easy wall vario
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid
 
Ertf
ErtfErtf
Ertf
 
Microkernel
MicrokernelMicrokernel
Microkernel
 
Tube Frame Structures:An overview
Tube Frame Structures:An overviewTube Frame Structures:An overview
Tube Frame Structures:An overview
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differences
 
Highrise buildings....
Highrise buildings....Highrise buildings....
Highrise buildings....
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Slip formwork technique
Slip formwork techniqueSlip formwork technique
Slip formwork technique
 
Slideshare ppt
Slideshare pptSlideshare ppt
Slideshare ppt
 

Similar to Table formwork

July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORK
Sameer Malvankar
 
Type of concrete
Type of concreteType of concrete
Type of concrete
ZIyeeTan
 
Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdf
LiesaStone
 

Similar to Table formwork (20)

Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORK
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Site report
Site reportSite report
Site report
 
Ct 1 report
Ct 1 reportCt 1 report
Ct 1 report
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Type of concrete
Type of concreteType of concrete
Type of concrete
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdf
 
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingPlanning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
 

More from Davis Ciprikis

More from Davis Ciprikis (6)

Green Building Rating Systems and the Role of the Project Manager
Green Building Rating Systems and the Role of the Project ManagerGreen Building Rating Systems and the Role of the Project Manager
Green Building Rating Systems and the Role of the Project Manager
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
 
Health and safety management 2
Health and safety management 2Health and safety management 2
Health and safety management 2
 
Project management document control software system
Project management document control software systemProject management document control software system
Project management document control software system
 
Exchange Rate Risk Management project
Exchange Rate Risk Management projectExchange Rate Risk Management project
Exchange Rate Risk Management project
 
Environmental Impact assessment
Environmental Impact assessmentEnvironmental Impact assessment
Environmental Impact assessment
 

Recently uploaded

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
meharikiros2
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 

Recently uploaded (20)

