4. 4
Construction
Activities
Area & Impacts Duration
Tentative
Date
Stage 2 - Piling
& Shallow
excavation
- Road occupancy south side of Eglinton Avenue,
west side of Bayview, and small area east of
secondary entrance
3-4 Months Restoration
Underway
Watermain
work
- At two locations - one near 591 Eglinton Ave E
and one right at the SW corner of Bayview and
Eglinton Avenue.
- Most of the work activities will be completed
during the day shift
- Some equipment is required to restore the area
around the watermain to achieve signoff from
Toronto water
- There may be some noise related to those
activities
- Overnight water shut offs associated with this
work
Two of the
overnight
periods
*Pending
overnight
permit.
Anticipated
for the 2nd or
3rd week of
May.
Stage 3 - Piling
& Shallow
excavation, and
wet utilities
- North side of Eglinton Ave, east & west of Bayview
- South east corner of Eglinton & Bayview
Approx. 3 – 4
months
*mid-late
May
Spring 2018
Leaside Station: What to Expect February 2018
5. 5
Stage 2 – Current Stage
Northbound left
turn restriction
6. 6
Stage 3.0 - Shoring and Shallow Excavation Stage
• Lane reductions will be in place with one lane of traffic in all
directions.
• Vehicular traffic will be shifted to the south side of Eglinton
Avenue, and the west side of Bayview Avenue.
• Intersection turn restrictions to be confirmed.
• The East N/S crosswalk will be closed with the remaining
three crosswalks maintained.
• All bus stop relocations established during the
implementation of Stage 2 will remain.
– The Westbound bus stop will move further east by Rollian
Sushi.
– The Northbound bus stop will move further north
• Temporary Metro driveway closure (on Eglinton).
11. 11
Laird Station: What to Expect
24 Hour Mining
• Mining operations are included in the 2010 Toronto Transit Project Noise By-Law
Exemption to allow for tunneling and related work to occur 24 hours a day.
• A robust noise reduction plan based on major international projects such as the Boston
Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to
minimize impacts on the local community.
– Implement noise reduction measures at the station construction sites
– Continually monitor noise and vibration throughout construction
– Adjust noise reduction measures at the construction sites as required
– If necessary, consider additional measures for residences in potentially sensitive zone
– Ensure proactive communications with the community before and during construction
Long Term Construction Activity Area Duration
24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019