SlideShare a Scribd company logo
1 of 17
CROSSTOWN LRT
Construction Liaison
Committee
February 21, 2018
2
Agenda
• Leaside Station Update
• EEB3 Update
• Laird Station Update
3
Leaside Station Update
4
Construction
Activities
Area & Impacts Duration
Tentative
Date
Stage 2 - Piling
& Shallow
excavation
- Road occupancy south side of Eglinton Avenue,
west side of Bayview, and small area east of
secondary entrance
- Main entrance & secondary Entrance
3-4 Months Underway –
*Traffic flip
April 2018
Wet Utilities
Works
- Work zone west of condo driveway Approx. 2 months Underway
Stage 3 - Piling
& Shallow
excavation
- North side of Eglinton Ave, east & west of
Bayview
- South east corner of Eglinton & Bayview
Approx. 3 months Spring 2018
Wet Utilities
works
- North side of Eglinton Avenue, west of
entrance to Metro
During stage 3 &
4, approx. 6
months
Spring 2018
Stage 4 - Piling
& Shallow
excavation
- North side of Eglinton Ave, east & west of
Bayview
- North west corner of Eglinton & Bayview
Approx. 3 months Summer
2018
Leaside Station: What to Expect February 2018
5
Leaside Station: What to Expect
• Support of Excavation will continue to be underway until late
2018
• Support of Excavation includes:
– Piling
– Shallow Excavation
– Temporary decking installation
• Work is completed in stages around the intersection
• Temporary decking is installed over completed sections
• Once all the stages are complete, deep excavation will
continue beneath the decking.
• Utility works will continue periodically over the next year.
6
Stage 2 – Current Stage
7
Leaside Progress
8
Leaside Progress
9
EEB3 Update
10
EEB3 Progress Update
• Trucks access the tunnel shaft from the construction site near
Bessborough Drive, pump concrete into a pipe, and drive the concrete
down the tunnel to where it will be poured into place.
• Steady progress is being made from EEB3 to Laird, the last pour was
conducted last week
• Progress continues at site with beam installations for the vehicle
maintenance
11
Progress Picture
12
Laird Station Update
13
Laird Station: What to Expect
24 Hour Mining
• Mining operations are included in the 2010 Toronto Transit Project Noise By-Law
Exemption to allow for tunneling and related work to occur 24 hours a day.
• A robust noise reduction plan based on major international projects such as the Boston
Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to
minimize impacts on the local community.
– Implement noise reduction measures at the station construction sites
– Continually monitor noise and vibration throughout construction
– Adjust noise reduction measures at the construction sites as required
– If necessary, consider additional measures for residences in potentially sensitive zone
– Ensure proactive communications with the community before and during construction
Long Term Construction Activity Area Duration
24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019
14
Laird Station Secondary – Progress
15
Laird Station Main – Progress
16
Laird Station Main – Progress
17
Local Area Map
Station(s) under construction

More Related Content

What's hot

Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017
Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017
Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017Crosstown TO
 
Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...
Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...
Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Crosstown TO
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Crosstown TO
 
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerOld Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerFairfax County
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationFairfax County
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
 
Scotts Run Fire Station
Scotts Run Fire StationScotts Run Fire Station
Scotts Run Fire StationFairfax County
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
October 2018 Updates on Construction Work
October 2018 Updates on Construction WorkOctober 2018 Updates on Construction Work
October 2018 Updates on Construction WorkRRFHPRusumo
 
Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project DirectorFabien Deschamps
 
Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14greenbelt82
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 

What's hot (20)

Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
 
Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017
Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017
Cedarvale & Forest Hill Construction Liaison Committee - November 29, 2017
 
Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...
Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...
Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017
Cedarvale & Forest Hill Construction Liaison Committee Meeting - July 2017
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
 
Woodlawn Fire Station
Woodlawn Fire StationWoodlawn Fire Station
Woodlawn Fire Station
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021
 
BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1
 
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerOld Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity Sewer
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road Presentation
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
 
Scotts Run Fire Station
Scotts Run Fire StationScotts Run Fire Station
Scotts Run Fire Station
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
October 2018 Updates on Construction Work
October 2018 Updates on Construction WorkOctober 2018 Updates on Construction Work
October 2018 Updates on Construction Work
 
Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project Director
 
Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 

Similar to CROSSTOWN LRT Construction Updates: Leaside, EEB3 & Laird Stations

Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Leaside laird clc construction update deck july 2018
Leaside laird clc construction update deck   july 2018Leaside laird clc construction update deck   july 2018
Leaside laird clc construction update deck july 2018Crosstown TO
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Crosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Crosstown TO
 

Similar to CROSSTOWN LRT Construction Updates: Leaside, EEB3 & Laird Stations (20)

Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
 
Leaside laird clc construction update deck july 2018
Leaside laird clc construction update deck   july 2018Leaside laird clc construction update deck   july 2018
Leaside laird clc construction update deck july 2018
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...Christina Parmionova
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersCongressional Budget Office
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationEnergy for One World
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024Energy for One World
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 

Recently uploaded (20)

Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists Lawmakers
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological Civilization
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 

CROSSTOWN LRT Construction Updates: Leaside, EEB3 & Laird Stations

  • 2. 2 Agenda • Leaside Station Update • EEB3 Update • Laird Station Update
  • 4. 4 Construction Activities Area & Impacts Duration Tentative Date Stage 2 - Piling & Shallow excavation - Road occupancy south side of Eglinton Avenue, west side of Bayview, and small area east of secondary entrance - Main entrance & secondary Entrance 3-4 Months Underway – *Traffic flip April 2018 Wet Utilities Works - Work zone west of condo driveway Approx. 2 months Underway Stage 3 - Piling & Shallow excavation - North side of Eglinton Ave, east & west of Bayview - South east corner of Eglinton & Bayview Approx. 3 months Spring 2018 Wet Utilities works - North side of Eglinton Avenue, west of entrance to Metro During stage 3 & 4, approx. 6 months Spring 2018 Stage 4 - Piling & Shallow excavation - North side of Eglinton Ave, east & west of Bayview - North west corner of Eglinton & Bayview Approx. 3 months Summer 2018 Leaside Station: What to Expect February 2018
  • 5. 5 Leaside Station: What to Expect • Support of Excavation will continue to be underway until late 2018 • Support of Excavation includes: – Piling – Shallow Excavation – Temporary decking installation • Work is completed in stages around the intersection • Temporary decking is installed over completed sections • Once all the stages are complete, deep excavation will continue beneath the decking. • Utility works will continue periodically over the next year.
  • 6. 6 Stage 2 – Current Stage
  • 10. 10 EEB3 Progress Update • Trucks access the tunnel shaft from the construction site near Bessborough Drive, pump concrete into a pipe, and drive the concrete down the tunnel to where it will be poured into place. • Steady progress is being made from EEB3 to Laird, the last pour was conducted last week • Progress continues at site with beam installations for the vehicle maintenance
  • 13. 13 Laird Station: What to Expect 24 Hour Mining • Mining operations are included in the 2010 Toronto Transit Project Noise By-Law Exemption to allow for tunneling and related work to occur 24 hours a day. • A robust noise reduction plan based on major international projects such as the Boston Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to minimize impacts on the local community. – Implement noise reduction measures at the station construction sites – Continually monitor noise and vibration throughout construction – Adjust noise reduction measures at the construction sites as required – If necessary, consider additional measures for residences in potentially sensitive zone – Ensure proactive communications with the community before and during construction Long Term Construction Activity Area Duration 24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019
  • 15. 15 Laird Station Main – Progress
  • 16. 16 Laird Station Main – Progress
  • 17. 17 Local Area Map Station(s) under construction