SlideShare a Scribd company logo
1 of 14
CROSSTOWN LRT
Construction Liaison
Committee
May 9, 2018
2
Agenda
• Leaside Station Update
• Laird Station Update
3
Leaside Station Update
4
Construction
Activities
Area & Impacts Duration
Tentative
Date
Stage 2 - Piling
& Shallow
excavation
- Road occupancy south side of Eglinton Avenue,
west side of Bayview, and small area east of
secondary entrance
3-4 Months Restoration
Underway
Watermain
work
- At two locations - one near 591 Eglinton Ave E
and one right at the SW corner of Bayview and
Eglinton Avenue.
- Most of the work activities will be completed
during the day shift
- Some equipment is required to restore the area
around the watermain to achieve signoff from
Toronto water
- There may be some noise related to those
activities
- Overnight water shut offs associated with this
work
Two of the
overnight
periods
*Pending
overnight
permit.
Anticipated
for the 2nd or
3rd week of
May.
Stage 3 - Piling
& Shallow
excavation, and
wet utilities
- North side of Eglinton Ave, east & west of Bayview
- South east corner of Eglinton & Bayview
Approx. 3 – 4
months
*mid-late
May
Spring 2018
Leaside Station: What to Expect February 2018
5
Stage 2 – Current Stage
Northbound left
turn restriction
6
Stage 3.0 - Shoring and Shallow Excavation Stage
• Lane reductions will be in place with one lane of traffic in all
directions.
• Vehicular traffic will be shifted to the south side of Eglinton
Avenue, and the west side of Bayview Avenue.
• Intersection turn restrictions to be confirmed.
• The East N/S crosswalk will be closed with the remaining
three crosswalks maintained.
• All bus stop relocations established during the
implementation of Stage 2 will remain.
– The Westbound bus stop will move further east by Rollian
Sushi.
– The Northbound bus stop will move further north
• Temporary Metro driveway closure (on Eglinton).
7
Leaside Progress
8
Leaside Progress
9
Leaside Progress
10
Laird Station Update
11
Laird Station: What to Expect
24 Hour Mining
• Mining operations are included in the 2010 Toronto Transit Project Noise By-Law
Exemption to allow for tunneling and related work to occur 24 hours a day.
• A robust noise reduction plan based on major international projects such as the Boston
Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to
minimize impacts on the local community.
– Implement noise reduction measures at the station construction sites
– Continually monitor noise and vibration throughout construction
– Adjust noise reduction measures at the construction sites as required
– If necessary, consider additional measures for residences in potentially sensitive zone
– Ensure proactive communications with the community before and during construction
Long Term Construction Activity Area Duration
24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019
12
Laird Station Secondary – Progress
13
Laird Station Main – Progress
14
Local Area Map
Station(s) under construction

More Related Content

What's hot

Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Crosstown TO
 
Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021Crosstown TO
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...Crosstown TO
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Crosstown TO
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Crosstown TO
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020Crosstown TO
 
Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Crosstown TO
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 Crosstown TO
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Crosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Crosstown TO
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Crosstown TO
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Crosstown TO
 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Crosstown TO
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Crosstown TO
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCrosstown TO
 

What's hot (20)

Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018
 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
 

Similar to Crosstown LRT Construction Updates: Leaside and Laird Stations Progress

Leaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee MeetingLeaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee MeetingCrosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Leaside laird clc construction update deck july 2018
Leaside laird clc construction update deck   july 2018Leaside laird clc construction update deck   july 2018
Leaside laird clc construction update deck july 2018Crosstown TO
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesCrosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
 

Similar to Crosstown LRT Construction Updates: Leaside and Laird Stations Progress (20)

Leaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee MeetingLeaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee Meeting
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018
 
Leaside laird clc construction update deck july 2018
Leaside laird clc construction update deck   july 2018Leaside laird clc construction update deck   july 2018
Leaside laird clc construction update deck july 2018
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escortsaditipandeya
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...Suhani Kapoor
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageTechSoup
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 

Recently uploaded (20)

Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized Storage
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 

Crosstown LRT Construction Updates: Leaside and Laird Stations Progress

  • 2. 2 Agenda • Leaside Station Update • Laird Station Update
  • 4. 4 Construction Activities Area & Impacts Duration Tentative Date Stage 2 - Piling & Shallow excavation - Road occupancy south side of Eglinton Avenue, west side of Bayview, and small area east of secondary entrance 3-4 Months Restoration Underway Watermain work - At two locations - one near 591 Eglinton Ave E and one right at the SW corner of Bayview and Eglinton Avenue. - Most of the work activities will be completed during the day shift - Some equipment is required to restore the area around the watermain to achieve signoff from Toronto water - There may be some noise related to those activities - Overnight water shut offs associated with this work Two of the overnight periods *Pending overnight permit. Anticipated for the 2nd or 3rd week of May. Stage 3 - Piling & Shallow excavation, and wet utilities - North side of Eglinton Ave, east & west of Bayview - South east corner of Eglinton & Bayview Approx. 3 – 4 months *mid-late May Spring 2018 Leaside Station: What to Expect February 2018
  • 5. 5 Stage 2 – Current Stage Northbound left turn restriction
  • 6. 6 Stage 3.0 - Shoring and Shallow Excavation Stage • Lane reductions will be in place with one lane of traffic in all directions. • Vehicular traffic will be shifted to the south side of Eglinton Avenue, and the west side of Bayview Avenue. • Intersection turn restrictions to be confirmed. • The East N/S crosswalk will be closed with the remaining three crosswalks maintained. • All bus stop relocations established during the implementation of Stage 2 will remain. – The Westbound bus stop will move further east by Rollian Sushi. – The Northbound bus stop will move further north • Temporary Metro driveway closure (on Eglinton).
  • 11. 11 Laird Station: What to Expect 24 Hour Mining • Mining operations are included in the 2010 Toronto Transit Project Noise By-Law Exemption to allow for tunneling and related work to occur 24 hours a day. • A robust noise reduction plan based on major international projects such as the Boston Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to minimize impacts on the local community. – Implement noise reduction measures at the station construction sites – Continually monitor noise and vibration throughout construction – Adjust noise reduction measures at the construction sites as required – If necessary, consider additional measures for residences in potentially sensitive zone – Ensure proactive communications with the community before and during construction Long Term Construction Activity Area Duration 24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019
  • 13. 13 Laird Station Main – Progress
  • 14. 14 Local Area Map Station(s) under construction