8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 

Table formwork

  • 1. DEPARTMENT OF CONSTRUCTION MANAGEMENT PROJECT COVER SHEET STUDENT NAME: DC STUDENT NUMBER: C 123 COURSE/ YEAR DT117/4 SUBJECT: Advanced Construction Technology PROJECT TITLE: Table Formwork (tutorial 2) LECTURER: FOR OFFICE USE ONLY: DATE DUE: 24th February 2016 DATE RECEIVED: RECEIVED BY: REPEAT PROJECT? MARKS:
  • 2. Table Formwork In the following study researcher will focus on ‘DOKA table formwork’ which a preassembled formwork is creating a complete bay of suspended floor slab. This system offers mobility and quick installations within repetitive structures. Researcher found that it is highly suitable for flat slabs and beam layouts. Table form is assembled by linking series of falsework sections including primary beams and props that are connected to form a complete table. Trusses are linked by cross-bracings. Table formwork can be fitted with wheels or trolley components allowing for movement on solid ground. The definition given to formwork is: ‘Formwork is the use of support structures and modules to create structures out of concrete which is poured into the modules. Formwork can be made using modules out of steel, wood, aluminium, or prefabricated forms.’ The supporting structure of formwork is known as false work. (Nemati, 2005) DOKA Formwork design and considerations DOKA Formwork is built to ensure that the concrete is formed on the required shape, size and position, as well as providing the specified surface finish on the concrete which will impact the material to be used as formwork. It should be possible to strike formwork easily and safely and without causing any damage to the concrete. Formwork has to be designed strong enough to take the pressure or weight of the fresh concrete during placing and compaction at bearing locations, as well as any other loads it might have to face. Weak forms will result in distortion, excessive deflections, leaks or other failure. It is important to consider all the safety concerns relating to access, working areas, platforms, toe boards and guardrails have to be provided separately. (Rupasinghe, 2007) The system requires space around the construction to fly the table after every use therefore sufficient carnage is required for lifting the table unit with appropriate lifting plans. Movement of tables must be controlled using appropriate castors and trolleys. Planning is required to ensure sufficient space for assembling the units. Pre-assembly is important on city centre sites with restricted construction space. Design loads on forms Table forms must be designed and constructed to safely support the vertically applied dead and live loads. The formwork will have to be designed to hold: -Form Dead Loads – the actual weight of the forms, plus the weight of wet concrete. -Form Live Loads – the weight of workers, equipment and material storage. -Lateral Loads - Wet concrete is like water it exerts lateral pressure which increases with the depth of the form. (More for the vertical formwork) (Ravishankar, 2015) During Erection Loads on formwork during erection can arise from: the weight of material, equipment, which may be stacked on it prior to pour and the effects of wind which may apply forces on the formwork and its supports. Care should therefore be taken to avoid excessive load concentrations and to ensure that bracing is installed as early as possible.
  • 3. During concrete pour Dead weight on the forms is placed. Also the weight of workers and equipment on the platform should be considered. At this stage, also, lateral stability should be considered. Dumping concrete on one span of the form member may cause uplift of the form in other spans. Forms must be designed to hold together under such conditions. (Formwork T. s., 2013) After pouring On multi-storey projects, it is usual for work to proceed on upper floors whilst the concrete structure below is still gaining strength. Consideration should therefore be given to the additional loads being imposed on the formwork. Materials Materials used on the formwork will determine the speed and quality of finish. (Nemati, 2005) Material Uses Timber Timber is the most common of the materials used for form, because it has the advantage of being easily cut and assembled on site. Also known as traditional formwork. Timber is graded by strength into classes. It is important to use the correct class of timber. Aluminium Range of proprietary beams and smaller joints made from aluminium may be used in formwork. Aluminium is strong and light, and often you need fewer supports and ties. Plywood Both traditional and proprietary forms use plywood for panels. The plywood should be farmed in the largest-size panel that can be handled on site. This is the most common formwork system in DOCA formwork Steel Steel is made in both proprietary and purpose-made forms. Proprietary systems usually consist of panels with steel frames, clad with either a plywood or steel facing. A range of adjustable props, soldiers, light walling and variety of ties and accessories is available for securing the formwork in place. Preparation for concrete pour Check that all the formwork is free of residue or any material that may damage the finish and spray the formwork with release agent to make dismantling of formwork easy without damaging the finish. Check that all repairs have been completed. Check that formwork joints have been sealed. Make sure the line, level and plumb are correct, props and supports are in the correct locations. All safety checks such as bracing systems, wedges are nailed, clamps are tight all bolts, jacks, are in place. Once the pour starts the work of vibrating can cause displacement of the forms. (Formwork) Safety Standard health and safety features include: -Guard rails and edge protection -The false work units can be assembled at ground level, minimizing work at height -Decking with non-slip surface to be used to improve safety -Interconnected truss members create strong and stable working platform. -The repetitive nature of work ensures that the site operatives can quickly become familiar with health and safety aspects of their job. (Ravishankar, 2015)
  • 4. Striking Concrete can be struck once the concrete has gained enough strength to be self-supporting, and to carry any other loads that may be put on it. (Nemati, 2005) Advantages of Table formwork Main advantages of table formwork allows for fast construction for large floor layouts. It comes in fully assembled units that can be lifted quickly into place. It offers high quality surface finish that can be achieved with quality control used. It reduces workforce requirements on site. For project management it is easier to plan construction activities due to the repetitive nature of the work. The formwork system is reusable with little waste generated compared to traditional formwork. The assembled units are intended for use throughout the duration of a project without dismantling. And Increased speed and time efficiency on site. (Ravishankar, 2015) Summary Innovations have focused on on-site efficiency of production, Health and safety, and environmental issues, moving towards increasing efficiency. Traditional formwork for concrete construction consisted of bespoke results requiring skilled workers. These types of formwork often had pour safety features and gives slow rates of construction on-site and great levels of waste. Modern formwork systems which are modular are designed for speed and efficiency therefor The quality of surface finish will depend on the quality of formwork used. The most populat formwork systems in industry are offered by propriatery systems such as ‘DOKA and PERI’ which specialise in formwork.